ML18011A818

From kanterella
Jump to navigation Jump to search
Insp Rept 50-400/95-02 on Stated Date.Violations Noted.Major Areas Inspected:Plant Operations,Review of Noncomformance Repts,Followup of Onsite Events,Maintenance Observation, Surveillance Observation,Security & Fire Protection
ML18011A818
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 03/02/1995
From: Christensen H, Elrod S, Steven Roberts
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML18011A816 List:
References
50-400-95-02, 50-400-95-2, NUDOCS 9503090229
Download: ML18011A818 (15)


See also: IR 05000400/1995002

Text

~p,S REG(g

P0

0O

Cy

gO

0p*~4

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION II

101 MARIETTASTREET, N.W., SUITE 2900

ATLANTA,GEORGIA 303234199

Report No.:

50-400/95-02

Licensee:

Carolina

Power

and Light Company

P. 0.

8ox 1551

Raleigh,

NC 27602

Docket No.:

50-400

Facility Name:

Harris

1

Inspection

Conducted:

January

7 - February 4,

1995

Inspectors:

S.

1 od, Senior Resi

'nt

spector

License No.:

NPF-63

Da e Signed

D. Roberts,

Residen

nsp

tor

Approved by:

H

ristensen,

Section

ie

Reactor Projects

Section

1A

Division of Reactor Projects

Date Signed

Da e

igned

SUMMARY

Scope:

This routine inspection

was conducted

by two resident

inspectors

in the areas

of plant operations,

review of nonconformance

reports,

followup of onsite

events,

maintenance

observation,

surveillance observation,

design

changes

and

modifications, plant housekeeping,

radiological controls, security,

and fire

protection.

Numerous facility tours were conducted

and facility operations

observed.

Backshifts tours

and observations

were conducted

on January

13,

16,

19,

21,

and 22,

and February 4,

1995.

Results:

0 erational

Safet

Control

room operations

and turnovers

were professionally conducted.

Operator

response

to annunciators

was observed to be thorough

(paragraph

3.b).

A diligent Shift Technical Advisor identified that the plant might be

outside

a Technical Specification Limiting Condition for Operation

and

operators

responded

properly to the information (paragraph 3.b).

9503090229

950302

PDR

ADOCK 05000400

6

PDR

Maintenance

Maintenance activities observed

were well planned

and executed

(paragraph

4.a).

One maintenance

program inconsistency

related to mandatory

gC hold

points for permanent

safety-related

wire lugs but not temporary

ones

(paragraph 4.a).

Surveillance

performance

was satisfactory with proper

use of calibrated

test equipment,

necessary

communications

being established,

proper

notification/authorization of control

room personnel,

and knowledgeable

personnel

performing the tasks

(paragraph

4.b).

Violation 95-002-01

was identified for failure to adequately test motor-

operated

valve thermal overload protection per

TS 4.8.4.2

(paragraph

3.b.(1)).

En ineerin

Activities

Violation 95-002-01

was caused

in part by previously inadequate

technical

reviews.

Auxiliary feedwater valve motor thermal

overload

bypasses

not being reasonably testable

per the

TS continued over

a

period of years

because

of failure to include the test switches in the

design

(even though previously-purchased

motor control centers

included

test switches).

This was coupled with inadequate

evaluation of

requirements

when this situation

was identified in 1989,

and continued

inadequate

evaluation in 1995,

when it was identified again

(paragraphs

3.b.(1)

and 5).

Plant

Su

ort

Plant support activities were adequate

(paragraph

6).

REPORT DETAILS

PERSONS

CONTACTED

Licensee

Employees

  • D. Batton,

Manager,

Work Control

D. Braund,

Manager,

Security

  • B. Christiansen,

Manager,

Maintenance

  • J. Collins, Manager,

Training

J.

Dobbs,

Manager,

Outages

  • J. Donahue,

General

Manager,

Harris Plant

R. Duncan,

Manager,

Technical

Support

  • M. Hamby,

Manager,

Regulatory Compliance

  • M. Hill, Manager,

Nuclear Assessment

  • D. McCarthy, Manager,

Regulatory Affairs

  • R. Prunty,

Manager,

Licensing

& Regulatory

Programs

W. Robinson,

Vice President,

Harris Plant

  • G. Rolfson,

Manager,

Harris Engineering

Support Services

  • H. Smith,

Manager,

Radwaste

Operation

B. White, Manager,

Environmental

and Radiation Control

A. Williams, Manager,

Operations

Other licensee

employees

contacted

included office, operations,

engineering,

maintenance,

chem'istry/radiation

and corporate

personnel.

