ML18005A667
| ML18005A667 | |
| Person / Time | |
|---|---|
| Site: | Harris |
| Issue date: | 10/11/1988 |
| From: | Bassett C, Hosey C, Lauer M NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| To: | |
| Shared Package | |
| ML18005A665 | List: |
| References | |
| 50-400-88-28, NUDOCS 8810280350 | |
| Download: ML18005A667 (24) | |
See also: IR 05000400/1988028
Text
~ps RfcII~
Vp0
~C
I
0
C
O
Y/+n
~O
+**+"
UNITEDSTATES
NUCLEAR REGULATORY COMMISSION
REGION II
101 MARIETII'ASTREET, N.W.
ATLANTA,GEORGIA 30323
OCT 1. 8 1988
Report No.:
50-400/88-28
Licensee:
Carolina
Power and Light Company
P. 0.
Box 1551
Raleigh,
NC
27602
Docket No.:
50-400
License No.:
Facility Name:
Harris
1
Inspection
Conducted:
August
Inspectors:
C.
H. Basset
15-19 and August 30-September
2,
1988
lc/a/I1'
N. T. Lauer
Approved by:
C.
M. Hosey,
ection
ie
Division of Radiation Safety
and Safeguards
SUMMARY
Da e
igned
~6/lt
Date Signed
Scope:
This routine,
unannounced
inspection
was conducted in the areas
of the
facility radiation protection
program including:
the solid radioactive
waste
program,
transportation
of radioactive materials
and the radiological
aspects
of the current outage.
Results:
No programatic
weaknesses
were
found in the radiation protection
program.
The licensee's
radiation protection
program for outages
appears
to be
generally
effective
in protecting
the health
and
safety
of occupational
radiation workers.
However, within the areas
inspected,
the following violations
were identified:
Failure to provide the proper monitoring devices for an individual
entering
Paragraph
2.c.
Inadequate
surveys
of items
released
from
a
contaminated
area,
Paragraph
2.e.
Failure
to follow procedures
for
response
checking
alarming
dosimeters,
Paragraph
2.e.
Failure to review
and
approve
Process
Control
Program
implementing
procedures,
Paragraph
3.d.
33>O23O~
,
oo4OO
50 331013
ADOCI:
Q
REPORT
DETAILS
Persons
Contacted
Licensee
Employees
- +L. Beidelman,
Senior Specialist,
Radiation Control
- +R. Biggerstaff, Principal Engineer,
Onsite Nuclear Safety
- C. Crawford, Director, Onsite Nuclear Safety
D. Elkins, Radioactive
Waste
Foreman,
Radiation Control
J. Floyd, Operations
Foreman Radiation Control
"+C. Gibson, Director, Programs
and Procedures
"+C. Hinnant, Plant General
Manager
- J. Leonard, Specialist,
Radioactive
Waste
+J. McDuffie, Supervisor,
Radiation Control
+T. Morton, Manager,
Maintenance
J. O'Halloran,
Foreman,
Dosimetry
- C. Olexik, Supervisor,
Operations
- +A. Poland,
Project Specialist,
Radiation Control
+M. Pugh, Project Specialist,
In-service Inspection
F. Reck,
Foreman,
Support
- +J. Sipp, Manager,
Environmental
and Radiation Control
- D. Tibbitts, Director, Regulatory Compliance
+R.
Van Metre, Manager,
Technical
Support
- M. Wallace, Senior Specialist,
Regulatory Compliance
- R. Watson,
Vice President,
Harris Nuclear Plant
L. Williams, Principal Engineer,
Corporate
Other
licensee
employees
contacted
during this
inspection
included
craftsmen,
engineers,
technicians,
and administrative personnel.
Other Organizations
Nuclear Regulatory
Commission
(NRC), Region II
- P. Fredrickson,
Section Chief, Division of Reactor Projects
- C. Hehl, Deputy Director, Division of Reactor Projects
- C. Hughey, Radiation Specialist,
Division of Radiation Safety
and
Safeguards
- E. Merschoff, Deputy Director, Division of Reactor Safety
NRC Resident
Inspectors
- +W. Bradford, Senior Resident
Inspector
G. Maxwell, Senior Resident Inspector
- wM. Shannon,
Resident
Inspector
- Attended exit interview on August 19,
1988
+Attended exit interview on September
2,
1988
and initialisms
used
throughout this report are listed in the
last paragraph.
2.
Occupational
Exposure
During. Extended
Outages
(83729)
a ~
Organization
and management
Controls
(83722)
Organization
The licensee
is required
by TS 6.2 to establish specific onsite
and offsite organizations
for unit operation
and
corporate
management.
The responsibility, authority and other management
controls
necessary
for establishing
and maintaining
a health
physics
program for the facility are further outlined
in
Chapters
12
and
13 of the
FSAR.
specifies
the
composition of the Plant
Nuclear Safety
Committee
(PNSC)
and
delineates its functions, responsibilities
and authority.
The inspector
reviewed the licensee's
site organization,
as well
as
the
responsibilities,
authority
and
control
given
to
management
as
they relate
to the site radiation protection
program.
Recent
changes
in plant management
were reviewed to
verify that they would not adversely affect the'bility of the
licensee
to continue
implementing the critical elements
of the
program.
The inspector
discussed
the support
received for the
radiation
protection
program
with the
ESRC
Manager
and
determined that it was adequate.
(2)
Staffing
TS 6.2 also specifies
the minimum staffing requirements for the
facility.
FSAR Chapters
12
and
13 outline further details
on
staffing levels at the site.
