ML18016A350
| ML18016A350 | |
| Person / Time | |
|---|---|
| Site: | Harris |
| Issue date: | 03/11/1998 |
| From: | Scott Flanders NRC (Affiliation Not Assigned) |
| To: | NRC (Affiliation Not Assigned) |
| References | |
| NUDOCS 9803200255 | |
| Download: ML18016A350 (33) | |
Text
gP,R RE00
~o Cy C
O I
EO0
> ~0
'++*++
LICENSEE:
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 2055&4001 March ll, 1998 CAROLINAPOWER AND LIGHTCOMPANY PLANT:
SHEARON HARRIS, UNIT 1
SUBJECT:
SUMMARY
OF MEETING WITHTHE CAROLINAPOWER AND LIGHT COMPANY (CP&L)
On March 3, 1998, the staff met with representatives of Carolina Power 8 Light Company (CP8L) to discuss the Shearon Harris Nuclear Power Plant (SHNPP) 'C'nd 'D'pent fuel pools activation project.
Enclosure 1 is a list of meeting attendees. is a copy of the handout provided at the meeting. The CP8L presentation included background information, a discussion of licensing activities, and the project schedule.
~a:kiikgund Originally, SHNPP was intended to be a four unit site with four fuel pools (A,B,C, and D) and two Fuel Pool Cooling and Cleanup systems (FPCCS). Although three of the four units were canceled, the construction of all four pools and one of the FPCCS was completed.
Also, a portion of the piping for the other FPCCS was installed. Currently pools 'A'nd 'B're in service and not only store SHNPP fuel, but also store spent fuel from other CP8L plants (Brunswick Units 1& 2, and Robinson).
Pools 'C'nd 'D're not in service.
CP8L has determined that pools 'C'nd 'D'illbe needed to ensure all four units maintain a prudent operating reserve for core off loads. According to CP8L, pool 'C's needed by early 2000 to support fuel shipments from Brunswick and Robinson.
In order to place pools 'C'nd
'D'n service, the FPCCS and pool racking must be completed for pools 'C'nd 'D'.
IC I
The second licensing activity discussed involved piping certification for the 'C'nd 'D'PCCS.
A portion of the piping for the 'C'nd 'D'PCCS is already installed, with some embedded in concrete, making approximately 14 field welds inaccessible.
CP8L inadvertently disposed of the piping certification records for the installed piping, which makes it unable to demonstrate that the piping satisfies the design requirements of American Society of Mechanical Engineers (ASME) Code Section III. CP&L stated that it intends t Section III. The staff stated that a relief request from o request relief from ASME Code the requirements of ASME Code IIIMRE CEImy~ ~y 9803200255 9803ii PDR ADQCK 05000400 PDR CP8L identified three licensing activities associated with the completion of pools 'C'nd 'D'.
The first is a potential unreviewed safety question (USQ) associated with the modification of the Unit 1 Component Cooling Water (CCW) System.
Although the Unit 1 CCW system was not originally designed to cool the FPCCS for pools 'C'nd 'D', CP&L has determined that the Unit 1 CCW system has sufficient margin to accept the 'C'nd 'D'PCCS load. The original design was for the Unit 1 CCW to cool the FPCCS for pools 'A'nd 'B', and for the Unit 2 CCW system to cool the FPCCS for pools 'C'nd 'D'. The staff asked several questions about the spent fuel pool, the FPCCS, and CCW system designs.
The staff also inquired about SHNPP fuel handling practices.
0 Pi Section III would not be appropriate.
The staff recommended that CP8L propose an alternative method, as allowed by 10 CFR 50.55a, that provides an acceptable level of safety and quality.
CP8L agreed with the staff's comments and stated that a relief request was not the appropriate terminology for its request.
CP8L stated that it intends to propose a piping certification plan, which includes tests and inspections, as an alternative method to the requirements of ASME Code Section III.
CP8L also intends to submit a Technical Specification (TS) change for high density racks in pools 'C'nd 'D'. The TS change would modify SHNPP spent fuel capacity.
~Sh.dt.ILe I
CP8L stated that the TS change and the piping certification plan will be ready for submittal this summer, and the CCW USQ will be ready by fall. Due to the complex nature of this review, the staff recommended that CP8L make one complete submittal that includes all three licensing activities as oppose to three separate submittals.
The staff also recommended that CP8L may want to meet with the staff again in the summer to discuss, in more detail, the TS change and the piping certification plan.
CP8L agreed with the staffs recommendations, and intends to submit 'one amendment encompassing all three licensing activities in the fall. CP8L stated that approval is needed by the end of 1999.