NRC Personnel

H. Christensen,

Acting Branch Chief, Division of Reactor Projects,

NRC

Region II

  • S. Elrod, Senior Resident

Inspector,

Harris Plant

J.

Lenahan,

Reactor Inspector,

NRC Region II

C. Patterson,

Senior Resident

Inspector,

Brunswick Plant

R. Pichumani,

NRC Office of Nuclear Reactor Regulation

D. Roberts,

Resident

Inspector,

Harris Plant

R. Shewmaker,

NRC Office of Nuclear Materials Safety

8 Safeguards

NRC Contractors

R. Bryant,

Federal

Energy Regulatory

Commission

(FERC), Atlanta,

GA.

  • Attended exit interview

Acronyms

and initialisms used throughout this report are listed in the

last paragraph.

2.

PLANT STATUS AND ACTIVITIES

a.

The plant continued in power operation

(Mode 1) throughout this

period,

ending the period in day 87 of power operation

since

startup

on November 8,

1994.

b.

During this period, Hr.

C. Patterson,

Senior Resident

Inspector at

the Brunswick Plant,

was

on site

on January

17-18,

1995, for

familiarization.

Inspectors

at his site are back-ups for the

Harris inspectors.

His activities included familiarization tours,

badging,

and organizational

interviews with managers.

There will

be

no inspection report for this activity.

During this period, Hr.

R.

Shewmaker,

of the

NRC Office of Nuclear

Materials Safety

& Safeguards,

was

on site

on January

23-24,

1995,

to conduct

an auxiliary reservoir

dam inspection.

He was

accompanied

by Hr.

R.

Pichumani of the

NRC Office of Nuclear

Reactor Regulation,

Hr.

R. Bryant of the Federal

Energy Regulatory

Commission

(FERC) Office in Atlanta,

GA., and Hr. J.

Lenahan of

NRC Region II.

They intend to issue

a report in several

months-

after receipt of the

FERC evaluation report.

Hr. Lenahan

remained

at the site until January

27, additionally inspecting pipe

supports.

His results

were documented

in IR 400/95-01.

During this period,

Mr. H. Christensen,

Acting Branch Chief,

Division of Reactor Projects,

NRC Region II, visited the site

on

January

25-26,

1995.

His activities included plant tours,

interviews with licensee

management,

and review of resident

inspector activities

and resident office administration.

3.

OPERATIONS

a ~

Plant Operations

(71707)

The plant continued in power operation

(Mode 1) for the duration

of this inspection period.

(1)

Shift Logs and Facility Records

The inspector

reviewed records

and discussed

various entries

with operations

personnel

to verify compliance with the

TS

and the licensee's

administrative procedures.

The following

records

were reviewed in part:

shift supervisor's

log;

control operator's

log; night order book; equipment

inoperable record; active clearance

log; temporary

modification log; chemistry daily reports;

and shift

turnover checklist.

In addition, the inspector

independently verified clearance

order tagouts.

The inspectors

found the logs to be readable,

well

organized,

and to provide sufficient information on plant

status

and events.

Clearance

tagouts

were found to be

properly implemented.

No violations or deviations

were

identified in this area.

(2)

Facility Tours

and Observations

Throughout the inspection period,

the inspectors

toured the

facility to observe activities in progress.

Inspectors

made

some of these

observations

during backshifts.

Also, during

this inspection period, the inspectors

attended

several

licensee

meetings to observe

planning

and management

activities.

Facility tours

and observations

encompassed

the

following areas:

security perimeter fence; control

room;

emergency diesel

generator building; reactor auxiliary

building; waste processing

building; turbine building;

battery rooms; electrical

switchgear

rooms;

and the

technical

support center.

During these tours,

the inspectors

made observations

regarding monitoring instrumentation

- including equipment

operating status,

electrical

system lineup, reactor

operating

parameters,

and auxiliary equipment operating

parameters.

They verified indicated

parameters

to be per

the

TS for the current operational

mode.

The inspectors

also verified that operating shift staffing was in

accordance

with TS requirements

and that control

room

operations

were being conducted

in an orderly and

professional

manner.

The inspectors

additionally observed

shift turnovers

on various occasions

to verify the turnover

continuity of plant status,

operational

problems',

and other

pertinent plant information.

Licensee

performance

in these

areas

was satisfactory.

No violations or deviations

were

identified.