The inspector
reviewed the
Rad
Con or
HP organization with the
ESRC Hanager.
The subjects of attrition rate,
use of contractor
HP personnel,
promotions, staff qualifications
and actual
versus
authorized staffing levels were also reviewed
and discussed.
At
the time of the inspection,
22 of the
27 authorized
senior or
ANSI qualified technician positions
were filled.
The licensee
indicated that there
was
an active recruitment
program in place
and that the five empty positions
would be filled as
soon
as
personnel
accepted
job offers.
It was
also
noted that
the
licensee
had
12 junior technicians
in training status.
The
licensee
indicated that the junior technicians
were being
used
during the current outage
to perform closely supervised
routine
jobs.
Licensee
representatives
also indicated that they would
be qualified by February
1989.
In addition
to the
permanent
personnel,
the
licensee
had
acquired
the
assistance
of
70 contractor
HP technicians
to
augment
the staff during the outage.
Upon completion of the
outage,
the licensee
planned to reassess
the personnel
needs
in
the
group
and explore
the possibility of increasing
the
"permanent
staff,
especially
in
the
ALARA section
(see
Paragraph f(1) ) .
{3)
Management
Controls
The inspector
reviewed the licensee's
Radiation Safety Violation
(RSV) reports
which were
used to identify and document safety
and radiological incidents.
It was noted that most of the
RSVs
involved
personnel
failure to follow good radiological
work
practices
or failure to comply with instructions.
The inspector
discussed
these
problems
with the
ESRC Manager
who indicated
that these
problems would likely be eliminated
as the work force
became
more
experienced
in dealing with actual
radiation
and
contamination.
It was
noted that
adequate
corrective actions
had
been initiated, as required.
No violations or deviations
were identified.
b.
Training and gualifications
(83723)
10 CFR 19. 12 requires that all individuals working in or frequenting
any portion of a restricted
area shall
be provided basic radiation
protection training.
The licensee's
General
Employee Training
(GET) was divided into two
parts.
If individuals were only entering the'protected
area
then
Level I training was required.
Level I required approximately
seven
hours of classroom
work with
a written test
and
covered
workers
rights,
conduct,
and plant specifics.
If the individual needed
to
enter the radiation control area,
Level II GET was required.
Level
II required approximately nine hours of classroom
work which included
a test
and "mock-up".
"Mock-up" was the practical factors portion of
the course
and required the worker to demonstrate
the proper use of a
survey
instrument,
proper
dress-out
in protective
clothing,
comprehension,
and
SRPD reading.
The inspector
reviewed lesson
plans
for Level I and !I and verified that all topics specified in 10 CFR 19. 12 were covered during the training.
Selected training records of
licensee
and contractor
personnel
working in the radiation control
area
were
reviewed.
Licensee
representatives
stated
that
retraining
was
given
every
twelve
months
and
consisted
of
approximately four and
a half hours of classroom work, "mock-up", and
a written test.
Respirator
training,
which required
approximately four hours
and
included
hands
on work, was reviewed
by the inspector
and found to be
adequate.
Training personnel
stated,
that since the staff could be supplemented
with trainers
from other training groups,
an adequate
number of GET
trainers
were available for the
increased
number of individuals
requiring
GET training due to the outage.
Because
the inspector
observed
individuals improperly wearing
PCs
within the
RCA (see
Paragraph 2.e.(3)), specific attention
was given
to the type and amount of information conveyed to the worker relating
to
PC donning
and wearing.
Training appeared
adequate
in this area;
however,
more emphasis
may be required.
Through discussions
with training personnel
the inspector determined
that
a good line of communication existed
between operational
HP and
GET training personnel
to quickly address
any possible
poor work
practices identified in the field through improvements in training.
No violations or deviations
were identified.
External
Exposure Control
and Dosimetry
(1)
Dosimetry
The licensee is required
and 20.102 to maintain
workers'oses
below specified levels.
10 CFR 20.202 requires
each licensee
to supply appropriate
personnel
monitoring devices
to specific individuals and require the use of such equipment.
The licensee's
external
exposure
control
and personnel
dosimetry
programs
were
reviewed
by
the
inspector.
This
included
facilities, equipment,
personnel,
records,
and procedures
used
to control exposures
and determine
doses.
The
licensee
uses
Panasonic
four element
thermoluminescent
dosimeters
(TLDs) which are routinely read
on
a quarterly basis.
The Dosimetry
Program is due for National Voluntary Laboratory
Accreditation
Program
(NVLAP) accreditation
renewal
October 1,
1988.
The licensee
also participates
in a
TLD spiking program
with Battelle
National
Laboratory.
Licensee
representatives
stated
that
they will soon
begin
using
a
newly developed
finger-ring dosimeter
from Panasonic for extremity 'monitoring of
the
hands.
Previously,
the licensee
used
band-aid
type finger
dosimeters
with Panasonic
elements.
(2)
Administrative Control Levels
The inspector
reviewed
the licensee's
administrative
exposure
controls
and
determined
that
those
controls
were designed
to
maintain exposure
as
low as reasonably
achievable
(ALARA).
The
licensee
required
consecutively
higher tiers of supervision to
approve
dose
extensions
with the plant manager
having approval
5
authority for whole body exposures
in excess
of 2400 mrem during
the calendar quarter.
Records
Exposure
records
of plant
and contractor
personnel
for 1988,
year-to-date,
were selectively
reviewed.
No exposure
greater
than limits in
or the station's
quarterly
administrative control level
was noted.