Docket No. 50<00 (Original Signed By)
Scott C. Flanders, Project Manager Project Directorate II-1 Division of Reactor Projects - I/II Office of Nuclear Reactor Regulation cc w/enclosures:
See next page
~oietrtbu ion See next page G:>HARRIS>0303. um OFFICE NAME DATE COPY PM:
1 SFI dere
~ ////98 Yes/No LA:PDII-1 Dunnington +7D 3/1/98 e
No D:PDII-1
/I)98 (Qes ego
Mr. W. R. Robinson Carolina Power & Light Company Shearon Harris Nuclear Power Plant Unit 1
'CC:
Mr. William D. Johnson Vice President and Senior Counsel Carolina Power 8 Light Company Post Office Box 1551 Raleigh, North Carolina 27602 Resident Inspector/Harris NPS c/o U.S. Nuclear Regulatory Commission 5421 Shearon Harris Road New Hill, North Carolina 27562-9998 Ms. Karen E. Long Assistant Attorney General
,State of North Carolina Post Office Box 629 Raleigh, North Carolina 27602 Public Service Commission State of South Carolina Post Office Drawer Columbia, South Carolina 29211 Regional Administrator, Region II U.S. Nuclear Regulatory Commission Atlanta Federal Center 61 Forsyth Street, SW, Suite 23T85 Atlanta, Georgia 30303 Mr. Mel Fry, Acting Director Division ofRadiation Protection N.C. Department of Environment, 3825 Barrett Dr.
Raleigh, North Carolina 27609-7721 Ms. D. B. Alexander Manager Performance Evaluation and Regulatory Affairs Carolina Power 8 Light Company 412 S. Wilmington Street Raleigh, North Carolina 27601 Mr. Bo Clark Plant General Manager - Harris Plant Carolina Power 8 Light Company Shearon Harris Nuclear Power Plant P.O. Box 165 New Hill, North Carolina 27562-0165 Mr. J. W. Donahue Director of Site Operations Carolina Power & Light Company Shearon Harris Nuclear Power Plant Post Office Box 165, MC: Zone 1
New Hill, North Carolina 27562-0165 Mr. Robert P. Gruber Executive Director Public Staff NCUC Post Office Box 29520 Raleigh, North Carolina 27626
'Chairman of the North Carolina
'tilities Commission Post Office Box 2951 0 Raleigh, North Carolina 27626-0510 Mr. Milton Shymlock U.S Nuclear Regulatory Comm.
Atlanta Federal Center
- 61. Forsyth Street, SW, Suite 23185 Atlanta, Georgia 30303 Mr. Stewart Adcock, Chairman Board of County Commissioners of Wake County P. O. Box 550 Raleigh, North Carolina 27602 Health and Natural Resources Margaret Bryant Pollard, Chairman Board of County Commissioners of Chatham County P. O. Box 87 Pittsboro, North Carolina 27312 Mr. Chris A. VanDenburgh, Manager Regulatory Affairs Carolina Power 8 Light Company Shearon Harris Nuclear Power Plant P.O. Box 165, Mail Zone 1 New Hill, NC 27562-0165 Mr. Johnny H. Eads, Supervisor Licensing/Regulatory Programs Carolina Power 8 Light Company Shearon Harris Nuclear Power Plant P. O. Box 165, Mail Zone 1
New Hill, NC 27562-0165
Distribution:,
E-gaddi J. Zwolinski (JAZ)
P. Kuo (PTK)
L. Plisco (LRP)
S. Flanders (SCF)
E. Dunnington (ETD)
T. Marsh (LBM)
R. Wessman (RHW)
G. Bagchi (GXB1)
T. Collins (TEC)
G. Hubbard (GTH)
K. Manoly (KAM)
R. Rothman (RLR)
J. Rajan (JRR)
L. Kopp (LIK)
C. Gratton (CXG1)
V. Ordaz (VLO)
D. Jackson (DTJ)
M. Shymlock (MBS)
J. Brady (JBB1)
L. Trocine (LXT)
K. Clark (KMC2) Rll
~ard~Co
~Docket. File.=--
PUBLIC PD¹ll-1 Reading cc: Licensee & Service List
8IIBkDDGE E
MEE W
A L
P ar
- g. c
/VPlz p Q-f COY'<C Hlh 54rA l"et Vl~h cP&a.~0'4 Chgs 6m~
)i (i3 SH u~
P//c/V///,f ~l lg
<0-c wP-r~iRPLE Ac. QW.
