ML18010A639

From kanterella
Jump to navigation Jump to search
Insp Rept 50-400/92-06 on 920406-10.No Violations or Deviations Identified.Major Areas Inspected:Program Developed in Response to GL 89-10, Safety-Related MOV Testing & Surveillance
ML18010A639
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 04/30/1992
From: Schnebli G, Casey Smith, Taylor P
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML18010A638 List:
References
50-400-92-06, 50-400-92-6, GL-89-10, NUDOCS 9205190151
Download: ML18010A639 (28)


See also: IR 05000400/1992006

Text

~p,S IlEQII,

(4

fp.

~4

0

ce

nO

g

ce

4~

~O

+>>*++

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION II

101 MARIETTASTREET, N.W.

ATLANTA,GEORGIA 30323

Report No.. 50-400/92-06

Licensee:

Carolina Power and Light Company

P. O. Box 1551

Raleigh, NC 27602

- Docket No. 50-400

Facility Name:

Harris

1

License No. NPF-63

Inspection Conducted:

April 6-10, 1992

Lead Inspector:

P. Taylor

Inspectors:

.

C. Smith

Date Signed

C

DaeSi

d

+~G.

c

ebli

Others Contributing to This Inspection:

Date Signed

R. Cain, Idaho National Engineering Laboratory

Approved by:

F. Jape, Chief

Test Program Section

Engineering Branch

Division of Reactor Safety

Date Signed

SUMMARY

Scope:

This special, announced inspection examined the program developed in response to

NRC Generic Letter (GL) 89-10, "Safety-Related Motor Operated Valve Testing and

Surveillance."

The inspection was conducted

in accordance

with NRC Temporary

Instruction 2515/109, issued January 14, 1991.

9205190151

920506

PDR

ADOCK 05000400

8

PDR

Results:

In the areas inspected, violations or deviations were not identified.

The inspectors determined that the GL 89-10 MOV program was satisfactory at the

current stage of development.

Concerns were identified in some of the MOVprogram

areas.

The MOV program was also found to contain strengths.

The concerns identified involved licensee MOV program documents whose adequacy

willrequire further review.

In addition concerns similar to these are largely the result

of technological uncertainties regarding the predictability of MOV operation..These

uncertainties

should

be resolved

as

MOV data

is disseminated

throughout the

industry. The concerns and strengths identified for the Harris MOVprogram are listed

below:

CONCERNS

(1)

Present commitments require DP-Flow testing MOVs where practicable.

CPL

letter dated June 6, 1991 and discussions with engineers responsible for the

program indicate that selected

MOVs may not be in-situ tested

that are

practicable to be tested.

If MOV testing is discontinued the NRC should be

notified and technical justification provided (paragraph 3d).

(2)

The rate of loading effects had not been addressed

in MOV sizing and thrust

calculations.

Industry tests

have

shown

rate

of loading to yield non-

conservative

(ie lower) thrust values.

The rate of loading is planned to be

evaluated for those MOVs that are DP-flow tested.

Appropriate evaluation of

rate of loading should be documented for all MOVs in the program.

It is not

clear at this time what DP range will bound the rate of loading phenomenon

(paragraph 3c).

(3)

Static tests are planned during periodic testing to demonstrated MOVcapability

to perform under design basis conditions. It is not clear that static testing can

demonstrate

design basis capability because of the uncertainties between the

performance of MOVs under static and design conditions.

The licensee will

need to justify that the present periodic test methodology will demonstrate

MOV operability at design basis conditions (paragraph 3e).

(4)

MOV program procedures

do not require that "as found" periodic test

be

perform prior to conducting

any MOV preventive

maintenance.

This is

necessary

in order to properly evaluated existing MOV conditions, trends and

degradation

(paragraph 3e)

~

3

Other program procedures that are being changed and will require further NRC

review are:, TMM-406, Changes that will strengthen

the MOV operability

evaluations and onsite re'views of test results; PM-I0043, Changes that will

identify the use of equipment data base system'for torque switches and for

lirriit:switches in procedure

CM-l002 and changes

to PLP-112 which will

describe MOV test program activities and responsibilities (paragraph

3d and

3e).

(5)

The licensee, took exception to GL 89-10 recommendation

regarding MOV

mispositioning in their letter dated June 6, 1991.

The final disposition of this

" item remains to be determined and is under review by the NRC (paragraph 3a).

(6)

The

licensee

is using

a 0.40

locked

rotor power factor for AC MOV

calculations.

Higher locked rotor power factors have recently been published

by Limitorque.

The licensee should address the effects that the new power

factors have on MOV calculations

and corrections

applied as appropriate.

(paragraph 3.b).

STRENGTHS:

Engineers

responsible

for the

MOV programs

were

found

to

be

very

knowledgeable regarding ongoing MOV issues and state-of-the 'art regarding

diagnostic systems.

(2)

Involvement in industry groups is extensive, sometimes

in a leadership role.

(3)

The extend to which DP-flow testing has already been corn'pleted

and the

priorities and resources given to testing MOVs at the Harris Plant,

(4)

The programs that are in place for ensuring industry experiences

and vendor

information are incorporated into plant documents and training programs were

found to be very effective.

TABLE OF CONTENTS

Page

1.

BACKGROUND

.

~ .

~ ~ ..

~ .....

~ ,

~ .

~ ...=..

~ .

~ ..............

1

2.

INSPECTION PLAN .. ~.....

~ .'...........................

1

3.

PROGRAM AREAS INSPECTED AND FINDINGS......... ~........

2

a.

Scope of the Generic Letter Program..........

b.

Design-basis Review....... ~...

~ ~........

c.

MOV Switch Settings

~

~

~

~

0

~

~

~

~

~

~

~

~

~

~

~

~

~

~

~

d.

Design-basis Differential Pressure

and Flow Testing

e.

Periodic Verification of MOV Capability ... ~....

f.