A review of. the station
Dose
Report,
dated
September
1,
1988,
indicated
a
maximum
individual dose of 924 mrem for the current quarter.
Skin and
extremity doses
were negligible.
(S/G)
Work
The inspector
reviewed the licensee's
procedure for working in
and
around
steam
generators,
Health Physics
Procedure
HPP-010,
Steam
Generator
Entry, Revision 3, dated
August 22,
1988.
It
was noted that the procedure
contained
references
to protective
clothing,
respiratory
protection,
dosimetry
requirements
and
exposure
control,
as well
as
"jump sheets"
to control entries.
The
Procedure
also
specified
requirements
for radiological
surveys
which were
performed
by the licensee
on August 28-29,
1988,
during
and following the
removal of the
manway covers,
and inserts for the three
S/Gs.
The results of the
surveys
indicated
that
beta
radiation levels just inside the
manway
openings
were from 4 to
5 times higher than the
gamma
radiation levels,
the highest
being
44
Rad per hour
beta
and
10 R/hr
gamma.
The inspector
discussed
beta
radiation
exposure
control with
licensee
representatives
and
reviewed
the
licensee's
investigation
of the
isotopes
present
in the
S/Gs
and
the
energies
involved.
This
was
being
done to ensure
that the
controls
being
used
during
S/G entries
were
adequate
and to
assess
the
possible
need for other
measures
such
as
beta
radiation
stay
times.
It was
noted
that,
although
the
licensee's
procedure
required
surveys
prior to
S/G entry,
no
mention
was
made
of the
beta
radiation
exposure
control
evaluations.
The
licensee
acknowledged
this
and
agreed
to
revise the procedure
to add
a requirements for such evaluations
prior to
S/G entry.
In addition,
the
licensee
agreed
to
consider
inclusion of attentuation
studies
using various
samples
of clothing and eye protection in the evaluations
to be required
by procedure.
The
inspector
reviewed
the
TLD dose
value results
from the
multiple badge
sets
worn by workers during various
S/G entries,
These results
did not indicate
any lens of the eye dose greater
than the whole body dose.
High Radiation Area Control
Technical
Specification
6. 12
requires
that
any
individual
permitted to enter
a high radiation area in which the intensity
of radiation is equal
to or less
than
1000 millirem per hour at
'8
inches shall
be provided with or accompanied
by:
(a)
a radiation monitoring device that continuously indicates
the radiation
dose rate in the area;
or
(b)
a radiation monitoring device that continuously integrates
the radiation
dose
rate
in the
area
and
alarms
when
a
preset integrated
dose is received;
or
(c)
an individual qualified in radiation protection procedures,
with a radiation dose rate monitoring device.
During tours of the Unit 1 containment,
the inspector verified
dose
rates
in various
areas,
throughout
containment
and
high
radiation areas
(HRAs).
The inspector also reviewed survey
maps
of various
areas
in the
RCB and
noted that
dose
rates
up to
800 mrem/hr at contact
and
250 mrem/hr at
18 inches existed in
the area
near the
"A" S/G inside the biological shield.
Other
areas
within the containment
were noted with similar radiation
levels.
During tours
on August 15-17,
1988, the inspector
observed
work
in progress
on all elevations
in the
RCB including work in HRAs.
During that time period the inspector
noted that the licensee
issued
a survey meter or
an integrating/alarming
dosimeter to
individuals entering
HRAs or to groups of individuals entering
HRAs who would be working in the
same location.
The inspector
questioned
three individuals
on August
16 and five individuals
on August
17 about the use of these
devices to monitor radiation
dose
rates
and control
exposure
and found that all individuals
either
had
a meter or an alarming dosimeter or were accompanied
by someone
who had one.
On the morning of August 18,
1988, at approximately 9:30 a.m.,
a
worker was
observed within a posted
HRA inside the biological
shield in Unit 1
RCB.
The inspector
questioned
the individual
as to the nature of the work he
was performing
and about the
possession
and use of an integrating dosimeter or a survey meter
in a
HRA.
The worker indicated that
he was performing snubber
inspections
under the requirements
of
SRWP 318,
Inspection
and
Functional
Testing
of
$nubbers,
Support
and
Support,
which required individuals to have access
to all areas
inside
and
outside
the biological shield.
When
asked,
the
individual
stated
that
he
had
neither
a
meter
nor
an
integrating/alarming
dosimeter.
The worker left the
HRA and
went to the containment
control point and obtained
an alarming
dosimeter for work in the
HRA.
The inspector also reviewed the
requirements
of
SRWP 318 which required
the
use of
a survey
meter (or alarming dosimeter)
in HRAs.
Failure of the licensee
to provide the worker with a survey
meter or an integrating/alarming
dosimeter or to have the worker
accompanied
by an individual qualified in radiation protection
procedures
with
a monitoring device for entry into
a
HRA was
identified
as
an
apparent
violation
of
(50-400/88-28-01)-.
d.
Internal
Exposure Control
and Assessment
(83725)
Engineering
Control s
requires
that the licensee
use
process
or
other engineering
controls to the extent practicable
to limit
concentrations
of radioactive
materials
in the air to levels
below those
which delimit an airborne radioactivity area
as
defined in 20.203(d)(1)(ii).
During tours of the Auxiliary Building and the Unit 1 Reactor
Containment Building, the inspector
observed
the use of various
engineering
controls
employed
to limit the concentrations
of
radioactive material
in air.
