Amend 34 to License NPF-63,revising TS 3/4.6.3,containment Isolation Valves,By Adding Statement to LCO
ML18010A913
Person / Time
Site: Harris 
(NPF-063)
Issue date: 11/17/1992
From: Adensam E
Office of Nuclear Reactor Regulation
To:
Shared Package
ML18010A914 List:
References
GL-91-008, NPF-63-A-034 NUDOCS 9211230331
Download: ML18010A913 (4)


Text

~

~p,g REgy~

~Q

~p

+c O

Vlp Cy Cy o~

t7 ++*++

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555 CAROLINA POWER

& LIGHT COMPANY et al.

DOCKET NO. 50-400 SHEARON HARRIS NUCLEAR POWER PLANT UNIT 1

AMENDMENT TO FACILITY OPERATING LICENSE Amendment No. q4 License No.

NP7-63 1.

The Nuclear Regulatory Commission (the Commission) has found that:

A.

The application for amendment by Carolina Power

& Light Company, (the licensee),

dated July 26,

1991, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act),

and the Commission's rules and regulations set forth in 10 CFR Chapter I;

8.

The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C,

There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; D.

The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E.

The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.

2. Accordingly, the license is amended by changes to the Technical Specifications, as indicated in the attachment to this license amendment; and paragraph 2.C.(2) of Facility Operating License No.

NPF-63 is hereby amended to read as follows:

9211230331 921117 PDR ADDCK 05000400 P

PDR

(2)

Technical S ecifications and Environmental Protection Plan The Technical Specifications contained in Appendix A, and the Environmental Protection Plan contained in Appendix B, both of which are attached

hereto, as revised through Amendment No. qq, are hereby incorporated into this license.

Carolina Power

& t.lght Company shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.

3. This license amendment is effective as of the date of its issuance and shall be implemented within 60 days of issuance.

FOR THE NUCLEAR REGULATORY COMMISSION

Attachment:

Changes to the Technical Specifications Date of Issuance:

November 17, 1992 Elinor G. Adensam, Director Project Directorate II-I Division of Reactor Projects I/II Office of Nuclear Reactor Regulation

ATTACHMENT TO LICENSE AMENDMENT N FACILITY OPERATING LICENSE NO.

NP F-63 DOCKET NO. 50-400 Replace the following page of the Appendix A Technical Specifications with the enclosed page.

The revised areas are indicated by marginal lines.

Remove Pa es 3/4 6-14 Insert Pa es 3/4 6-14

1 ~

CONTAINMENT SYSTEMS 3/4.6.3

-CONTAINMENT ISOLATION VALVES LIMITING CONDITION FOR OPERATION 3.6.3 Each containment isolation valve specified in the Technical Specification Equipment List Program, plant procedure PLP-106, shall be OPERABLE with isolation times less than or equal to required isolation times.

APPLICABILITY:

MODES 1, 2, 3, and 4.

ACTION:

With one or more of the containment isolation valve(s) inoperable, maintain at least one isolation valve OPERABLE in each affected penetration that is open and:

a ~

Restore the inoperable valve(s} to OPERABLE status within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />, or b.

Isolate each affected penetration within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> by use of at least one deactivated automatic valve secured in the isolation position, or c.

Isolate each'affected penetration within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> by use of at least one closed manual valve or blind flange, or d.

Be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.

e.

The provisions of Specification 3.0.4 are not applicable.

SURVEILLANCE RE UIREMENTS 4.6.3.1 Each isolation valve shall be demonstrated OPERABLE prior to returning the valve to service after maintenance, repair or replacement work is performed on the valve or its associated

actuator, control or power circuit by performance of a cycling test, and verification of isolation time.

'I SHEARON HARRIS - UNIT 1

3/4 6"14 Amendment No.