ML18005A369
| ML18005A369 | |
| Person / Time | |
|---|---|
| Site: | Harris |
| Issue date: | 02/22/1988 |
| From: | Blake J, Robert Carrion, Lenahan J NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| To: | |
| Shared Package | |
| ML18005A361 | List: |
| References | |
| 50-400-87-41, NUDOCS 8803160361 | |
| Download: ML18005A369 (22) | |
See also: IR 05000400/1987041
Text
~gA REgII
0
A
0
k~*~+
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION II
101 MAR I ETTA ST R E ET, N.W.
ATLANTA,GEORGIA 30323
Report No.:
50-400/87-41
Licensee:
Carolina
Power
and Light Company
P. 0.
Box 1551
Raleigh,
NC
27602
Docket No.:
50-400
License No.:
Facility Name:
Harris
1
Inspection
C
te
ovember
16
December
11,
1987
Inspectors
JC.
Approve
b
Lena
n
ar
on
lake, Chief
terials
and Processes
Section
ivision of Reactor Safety
Date Signed
gg.
Ge
Date Signed
Z2. S~
Da
e Signed
SUMMARY
Scope:
This
special
announced
inspection
was
in the
areas
of followup on
previous inspection findings and
on concerns
pertaining
to design activities.
Results:
One violation was identified - Uncontrolled
Change to Design Input,
paragraph
6.b.
8803 fbp3b> 85000400
apg25
ADOCH 0
0
REPORT DETAILS
Persons
Contacted
Licensee
Employees
p.
V.
"R.
A.
AAAJ
G.
J.
- R.
M.
8*D
J.
%*M
R.
L. Brady, Civil Engineer
Cox, Project Specialist,
Electrical
Knott, Structural
Engineer
Lewis, Civi 1 Engineer
I. Loflin, Manager,
Harris Plant Engineering
Section
W. McKay, Resident Civi 1 Engineer
A. Meyer, Manager, Modifications Projects
A. Nevi 11, Manager,
Nuclear
Engineering
Department
Panelle,
Senior Structural
Engineer
Sealey, Civil Engineer
Stephenson,
Senior Structural
Engineer
Tibbitts, Manager,
Licensing
Turner, Civil Engineer
Wagner,
Manager,
Plant Engineering
G. Wallace,
Regulatory
Compliance Specialist
A. Watson, Vice'resident,
Harris Plant
L. Williams, Principal
Engineer
Other licensee
employees
contacted
included four civil engineers,
and
one
electrical specialist.
NRC Resident
Inspectors
S.
P. Burris
G. Maxwell
"Attended November
20 exit interview
"*Attended December ll exit interview
"**Attended both exit interviews
2.
Exit Interview
The
ins'pection
scope
and
findings
were
summarized
on
November
20
and
December."11,
1987,
with those
persons
indicated
in
paragraph
1.
The
inspector
described
the
areas
inspected,
and
discussed
in detail
the
inspection findings listed below.
Dissenting
comments
were not received
from the licensee.
The following new items
were identified during this
inspection:
Inspector
Followup item 400/87-41-01,
Add ANSI N690-1984 to List of
Applicable
Codes,
Standards
and
Specifications
in
Section
3.8.3.2.
Violation 400/87-41-02,
Uncontrolled Change to Design Input
q P
The licensee
did not identify as proprietary
any of the material
provided
to or reviewed
by the inspectors
during this inspection.
3.
Licensee Action on Previous
Enforcement Matters
(Closed)
Violation item 400/86-69-01,
Failure to Protect
Permanent
Plant
Equipment.
This violation involved
craftsmen
using
safety
related
cable
trays
as
and
attaching
to
permanent
safety-related
equipment.
The
licensee's
corrective
actions
for this violation are
stated
in their
December ll, 1986
response
to
NRC Region II for Inspection
Report
No. 50-400/86-69.
The cause of this violation was that the two craft personnel
who were
using
cable
tray
L1901
SR4
as
scaffolding failed to follow Work
Procedure
WP-48.
To correct this problem,
personnel
and construction
materials
were
removed
from the cable tray and the tray and installed
cables
were
inspected
for damage.
No
damage
was
noted.
The
two
craft
personnel
and their
foreman
were
reprimanded
and
the
construction
manager
issued
a
memorandum
dated
September
8,
1986 to
the project craft supervisor reiterating the requirements
of WP-48.