spy
~webb/sm h/Pc 6/~ z/'c8 AEc A'Zg N
NfV K
I d~t -8l(~~S i ~
I S4 2/e
/'
/ZocZ~
~P c L Ave Ca
~w l
Hc g+ +do+~
C~ c JH P
E gd7Ez75 Nl~e hlR<
EH'cKc-Z~
Enclosure 1
HNP Spent Fuel Pool 'C'nd
'D'ctivation Project Status March 3, 1998 Enclosure 2
Meeting Objectives e Present purpose, scope, and schedule for HNP spent fuel pool 'C'nd 'D'ctivation project e Identify NRC submittals
+ Potential USQ for modification to complete Component Cooling Water (CCW) tie-ins to fuel pool cooling and cleanup system
+ ASME Section III relief request for fuel pool cooling system piping
+ Tech Spec change for high density racks e Discuss development of submittals
+ Separate submittals vs single, comprehensive submittal
Discussion Topics o BackgroundlHistory
+ Original Design
+ Spent Fuel Shipping Plan
+ Options Considered e Schedule o Project scope and anticipated licensing activities
+ Com lete cooling and cleanup system for pools
'C'nd.
~ Potential USQ for CCW System Tie-in
+ ASME Section III certification for installed piping
~ ASME Section III relief request
+ Rack Design and Pool Analysis
~ Tech Spec change for high density racks I Summary
0 0
Background/History A
o Original HNP Design
+ Four (4) nuclear units; four (4) fuel pools; two (2) cooling systems e Units 2, 3 and 4 canceled in early 1980's,
+ Allfour pools completed
+ Pools 'A'nd 'B'laced in service to support HNP Unit 1 and spent fuel shipping fiom BNP and RNP
+ Cooling system for pools 'C'nd 'D'as not completed
+ Plan at time of Unit 1 license was to corn lete cooling s stem and place pools 'C'nd '
in service w en necessary
Backgm oundlHistory Continued f
T A
o Some installation documentation not available
+ System cannot be certified to ASME Section III without all documentation o Fuel Pool 'C's needed in early 2000 to support spent fuel shipping requirements from BNP and RNP
- e. Without pool 'C' All 4 units lose prudent operating reserve by Spring 2000
+ HNP loses full core reserve in fall 2001
+ HNP forced shutdown in 2006
BackgroundlHistory Continued o Pools 'C'nd '0'using optimized rack designs} are needed to provide spent fuel storage capacity for all four units through end of licensed life
+ BNP and RNP pools willbe full when licenses expire
+ Additional storage capacit (such as dry storage facilities) willbe needed if ife extension is pursued at any of the units
Schedule 1998 1999 J
F M
A M
J J
A S
0 N
D J
F M
A M
J J
A S
0 N
D A Submit Piping Certification Relief Request Submit Tech Spec Change for high density racks X Submit Potential USQ for CCW Tie-ins (ifrequired)
X Cooling System Study Phase X Cooling System Detailed Design Cooling System Installation X Install CCW Tie-ins and Complete System Testing A A Rack and Pool Analysis A Order Racks - 1" Campaign X Fabricate Racks Install Racks in Pool 'C' Pool 'O'n Service X 3i2I98 8:00
SFP Cooling Options Considered 4XPCNWCCIR~
o Independent Cooling
+ With and without dedicated emergency diesel generators o Unit 1 Component Cooling Water (CCW)
+ 'As Is'current design assumptions)
+ CCW with some changes in design assumptions (foulinq factors, tube plugging limits, flow rates, IST limits, etc.)
+ CCW with s stem modifications to improve thermal-hy raulic performance o Dry storage facilities instead of pools 'C'nd 'D'
Cooling System Completion
\\
o Use CCW to provide cooling to fuel pool cooling
+ Phase 1 - Complete fuel pool cooling loop work and tie-ins to CCW (1998-1999)
~ Existing system adequate for near-term operation until power uprate is implemented
+ Phase 2 - Perform CCW system upgrade concurrent with power uprate (1999 - 2001)
~ Final scoping and detailed design/implementation to occur after sufficient power uprate arialysis has been completed
Projected CCW Heat Loads Ar Projected CCW Heat Loads (MBTU/hr)
Maxfmurn CCW Capabtt tty without system upgrades
+gP
>() A)@
g) Q X.<<, fJ
~<<~A '
JV~ f+()JJg(kl >> I+la I ()e
(
]((JYJ~~Y)AA)(>>J)g>p )i)p+>>g+P()"<<6>><<(.'>>>>+t+)'a<<))>>(tr,r J<<'y+'g Yg<(+ggg+
$~?~, '~+~()~ ~l&WAA,~Q,)J>>)AA(vg~+rpgM '+~))QH+4(>> Y) ~
!+'-ra(.~S~')->>)) C.(+A
- -.Q(A-" >>i P.
) 0<<
hcorporates potential tlnalphase of power q>rate (15%).