MOV Failures, Corrective Actions, and Tending

g

Schedule.......

~ . ~........ ~....-......

h.

Overall Administration of MOVActivities.......

i ~

MOV Setpoint Control...

~ ~.............

~ .

J.

Training

o

~

~

~

~

~

~

~

~

~

~

~

~

~

~

~

~

~

~

~

~

~

~

~

~

~

~

~

~

k.

Industry Experience and Vendor Information.....

Use of Diagnostics .................. ~...

2

3

5

7

9

11

..12

12

13

~

14

14

16

4.

= EXIT INTERVIEW

~ . ~...... ~.......

~ .. ~......

APPENDIX 1 - PERSONS CONTACTED

~

~

~

~

~

~

~

~

~

~

~

~

1 7

~

~

~

~

~

~

~

~

~

~

~

e

1 8

REPORT DETAILS

NRC Inspection of the Program Developed in Response to Generic Letter 89-10 at

the Harris Facility

Background

Generic Letter (GL) 89-10, Safety-Related

Motor-Operated Valve Testing and

Surveillance,

was

issued

June 28,

1989

and

requested

licensees

and

construction

permit holders to establish

a program to ensure that switch

settings for safety-related

motor-operated

valves (MOVs) and certain other

MOVs in safety-related

systems

are selected,

set and maintained properly.

Supplement

1 to GL 89-10 was issued June 13, 1990 to provide the results of

those public workshops.

Supplement 2 to GL 89-10 issued August 3, 1990,

stated that inspections of programs developed in response to GL 89-10 would

not begin until January 1, 1991.

Supplement 3 to GL 89-10 was issued on

October 25, 1990 and requested that boiling water reactor licensees evaluate

the capability of MOVs used for containment isolation in several systems.

In

addition all licensees

and construction

permit holders should consider the

applicability of the information contained in Supplement 3 and should consider

this information in the development of priorities for implementing the generic

letter program.

The NRC staff requested licensees to submit a response to the generic letter by

December 28, 1989. Carolina Power and LightCompany submitted a response

to the generic letter for its Harris Facility on December 27, 1989 and June 6,

1991.

In those

response,

CP5L indicated that it planned

to meet the

recommendations

of the generic letter and would comply with the 5-year

schedule (completion by June 28, 1994) for the Harris Facility.

2.

Inspection Plan

The

NRC

inspectors

followed

Temporary

Instruction

(Tl)

2515/109

(January 14,

1991),

"Inspection

Requirements

for Generic Letter 89-10,

Safety-Related Motor-Operated Valve Testing and Surveillance," in performing

this inspection.

The inspection focused on Part

1 of the TI which involves a

review of the program being established

by the licensee

in response

to GL 89-10.

Part 2 of the Tl, which involves

a detailed

review of program

implementation, was not performed. Implementation was examined only where

this aided in evaluating the program.

Program Areas Inspected and Findings

a 0

C

Scope of the Generic Letter Program

The scope of GL 89-10 includes all safety-related MOVs and other MOVs

"that are position-changeable

in safety-related piping systems.

GL 89-10

Supplement

1 defined "position-changeable"

as any MOV in a safety-

related piping system

that can be inadvertently operated as a result of

an action in the control room.

The inspectors

reviewed

and discussed

the scope

of the GL 89-10

Program with licensee's

personnel

to ascertain

compliance with the

above GL recommendation.

The inspectors determined that the scope

of GL program consisted

of 116 MOVs.

Criteria used for selecting

- GL 89-.10 MOVs were delineated in Section 3.0 of Nuclear Engineering

Department Document No. Q9-MO-002, Revision 2. 'he licensee

in

their

response

dated

June 6,

1991,

stated

that

inadvertent

mispositioning of MOVs, initiated from the control room, in conjunction,

with an additional single active failure is beyond the current licensing

basis for CP&L plants..

The MOV program, therefore only considered

events that are within the current Iicensihg basis for Shearon

Harris

[Concern (5)].,

The inspectors. independently verified the accuracy of the GL program

scope by comparison of selected

MOVs shown on P&ID's with those

identified in the licensee's

GL 89-10 MOV List. The P&ID's used as the

basis for this review were the Component

Cooling Water System

(CCWS), Chemical and Volume Control System

(CVCS), Containment

Spray (CS) and Residual Heat Removal (RHR). Additional verification. of

the program scope was accomplished by reviewing selected

EOPs.

The

following EOPs

contained

required

operator

actions

for positioning

selected

MOVs during events.

These

MOVs were compared to the

licensee's

GL 89-10 MOV List to verify in'elusion in the program.

Procedure No. EOP-RPP-008,

SI Termination, Revision 4.

Procedure No. EOP-EPP-033,

Loss of AllAC Power Recovery with

Sl Required, Revision 4.

Procedure No. EOP-EPP-044.

Reactor Trip Response,

Revision 4.

All MOVs selected for review was determined to have been included in

the scope of the GL 89-10 Program.

No deficiencies were identified.

Design-Basis Reviews

Recommended

action

a

of

GL 89-10,

requests

the

review

and

documentation of the design basis for the operation of each MOV within

the

generic

letter program to determine

the

maximum differential

pressure

and flow (and

other factors)

expected

for both

normal

operations and abnormal conditions.

4

The inspectors reviewed the licensee's Motor Operated Valve Program

document

as

well as

other

documents

as

they

pertained

to the

development

of- design

basis'reviews.

Those

documents

included

09-MO-002;

"NED Scope

Document for work tasks

authorized

by

CPSL's Nuclear Facilities in response

to Generic Letter 89-10, Motor

Operated

Valves,"

(Rev; 2, May 31,

1991), AF-0029; ."Mechanical

Analysis and Calculations for 1AF-93," (Rev. 2, February 24, 1992), AF-

0031; "Mechanical, Analysis and Calculations for 1AF-143," (Rev.

