ML18017B201
| ML18017B201 | |
| Person / Time | |
|---|---|
| Site: | Harris |
| Issue date: | 06/03/1980 |
| From: | Murphy C NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| To: | Jackie Jones CAROLINA POWER & LIGHT CO. |
| Shared Package | |
| ML18017B198 | List: |
| References | |
| NUDOCS 8008140031 | |
| Download: ML18017B201 (3) | |
See also: IR 05000400/1980012
Text
)
n-Reply
- .;RII:
400/SO-22
50"401/80-10
50-402/80-10
50"403/8 "
er To:
NUCLEAR REGULATORY COMER+SION
REGION II
%0'l MAFL)ETiAST>> X.W>> SUlTE 3CCO
ATLAI4TAeGEORGl*30303
JUN -3am
Carolina Power and I.ight Company
ATTN: J. A. Jones
Senior ExecutivepVice Presiderit and
Chief Operating Officer
. 411 Zayetteville.Street
. Raleigh,
NC
27402
'
Gentlemen:
This refers to the: inspection'onducted
by V. L. Brovnlee 'of this:office'n
.April 28 through Hay 2,'980 of activities authorized
by NRC Construction Permit
Nos.
CPPR-158,
CPPR-159,
CPPR-160,
and CPPR-161 for the Shearon -'Harris facflity,
and to the discussion
of our findings held vith Messrs.
P. V.
Howe and
R. N.
Parsons at the conclusion of the inspection.
.A eas axamhed
51xrlhg -the =inspection
and::our- finikin'gs.-.aze .discussed ia the
- tnclosed'spectidri=?epos.
%&in thhsh
a~e'aS,. &'Qispection --coniisted of
selective
examinations. of procedures
and representative
records,
interviews with
personnel,
and observations
by the inspectors.
- During the inspection,
it'vas.'foluid that 'certa'in ~'ctivfhes under. your'icense
- appear.: to 12e in'nncompl&ace ~i'C requirements. 'hese
Stems
'an'd references
to-: pertinent requi~ertts 'awe 'lasted 'xn'he Yot:ice of'S.olation enC10Sed herewith
. is Appendix A;. This noti'ci: is sent to.you pursuant Xo the pro'Csues
of Se'ction
2'20l of the NRC's'":Rules of Practice," Part 2, Title 10, Code of Federal Regula-
tions.
Section
2.201 requires
you to submit to this office, within 20 days of
your receipt of this notice,
a vritten statement or explanation in reply including:
(1) corrective steps
which have been taken by you and the results
achieved;
(2)
corrective steps vhich vill be taken to avoid further noncompliance;
and (3) the
date when full compliance villbe achieved.
In accordance
with Section 2.790 'of the NRC's "Rules of Practice," Part 2, Ti.tie
=%0',:Cpde-:of Federal.regulations,
a copy of this letter and the enclosed inspection
report will be placed in the NRC's Public Document Room. If this. report contains
-any 4nformati~>:that you '(or your contractor) believe to be proprietary, it is
-ne'cessary
.that you make
a vritten application vithin 20 days to this office to
.yithhog+auch
jjxformation from public disclosure.
Any such application must
include a full statement of the reasons
on the basis of which it is claimed that
.the infognation is proprietary,
and
should be prepared
so that proprietary
'information identified in the application is contained in. a separate
part of the
document. If ve do not hear from you ia this regard vith'in the specified period,
the report villbe placed in the Public Document Room.
~
ey
-2--
'=)FHIV246009.
Both wall'ours
were being set
up simultaneously
when
the first shift ended.
The second shift was instructed to finish set.
up
on both walls
and pour wali'HD>246001.
When the
second shift
concrete
personnel
arrived at the fuel handling building, both pours
appe'ared
to be set
up.
Without checking
the pour card
numbers,
the
second
shift
concrete
General
Foreman
and
Construction
Inspector
assumed
that pour
1FHIW246009,
which was almost set up, was the pour
that=had-'a-completed's'ign
off.
- -CPU 's investigate.on
con'eluded that inspector's
reports 'for the'"placed"
wall. (1HOW246009)- indicate that all rebar
and
embedded
items
were
.. - -: -- installed -as:-required
by design
documents
and only minor clearance
and
form tolerances
remained 'to be resolved.
CPU. has submitted
PW-'C"1419
(pezmanent waiver) to Ebasco
(AE) to allow wall to remain "as is".
The inspectors
held discussions
with CPGI
QA management
and engineering
--". ----personne1-',
and--inspected- the.-pour sites.
- The- inspectois=concui-wit'h
the--linens'ee
s -conclusion- tk~'t-'the "-presign. i'nugent- of: the-'"wall
waN '=
--"satisfied.
b.