The licensee
used
enclosures
or
tents
constructed
around
equipment
or
areas
which were highly
contaminated
and provided
HEPA filtered ventilation systems for
the enclosures.
In other areas,
the licensee
used ducting to
draw air
away
from contaminated
areas
and into the filtered
ventilation system.
Nachining or grinding was also performed in
tents
or using
directed
ventilation to control
and limit
airborne radioactivity.
The inspector also observed
the use of
a continuously oscillating water sprayer
used to keep the upper
internals of the reactor wet while stored in the drained portion
of the cavity.
(2)
Respiratory Protection
Program
requires
that,
when it is impracticable
to
apply process
or engineering controls to limit concentrations
of
radioactive
material
in air below
25% of the concentrations
specified in Appendix B, Table 1,
Column 1, other precautionary
measures
should
be
used
to maintain the intake of radioactive
material
by any individual within seven
consecutive
days
as far
below 40 Naximum Permissible
Concentration-hours
(NPC-hrs)
as is
reasonably
achievable.
Through
records
review,
observations
and
discussions
with
licensee
representatives,
the
inspector
evaluated
the
respiratory
protection
program
including training,
medical
qualifications, fit testing,
NPC-hr assignment,
and issue,
use,
(3)
(4)
decontamination
and storage
of respiratory protection devices.
The records,
observations
and discussions
indicated that only
those
personnel
who have
been trained
and qualified to wear
a
respiratory protective
device
were issued respirators.
Review
of the MPC-hr assignments
for selected
individuals revealed that
all exposures
were
below the
40 NPC-hr per week control level
and below the facility's administrative control levels
as well.
Air Sampling
and Bioassays
10 CFR 20. 103 establishes
the limits for exposure of individuals
to concentrations
of radioactive materials in air in restricted
areas.
Section 20.103 also requires that suitable
measurements
of concentrations
of radioactive material in air be performed to
detect
and evaluate
the airborne radioactivity in restricted
areas
and that appropriate
bioassays
be performed to detect
and
assess
individual intakes of radioactivity.
The inspector
reviewed the results of selected air samples
taken
during the current outage.
The air sample
log indicated that
the airborne concentration
had
seldom
been
above
25K of the
NPC
of radionuclides
specified in 10 CFR 20,
Appendix B, Table 1,
Column 1.
The licensee
also indicated that
no problems
had
been
encountered
during the
outage,
to date,
concerning
airborne
radioactivity including radioiodine.
It was noted that the air
samples
had
been
evaluated for alpha,
beta
and
gamma activity
and analyzed to determine the specific isotopes
present.
The results of selected
WBCs were also reviewed.
No instances
were
noted in which personnel
received greater
than the limits
specified
in
Through
records
review
and
discussions
with licensee
representatives,
it was
determined
that
there
had
been
no detectable
intakes
of radioactive
material
since
the last inspection
and
no confirmed internal
exposures.
Air equality
The
inspector
discussed
with licensee
representatives
their
procedures
for
ensuring
air quality
supplied
to airline
respirators,
bubble
hoods
and
self-contained
breathing
apparatuses
(SCBAs).
It was
noted
that
a
dedicated
air
compressor
was
used
to fill air bottles
used
in SCBAs.
The
compressor
was tested
every
3 months to maintain
Grade
D air.
Plant instrument air was used for airline respirators
and bubble
hood air supply
and air quality was
checked
onsite
every
3
months or the first time
a connection
was made to
a given outlet
to ensure
Grade
D air was always available.
No violations or deviations
were identified.
Control
of Radioactive
Material
and
Contamination,
Surveys
and
Monitoring (83726)
Contamination
Surveys
requires
each licensee
to make or cause
to be
made
such
surveys
as
(1) may
be necessary
for the licensee
to
comply with the regulations
in this part and (2) are reasonable
under
the circumstances
to evaluate
the extent of radiation
hazards that may be present.
Health
Physics
Procedure
HPP-030,
Control
and
Release
of
Equipment/Material
from the
RCA/Restricted
Area,
Revision 3,
dated
August 27,
1987,
requires
in
Section 10.1.1
that
material/equipment
being transferred within the
RCA be surveyed
for radiation
and
contamination
per
HPP-060,
Performance
of
Radiation
and
Contamination
Surveys.
Also,
Section 10.1.2
states
that, if radiation/contamination
levels
are
less
than
100 net
cpm per
probe
area
as measurable
within a thin window
pancake-type
GM detector
by direct frisk and
less
than
(defined
as
100 net
cpm per
100 cm~) for the counting instrument
used
by smear
survey (removable),
the material/equipment
can
be
released
for transfer.
Health Physics
Pro'cedure'PP-060,
Performance
of Radiation
and
Contamination
Surveys,
Revision 2,
dated
September
29,
1987,
requires
in
Section 7.12
that,
when
counting
smears
for
beta-gamma
contamination
using
a frisker,
a minimum count time
of about
20 seconds
is
recommended
to allow for a
90 percent
deflection of full scale
on the
slow response
mode.
Also,
Section 10.8.2 requires
a frisk of the accessible
surfaces
of
the material
being surveyed
by moving the probe slowly over the
surfaces within one-half inch of the surface.
While touring the Auxiliary Building, the
RCB and the
Radwaste
Building
to
determine
whether
or
not
adequate
personal
contamination
surveys
were
being
performed,
the
inspector
observed
workers exiting contaminated
areas
and exiting the
RCA.
The
movement of material
from contaminated
areas
and from the
RCA .also
was
observed
to determine if adequate
direct
and
smearable
contamination
surveys
were
being
performed.