1

January 31, 1992), Sl-0021; Mechanical Analysis and Calculation for

1CS-278," (Rev.-1 February 24, 1992), Sl-0023; "Mechanic'al Analysis

arid Calculations for 1SI-359," (Rev. 0, February 24, 1992).

Shearon Harris Nuclear Power Plant (SHNPP) determined the designbasis

differential pressure 'for each

MOV by reviewing their Final Safety

Analysis Report (FSAR), Design Basis Documents (DBDs), plant normal,

abnormal and emergency'perating

procedures.

Fluid temperature

and

'low were specified for design basis condition but was not included in

the review for determining the design basis differential pressure.

The

licensee engineers noted that there is no factor for flow or temperature

in the standard industry calculation forthrust. SHNPP intends to monitor

and record flow and temperature during the differential pressure test.

If

these parameters

are not the same as would be found during the actual

design basis differential pressure for which the MOV is designed, then

these

differences

would

have

to

be

reconciled

prior to

= the test

considered acceptable.

SHNPP used conservative assumptions

in determining their design basis

differential pressures.

In'ost'cases

pipe frictional losses

were not

included,

pumps

were considered

to be operating

at shutoff head,

elevational differences were not considered if it reduced the differential

pressure,

and the highest safety setpoint was used with the appropriate

amount of accumulation added to the setpoint.

However, the licensee

did not determine if valve mispositioning would cause the design basis

4

differential pressure to be larger.

SHNPP and CPSL stated

in their response letter to Generic Letter 89-10 (GL 89-10)

that valve mispositioning is beyond the design basis for

SHNPP'and

other CP8iL plants.

Valve mispositioning for

pressurized water reactor (PWRs) is currently under review

by the NRC staff.

SHNPP

reviewed

their documentation

on plant seismic

events

to

determine the'effects, if any, on MOV operation.

Licensee engineers

showed that seismic events for MOVs were considered

in the. original

.

design basis documents and the FSAR, and that these documents. would

bound any seismic event which could effect MOV performance.. The

inspectors discussed with licensee engineers the Limitorque Corporation

Technical

Update

¹92-01,

which

reviews

the

Kalsi

Engineering

Department '¹1707-C,. (Rev. 0, November 25, 1991).

The Limitorque

Updates included thrust rating increase for SMB-OOO, SMB-OO, SMB-O,

and

SMB-1 actuators

and section 4.5,included

seismic qualification

tests.

Licensee engineers indicated that the seismic qualification tests

and results were part of the thrust rating increase report and would'be

used when SHNPP used the study to increase actuator thrust ratings.

The inspectors did not identify any'actuators that had implemented the

Kalsi study during the inspection.

SHNPP performed-degraded

voltage calculations for each MOV in their.

program.

Documents

used for this analysis were, "Design Guide for

Electrical Evaluation of AC Power Motor-Operated

Valve." DG-V.67

(Rev. 2, April 1, 1992), "Design Guide for Electrical Evaluation of DC

Powered Motor-Operated Valves," DG-V.69 (Rev. 4, April 4, 1992), and

SHNPP

Design

Basis Document,

"Plant Electrical Systems,

Off Site

Power Systems, Generator, Exciter, Isolated Phase Bus Duct, Generator

and

Exciter Mechanical

Support

System,"

DED No. 202

(Rev.

0,

January 12, 1987).

The purpose of the calculations were to determine

the starting terminal voltage at degraded grid and accident

temperature'onditions

for MOVs in the program. These voltages were then used to

determine the amount of torque the MOV motor is capable of developing

during design

basis

conditions.

SHNPP

considered

elevated

cable

temperatures

by determining

what compartments

the cable

passed

through

and

then

used

the

worst

case

temperatuie

(highest

temperatures) for that compartment and applied it to the entire length of

the, cable.

Cable lengths and thermal overload (TOL) resistances

were

used in the calculations with a assumed

MOV starting power factor of

0.40 at locked rotor as recommended

by Limitorque.

The inspectors determine that Limitorque had recently published higher

locked rotor power factors than the 0.40 value

used

in electrical

calculations of AC MOVs. The licensee indicated that they were aware

of the new locked rotor power factors recommended

(telecon P. Taylor

Rll and 'M. Pugh, Nuclear Engineering Department April 30, 1992) by

Limitorque and were evaluating the information.

The incorporation of

Limitorque recommendations

in to design

guide

DG V.67, Electrical

Evaluation of AC Power MOVs will be reviewed during a subsequent

inspection [Concern (6)).

SHNPP

utilized TOL devices

to protect their MOVs during normal

operation.

However, during a safety system actuation SHNPP bypasses

their thermal overloads.

This was based

on the recommendations

of

Regulatory Guide 1.106.

The selection criteria for normal operation

included,

but was not limited to, ambient temperature

differences

between the MOV and the motor starter, motor full load amps, motor

service factor, relay trip time, and valve stroke time requirements.

Licensee personnel'were familiar with the possible degraded AC and DC

motor torque output due to MOVs being

located

in high ambient

temperature.

For DC MOVs, the licensee had used the recommendations

of Limitorque. For AC MOVs, the licensee had developed an on site plan

to be used.

The SHNPP plan reviewed plant documentation

in order to

determine the highest ambient temperature that will be seen by a given

MOV. Motor resistances

are recalculated based on the highest ambient

temperature.

With these new resistance values, licensee personnel then

recalculated the available AC motor torque.

Licensee engineers plan to

review Limitorque's high ambient temperature

findings when

made

available and will determine which method would best envelop their

MOVs.

SHNPP had reviewed the Generic Letter 89-10 issues concerning design

basis operating conditions for MOVs in their program.

The inspectors

concluded the licensee

had adequately

addressed

the area of design

basis

reviews

and

it

appeared

to

be

consistent

with

the

recommendations

of GL 89-10.