Quality Assurance,
Quality Control Functions - Onsite
V
~
V
~ (2)
~
~
Quality Assurance
Program
Section
1.8.2 -of the
PSAR (item a'n
page
1.8.2) states
that
Quality Assurance
and inspection of construction activities will
be the responsibility of the
CPoL Engineering
and Construction
Quality Assurance
Section of the Technical
Services
Department.
As currently organized,
the.QC function is split between
the: S'ite-
QA group and Construction Inspection group.
Implementation
The inspector
observed
QA/QC field activities:and-intervi.ewe'd'-=:
twe1ve 'per'sons:.'ehgaged
in these activities<
'-During t'e--'interviews
."."and .obsezvation's,'-
the 'inspector
ascertained
'-that there- was'o
apparent
lack of objectivity in the
QA/QC functions
as
a result
of contract
(Daniels) personnel
under
CPU. supezvision performing
these activities an Daniels
work.
While no lack of objectivity was observed,
persons
inte'rviewed
indicated, either
on their own initiative or as
a result of a
specific question
by the inspector,
that the combined functions
af
QA and
QC under the
same
group
and performed
by- the
same-
personnel
was causing
a strained if not inadequate
performance'f-'hese
activities.
Although neither the inspector's
observations
nor the interviewee's
accounts 'gave
a single
case
of improper
functioning of either
.QA or
QC,
the
con'cerns
expressed
were
valid.
Since
a person
performs
QC of an activity one
day and
provides the site
QA of the same area the following day,
a possi-
'ility of a conflict exists
even
though
no cases
were found or
stated
where
an inspector ever performed
QA on the
same job where
~ 3a
~
he
had previously performed the
QC.
In addition,
the
demands of
the
QC function, according'o
the
inte viewees,
occasionally
prevented them from performing "as
much
QA as they would'ave
liked" to perform, although, in all cases
reviewed or discussed,
the minimum requirements
were met.
Since.,the licensee's'urrent
organization
is. not:as. defin'ed
xn:
the PSAR,
a change notificati:on will be, required .for NRR s review'.
.. .The .Site
Manager .also. stated,.the
current:dual.
QA/QC=functions=
'--
~ within the Site QA:group would be reviewed
and evaluated'.in light
of the inspector's
findings,
and
any
changes
would be proposed
and- inc3.uded-'in the-'submittal. to.:NRR;.-.3Jntil-.this ieviewganf- th'-'
proposed
changes .have been..submitted;.this. i.tern.will:be designated
."
- a
inspector. followup item-400/80-12-11
'401/402/403'/Bi=10-;11:
'verall
. evxew -and.Inspection.
o -the Quality.Assuiance
(gA) 2'rogram"Imp e-
mentation
a
s
COL received
the construction
permits for the ..Shearon
Harris..Power
Plant cnins.(Harris)'n Jannarjj
28, 197g.
Ebasco Services,
Incorporated
(Ebasco)
was engaged for engineering nf Barris
1
CPSL-;Power Plant Engin-
eering Department
(PPED) has overall responsibility for proper application
of quality standards-practices,
and procedures
during the engineering,
design
and procurement
phase.
PPED fulfills this responsibility by
approving specifications,
recommended
bidders lists', successful bidders,
selections,-
purchase
order placement- and review. of:
aelecte'd-drawings"'PED
presently
has- 26 engineers
-at th'e site that,:provide engineering
inter ace activities with Zbasco.
Vestinghouse
Electric Corporation.
was
contracted
- to design,
fabricate,
and . deliver the Nuclear .Steam
.=
Supply System
(NSSS)g."fuel: and turbine,:generators
for Harris.
Daniel
Construction
Company
(DCC) is the constructor.
Site construction is
'performed in accordance
with Ebasco specifications,
drawings
and other
engineering
documents
by the various
CPQ, contractors.
CPGL manages
site
construction ~nd
QA/QC
ac ivities',
Daniel works- under. direct.
supervision.
and= technical,:control .of-,CPSL:.-'=CPU,'s:.QA
program ms=-c
.
imposed--upon
.DCC.-:.CPS's .site -QA -Unit and -Construction -Inspection:
group
performs
QA/QC
functions.
Field
storage
and..installation
requirements
are- the resp'onsibi.lity of the CPK Site Manager.--Site=--
construction procurement
is- performed by CPA,.
CP&L furnishes
vendor
surveillance inspection functions for construction purchased
items and
CPU. contracts.
b.
QA Hanual, Inspection and Enforcement History
The inspectors
performed
a review of- the
QA- manuals
and locket-. files:=
to include
the following: ---inspections
relative
to:.QA programs
and..
site;
enforcement
correspondence
and responses;.;and
the construction
deficiency and Part
21 report. Sile.
a
~
~