Onsite

Response

To Events

(93702)

(I)

On January

13,

a licensee

STA was reviewing 18-month

electrical

OSTs to ensure that

TS requirements

were met.

, This was

a follow-on action for a Fall,

1994,

TS violation

in the electrical surveillance

area.

During the review, the

STA perceived

an inadequacy

in the

OSTs that implement

TS 4.8.4.2,

"Motor-Operated Valves Thermal Overload

Protection", for six auxiliary feedwater valves.

The test

for these

valves verified actuation of the bypass relay but

did not seem to demonstrate

that the bypass relay contacts

actually bypassed

the thermal

overload contacts.

The

licensee

entered

the 8-hour action statement for TS 4.8.4.2

at 2:54 p.m.,

and

commenced

an intense

review of how to

satisfy the

TS by either testing these

valves or bypassing

the thermal

overloads

at power.

During this period,

the inspector reviewed the

TS and

determined that:

~

This licensee

had not obtained

a TS change,

announced

in 1987 in

GL 87-09, that addressed

how to respond to

the discovery that previous surveillance

actions

had

not been

accomplished

or were inadequate

on otherwise

normally-functioning systems.

That change would'have

given

a minimum of 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> to develop

and accomplish

considered

actions vice the present

8-hour limit in

the existing

TS action statement.

~

For the Harris plant, the basis for TS 4.0.3 stated

that action statements

are entered

at the time

a

surveillance

should

have

been

performed rather than at

the time it is discovered that they were not

performed.

Therefore,

discovering

a long standing

surveillance failure usually required finding that the

unit had already

exceeded

the

LCO.

Finding that the

unit had already

exceeded

the

LCO usually forced

some

extreme condition - perhaps

immediate

shutdown.

Following discussion

with the licensee,

the licensee

recognized

the implications of TS 4.0.3

and, at 7:20 p.m.,

declared

the unit to have previously exceeded

the

TS 4.8.4.2

8-hour action statement.

The licensee

entered

AFW system

TS 3.7. 1.2 action c,

and declared all three

AFW pumps to be

inoperable.

Such

a condition suspended

LCO 3.0.3

and all

other LCO-required actions requiring mode changes until one

pump was restored.

While continuing to review how to satisfy the

TS by testing

these

valves or bypassing

the thermal

overloads

at power,

the licensee

found objective evidence that:

These tests

had

been

reviewed

by licensee

persons

in

1989.

A condition

had

been identified where

one of the

steam-driven

AFW pump steam supply valves

had two

relays vice the one relay usually found,

and only one

of those

two relays

was being tested.

The condition was identified in 1989

as

a TS violation

and

LER 400/89-08

was issued.

NRC inspection reports

400/89-08

and 90-02 reviewed

the licensee-identified violation and the

LER, closing

them

as satisfactory.

5

The licensee

noted at that time that the relay testing

involved in the "violation" and the

LER was clearly testing

of relay actuation vice testing of correct performance of

each circuit operated

by individual relay contacts.

The

violation involved not testing all the relays of one valve

of the many valves that were being otherwise correctly

tested.

The licensee

concluded

now in January,

1995, that,

while a "better" way of testing the relays exists

and

has

been

used in many cases,

the present

way has

been evaluated

by both the licensee

and

NRC and found to be satisfactory.

At 11:35 p.m.,

on January

13, the licensee

exited the

LCOs

and resumed

normal operations.

Subsequent

NRC inspector,

Region II, and Headquarters

review

of TS 3/4.8.4.2,

"Motor-Operated Valves Thermal

Overload

Protection";

TS definition 1.38

"TRIP ACTUATING DEVICE

OPERATIONAL TEST"; and

TS definition 1.21

"OPERABLE-

OPERABILITY", found quite clear the requirement to

demonstrate

that the

MOV thermal

overloads

were actually

bypassed

under accident conditions

by an operable integral

bypass

device.

"TRIP ACTUATING DEVICE OPERATIONAL TEST" is defined

as

operating

the Trip Actuating Device [relay] and

verifying "OPERABILITY" of alarm, interlock and/or

trip functions.

"OPERABILITY" is defined,

in part,

as being capable of

performing its specified function(s).

~

The technical specification material

reviewed did not

imply that "cycling of the relay" was equivalent to

. "demonstrating operability of output functions".

The inspectors notified the licensee

on January

19 that the

NRC staff had determined that Harris was not meeting

TS

3/4.8.4.2,

"Motor-Operated Valves Thermal Overload

Protection".