All
personnel
surveys
observed
appeared
to
be
adequate
and
the
material
surveys
performed
at the exit of the
RCA were also
adequate.
However, the contamination
surveys
performed at the
main
control
point to
the
RCB, for items
cross'ing
the
contaminated
area
boundary,
were less
than adequate.
On
numerous
occasions
during the period of August 15-18,
at
varying times during the day, the inspector
noted
HP technicians
surveying
items out of the
RCB contaminated
area
at the
main
10
control point.
Various survey techniques
were observed
during
the time period,
the most prevalent of which was the
use of a
white cotton liner to "smear"
an item. If the liner was worn on
the hand,
the fingers of the liner would be wiped over
a portion
of the item being .surveyed
and then checked for contamination
by
placing
the, fingertips over
a frisker probe for 3-5 seconds.
Another method involved the
use of a cotton liner to wipe over
the item in question
continually folding the liner as it was
used.
The liner would then
be
checked for the presence
of
contamination
by placing the folded liner over
a frisker probe
for 3-5 seconds.
The liner was. not unfolded or spread
out on a
flat surface
to frisk the entire surface
used to "smear" .the
item.
When
a
smear
patch
was
used
to
smear
an item, it was-
seldom
counted for more than
2 seconds
with a frisker probe.
Only
on infrequent
occasions
were
items
such
as electrical
cords,, hoses,
cables
or other pieces of equipment wiped down or
smeared
along their entire length or over the entire
surface
area to check for contaminat'ion.
(3)
The inspector also noted that such items were not frisked with a
probe
along their entire length or over their entire external
surface.
Usually only a cursory frisk of the item was performed
before
removing
the
item from the
contaminated
side of the
barrier
and
placing
the
item
on the
"clean"
side of the
boundary.
Failure to perform
an
adequate
survey of items being released
from a contaminated
area
was identified as
an apparent violation
(50-400/88-28-02).
Personnel
Contamination
Reports
The inspector
reviewed selected
personnel
contamination reports
for 1988
and all reports
of contamination
that
had occurred
since
the current
outage
began.
It was
noted that, of those
involving skin contamination,
most were determined to have
been
caused
by tom
PCs
or from improperly
removing
the
PCs.
Licensee
representatives
indicated
an
awareness
of these
problems
and
had
made
suggestions
and
recommendations
to the
training group about the proper
use
and
removal
of PCs.
The
inspector verified that the training group
had
been
advised of
these
issues
and
had
taken
steps
to emphasize
the correct
use
and removal of PCs in GET and retraining. classes.
Protective Clothing (PCs)
During tours of the
RCB, the inspector
observed
various jobs in
progress
including installation
of the
guide
pins
in the
reactor,
inspection,
installation
of
shielding,
decontamination efforts following a spill from the
as well
as other maintenance
activities.
During these
tours,
the inspector
also
noted isolated
instances
in which workers
were wearing the
PC cloth hood with the flaps tied or attached
behind their
heads.
Two workers were also
noted to be wearing
their
PC coveralls with the front zipper partially undone
thus
exposing
the upper portion of the neck
and chest.
When asked
about this practice,
licensee
HP representatives
indicated that
this was
an improper practice
and that this would be monitored
during future
management
and
HP tours
of the
containment.
Through review of personnel
contamination reports,
the inspector
found
no
evidence
that this
problem
was contributing to
an
increased
incidence
of personnel
contaminations.
This issue
will be
reviewed
during
subsequent
inspections
and will be
tracked
by the
NRC
as
an
Inspector
Followup
Item (IFI)
(50-400/88-28-03).
Radioactive Material Labeling and Storage
requires
each
area
or room in which licensed
material
is
used
or stored
and which contains
any radioactive
material
in an
amount
exceeding
10 times the quantity of such
material
specified
in
Appendix
C of this
part
shall
be
conspicuously
posted with a sign or signs bearing the radiation
caution
symbol
and the words:
"CAUTION, RADIOACTIVE MATERIAL."
requires
that
each
container
of radioactive
material
bear
a durable, clearly visible label identifying the
radioactive contents.
During tours of the
RCA, adjacent
storage
areas
and warehouses,
the
inspector
observed
the
licensee's
radioactive
material
storage
areas.
The
rooms
or
areas
used
for storage
of
r'adioactive material
were posted
as required
and the items kept
therein
were properly labeled.
It was noted that the licensee
had very little radioactive material in storage.
Radi ati on Detecti on and Survey Instruments
During plant tours,
the inspector
observed
the proper
use
and
selection
of
instruments
appropriate
for the
radiation
protection activity in progress.
The inspector verified that
instruments
in use
or available for use
had
been calibrated
within the prescribed
time period.
Licensee
personnel
stated
that
the quantity
and
type of portable radiation detection
instruments
were adequate for the increased
radiation protection
activities resulting from the outage.
The
inspector
discussed,
with
licensee
representatives,
operation
and calibration
of the
whole
body
contamination
monitors
permanently
located at the
RCA exit and,
during the
outage,
at
the
main
containment
control
point.
Licensee
representatives
stated that three
Nuclear Enterprise
IPM-7s and
12
six Helgeson
2As were currently onsite.
The inspector
reviewed
procedures
SIC-046,
Calibration of
IPM-7, Revision 1,
dated
November 25, 1986,
and SIC-045, Calibration of HECM-2A, Revision
0,
dated
May 19,
1987,
and
inquired
as
to the
supporting
documentation
for the
set-up
parameters
dictated
by these
procedures.
