AC CELE RATED DIP+ BUTl ON DE MONSTR+ON SYSTEM REGULATORY INFORMATION DISTRIBUTION SYSTEM (RIDS)
ACCESSION NBR:8905180351 DOC.DATE: 89/05/11 NOTARIZED: NO FACIL:50-400 Shearon Harris Nuclear Power Plant, Unit 1, Carolina AUTH.NAME AUTHOR AFFILIATION BECKER,R.A..
Project Directorate II-1 RECIP.NAME RECIPIENT AFFILIATION EURY,L.W.
Carolina Power 6 Light Co.
SUBJECT:
Informs util of implementation schedule for NRC Bulletin 88-011,Item l.b.
DISTRIBUTION CODE:
DFOID COPIES RECEIVED:LTRf ENCL g SIZE:
TITLE: Direct Flow Distribution: 50 Docket (PDR Avail)
NOTES:Application for permit renewal filed.
DOCKET 05000400 05000400 5 RECIPIENT ID CODE/NAME INTERNAL: NUDOCS-ABSTRACT EXTERNAL: LPDR NSIC COPIES LTTR ENCL RECIPIENT ID CODE/NAME 01 NRC PDR COPIES LTTR ENCL h
D
'D NOIE 'lO ALL "RIES" RZCZPrWrS; PLEASE HELP US IO REDUCE WASTE!
CDNZAC1' DOQJNEMl'ONTROL DESK RXM Pl-37 (EXT. 20079)
KO ELI2QNiLTE YOUR NAME FRY DISTRIKJTIGN LISTS FOR DOCUMEXZS YOU DON'T NEED!
v TOTAL NUMBER OF COPIES REQUIRED:
LTTR 5
ENCL
gS 4
}
~p
~O~
+n +*
Racy
~o 0O C
~O
- <<+
UNITED STATES t
N CLEAR REGULATORY COMMISSION WASHINGTON, O. C. 20555
'ay ll, 1989 Docket No. 50-400 Mr. Lynn W. Eury Executive Vfce President Power Supply Carolina Power 8 Light Company Post Office Box 1551
- Raleigh, North Carolina 27602
Dear Mr. Eury:
SUBJECT:
SCHEDULAR RELIEF REQUEST RELATED TO NRC BULLETIN 88-11, "PRESSURIZER SURGE LINE THERMAL STRATIFICATION," ITEM 1.b,-
SHEARON HARRIS NUCLEAR POWER PLANT, UNIT I (TAC NO. 72137)
The purpose of this letter is to inform you of the implementation schedule for Item I.b of NRC Bulletin 88-11, "Pressurizer Surge Line Thermal Stratifi-cation," that was mutually agreed upon between the NRC staff and the Westinghouse Owners Group (WOG) during an April Il, 1989 meeting.
By letter dated February 28, 1989, Carolina Power h Light Company proposed an alternate schedule for the completion of the bounding analysfs required by Item I.b of NRC Bulletin 88-11 regarding the design adequacy of the pressurizer surge line, taking into account the effects of thermal stratifica-tion.
Your proposed schedule for completion of Item 1.b by December 20,
- 1990, two years from the date of the Bulletin, was consistent with the alternate schedule proposed by the WOG.
During an April 11, 1989 meeting between the staff and the WOG, the staff indicated that the alternate
- schedule, as originally proposed by the WOG, was unacceptable.
Based upon additional discussion, the WOG agreed to notify fts membership that licensees of plants in operation less than 10 years should complete the required actions of Item 1.b within the originally stated period (one year from receipt of the Bulletin).
Licensees of plants fn operation over 10 years should complete their bounding analysis, as related to Item 1.b of the Bulletin, and have ft available for NRC audft by the end of May 1989.
In addition, licensees should submit a justification for continued operation (JCO) to the NRC in the event the bounding analysis does not confirm the adequacy of the pressurizer surge line for the design life of the plant.
The staff found these proposals to be acceptable.
l 8905i8035i 8905ii PDR ADOCK 05000400 9
Mr. L. W. Eury May ll, 1989 It is our understanding that the WOG will provide you with a "generic" bounding
- analysis, to which your plant specific variables (e.g., seismic and thermal loadings), will need to be added and incorporated.
Your analysis should assess all aspects of thermal stratification and thermal striping, including bounding evaluations on stresses and fatigue, based on currently available information.
Based upon your participation in the WOG program regarding this issue, and absent any other justification, your proposed alternate schedule for completing Item l.b is not approved.
It is our expectation that your efforts will be accelerated to meet the completion date(s) as committed by the WOG.
Sincerely, cc:
See next page Original Signed By:
Richard A. Becker, Project Manager Project Directorate II-1 Division of Reactor Projects -I/II Office of Nuclear Reactor Regulation DISTRIBUTION
'Docket:F-il e -"
NRC PDR Local PDR PDII-1 Reading S.
Varga G. Lainas E.
Adensam P. Anderson R. Becker OGC (For inform. Only)
E. Jordan B. Grimes T.
Chan ACRS (10)
HARRIS PLANT FILE 14-E-4 14-H-3 14-D-20 14-D-20 14-D-20 15-B-18 MNBB-3302 9-A-2 13-E-16 P-315 I-A d rson 5/~II/89 PDI I-1 P
1
~:sw EAdensam 5//o/89 5g
/89
r V4 I
I
~
I
~
~ ~
,Mr. L. W. Eury Carolina Power 5 Light Company CC:
Shearon Harris Mr. R.
E. Jones, General Counsel Carolina Power 8 Light Company P. 0.
Box 1551 Raleigh, North Carolina 27602 Mr. D.
E. Hollar Associate General Counsel Carolina Power 8 Light Company P. 0.
Box 1551 Raleigh, North Carolina 27602 Resident Inspector/Harris NPS c/o U. S. Nuclear Regulatory Commission Route I, Box 315B New Hill, North Carolina 27562 Mr. R. A. Watson Vice President Harris Nuclear Plant P. 0.
Box 165 New Hill, North Carolina 27562 Mr. H. A. Cole Special Deputy Attorney General State of North Carolina P. 0.
Box 629
- Raleigh, North Carolina 27602 Nuclear Energy Public Information Coaeittee c/o Triangle J Council of Governments P. 0.
Box 12276 Research Triangle Park, NC 27709 Regional Administrator, Region II U.S. Nuclear Regulatory Commission 101 Marietta Street Suite 2900 Atlanta, Georgia 30323 Mr. C. S. Hinnant Plant General Manager Harris Nuclear Plant P. 0.
Box 165 New Hill, North Carolina 27562 Mr. Dayne H. Brown, Chief Radiation Protection Section Division of Facility Services N.
C. Department of Human Resources 701 Barbour Drive
- Raleigh, North Carolina 27603-2008