Forwards IE Insp Repts 50-400/79-19,50-401/79-19, 50-402/79-18 & 50-403/79-18 on 790918-21 & Notice of Violation
ML18017A977
Person / Time
Site: Harris  
Issue date: 10/22/1979
From: Murphy C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Jackie Jones
CAROLINA POWER & LIGHT CO.
Shared Package
ML18017A974 List:
References
NUDOCS 8003210307
Download: ML18017A977 (3)


See also: IR 05000400/1979019

Text

l

~R REOI

/

"I

0O

IVi

Cy

V/+n

~O

++*++

In Reply Refer To:

RII:JRH

50-400/79-19

50-401/79-19

50-402/79-18

50"403/79-18

UNITEDSTATES

NUCLEAR REGULATORY COMMISSION

REGION II

101 MARIETTAST., N.W., SUITE 3100

ATLANTA,GEORGIA 30303

OCT 22 1S79

Carolina Power and I,ight Company

ATTN:

Mr. J. A. Jones

Executive Vice President

and

Chief Operating Officer

411 Fayetteville Street

Raleigh,

NC

27602

Gentlemen:

This refers

to the

inspection

conducted

by J.

R. Harris of this office on

September

18-21,

1979, of activities authorized

by NRC Construction Permit Nos.

CPPR-158,

CPPR-159,

CPPR-160,

and

CPPR-161 for the Shearon Harris facility, and

to the discussion

of our findings held with R.

M. Parsons

at the conclusion of

the inspection.

Areas

examined

during the inspection

and

our findings

are

discussed

in the

enclosed

inspection

report.

Within these

areas,

the inspection

consisted

of

selective

examinations

of procedures

and representative

records,

interviews with

personnel,

and observations

by the inspector.

We have

examined

actions

you have

taken with regard to previously identified

enforcement matters

and unresolved

items.

The status of these items is discussed

in the enclosed report.

During the inspection, it was

found that certain activities under your license

appear

to be in noncompliance

with NRC requirements.

This'item and references

to pertinent requirements

are listed in the Notice of Violation enclosed herewith

as Appendix A.

This notice is sent to you pursuant to the provisions of Section

2.201 of the NRC's "Rules of Practice," Part 2, Title 10,

Code of Federal Regula-

tions.

Section 2.201 requires

you to submit to this office, within 20 days of

your receipt of this notice,

a written statement or explanation in reply including:

(1) corrective steps

which have been taken by you and the results

achieved;

(2)

corrective steps

which will be taken to avoid further noncompliance;

and (3) the

date when full compliance will be achieved.

In accordance

with Section 2.790 of the NRC's "Rules of Practice," Part 2, Title

10, Code of Federal Regulations,

a copy of this letter and the enclosed inspection

report will be placed in the NRC's Public Document Room. If this report contains

any information that you (or your contractor) believe to be proprietary, it is

necessary

that you make

a written application within 20 days to this office to

withhold such

information from public disclosure.

Any such application

must

include a full statement of the reasons

on the basis of which it is claimed that

Cg

Carolina Power and Light Company

"2-

OCT 22 1S79

the

information is proprietary,

and

should

be

prepared

so that proprietary

information identified in the application is contained in a separate

part of the

document. If we do not hear from you in this regard within the specified period,

the report will be placed in the Public Document Room.

Should you have

any questions

concerning this letter,

we will be glad to discuss

them with you.

Sincerely,

C. E.

Mu

,

hief

Reactor Construction

and Engineering

Support Branch

Enclosures:

1.

Appendix A, Notice of Violation

2.

Inspection Report Nos. 50-400/79-19,

50-401/79-19,

50-402/79-18,

and 50-403/79-18

cc w/encl:

R. Parsons,

Site Manager

P. 0.

Box 10l

New Hill, NC

27562