MOV Switch Settings

Recommended

action b of Generic Letter 89-10, requests licensees to

review, and to revise as necessary, the methods for selecting and setting

all MOV switches. (i.e., torque, torque bypass, limit, thermal overload)

6

The inspectors reviewed the licensee's documents for MOV sizing and.

switch

settings.

These

documents

included,

"Design

Guide

for

Limitorque Motor-Operated Valve Mechanical Evaluations," Design Guide.

DG-1.11,

(Rev. 4,

February 3,

1992)

and

calculations:

AF-0029;

"Mechanical

Analysis

and

Calculations

for

1AF-93,"

(Rev.

2,

February 24, 1992), AF-0031; "Mechanical Analysis and Calculations for

1AF-143," (Rev. 1, January 31, 1992), SI-0021; "Mechanical Analysis

and Calculations for 1SI-340," (Rev: 0, February 24, 1992) CS-0007;

"Mechanical

Analysis

and

Calculation

for

1CS-210,"

(Rev. -1,

January 28, 1992), CS-0016;.Mechanical

Analysis and Calculation for

1CS-278," (Rev. 1, February 24, 1992), SI-0023; "Mechanical Analysis

'nd

Calculation for 1SI-359," (Rev. 0, February 24, 1992). The licensee

had 116 MOVs in their program.

Of these 116 MOVs, 36 calculations

had been completed and undergone internal review.

The remaining 80-

calculations werestill considered to be in draft form until the internal

review had been completed.

The licensee's

engineers

performed the MOV calculations

using the

standard

industry equations for determining minimum required valve

thrust and torque.

For added conservatism,

SHNPP used a valve stem

coefficient of friction (COF) of 0.20 for calculating the minimum required

thrust value and a value of 0.15 to determine the maximum thrust valve.

SHNPP intends to verify their assumption

of COF through their test

program.

The licensee used a valve factor (VF) of 0.40 for gate valves

. and the mean

seat

diameter

in their MOV sizing calculations.

An-

exception to this methodology was with Westinghouse supplied valves.

Westinghouse supplied valve factors to SHNPP for We'stinghouse valves

which varied from 0.485 to 0.55. After reviewing industry data, SHNPP

engineers considered

a VF of 0.40 to be the average from the industry

data available to date.

A VF of 1.1 was used for globe valves.

The

licensee is planning to use the test results from insitu testing to validated

MOV calculation assumptions.

A margin of 15% is added

to the

minimum

required

thrust

to

account

for

diagnostic

equipment

inaccuracies

and torque switch repeatability.

The maximum actuator

thrust and torque rating is reduced by 10% to account for inertial effects

and diagnostic inaccuracies.

The inspectors noted that the 10% margin

may not be sufficient to bound diagnostic equipment inaccuracies, inertia

effects, and torque switch repeatability. The latest Limitorque Technical

Update (92-01) extending actuator thrust ratings.

Licensee engineers

stated, they would consider these effects if.they used the extended

thrust ratings for their actuators.

7

SHNPP replaces, or installs limiter plates. on their MOVs.

This action

is specified

in their procedures

RM-10020,

Rev. 3, and CM-10002, Rev. 4.

When it is necessary

to

increase the torque switch setting greater than the vendor

recommended

maximum, a design change notice (DCN) or

similar document is issued and an appropriate engineering

analysis

is performed.

The analysis

would considered

spring pack capability, degraded voltage performance, and

other factors to ensure

maximum actuator

torque

and

thrust rating was not exceeded.

'A new limiter plate would

be ordered and installed.

SHNPP bypasses

the open torque switch for the MOVs.

The open

torque switch is placed back in service above the open limit switch

setpoint as a safety-feature

in case of limitswitch failure. Valves which

utilize the torque switch in the close direction have their torque switches

bypassed for 96% of travel and then the torque switch is placed in the

circuit for the last 4% of valve travel to ensure seating.

The licensee

had a very small population of valves which used the closed limitswitch

to stop motor operation.

The inspectors questioned the licensee if any

of their valves which used

the closed

limit switch to stop

motor

operation also had specified criteria for leakage.

The licensee responded

that- they did have some limit-close valves which do have specified

leakage criteria. However, licensee personnel stated that all the valves

which limit close and have specified

leaka'ge

criteria are of the

SB

actuator type which utilizes an additional compensating

spring.

This

compensating spring allows setting of the limitswitch setpoint to ensure

hard seating of the valve has been accomplished.

SHNPP has investigated

the phenomena

of "rate of loading" (ROL).

SHNPP described this phenomena

as the difference in the value of thrust

indicated at torque switch trip under static conditions as compared to

the thrust value at torque switch trip under dynamic conditions.

SHNPP

personnel

stated

this phenomena

has

not been

observed

on site,

although the existence of ROL has been proven in several industry tests.

SHNPP plans to use the results of their diagnostic testing to determine

where

the condition applies

at their plant,

and to take

actioh

as

appropriate.

The inspectors were concerned that without a margin set

aside in the calculations forunknown phenomena,

such as ROL, torque

switch settings may be set non-conservatively.

This could lead to valves

failing to operate

under design basis conditions.

Further, for valves

which cannot practicably be tested

in situ at design basis conditions,

SHNPP did not have in place a method to account for ROL that these

valves could experience.

Margins assigned

for unknown phenomena

8

based on dynamic test results should be included in the calculations for

these valves to ensure that torque switches are set conservatively and

to ensure that valves will function under design ba'sis conditions.

This

area will be reviewed during a future inspection [Concern (2)].

Design Basis Differential Pressure

and Flow Testing

Recommended

action c of the generic letter, requests licensees 'to test-

MOVs within the generic letter program in situ under their design-basis

differential pressure

and flow conditions.