Regarding
the scaffolding which was attached
(wired) to an instrument
tubing track
and
was in contact with an
HVAC valve actuator,
the
licensee's
corrective
actions
included relocation of the scaffolding
and inspection of the track and actuator for damage.
No
damage
was
noted.
The
foreman
responsible
for erection of the scaffolding was
reprimanded.
b.
The
inspectors
examined
CP&L procedure
number
CMP-4,
Rigging
and
Temporary
Loads,
and
procedure
number
MMM-022, Rigging
Loads
from
Permanent
Plant Components.
These
procedures
were written to replace
procedure
WP-48 which was
a construction
procedure
and control
the
attachment
of rigging
and
temporary
loads
to
permanent
plant
equipment.
Violation 400/86-69-01 is closed.
(Closed)
Unresolved
Item
400/86-69-03,
Evaluation
of Containment
Bui'1'ding
Load
Reversal
Design
Error
as
Nonconformance
and
for
Reportability
to
NRC.
During
the
special
inspection
conducted
S'eptember
4-11,
1986,
documented
in
Inspection
Report
Number
50"400/86-69,
licensee
design
engineers
informed the inspector
that
errors
were
discovered
in
the
original
EBASCO
design
for
the
containment
building
(CB)
platform
steel.
Unresolved
Item
400/86-69-03
was identified by the inspectors
as
a result
of the
fai lure of the licensee
to write an
NCR to document
and disposition
this problem.
Subsequent
to inspection
86-69,
the
inspector
held
further discussions
with licensee
engineers pertaining to the final
design
verification
program
for the
CB platform steel.
These
discussions
disclosed that the final design verification program
was
a
systematic
in-depth
review of the
EBASCO design
and
was
being
conducted
to
include all
final
attachment
loads
(e.g.
piping,
equipment,
conduit cable trays, etc.) which were not in the original
analysis.
The
purpose
of this
review
was
to verify that
the
"as-built"
CB platform steel
structures
conformed to
and
NRC
design
requirements,
and
to modify the
CB steel
structures
when
necessary
to
restore
the
original
design
margin.
The
discussions
also
disclosed
that
the
licensee
only
suspected
the
problem concerning
the
load reversals
during inspection
86-69.
The
extent of the
problem
was
not identified until late September
1986,
after conferring with the
EBASCO design
engineers,
and
performing
some
additional
design
verification studies.
At that
time,
86-600
was written to disposition
the
problem.
The
CB steel
design
verification program
and disposition of
NCR 86-600
was tied to
an
oral
commitment to re-inspect
on the connections
for the
92
heaviest
loaded
beams
on the
CB platform.
This commitment
was
made
by
a
licensee
representative
during
the
September
4-11,
1986
inspection.
These
beams
were
defined
as
those
loaded
to 0.85 or
greater of the
code
allowable
stresses
(Note:
In Inspection
Report
Number 50-400/86-69,
this definition was incorrectly written that the
heavily
loaded
beams
were those
loaded at 0.75 or greater of the code
allowable
stresses.
The figure of 0.75 is in error.
The correct
figure should
have
been 0.85.)
During the licensee's
in-depth review
of
the
CB platform
steel
design,
licensee
engineers
identified
several
questions
regarding
design methodology.
These questions
were
documented
and
resolved
in
memoranda
and
various
design
calculation
books.
The
inspector
reviewed
portions
of the
CB
structural
steel
design calculations.
The calculations
reviewed are
discussed
in paragraphs
5.b and S.c below.
Based
on the discussions
with licensee
engineers,
review of various
design
calculations,
and
other
documentation,
and
review of the
sequence
of events,
the s"nspectors
concluded that
NCR 86-600
was not
reportable
under
and
that
the
licensee
acted
properly in delaying initiation of an
NCR unti 1 late
September
when
NCR 86-600
was issued.
Unresolved
Item 400/86-69-03 is closed.
(Open)
Violation Item 400/86-77-01,
Failure
to
Implement
Adequate
Design Control Measures.
The licensee's
corrective actions for this
violation
are
stated
in their July 2,
1987,
August 4,
1987,
and
October
30,
1987
responses
to'RC
for
Inspection
Report
No.; 50-400/86-77.
The
August 4,
1987
response
corrected
some
statements
in
the
July 2,
1987
response.
The
October
30,
1987
response
extended
the date for completion of corrective action from-
November
1987 to March 31,
1988.
