ML18005A631
| ML18005A631 | |
| Person / Time | |
|---|---|
| Site: | Harris |
| Issue date: | 09/26/1988 |
| From: | Herdt A NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| To: | Utley E CAROLINA POWER & LIGHT CO. |
| Shared Package | |
| ML18005A632 | List: |
| References | |
| NUDOCS 8810070321 | |
| Download: ML18005A631 (3) | |
See also: IR 05000400/1988031
Text
ACCELERATED
DISTRIBUTION
DEMONSTRATION
SYSTEM
~
~
j
REGULATORY INFORMATION DISTRIBUTION SYSTEM (RIDS)
ACCESSION NBR:8810070321
DOC.DATE: 88/09/26
NOTARIZED: NO 'OCKET g
FACIL:50-400 Shearon Harris Nuclear Power Plant, Unit 1, Carolina
05000400
AUTH.NAME
AUTHOR AFFILIATION
HERDT,A.R.
Region 2, Ofc of the Director
RECIP.NAME
RECIPIENT AFFILIATION
UTLEY,E.E.
Carolina Power
& Light Co.
SUBJECT:
Forwards Insp Rept 50-400/88-31
on 880822-26.No violations
or deviations noted.
DISTRIBUTION CODE: IEOID
COPIES RECEIVED:LTR J
ENCL
i
SIZE:
TITLE: General
(50 Dkt)-Insp Rept/Notice of Violation Response
NOTES:Application for permit renewal filed.
o5ooo4oo >
RECIPIENT
ID CODE/NAME
PD2-1
INTERNAL: ACRS
DEDRO
NRR/DLPQ/PEB 11
NRR/DOEA DIR 11
NRR/DREP/RPB
10
NRR/PMAS/ILRB12
EXTERNAL: LPDR
'OPIES
,LTTR ENCL
1
1
2
2
1
1
1
1
1
1
2
2
1
1
1
1
1
1
1
1
~
)' RECIPIENT
ID CODE/NAME
BUCKLEY,B
NRR MORISSEAU,D
NRR/DLPQ/QAB 10
NRR/DREP/EPB
10
NRR/DRIS DIR 9A
NUDOCS-ABSTRACT
OGC/HDS1
RES/DSIR
DEPY
NRC PDR
COPIES
LTTR ENCL
2
2
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
i'
TOTAL NUMBER OF COPIES
REQUIRED
LTTR
25
ENCL
25
SEP 261986
yzIIm
Docket No. 50-400
License
No.
Carolina
Power
and Light Company
ATTN:
Mr. E.
ED Utley
Senior Executive Vice President
Power Supply and Engineering
and Construction
P.
O.
Box 1551
Raleigh,
NC
27602
Gentlemen:
SUBJECT:
NRC
INSPECTION
REPORT
NO. 50-400/88-31
This refers to the Nuclear Regulatory
Commission
(NRC) inspection
conducted
by
R.
P. Carrion
on
August 22-26,
1988.
The
inspection
included
a
review of
activities
authorized
for your Harris facility.
At the
conclusion
of the
inspection,
the
findings
were
discussed
with those
members
of your staff
identified in the enclosed
inspection report.
Areas
examined
during
the
inspection
are identified in the report.
Within
these
areas,
the
inspection
consisted
of selective
examinations
of procedures
and
representative
records,
interviews with personnel,
and
observation
of
activities in progress.
Within
the
scope
of
the
inspection,
no violations
or deviations
were
identified.
In accordance
with Section
2.790
of the
NRC's
"Rules of Practice,"
Part 2,
Title 10,
Code of Federal
Regulations,
a copy of this letter and its enclosures
will be placed in the
NRC Public Document
Room.
Should you have
any questions
concerning this letter,
please
contact
us.
Sincerel
Alan R. Herdt, Chief
Engineering
Branch
'ivision of Reactor Safety
Enclosure:
NRC Inspection
Report
cc:
(See
page
2)
881007032l
880926
ADOCK 0 000400
0
SEP 26 1988
Carolina
Power
and Light Company
J.
cc w/encl:
R. A. Watson,
Vice President
Harris Nuclear Project
gD.
L. Tibbitts, Director of Regulatory
Compliance
C.
S. Hinnant, Plant General
Manager
State of North Carolina
bcc w/encl:
. Barth,
JJRC Resident
Inspector
/A. Upchurch,
Chairman,
Triangle J
Council of Governments
DRS, Technical Assistant
Document Control
Desk
R I
PC.
RPCarrion:es
9/~l/88
Blake
~/88
RII
PFre rickson
9/~+8