Licensee
representatives
stated that the vendor's
Technical
Manuals
were
used
and
supplemented
by start-up
operational
testing
performed
by the licensee.
The licensee
could not supply specifics of the start-up testing
because
the
reports
documenting
the tests
had been lost.
Concerns
raised
by
the inspector,
such
'as
the monitors'etection
efficiency for
commonly
found
isotopes
other
than
the
used
for
calibration
and the difference in the monitors'ensitivity for
point sources
versus
plate
sources,
were not addressed
in the
Technical
Manuals.
The inspector
discussed
with the licensee
the adequacy of personnel
contamination
surveys
and the need to
review the documentation
of the operational
tests
conducted
by
the licensee.
The licensee
agreed that documentation of the old
operational
tests
should
be obtained
or that
new operational
tests
be
performed
and
properly
documented.
Documentation
supporting
the set-up
parameters
used for'he
IPM-7 and the
HECM-2A personnel
contamination monitors will be reviewed during
a
subsequent
inspection
and
tracked
by the
NRC as
Inspector
Followup Item (IFI 50-400/88-28-04).
Response
Checks
TS 6.12 allows individuals to enter high radiation areas if they
are
provided
with
a
radiation
monitoring
device
that
continuously integrates
the radiation
dose rate
and alarms at
a
preset integrated
dose.
TS
6. 11. 1 requires
that
procedures
for personnel
radiation
protection shall
be prepared
consistent with the requirements
of
10 CFR 20 and shall
be approved,
maintained
and adhered
to for
all operations
involving personnel
radiation exposure.
Health Physics
Procedure
HPP-460,
Operation of the Dositec
502A,
Revision 1, dated
June
25,
1987, states
that
a Dositec
502A may
be used if specified
acceptance
criteria are met,
one of which
is passing
a response
check.
The inspector
discussed
the source
check
and response
check of
Dositecs
with
licensee
representatives
and
reviewed
documentation
of the results.
Through discussions
and record
reviews,
the
inspector
verified that
during
the
period of
August 15-17,
1988, all
Dositec
502As
issued
from the
main
control point of the
RCP were not. response
checked prior to the
instruments
being
used.
The inspector
informed the licensee
that failure to perform the required
response
checks
was
an
apparent violation of TS 6.11. 1 (50-400/88-28-05).
13
f.
Program for Maintaining Exposures
As
Low As Reasonably
Achievable
(ALARA) (83728)
10 CFR 20. 1(c) specifies
that licensee
should
implement
programs
to
maintain workers'oses
Other
recommended
elements
of an
ALARA program are outlined in Regulatory
Guides 8.8 and 8.10.
The
FSAR, Chapter
12, also contains
licensee
commitments
regarding worker
ALARA actions.
(1)
Site
ALARA Group
Prior to the
outage,
the
ALARA group
was
composed
of one
specialist
and
one contract technician.
During the outage,
the
ALARA group
was
augmented
by
two
additional
contract
technicians.
Their major functions
were
to
review Plant
Operating
Manual
procedures,
perform pre-plan
and
post-job
reviews,
provide
trend
analyses
of
such
items
as
current
personnel
exposure,
job exposure,
and personnel
contaminations
and establis'h
and track trends
against established facility and
group exposure
goals.
The ALARA personnel
were also required to
make tours of the plant
and observe
jobs in progress
whenever
possible.
The inspector discussed
the staffing of the
ALARA group with the
E&RC Manager.
While the group
was able to perform the various
tasks
assigned, it was
apparent
that
more
personnel
would
facilitate better tracking of exposures
and more field coverage.
Licensee
management
indicated that the subject of increasing
the
size of the
ALARA staff had been considered
and that, following
the
outage,
an
increase
would again
be evaluated
and
given
serious consideration.
(2)
ALARA Subcommittee
The
ALARA Subcommittee
was
composed of representatives
from each
of the major work groups onsite.
The
PNSC representative
on the
subcommittee
was the
E&RC Manager with the
ALARA specialist
from
the
group
acting
as
committee
chairman.
The
group
was
established
to report to the
PNSC
and
make
recommendations
to
management
on
ways
to
maintain
exposures
The
subcommittee
also
functioned
as
a review committee for jobs
whose total
exposure
exceeded
25 person-rem.
The majority of
the
recommendations
made to date
consisted
of suggestions
for
plant modifications.
The committee
chairman also tracked these
recommendations
and the progress
made in implementing
them or
lack thereof.
The
subcommittee
meets
monthly
as
outlined
by procedure
to
review past
performance
and
recommendations
and
consider
new
recommendations.
The inspector
reviewed
the minutes
of the
subcommittee
meetings for 1988
and the recommendations
that had
14
been
made.
It was noted that
many of the recommendations
were
still pending.
The licensee
indicated that,
because
most of the
recommendations
dealt with plant modifications,
a great deal
of,
time
was often required
to implement the
ones that
had
been
adopted.
Job Review
The inspector discussed
the job evaluation
and review process
in
detail
with the
ALARA specialist.
Prior to
a job being
performed,
the job coordinator
was required to determine if an
ALARA prejob review was required.
If a review was required,
the
job coordinator filled out
a checklist to ensure that various
aspects
of the
job were
or
had .been
considered,
such
as,.
approval
of
procedures,
staging
of
necessary
materials,
availablity of service 'lines,
and availability of communications
equipment.
The
ALARA specialist
or his
designee
would then
complete
a checklist
addressing
such
items
as
review of
historical
data,
temporary
shielding,
and
decontamination
requirements.