The cause of the violation was
due
to errors
in
design
assumptions
made
for distribution of weld
stresses
under specific connection
types
and loading conditions.
In
addition,
a. supervisor
was
involved
in
the
design
verification
process
for the calculation
for
FCR-AS-10360
in violation of the
licensee's
design
control
procedures.
The licensee's
actions
to
correct this violation involved review of the specific calculations,
i.e.,
Detail
G,
and
FCR
AS-10360,
which contained
the errors
in
design
assumptions
identified in the violation.
This
review
was
accomplished
during the inspection
and resulted
in issuance
of
NRC
Nos.
OP-86-0183
and
OP-86-0185
to
document
and
disposition
these
design
errors.
The specific errors
were corrected
through issuance
of field modifications for Detail
G and
a plant
change
request
for
the
spent
fuel
rack
support
design
(FCR
AS-10360).
Further
corrective
action
included
review of civil-structural calculations
for the
CB platform steel,
the
248 platform steel
and
steam
generator
lower lateral
supports.
This
review
has
been
completed
within the
corporate
Nuclear'ngineer
Department,
Civil-Structural
Design
Section.
However,
due
to
other
concerns
identified
by
individuals within the
CP&L organization
regarding
these
same design
calculations,
the
licensee
has
decided
to
conduct
an
independent
review of these
calculations
and
others
which involve structural
steel
design at the Harris Plant.
NCR Nos.
OP-86-0183
and
0185
are
still
open
pending completion of this independent
review.
The scope
of the
independent
review is outlined
in
a
CP&L memorandum
from
R. A. Watson
to
A. B. Cutter
and
HE
R.
Banks
dated
September
15,
1987, Subject:
Independent
Review of Structural
Steel
Design Issues.
This
memorandum
summarized
the areas
of concern
expressed
by various
individuals within the
CP&L organization.
The
concerns
are
as
fol 1 ows:
(1)
Potential
errors
in
248
platform
steel
calculations
identified in CP&L Letter No. MS-876288(E),
dated June
22,
1987.
(2)
Effect of addition of attachments
to the
lower
lateral
supports.
(3)
Resolution of previously identified design deficiencies
in the
CB
platform
steel
calculations.
Also,
the
resolution
of
questions
raised
by HPES engineers
during review of the platform
steel
design.
The
questions
regarded
the
original
EBASCO
'design.
(4)- Possible
discrepancies
in the
HPES civil program for cataloging
,j:;-";-",'.and analyzing the effects of additional
attachments
to various
> -"..'-;:l':steel
structures.
(5)"'ossible
improper
FCR/FM justifications performed
by the
HPES
civil unit,
The inspectors
discussed
the
independent
design
review program with
the Manager of the Nuclear Engineering
Department.
These discussions
disclosed
that
an outside
consultant will be
retained
by
CP&L to
perform
an overall
review of the structural
steel
design
to assess
proper methodology in relation to AISC Code compliance.
In addition,
a
detailed
review will
be
conducted
by
two
senior
structural
engineers
who were not involved in the Harris structural
steel
design
work.
These
individuals are
independent
and
do not work under the
supervision of the principal engineer
who was formerly the Hanager of
the
HPES civil unit.
The results of the Independent
Review of the Harris Structural
Steel
design
issues will be examined
by
NRC Region II.
Pending
completion
of this review,
and closeout
of
NCR OP-86-0183
and
0185, Violation
Item 400/86-77-01 will remain
open.
(Open) Violation Item 50-400/86-77-02
Undersized
on Cable Tray
Supports.
The licensee's
corrective
actions for this violation are
stated
in their July 1,
1987
response
to
NRC for Inspection
Report
50-400/86-77.
The
cause
of the violation was due to failure of the
welders to provide acceptable
weld profiles
on the identified Detail
G welds
and fai lure of the
QC inspector s to identify the undersized
The licensee
issued
Nonconformance
Report
numbers
OP-86-0149
and
OP-86-163
to
document
and di sposition
the
undersized
Detai 1
G
During construction
of the Harris Plant,
the licensee's
staff issued
several
NCRs regarding
undersized
These
NCR were
examined
by a Region II QA specialist during the September
4-11,
1986
inspection.
(Note:
For
a listing of these
see
Inspection
Report
Number
50-400/86-69.)
An indepth
review of
the
licensee
corrective
actions
pertaining
to identification
and correction
of
undersized
structural
steel
welds will be conducted
by
a
Region II
welding
specialist
(i.e.