..r.
A>>8'i+j g
.Qq!
Ye~(
4g g
~~C'$
)<<
i(<<
1)
JgC
(.)Y,)
J)J,
>>Y~
K~y Exfstt D
n tfons tes BNPiRNP fpora Transshlpmert
) ~",
f,r)%
"g
>~*'i
'1
!A gb A+
T.
$(AAi "s
'Jc" g hcotporates Inttfatphase of power q>rate (4$%)l
~ Steam Generator Rephcement h +?i rgb A~(
>>)u,
'i;fg
'.-~Pi )
'j>>'
jdk JQ
'(()(
'y), '
A~~,
rPw)
,'A>>A<<v?
1
>>+r&'(i(1("
~)
Y!
"mg
!cP.'998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2(
3)2/98 8:00 10
Cooling System Licensing Activities QFRS5X~
o 10CFR50.59 for tie-in to CCW may be identified as potential unreviewed safety question
+ Adding additional cooling load to existing CCW system o Detailed design willstart in April 1998 o Expect plant modification package with 50.59 this fall
+ Design schedule has not been negotiated with AE o Willsubmit to NRC as soon as available
Certification of Installed Piping o Cooling system piping originally designed and installed to ASME Section III requirements
+ Section III program in place
~ Included approved procedures, certified welders, certified materials, and required inspections/tests performed o Allnew piping willbe designed and installed to ASME Section III requirements
Certification of Installed Piping Cont.
A A
%ARESN5
~SV8%%.
A o Records are available for all shop welds on piping abandoned during construction (209 of 248 welds) o Field installation records generally not available (39 of 248 welds)
+ Weld data reports, test records, welder qualification not available
+ Portion of piping is embedded arid not accessible for NDE (14 welds of 39 field welds) o Plan to inspect accessible welds (visual and liquid penetrant) and pressure test complete system
Piping Certification Licensing Activities e Relief from ASME Section III certification for fuel pool cooling system is required o Developing plan now o Expect to submit in early summer o Plan to perform inspections/tests concurrent with installation activities for new equipment
Original Fuel Rack Design 520 PWR Cells 2662 BWR Cells 3382 r
A e Original design for racks in pools 'C'nd 'D' Same as existing design for racks in pools 'A'nd cBP
+ Cell Pitch {Center-to-center spacing)
~ PWR racks - 1Q.5"
~ BWR racks - 6.25" o Pool Capacity
+
PoolC-
+
PoolD-
+
Total 680 PWR Cells 3862 Cells
Optimized Rack Design Additional Cells 407 PWR 101 BWR 927 PWR Cells 2763 BWR Cells A
e SFP Optimization Plan for pools 'C'nd 'D' Cell Pitch
~ PWR - 9;0"
~ BWR - 6.25" o Optimized Pool Capacity
+ Pool C-D 11 PWR Racks
~ 19 BWR Racks 3690 508
+ PoolD-
~ 12 PWR Racks 1025 PWR Cells 345 PWR
+ Total 47l5 Cells
Optimized Rack Design Continued Ae e First Campaign of Racks
+ Install late 1999
+ 4 PWR racks - 360 cells
+ 10 BWR racks - 1320 cells o Racks willbe Region 2 style
+ Neutron absorber material - Boral
+ PWR enrichment/burnup limitations
+ Administrative controls will be in place
+ No BWR Racks enrichment/burnup limitation since criticalityanalyses performed for maximum reactivity over burnup
Optimized Rack Design Continued-SPCRW&~@
e HNP high-density rack design has been successfully licensed and installed at other plants o PWR and BWR rack sizes selected to be inter-changeable
Holtec Analysis Report o License Report
+ In accordance with NRC Guidance for Review and Acceptance of Spent Fuel Storage and Handling Applications Supporting Analyses
+ Heavy Load and Construction Considerations
+ Criticality
+ Thermal-Hydraulic
+. Structural and Seismic
+ Radiological Evaluation
Pool/Rack Licensing Activities o Tech Spec Change required for high density racks
+ Driven by PWR pitch change o Finalizing analysis and report now o Plan to submit early summer
4 Tg
Summary e Pool 'C'eeds to be in service in early 2000 o Tech Spec Change for high density racks
~ Submit early summer 1998 e Fuel pool cooling phase 1 -. complete system and tie-in to CCW (1998-1999}
+ ASME Section III certification relief required due to unavailable field documentation
~ Submit early summer 1998
+ Potential USQ for CCW tie-in anticipated
~Submit fall 1998 pending AE design schedule o Fuel pool cooling phase 2 - determine CCW system upgrades required to support power uprate {1999-2001}