Forwards Insp Rept 50-400/89-31 on 891113-17.No Violations or Deviations Noted
ML18009A285
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 12/01/1989
From: Julian C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Eury L
CAROLINA POWER & LIGHT CO.
Shared Package
ML18009A286 List:
References
NUDOCS 8912110206
Download: ML18009A285 (4)


See also: IR 05000400/1989031

Text

ACCELERATED DISTRIBUTION DEMONSTRATION SYSTEM

REGULATORY INFORMATION DISTRIBUTION SYSTEM (RIDS)

CCESSION

NBR: 8912110206

.

DOC. DATE: 89/12/01

NOTARIZED: NO

FACIL:50-400'Shearon Harris Nuclear Power Plant, Unit 1, Carolina

AUTH.NAME

AUTHOR AFFILIATION

JULIAN,C.A.

~

Region 2, Ofc of the Director

RECIP.NAME

RECIPIENT AFFILIATION

EURY,L.W.

Carolina 'Power

& Light Co.

SUBJECT:

Forwards Insp Rept 50-400/89-31

on 891113-17.No violations

or deviations noted.

DISTRIBUTION CODE:

IE01D

COPIES

RECEIVED:LTR 'NCL

SIZE:

TITLE: General

(50 Dkt)-Insp Rept/Notice of Violation Response

NOTES:Application for permit renewal filed.

DOCKET

N

05000400

05000400

I

RECIPIENT

ID CODE/NAME

PD2-1

PD

COPIES

RECIPIENT

LTTR ENCL

ID CODE/NAME

1

1

BECKER,D

COPIES

LTTR ENCL

1

1

INTERNAL: ACRS

AEOD/DEIIB

DEDRO

NRR/DET/DIR 8H3

NRR/DOEA DIR 11

NRR/DREP/PRPB11

NRR/DST/DIR 8E2

NUDOCS-ABSTRACT

OGC/HDS1

RES MORISSEAUiD

2

2

1

1

=

1

1

1

1

1

.

1

2

2

1

1

1

1

1

'1

1

1

AEOD

AEOD/TPAD

NRR SHANKMAN,S

NRR/DLPQ/LPEB10

NRR/DREP/PEPB9D

NRR/DRIS/DIR

NRR/PMAS/ILRB12

'

EBERMAN,J

EG

02

GN

LE

01

1

1

1

1

1

1

1

1

1

1

1

1

1'

1

1

1

1

1

1

EXTERNAL: LPDR

NSIC

1

1

NRC

PDR

1

1

1

1

A

R

D

NOTE TO ALL"RIDS" RECIPIENTS:

D

~

D

PLEASE HELP US TO REDUCE WASTE! CONTACT THE DOCUMENT CONTROL DESK,

ROOM'Pl-37 (EXT. 20079) TO ELIMINATEYOUR NAMEFROM DISTRIBUTION

LISTS FOR DOCUMENTS YOU DON'T NEED!

TOTAL NUMBER OF COPIES

REQUIRED:

LTTR

27

ENCL

27

December

1,

1989

Docket No.

50-400

License

No.

NPF-63

Carolina

Power

and Light Company

ATTN:

Mr.

Lynn W. Eury

Executive Vice President

Power Supply

P. 0.

Box 1551

Raleigh,

NC

27602

Gentlemen:

SUBJECT:

NRC

INSPECTION

REPORT

NO. 50-400/89-31

This refers to the Nuclear Regulatory

Commission

(NRC) inspection

conducted

by

R.

Newsome

and

R.

Chou

on

November

13-17,

1989.

The inspection

included

a

review of activities authorized for your Harris facility.

At the conclusion of

the inspection,

the findings were discussed

with those

members

of your staff

identified in the enclosed

Inspection

Report.

Areas

examined

during

the

inspection

are identified in the report.

Within

these

areas,

the inspection

consisted

of selective

examinations

of procedures

and

representative

records,

interviews with personnel,

and

observation

of

activities in progress.

Within

the

scope

of

the

inspection,

no violations

or deviations

were

identified.

Your attention

is invited to the unresolved

item identified in the Inspection

Report.

This matter will be pursued during future inspections.

In

accordance

with Section 2.790 of the

NRC's

"Rules of Practice,"

Part 2,

Title 10,

Code of Federal

Regulations,

a copy of this letter and its enclosures

will be placed

in the

NRC Public Document

Room.

Should you have

any questions

concerning this letter,

please

contact

us.

Sincerely,

Original Signed

by

Caudle

A. Julian

Caudle A. Julian,

Chief

Engineering

Branch

Division of Reactor Safety

Enclosure:

(See

page

2)

SWSZ<i.OZONE

SSS"O1

roe

oriocK ovoco4OO

9

PDC

Carolina

Power and Light Company

December

1,

1989

Enclosure:

NRC Inspection

Report

cc w/encl:

R.

B. Richey,

Manager

Harris Nuclear Project

Box 165

New Hill, NC

27562

C.

S. Hinnant

Plant General

Manager

Harris Nuclear Project

Box 165

New Hi 1 1,

NC

27562,

Richard

E. Jones

General

Counsel

Carolina

Power

& Light Company

P. 0.

Box 1551

. Raleigh,

NC

27602

Dayne

H. Brown, Chief

Radiation Protection

Branch

Division of Facility Services

N.

C. Department of Human Resources

701 Barbour Drive

Raleigh,

NC

27603-2008

Nuclear

Energy Public Information

Committee

c/o Triangle J Council of Governments

P. 0.

Box 12276

Research

Triangle Park,

NC

27709

State of North Carolina

bcc w/encl:

C. Barth,

OGC

A. Upchurch,

Chairman,

Triangle J

Council of Governments

Document Control

Desk

NRC Resident

Inspector

U.S. Nuclear Regulatory

Commission

Route

1,

Box 315B

New Hill, NC

27562

bcc w/encl cont'd:

H. Dance

J.

Blake

R.

Newsome

R.

Chou

RII:DRS

RNewsome

11/ES /89

JPP(RS

ou

1/I"'/89

ake

1/gvp'89

RII:DRP

HDance

ll/g'/89