For
high risk
or
complicated
jobs,
a prejob
review would be held including representatives
from the various
groups
involved to perform
and cover the work.
During such
a
review,
the
actual
details
of the job evolution would
be
reviewed
and the expected
actions -of the workers
and the results
of the work discussed.
The
inspector
also
reviewed
the job evaluation
and
review
procedure,
Administrative
Procedure
AP-514,
Job
Evaluations,
Revision 1,
dated
December
12,
1986.
While the
procedure
specifically
covered
pre-plan
and
post-job
reviews, it did not address
the subject of review of jobs/work
in progress.
The licensee
indicated that,
when the scope of the
job changed
which could entail
more exposure,
the
HP technician
covering
the
work would inform the
ALARA group.
The
specialist
would then review the
change
and make changes
to the
exposures
estimated
as
necessary.
Licensee
representatives
indicated
that
the
procedure
was
under
review
and
would
be
revised,
following the outage,
to facilitate its usage
in the
future.
The inspector
reviewed
numerous
ALARA pre-job reviews
and the
associated
documentation
delineating the estimated
person-rem to
be
expended,
the aspects
of the work considered,
any extra or
additional
requirements
established
as
a result,
and
the
required approvals.
The reviews included
S/G opening
and entry,
weld inspections,
and sludge lancing.
The-
estimates,
work reviews
and additional
requirements
appeared
to
be adequate.
All pre-job reviews
had been
approved
as required
by procedure.
15
(4)
Job Performance
The
inspector
reviewed
the
jobs
being
performed
during the
outage.
The licensee
indicated that,
as of September
1,
1988,
they were in day
34 of
a scheduled
56-day outage.
The major
jobs
performed
and the total
dose
received
in person-rem for
each job were:
Job
Pe'rson-rem
HP Coverage
5 Surveys
Scaffold
5 Insulation Work
Guide Stud Repairs
S/G Nanway Removal
Nozzle
Dam Installation
Decontamination
Section
XI Weld Inspection
S/G Secondary
Work
Reactor
Head Work/Refueling
Pump
PNs
Snubber Inspections
Routine Naintenance
Nanagement
Inspections
(5)
Annual
and Outage
Exposure
Goals
13.2
12.1
1.6
4.1
8.5
3.4
10.3
6.3
8.3
3.1
4.6
2.6
2.6
The person-rem
exposure
goal for the outage
was set at 200 with
an
annual
goal of 363 person-rem.
As of August ll, 1988, the
licensee
had
expended
approximately
63 person-rem,
including
both routine
and outage activities,
as determined
by SRPD.
The
licensee
had only expended
33 person-rem during their first year
of operations
in
1987.
Personnel
contaminations
for
1988
totaled
67, with
17 of those
occurring during the outage
to
date.
The
licensee
experienced
a total
of
87
personnel
contaminations
during
1987,
48
skin
and
39
clothing
contaminations.
No violations or deviations
were identified.
3.
Solid Waste
(87422)
10 CFR 20.311 requires
a generating
licensee
who transfers
radioactive
waste
to
a land disposal facility or to
a licensed
waste collector to
prepare
all waste
so that the waste is classified
according
to
and
meets
waste characteristic
requirements
of
The
regulation
further establishes
specific
requirements
for conducting
a
quality control
program.
16
Waste Characterization
and Classification
Licensee
representatives
stated that updated
scaling factors
used to
classify waste
streams
at the plant were received
from an offsite
vendor the
week of the inspection.
The frequency of these
updates
had
previously
been
on
a
quarterly
cycle;
however,
licensee
representatives
stated
that
beginning
next quarter,
waste
stream
sampling
and
analysis will be
on
an
annual
frequency.
Special
samples will be taken if anomalies in a system which is the source of
a waste
stream
become apparent.
Shipments
As of August 17,
1988, eight shipments
of evaporator
concentrates
solidified in
cement
had
been
made
to
a disposal
site
and
one
shipment of dry active
waste
(DAW)"was transferred
to
a licensed
waste collector.
(vendor supercompactor).
- The inspector
rev'iewed the
waste manifest for these
shipments
and verified that
requirements
had
been
met.
Licensee
representatives
stated that
no
dewatered
resins
had
been
shipped this year.
The inspector
noted
that the licensee
has
never
shipped
Chemical
Volume Control
System
(CVCS) resins
or primary water
system filters both of which have
higher specific activities
than material
currently
being
shipped.
However,
CYCS resins
and primary filters will be processed
in the
near
future
and
subsequently
shipped.
Licensee
representatives
stated
that
as
of July 20,
1988,
5,330 ft~ of radioactive
waste
containing
1.825 curies of activity had
been shipped offsite and 824
ft~ was stored onsite awaiting shipment.
Waste Segregation
The inspector
discussed
the methods
and procedures
used for release
of. "clean"
trash
and
segregation
of "contaminated"
trash
with
licensee
representatives
and
reviewed
licensee
procedure
HPP-100,
Segregation
and
Release
of
Waste
from the
RCA/Protected
Area,
Revision 2, dated
December
15,
1987.
All trash
taken from the
RCA,
both clean
and potentially contaminated,
is spread
out under
a
filtered hood.
Each
piece is then
surveyed
and segregated.
The
"clean"
bags of trash
are
then
taken to
a low background
area
and
surveyed with a microR meter
and released
to the licensee-controlled
landfill.
Licensee
representatives
stated that the landfill is also
surveyed
with
a microR meter
once
a week.