If testing in situ under those

conditions is,not practicable, the staff allows alternate methods to be

used to demonstrate the-capability of the MOV. A two-stage approach

is suggested

for situations

where design-basis

testing

in situ is not

practicable and, at this time, an alternate method of demonstrating MOV

. capability cannot be justified. With the two-stage approach,

a licensee

would evaluate the capability of the MOV using the best data available

and then would work to obtain applicable test data within the schedule

of the generic letter.

CPSL MOV Program Plan (Q9-MO-001, Q9-MO-'002) and letters dated

December 27, 1989 and June 6, 1991 commit to in situ testing MOVs

under design basis conditions where practicable and baseline tests (static

conditions) of all MOVs in the program would also be performed.

The

June 6,

1991

CPSL

letter

indicated

that

a

preliminary review

is

underway which would delete MOV testing that are practicable to DP-

flow tests,

The exa'mples given were small gate and globe valves two

inches or less.

These would be grouped and a few of these MOV would

be differential pressure tested.

It is not clear how the licensee. will apply

tests

results to the similar non tested

MOVs in the group.

The

inspectors cautioned that the discontinuation of MOV testing that are

practicable

to test

is

a deviation from their present

commitment.

'herefore

NRC notification with appropriate technical justification should

be piovided. [Concern (1)].

The inspectors reviewed the following documents, which describes the

DP-flow testing program requirements and guidance:

Q9-MO-002,

Revision 2

dated,

May 31,

1991,

. NED

Scope

Document GL 89-10 MOVs Enclosure

1, MOV DP Test Program

Design

Guide

DG-1.12,

Revision

2 dated,

February 6,

1992,

Review and Reconciliation of MOV Diagnostic Tests

Technical Support Guide TSG-242, Revision 0 dated March 23,

1992,

Guidance

for Preparation

of MOV Engineering

Periodic

Tests

Technical Support Management

Manual, TMM-406 Revision

1

dated

January 28,

1992

Analysis

and

Trending

of

MOV

Performance

The inspectors found that the guidance provided in the aforemention

documents

address

MOV operability and

the

reconciliation of the

assumptions

(e.g

stem

factor,

valve factor)

used

in the

MOV's

torque/thrust calculations.

The SHNPP had performed in situ DP-flow

tests on 42 MOVs during refueling outage 3 (Spring 1991). The licensee

recently completed

the review and approval of the test results

and

reconciliation of torque/thrust calculation assumptions.

The inspectors

expressed

a concern with the significant length of time to complete the

review and approval of test results.

The licensee indicated that the

review/approval process would be completed in more timely manner.

In

addition the licensee

should consider

a more detailed review of test

results onsite by the Technical Support Group to ensure

MOV thrust

margins are adequate

and any MOV abnormality is addressed

prior to

returning the MOV/system to operation [Concern (4)].

Periodic Verification of MOV Capability

Recommended

action d of the generic letter, requests the preparation or

revision of procedures to ensure that adequate

MOVswitch settings are

determined and maintained throughout the life of the plant.

In Section

j of the generic letter, the staff recommends surveillance to confirm the

adequacy of the settings.

The interval of the surveillance is to be based

on the safety importance of the MOV as well as its maintenance

and

performance history, but is not to exceed 5 years or 3 refueling outages.

Further, the capability of the MOV is to Se verified if the MOV is

replaced,

modified, or overhauled to an extent that the existing test

results are not representative of the MOV.

The licensee's upper-tier program document number Q9-MO-001, GL 89-

10 MOV Program Specification, Revision 0, Section 11.0, established

requirements for'performing periodic diagnostic testing to identify MOV

degradations.

The frequency for performing periodic tests was given as

every 5 years or 3 RFO from the date of the initial baseline test or

differential test, whichever was performed later.

Site level procedures

numbers PLP-112, Motor Operated Valve Program; TMM-406, Analysis

and Trending of MOVPerformance and PM-I0043; Motor Operated Valve

'

10

Testing

and

Calibration,

collectively implement

these

requirements

delineated in the upper-tier program document. The inspectors identified

a

concern

with procedure

PLP-112

in that

the

program

controls

described

in paragraph

5.3 did not specifically address

periodic test

requirements.

Additional

programmatic

inadequacies

related

to

procedure

PM-10043,

paragraph 6.0 was identified.

The inspectors

determined that the Equipment D'ata Base System

(EDBS) will be the

source of design basis information involving torque switch and limit

switch settings.

Lower-tier site

level procedure

PM-I0043, which

implements

periodic test activities involving torque switch settings,

needs to be revised to reflect the use of EDBS in this activity. Similarly,

procedure CM-I0002, A.C. Limitorque Calibration. Check and Stroking

will be revised to require limit switch settings to be obtained from the

EDBS. These items are identified as concerns that will be reinspected in

future MOV inspections [Concern (4)].

Discussion

with licensee

engineering

personnel

revealed

that static

diagnostic testing would be performed periodically to reverify design

basis capability of the MOVs within GL 89-10 program scope.

The

inspectors informed licensee management that the use of static testing

to verify continued capability of an MOV to operate under worst case

differential pressure

and flow conditions was not considered adequate

at this time.

The reason given was the unknown relationship between

the performance of an MOV under static conditions and under design

conditions.

The'licensee

will be

expected

to provide

a technical

justification for whatever method

is used for periodic verification of

MOVs capabilities.

Additional NRC inspection of this area

will be

required in order to evaluate the verification method used [Concern (3)].

The licensee's GL 89-10 MOV Program has established requirements for

. post-maintenance

tests to be performed on MOVs following any type of

maintenance

on the'perator or valve. These requirements are specified

in Section 9.0 of upper-tier program document Q9-MO-001

and are

implemented via site level procedure number PLP-400, Post Maintenance

Testing, and CM-P0001, Post Maintenance Testing Requirements for

Limitorque Operated

Valves.

Post maintenance

test requirements for

MOVs have

been

established

and

provisions

have- been

made

for

incorporating

baseline

tested

MOVs into the

PM

program.