The licensee

PNSC met on this issue

and,

following a Licensee

-

NRC Region II management

telephone

conference,

entered

the 8-hour action statement

for TS 3.8.4.2.

and proceeded

to install temporary modifications to

bypass

the thermal

overloads.

The modifications are

discussed

in paragraphs

4.a.

and 5.a.

The modifications

were completed

by ll:05 p.m.,

on January

19.

The licensee

then met the requirements

of the 8-hour action statement.

Failure to adequately test motor-operated

valve thermal

overload protection per

TS 4.8.4.2 is Violation

400/95-002-01,

"Inadequate

Testing of Motor-Operated

Valve

Thermal

Overload Protection".

On January

25, the licensee

found, through further review,

that three additional

thermal

overload devices

had not been

tested.

They immediately entered

LCO 3.8.4.2

and tested

them.

(2)

On February

2,

an operator

making rounds identified

a

lighted "Power Supply Failure" light on

a rod control

system

cabinet.

It was traced to a failed redundant

DC power

supply.

The licensee

responded

to the situation with

thoroughness

and

has subsequently

planned

an on-line repair,

including sending technicians

to the Westinghouse training

facility to practice

on, training equipment.

c.

Effectiveness

of Licensee

Control in Identifying, Resolving,

and

Preventing

Problems

(40500)

Adverse Condition and Feedback

Reports

(ACFRs) were reviewed to

verify that

TS were complied with, corrective actions

and generic

items were identified,

and items were reported

as required

by 10 CFR 50.73.

The

ACFR system

appeared

to be functioning well.

Many of the 347

items listed in January

were minor items, or feedback

items, or

not safety-related

or quality program related.

The licensee

has

encouraged

use of this program.

The listing of items with

assignments

and status

was easy to obtain,

making the program

appear fairly simple to manage.

During this period, control

room operations

and turnovers

were

professionally

conducted.

Operator

response

to annunciators

was

observed to be thorough.

A diligent STA identified that the plant might

be outside

a TS

LCO and operators

responded

properly to the information.

A diligent operator

found

a failed power supply in the rod control

system.

Violation 95-002-01

appeared

to be caused

by an inadequate

previous technical

review.

MAINTENANCE

Maintenance

Observation

(62703)

The inspector

observed/reviewed

maintenance activities to verify

that correct equipment clearances

were in effect; work requests

and fire prevention work permits were issued;

and

TS requirements

were being followed.

Maintenance

was observed

and work packages

were reviewed for the following maintenance activities:

~

WR/JO 95-AAWCI, WR/JO 95-AAWDI, WR/JO 95-AAMFI, "Temporary

Modification 95-00039,

Bypass the Thermal

Overloads for

Motor-Driven AFW Pump Valves

IAF 55, 74,

and 93".

~

WR/JO 95-AAWBI, WR/JO 95-AAWE1, WR/JO 95-AAWF1, "Temporary

Modification 95-00058,

Bypass the Thermal Overloads for

Turbine-DriVen AFW Pump Valves

lAF 137,

143,

and 149".

In general,

the work performance

was satisfactory with proper

documentation of removed

components

and independent verification

of the reinstallation.

During the manufacture

and installation of the jumpers bypassing

the thermal

overloads,

lugs were crimped onto the jumper wires.

The inspector

had just reviewed

an

ACFR on another

system stating

that, contrary to site procedures,

shop personnel

were crimping

lugs without gC inspectors

witnessing.

There were

no

gC

inspectors

present for this job either.

The licensee

explained

that procedure

MHM-01, Rev 7,

"Maintenance

Conduct of Operations",

required

gC witnessing only if the lug was permanent.

Subsequently,

having considered

the inspector's

concern that

temporary lugs sometimes

actually carry out

a safety function

defined in the TS, the licensee

decided to initiate

a procedure

change to MHM-Ol to require

gC inspection for all safety-related

lugs, whether temporary or permanent.

Maintenance activities observed

were well planned

and executed.

The inspector identified one maintenance

program inconsistency

related to mandatory

gC hold points.

No violations or deviations

were identified.

Surveillance

Obser vation (61726)

Inspectors

observed

and reviewed surveillance tests to verify that

approved

procedures

were being used; qualified personnel

were

conducting the tests;

tests

were adequate

to verify equipment

operability; calibrated

equipment

was utilized;

and

TS

requirements

were followed.

The following tests

were observed

and/or data reviewed:

OST-1214, "Auxiliary Feedwater

Pump

IX-SAB Operability Test,

quarterly Interval."

