October 5," =1989
'arolina Power and Light Company ATTN:
Mr. L.
W. Eury Executive Vice President Power Supply P. 0.
Box 1551
- Raleigh, NC 27602 Gentlemen:
SUBJECT:
SHEARON HARRIS NUCLEAR POWER PLANT EXAMINATION REPORT 400/OL-89-01 On August 21 - 24, 1989, the NRC administered examinations to employees of your company who had applied for licenses to operate your Shearon Harris Nuclear Power Plant.
At the conclusion of the examination, the examination questions and preliminary findings were discussed with those members of your staff identified in the enclosed report.
In accordance with 10 CFR 2.790 of the Commissions regulations, a copy of this letter and the enclosures will be placed in the NRC Public Document Room.
Should you have any questions concerning this examination, please contact us.
Sincerely,,
Enclosures:
1.
Examination Report 50-400/OL-89-01 2.
Examination and Answer Key (RO) 3.
Facility Comments 4.
NRC Resolution of Comments 5.
Simulation Facility Report (Original signed by C, Casto for)
Thomas A. Pebbles, Chief Operations Branch Division of Reactor Safety cc w/encls 1 and 5:
L. H. Martin, Manager - Nuclear Training Section R. B. Richey, Manager - Harms Nuclear Project cc w/encls 1, 2, 3, 4, and 5:
A; W'. Powell,, Manager - Training bcc w/encls (See page 2).
- =910200039 891005 PDR ADOCK 05000400 V
Carolina Power and Light Company October 5, 1989'cc w/encl 1:
R. Becker, NRR H. Dance, DRP Harris Senior Resident Inspector N. Ernstes, DRS B. Holbrook, DRS bcc w/encls 1, 2, 3, 4, and 5:
NRC Public Document Room bcc w/encls 1 and 5:
Operator Licensing Branch, DLPq:NRR RIQ NErnstes:btm 10/3 /89 RII CCasto 10
, /89 RII~
HDance 10/4'/89 RII TPeebles 10/
/89