The

inspectors verified by review of objective evidence that selected MOVs,

that were baseline tested during RFO3, have been included in the PM

with a frequency for implementing PM activities that is consistent with

program

requirements.

Additionally, lubrication requirements

were

verified to have been established; and site level procedures developed for

implementing

these

requirements,

in

accordance

with

specified

11

frequencies

based

on plant operating

experience.

MOV program

procedures

do not require that "as found" periodic test be performed

prior to conducting any MOV PM's.

This is necessary

in order to

properly evaluate

existing MOV conditions, trends

and degradation

[Concer'n (4)].

The Licensee's

GL 89-10

MOV Program

does

not address

thermal

overloads

(TOLs).

The Licensee's

commitment to Regulatory Guide 1.106 is contained

in FSAR Section 7.3.1.5.1a

Amendment No. 40.

The TOLs and torque switches

are bypassed

under,DBA conditions.

Technical Specification Section 3.8.4.2, Motor Operated Valve Thermal

Overload Protection, specifies the surveillance required to demonstrate

operability.. Discussions with licensee's engineering personnel revealed

that TOLs ar'e sized in accordance

with guidance of IEEE 741-1990.

Surveillance requirements

are satisfied on an 18 month frequency by

implementing procedure OST-1074, Operations Surveillance Test MOV

TOL and Torque Switch Bypass Test.

No deficiencies were identified in

this area.

MOV Failures, Corrective Actions, and Trending

Recommended

action

h of the generic letter requests

that licensees

analyze

and justify each

MOV failure and corrective

action.

The

documentation should include the results and history of each as-found

deteriorated condition, malfunction, test, inspection, analysis, repair, or

alteration.

All documentation

should

be

retained

and

reported

in

accordance

with plant requirements.

It is also suggested

that the

material be periodically examined (every 2 years or after each refueling

outage after program implementation)

as part of the monitoring and

feedback effort to establish trends of MOV operability.

These trends

could provide the basis for a licensee revision of the testing frequency

established to verify periodically adequate

MOV capability. The generic

letter indicates that a well-structured and component-oriented system is

necessary to track, capture, and share equipment history data.

The inspectors reviewed the licensee's activities related to MOVfailures,

corrective actions, and trending.

The program requirements for these

elements

are. contained

in Technical

Support Management

Manual,

TMM-406, Analysis and Trending of MOV Performance.

MOV failures

are processed through the site normal work control system using Work

Requests

and Authorizations (WRSA's) and Adverse Condition Reports

(ACR's) as required to correct a problem.

MOV coordinators

are on

distribution for all WRRA as ACR's issued each day and the coordinators

track the open items on a computer data base for each MOV in the

12

program.

In addition, completed maintenance

packages

are reviewed

and kept on file by the coordinators to ensure the appropriate steps were

taken to correct the problem and to determine if the problem is isolated

or generic.

The inspectors

reviewed several files for MOV's in the

program and consider them to be an accurate,

up-to-date, machinery

history record for each valve. Since this facilityis relatively new and has

not encountered

many MOV failures, the records were readily available

for inclusion in'the machinery history records.

The

licensee's

program

requires

that

all WR&A be

reviewed

by

Engineering Support prior to work performance to ensure the proper post

maintenance

test record (PMTR) is identified and the correct planning

and procedures are specified.

In addition, the completed work package's

are

reviewed

by this

group to

ensure

the

correct root cause

is

documented, proper corrective actions were taken, and the proper PMTR

was performed.

Currently, the licensee

only trends MOV failures, however,

as more

diagnostic data becomes available additional parameters willbe trended.

TMM-406, Section 5.2, requires that MOV performance

be trended by

retention of t'est results from VOTES testing. Trends to be evaluated will

include, but not be limited to; increased or decreased

thrust values to

open or close a valve, increased or decrease motor current values.

The

inspectors reviewed the final annual MOVTrend Report dated March 23,

1992.

This report contains the failure history of the 177 valves in the

program from September

16,'1987, to date.

The inspectors considered

this report to be. very informative and will be a good basis for trending

and identification of geheric MOV failures.

The inspectors concluded that the licensee's current program for MOV

failures,

corrective action, and trending, in conjunction with planned

developments willprovide the necessary framework to monitor, identify,

and correct any adverse MOV performance.

Schedule

In GL 89-10, the staff requested that licensees complete all design-basis

reviews, analyses, verifications, tests, and inspections that were initiated

in order to satisfy the generic letter recommendations by June 28, 1994,

or 3 refueling outages after December 28, 1989, whichever is later.

The inspectors held discussions

with licensee personnel and reviewed

scheduled

MOV program activities to support

a completion date of

June 28,

1994.

The

Harris

MOV program

document

(PLP-112,

13

Revision

1 dated March 10, 1992) currently identified 116 MOVs to be

in the program. =Design basis reviews and torque/thrust calculations have

been completed for 55 MOVs. An additional'30 MOVs are scheduled to

have these activities completed by July 1992.

Baseline test and in situ

DP-flow test have been performed for.42 MOVs (refueling outage

3,

Spring 1991).

An additional 43 MOVs will be tested during refueling

outage 4 (Fall 1992) with the remaining MOVs being tested

during

refueling outage

5 (Spring 1994)

~

The inspectors concluded that the

licensee's current schedule commitments are achievable.

Overall Administration of MOV Activities

The Licensee's lower-tier program document, procedure PLP-112, Motor

Operated Valve Program, Revision 1, described the overall administrative

control of the GL 89-10 program.

Responsibility for coordinating the

implementation of the program has

been vested

with the Technical

Support Manager. Additionally, a dedicated staff of two engineers from

Technical Support-Engineering Support Section has been assigned to the

MOVprogram. Discussions with plant personnel revealed that they were

very knowledgeable of the issues involved in GL 89-10and were actively

addressing the issues toward an acceptable solution.