The inspector

observed

the turbine-

driven

AFW pump being tested

on January

10 as part of a

continuing effort to troubleshoot

the cause of overspeed

events

from 1994.

The inspector

observed that the

pump

operated

smoothly

and that the system engineer

and operators

were diligently monitoring its performance.

Following a

troubleshooting

run, during which

a test recorder

was

installed to monitor various

pump performance

parameters,

the

pump was started

again in accordance

with portions of

the surveillance

procedure to verify its operability.

OST-1107,

"ECCS Flow Path

and Piping Filled Verification,

Monthly Interval."

This procedure satisfied monthly

requirements

contained

in TS 4.5.2.b.l

and

TS 4.5.2.b.2.

On January

12, the inspector

observed

the portion of this

procedure

which verified that the

ECCS piping was full of

water (void of air/gas pockets).

Operators

accomplished

this by installing

a test rig (consisting of a hose

and

water jug) at various high point vents

on

ECCS piping,

and

opening

system vent valves to allow water flow.

The

procedure

was performed within days of a modification which

replaced traditional vent pipe caps in the high and low head

safety injection systems with 3/8-inch diameter quick

disconnect

plugs.

These

new plugs facilitated quicker

installation

and removal of the test rig and lower

radiological

exposure to the operators

performing the job.

The inspector

observed that the operators

performed the job

in accordance

with the procedure

and that water flow from

the system vents

was evident.

The inspector considered

the

presence

of an

HP technician

who monitored the

new vent

plugs for unanticipated

leakage

hazards

to be beneficial

as

well.

~

FPT-3550,

"Fire Protection

Seal

Visual Inspection

18-month

Interval."

On January ll, the inspectors

observed

technicians

inspecting the control

room complex main

termination cabinets.

This inspection

was performed

on

cabinets for both safety

and non-safety related

cables

which

penetrated

the main control

complex from the cable spreading

area located at lower elevations.

The procedure

was

performed mainly to inspect the integrity of the cable

penetration fire protection seals.

While observing the work

performed

by the technicians,

the inspectors

observed

the

poor material condition of several

resistors

(mounted

on

terminal blocks) in Termination Cabinet

10B-SB (safety-

related),

and Termination Cabinet

13 (non-safety).

Several

resistors

had cracked covers, discoloration,

charred

edges,

or ends touching adjacent resistors.

The inspectors

asked

plant personnel

to investigate

the function of these

resistors

and their apparently heat-related

damage.

Licensee

personnel

initiated ACFR 95-00091 for these

cabinets with an initial assessment

of "potentially

inoperable" to facilitate an immediate investigation.

The performance of these

procedures

was found to be satisfactory

with proper

use of calibrated test equipment,

necessary

communications

established,

notification/authorization of control

room personnel,

and knowledgeable

personnel

having performed the

tasks.

No violations or deviations

were identified while

observing the surveillances

addressed

above.

Violation

400/95-002-01,

which is discussed

in paragraph

3.b. 1, applies to

the surveillance

area.

ENGINEERING

a 0

Onsite Engineering

- Design/Installation/Testing

of Modifications

(37551)

The inspectors

reviewed

ESRs involving the installation of new or

modified systems

to verify that the changes

were reviewed

and

approved

in accordance

with 10 CFR 50.59; that the changes

were

performed in accordance

with technically adequate

and approved

procedures;

that subsequent

testing

and test results either met

approved

acceptance

criteria or deviations

were resolved in an

acceptable

manner;

and that appropriate

drawings

and facility

procedures

were revised

as necessary.

ESRs documenting

engineering

evaluations

were also reviewed.

The, following

engineering

evaluations,

modifications and/or testing in progress

were inspected.

~

ESR 9500058,

"DC circuit jumpers for AFW valves".

~

ESR 9500039,

"AC circuit jumpers for AFW Valves".

No violations or deviations

were identified regarding these

ESRs.

The condition described

in paragraph 3.b.,

where the auxiliary

feedwater valve motor thermal

overload

bypasses

were not

reasonably

testable

per the TS, occurred

and continued

because

of

failure to include the test switches in the design

(even though

previously-purchased

motor control centers

included test switches)

coupled with inadequate

evaluation of requirements

when this was

identified in 1989,

and continued

inadequate

evaluation in 1995,

when it was identified again.

PLANT SUPPORT

a 0

Plant Housekeeping

Conditions

(71707)

- Storage of material

and

components,

and cleanliness

conditions of various areas

throughout

the facility were observed to determine whether safety and/or fire

hazards

existed.

b.