Multiple surveys of the
trash
prior to its
removal
from the
RCA is indicative of
a
radioactive
waste
program
committed
to ensuring
that radioactive
contamination is not released
to uncontrolled areas.
Process
Control
Program Procedures
TS 6.8.1 requires
that procedures
be established,
implemented,
and
maintained
covering Process
Control Program'(PCP)
implementation.
requires
that
each
procedure
of Specification
6.8.1,
and
17
changes
thereto,
shall
be reviewed
and
approved
in accordance
with
Specification 6.5. 1 prior to implementation.
During a review of the vendor supplied procedures
which implement the
Program for solidification of radioactive
waste,
the inspector
determined
that
no review
and
approval
conforming with Technical Specification 6.5.1
was
documented.
Licensee
representatives
stated
that
an informal review was conducted;
however, this review was not
documented
and
no
formal
approval
was
obtained
prior to the
initiation of waste solidification and
implementation
of the
procedures.
The licensee
produced
documentation
showing that the -NRC
had accepted
the vendor's topical report describing the mobile cement
solidification system
and
documentation
showing that
NRC acceptance
is pending for the vendor's
topical report which demonstrates
that
the
vendor's
final solidified product
meets
waste
structural
stability requirements
specified in 10 CFR Part 61.
The inspector
stated
that
these
NRC approvals
do not address
implementing
procedures
and that failure to review and approve
the
implementing
procedures
prior to implementation
was
an apparent
violation of TS 6.8.2 (50-400/88-28-06).
4.
Transportation of Radioactive Materials
(86721)
I
a.
Shipping Records
requires
that
each
licensee
who transports
licensed
material
outside of the confines of its plant or other place of use,
or who delivers licensed material
to
a carrier for transport,
shall
comply
with
the
applicable
requirements
of
the
regulations
appropriate
to
the
mode
of transport
of the
Department
of
Transportation
(DOT) in 49
CFR Parts
170 through 189.
In addition
to the
shipments
referenced
in Paragraph
3.b.,
the
inspector
reviewed selected
"special" radioactive material
shipments
shipped
in
1988.
These
shipments
included
such
items
as
hot
particles,
waste
stream
samples,
and
an alloy analyzer.
All
transportation
documentation
reviewed complied with applicable
49
CFR
regulations.
b.
Site Transportation
Organization
The transportation/shipping
staff was
composed of a foreman,
who also
assisted
HP operations
during the outage,
two permanent technicians,
and
a third position which was filled with
HP technicians
rotated
from the
HP operations
group.
Specialized training for the staff was
adequate
with retraining given at an appropriate
frequency.
18
c.
guality Assurance
Audits
Licensee
representatives
stated
that
a guality Assurance
audit
completed
in July 1988,
covered
proper
shipment
packaging
and
shipping
paper completion.
The report had not been
completed at the
time of the inspection
and
was not reviewed
by the inspector.
The
audit
was
conducted
by
gA personnel
supplemented
with technical
specialists
from other licensee facilities.
Licensee representatives
stated that no findings were identified in the area of transportation
and shipping.
No violations or deviations
were identified.
5.
Exit Interview
The inspection
scope
and results
were summarized
on August 19,
1988 and
on
September
2,
1988,
with those
persons
indicated
in Paragraph
1.
The
inspector
described
the
areas
inspected
and
discussed
in detail
the
inspection findings listed below.
No dissenting
comments
were received
from the licensee.
The licensee
did not identify as proprietary
any of
the material
provide to or reviewed
by the licensee.
Item Number
Descri tion and Reference
400/88-28-01
Violation - Failure to provide the proper monitoring
device for an individual entering
a high radiation
area,
Paragraph
2.c.
400/88-28-02
400/88-28-03
400/88-28-04
400/88-28-05
400/88-28-06
Violation - Inadequate
surveys of items released
from
a contaminated
area,
Paragraph
2.e.
IFI - Review wearing of protective clothing in
contaminatied
areas,
Paragraph
2.e.
IFI - Review documentation for pre use test of the
IPM-7
and
HECM-2A personnel
contamination
monitors,
Paragraph
2.e.
Violation - Failure to follow procedure for response
checking alarming dosimeters,
Paragraph
2.e.
Violation - Failure to review
and
approve Process
Control
Program
implementing
procedures,
Paragraph
3.d.
6.
Acronyms and Initialisms
As Low as Reasonably
Achieveable
ANSI
American National Standards
Institute
cpm
Counts
Per Minute
Dry Active Waste
19
ESRC
ft3
GM
IFI
IN
MPC-hr
mrem/hr
PCs
. PNSC
R/hr
RCB
S/G
SRPD
SRWP
TS
Department of Transportation
Environmental
and Radiation Control
Final Safety Analysis Report
Cubic Feet
General
Employee Training
High Efficiency Particulate Air (Filter)
Health Physics
Inspector Followup Item
Information Notice
Minimum Detectable Activity
Maximum Permissible
Concentration
Maximum Permissible
Concentration-hour
Millirem per hour
National Voluntary Licensee Accreditation Program
Personal
Protective Clothing
Process
Control
Program
Plant Nuclear Safety Review Committee
Quality Assurance
Roentgens
per hour
Radiation Control Area
Reactor
Containment Building
Radiation
Work Permit
Self-Contained
Breathing Apparatus
Self-Reading
Dosimeter
Self-Reading
Pocket Dosimeter
Special/Standing
Radiation
Work Permit
Thermoluminescent
Dosimeter
Technical Specification
Whole Body Count