Based on review

of the MOVTask Force Meeting Minutes, the inspectors concluded that

the Licensee

had developed

a strong interface with industry groups.

Licensee

personnel

actively

participate

in industry

activities

in

a

leadership role.

Additionally, discussions with site personnel revealed.

that they were also involved with industry programs to keep current with

MOV activities

and

MOV diagnostic

equipment

technology.

The

inspectors

considered

these

aspects

of the licensee

program to be a

strength.

The overall administrative controls described

in site level procedure

PLP-112,

MOV

Program,

Revision 1,

was

considered

adequate.

Responsibilities have been assigned;

program requirements

have been

established; and lower-tier site level procedures have been developed to

ensure

performance

of

design

basis

reviews;

control

of

plant

modifications; control of maintenance activities; and control of analysis

and tending of MOVTest data.

Based on review of procedure PLP-112,

Paragraph 5.3

the

inspectors

determined

that

program

control

requirements

for performing periodic MOV tests

in accordance

with

approved site level procedure PM-I0043 have not been incorporated in

the

program description.

This issue

was discussed

with Licensee

personnel

and will be identified as

a concern to be evaluated

during

future NRC inspections.

MOV Setpoint Control

The inspectors found'that the licensee controls torque switch'settings

and

limit switch

settings

using

Nuclear

Engineering

Department

Guidelines E-51, Revision 0 dated November 15, 1991, Control of Safety

Related

MOV Switch Settings.

The information provided

by this

procedure

is available on the licensee's

Equipment Data Base System

(EDBS), Function 480 screen.

The values determined for thrust, 'torque

and limitswitch settings for each MOV in the program are maintained at

the plant.

The ranges established for torque and limit switch settings

can not be changed without the review and approval of the Nuclear

Engineering -Department.

Training

The inspectors reviewed the licensee's MOVtraining program, courses,

facilities, and held discussions with training personnel.

The training is

conducted by the Harris Energy and Environmental Center (ELEC) which

.conducts

MOV training for all three CP5L sites.

The E5EC utilizes a

mobile training classroom

equipped

with MOVs and diagnostic test

equipment which is taken to each specific site for hands-on-training.

The inspectors reviewed the training requirements and training material

for personnel

performing MOV maintenance

and diagnostic testing.

MOV maintenance

personnel are required to complete a 40 hour4.62963e-4 days <br />0.0111 hours <br />6.613757e-5 weeks <br />1.522e-5 months <br /> course

titled:

Motorized Valve Operators

- MN037G.

Personnel

performing

diagnostic testing are required to complete an additional 40 hour4.62963e-4 days <br />0.0111 hours <br />6.613757e-5 weeks <br />1.522e-5 months <br /> course

titled: Valve Operator Test and Evaluation System (VOTES) MN6C01G.

The inspectors

reviewed the outlines, lesson plans, and tests for the

MOV course.

Included in the formal classroom material are discussions

of MOV 'related industry problems contained

in SOERs,

SERs,

NRC

Bulletins, Notices, and LERs.

In addition to the personnel performing

MOV maintenance

and testing, the licensee has included electrical and

mechanical

planners,

Nuclear

Engineer

Department

engineers,

and

Technical Support Group engineers in the MOV training program.

The

MOVcoordinators and various Technical Support Group personnel, have

received vendor training from BSW on the VOTES system for'diagnostic

testing.

The

inspector

reviewed

the

training records

fo'r several

maintenance/engineering

personnel associated

with the MOV program

and

found them to -be

accurate

and

adequate.

Additionally, the

inspectors reviewed the MOV awareness

training for both licensed and

non-licensed operators and found the program,to be excellent.

15

In

summary,

the

inspectors

determined

that

the

licensee

has

a

comprehensive training program and methodology to ensure that all MOV

maintenance and diagnostic analysis is performed by qualified personnel.

k.

Industry Experience and Vendor Information

The licensee's

program for reviewing industry experience

is controlled

under

Administrative

Procedure,

AP-031,

Operating

Experience

Feedback.

This procedure

provides

guidance

on the

review

and

processing of operating experience feedback information received at the

plant, and prescribes the mechanisms to ensure that any recommended

action items are identified and tracked until resolved.

This procedure

requires the Regulatory Compliance staff to screen the following OEF

items for applicability to this site and/or feedback to other CPS.L sites:

Significant Adverse Condition Reports; Documents

routed from other

company

Regulatory

Compliance

Units

which

are

designated

as

potentially warranting

OEF;

INPO Significant Operating

Experience

Reports;

Significant

Event

Reports,

Significant-by-others

Reports,

Significant

Event

Notifications,

and

Operations

and

Maintenance

Reminders;

NRC information Notices; Nuclear Network Items deemed

appropriate; and other sources deemed appropriate for OEF (e.g., Nuclear

Safety Analysis Center Reports, NRC Office for Analysis and Evaluation

of Operational Data information, etc.).

The control of 10 CFR Part 21

is under Administrative Procedure,

AP-616, Evaluating and Reporting of Defects'nd

Noncompliance

in

Accordance

with

10 CFR 21

~

Administrative

Procedure,

AP-610,

Processing

Vendor Manuals and Vendor Information, establishes

the

requirements to control the receipt,-review, approval, distribution, and

revision of vendor technical manuals

and vendor training information.

Issues

in the above categories

are tracked both manually and on

a

computer data base to ensure the required actions are complete.

The

inspectors reviewed the current indices for OEF and 10 CFR 21 items

and selected the following for further review:

90-003, Limitorque-Motor Pinion Keyway (10 CFR 21)

90-010,

Limitorque-SMB 00 Torque

Switch

Roll

Pin

Failure

(10 CFR 21).89-015, Limitorque-Cam Type Torque Switches (10 CFR 21).89-001, Limitorque-Melamine Torque Switch (10 CFR 21).