Radiological Protection

Program

(71750)

- Radiation protection

control activities were observed to verify that these activities

were in conformance with the facility policies

and procedures,

and

in compliance with regulatory requirements.

The inspectors

also

verified that selected

doors which controlled access

to very high

radiation areas

were appropriately locked.

Radiological postings

were likewise spot checked for adequacy.

The licensee identified

a weakness

in communications

between

various plant organizations

regarding control of incore detectors

when persons

were in the area.

No unplanned

exposures

occurred,

but the licensee

is pursuing this matter.

The inspector discussed

this issue with the

NRC Region II Facilities Radiation Protection Section.

10

C.

d.

e.

Security Control

(71750)

- The performance of various shifts of

the security force was observed

in the conduct of daily activities

which included:

protected

and vital area

access

controls;

searching of personnel,

packages,

and vehicles;

badge

issuance

and

retrieval; escorting of visitors; patrols;

and compensatory

posts.

In addition, the inspector

observed

the operational

status of

closed circuit television monitors, the intrusion detection

system

in the central

and secondary

alarm stations,

protected

area

lighting, protected

and vital area barrier integrity,

and the

security organization interface with operations

and maintenance.

Fire Protection

(71750)

- Fire protection activities, staffing and

equipment

were observed to verify that fire brigade staffing was

appropriate

and that fire alarms,

extinguishing equipment,

actuating controls, fire fighting equipment,

emergency

equipment,

and fire barriers

were operable.

During plant tours,

areas

were

inspected

to ensure fire hazards

did not exist.

Emergency

Preparedness

(71750)

- Emergency

response facilities

were toured to verify availability for emergency operation.

Duty

rosters

were reviewed to verify appropriate

staffing levels were

maintained.

As applicable,

emergency

preparedness

exercises

and

drills were observed to verify response

personnel

were adequately

trained.

The inspectors

found plant housekeeping

and material condition of

components

to be satisfactory.

The licensee's

adherence

to radiological

controls, security controls, fire protection requirements,

emergency

preparedness

requirements

and

TS requirements

in these

areas

was

satisfactory.

No violations or deviations

were identified.

EXIT INTERVIEW (30703)

The inspectors

met with licensee

representatives

(denoted

in

paragraph

1) following the inspection

on March 1,

1995.

During this

meeting,

the inspectors

summarized

the scope

and findings of the

inspection

as they are detailed in this report, with particular emphasis

on the Violation addressed

below.

The licensee

representatives

acknowledged

the inspector's

comments

and did not identify as

proprietary

any of the materials

provided to or reviewed

by the

inspectors

during this inspection.

No dissenting

comments

from the

licensee

were received.

Item Number

Status

Descri tion and Reference

400/95-002-01

Open

VIO, Failure to adequately test

motor-operated

valve thermal

overload protection per

TS 4.8.4.2,

paragraph 3.b.(l).

ACRONYMS AND INITIALISMS

ACFR

AFD

AFW

CFR

CSIP

DEHC

ECCS

ESFAS-

ESR

FERC

FPT

GL

IR

LCO

LER

MCC

MMM

MOV

NAD

NED

NPF

NRC

OST

PCR

PNSC

QC

0PTR

RAB

RCS

RHR

STA.

TDAFW-

TS

VAC

VDC

WR/JO-

Adverse Condition and

Feedback

Report

Axial Flux Difference

Auxiliary Feedwater

Code of Federal

Regulations

Charging Safety Injection

Pump

Digital Electro-Hydraulic Control

Emergency

Core Cooling System

Engineered

Safety Feature Actuation Sy

Engineering Service

Request

Federal

Energy Regulatory

Commission

Fire Protection Test

[NRC] Generic Letter

[NRC] Inspection

Report

Limiting Condition for Operation

Licensee

Event Report

Motor Control Center

Maintenance

Management

Manual

Motor-Operated

Valve

Nuclear Assessment

Department

Nuclear Engineering

Department

Nuclear Production Facility [a type of

Nuclear Regulatory

Commission

Operations

Surveillance Test

Plant

Change

Request

Plant Nuclear Safety Committee

guality Control

quadrant

Power Tilt Ratio

Reactor Auxiliary Building

Reactor Coolant System

Residual

Heat

Removal

Shift Technical Advisor

Turbine Driven Auxiliary Feedwater

Technical Specification

Volts Alternating Current

Volts Direct Current

Work Request/Job

Order

stem

license]