16

89-005, Limitorque - Defective Torque Switch Assembly (10 CFR 21).87-176, Limitorque Motor Operated Failure Caused by Excessive

Grease in,Spring Pack (INPO SER 20-87).87-261, Valve Inoperability Due to Unbalanced Limitorque Torque

Switches (INPO SER 38-87).

I

86-209, Inaccurate Closed Position Indication on Motor Operated

Valves (INPO SOER 86-2).

0

84-173, Loosening of Locking Nut on Limitorque Operator (NRC

IN 84-36, Supplement

1) ~

'I

86-217,

Recent

Identified

Problems

with Limitorque

Motor

Operators

(NRC IN 86-71)

~

88-066,

Spring

Compensator

Housing

on

Limitorque

Valve

Operators (Westinghouse NDIS-TB-88-01).91-297,

Preliminary

Results

of Validation Testing

of MOV

Diagnostic Equipment (NRC IN 91-61).91-303,, Motor Operated

Valve Drift Due to Valve Actuator

Misadjustment (INPO ORMR 391).92-042,

Torque

Switch

Improperly Set

(ACR 91-316

from

Robinson Plant).

These

issues

were found to meet the requirements of the licensee's

programs and were included in appropriate procedures

or were in the

review process to determine corrective actions, as required.

In addition,

the

inspectors

determined

controls

were

in effect to

ensure

the

events/issues

were incorporated into licensee training materials.

In summary, the inspectors consider the licensee programs that'are in

place for ensuring

industry experience

and vendor information are

incorporated into appropriate training programs are very effective.

h

Use of Diagnostics

17

SHNPP was using the Votes diagnostic system for measuring thrust

during MOV initial set up and to monitor MOV thrust delivered during

insitu testing. Licensee personnel converted thrust values from the MOV

sizing and thrust calculations into torque values.

These torque values

were then used to set up the torque switch trip setpoint.

This was

accomplished

by using

a torque wrench which would compress

the

spring pack until a given torque was reached.

Once this torque was

accomplished the torque switch trip setpoint was adjusted to achieve

this value.

SHNPP

then

performed

a static test

using the Votes

diagnostic equipment to monitor the thrust developed.

This thrust value

's

monitored by the use of a strain gauge which is mounted on the yoke

of the valve. This strain gauge is calibrated using the Votes diagnostic

equipment.

The thrust value developed

had to be in between

the

minimum and maximum values of thrust as specified by the licensee's

calculations.

If the thrust required adjustment, the licensee would use

the torque wrench to adjust the torque switch trip setpoint and repeat

the static thrust test to ensure the adjustment fell within the required

thrust band.

The inspectors inquired as to how the licensee intended to

measure torque during insitu design basis testing.

Licensee engin'eers

stated that the torque setting based on spring pack displacement, should

not vary during static verses

dynamic testing.

The inspectors

were

concerned that without measuring torque during dynamic insitu testing,

the licensee could not detect "peak torque" which could result from

continued motor operation.

The continued motor operation would occur

due to the lag time between torque switch trip and the deenergization of

the motor control circuit.

Further, the stem coefficient of friction is

generally'higher. just at flow closure

(when the valve disc initially

contacts the valve seat) than at torque switch trip. The torque at flow

closure may differ from the torque at torque switch trip. Since the value

of torque at flow closure is used to. back calculate a stem coefficient of

friction, SHNPP may be introducing an error into their verification of the

stem coefficient of friction and masking their ability to observe

the'ffects

of ROL.

Also, the back calculated stem coefficient of friction

could change the available margin between the calculation upper thrust

window limit and the torque switch trip 'setpoint.-

This analysis

is

necessary

to verify the assumptions

used when performing the MOV

calculations.

However, licensee maintenance

personnel were involved

in purchasing

a device to measure

spring pack displacement

during

in situ design basis testing.

The inspectors will review how Shearon

Harris uses the device to measure spring pack displacement during in situ

design basis testing and how the data obtained from it is used during a

future inspection.

18

The inspectors noticed that SHNPP intended to permanently mount the

Votes strain gauges on their valve yokes. Also, SHNPP had used current

transformers to hook up their diagnostic equipment and these were left

permanently

installed.

This enabled

licensee

personnel

to hook up

diagnostic equipment easily and quickly, thereby reducing radiation dose

received to those involved in the testing.

This also enabled the licensee

to hook diagnostic equipment for retesting if any maintenance

had been

performed with'ease and a minimal amount of set-up time required. The

inspectors considered this to be a strength.

4.

Exit Interview

The inspection scope and all findings were summarized on April 10, 1992, with

those persons indicated in the Appendix 1.

The licensee was apprised of the

concerns identified during the inspection and listed in the "SUMMARY"at the

beginning of this report..

19

APPENDIX

PERSONS CONTACTED .

Licensee Employees

"E. Burkhead, Senior Instructor, Nuclear Training

"M. Grantham, Senior Engineer, Nuclear Engineering Department

"D. Hawley, Senior Engineer, Nuclear Assessment

Department

"T. Helms, Project Engineer, Nuclear Engineering Department

"P. Hicks, Electrical Engineer, Nuclear Engineering Department

C.,Hinnant, General Manager, Harris Plant

"D. Kanning, Senior Engineering Technical Support

"S. Mabe, Project Engineer, Nuclear Assessment

Department

"M. McDaniel, Mechanical Engineer, Nuclear Engineering Department

"J. Nevill, Manager, Technical Support

"C. Olexik, Manager, Regulatory Compliance

"M. Pugh, Project Engineer, Nuclear Engineer Department

"M. Verrilli, Senior Specialist, Regulatory Compliance

"L. Woods, Manager, System Engineering-

"G. Young, Engineer, Technical Support

"R. Zula, Manager, Engineering/Technical Support

NRC Personnel

"J: Tedrow, Senior Resident Inspector"

"M. Shannon,

Resident Inspector

"Attended Exit Interview

e