Metallurgical
Engineer
or
an
specialist).
Pending
completion
of this
review,
Violation
Item
86-77-02 will remain
open.
4.
Unresolved
Items
Unresolved
items were not identified during this inspection.
5.
Case
RII"87-A"0086
Background
An,individual, hereinafter referred to as the alleger,
contacted
NRC
Region II and expressed
several
concerns relating to undersized
on',;,structural
steel,
structural
steel
design
methodology
and design
of;;-; welded
pipe
. attachments.
Followup
on
these
allegations
is
discussed
in paragraphs
5.b through 5.d below.
Deficiencies in Structural
Steel
Design
(1)
Concern
Design deficiencies
were previously identified by
NRC on major
structural
calculations.
Other
structural
steel
design
deficiencies
were also identified by licensee
engineers 'in
an
internal
memorandum
dated
June
22,
1987.
In addition,
there
are other questions
regarding
design
of the containment
building structural
steel.
These
concerns
are listed
in the
table below.
TABLE
CB Platform Steel
Design Concerns/Contentions
Concern
Number
Contention
'onnections
were
modeled
in
the
computer
analysis
as pinned connections
when in fact
some
were
as
built
as
rigid
(fixed)
connections.
Stress
calculations
were not performed for
angles
and plates in some connections.
Load reversals
not
summed correctly.
Eccentricity not considered
in connection
or
weld design.
Wrong load case
chosen
as most critical.
Torsional
loads not considered.
Whip restraint'loads
not considered.
Expansion
joints
used
to limit thermal
stresses
are not functional.
The value for accident
thermal
temperature,
i.e.
hT = 148'F,
was not justified.
10
Use
of
1. 1
interaction
factors
were
not
justified.
Reduced
horizontal
"g" values
were applied
to vertical
loads in seismic analysis.
12
Supplemental
steel
was
added to
CB platform
to stiffen
member
and
reduce
weak
areas
stresses.
However,
the
loads
from
the
supplemental
steel
were
not
included
in
analysi s.
13
Hanger foot print loads were not resolved to
beam centroids,
14
15
Effect of
DBE loads
from pipe
supports
on
platform steel
not checked.
l
Use
of rigid plate
theory
used
to
check
embeds is not justified.
Discussion
The
design
deficiencies
discussed
by the alleger
which were
identified
by
NRC
are
those
associated
with Violation
Item
400/86-77-01.
These
deficiencies
involved
the
Detail
G
connection
on
Drawing
number
CAR 2168-G-251-501
(containment
building cable
tray
frames)
and incorrect application of the
AISC Ultimate Strength
Method for welds in design of connections
for the
new fuel pool racks covered
by
FCR AS-10360.
As stated
in
paragraph
3.c
above,
the
licensee
issued
numbers
OP-86-0183
and
OP-86-0185
to
document
and disposition
these
errors.
The
248 platform steel
concerns
are
documented
in
Letter
No. MS-876288(E),
dated
June
22,
1987.
This letter is
discussed
in Paragraph
3.c above.
The
15 specific concern/contentions
regarding
the
CB platform
steel
were identified by
CP&L structural
engineers
employed in
the Harris Project
Engineering Staff Civil Structural
Unit in
Fall
1986,
during
the
final
design
verification of
the
CB
platform steel
design.
These specific questions
were
addressed
to
the
Harris project Architect-Engineer,
EBASCO in
a
hand
written
telecopy
transmitted
to
EBASCO
at
4:03
p.m.
on
October 20,
1986.
The
inspectors
reviewed
a
copy
of thi s
telecopy
and noted that the alleger's
concerns
are
verbatim
as
those listed in the telecopy.
The
EBASCO response
to the
questions
is
documented
in
an
EBASCO
'memo
to
Lee Williams/Ron Knott
(CP&L
HPES)
from
T. McCarthy
(EBASCO)
dated
January
6,
1987,
Subject:
Harris
RCB
Platform
Supplementary
Analysis.
Additional
responses
to address
these
concerns
were
prepared
by the
CP&L Design
Engineers
to cross
reference
responses
to
the
concern/contentions
to
specific
EBASCO or
CP&L design
calculations.
This cross
reference
is
outlined
as
an undated,
unlabeled listing of 16 contentions
and
specific
response
(including
referenced
calculation)
which
addressed
the contentions.
The cross
reference
is included in
the
CB structural
steel calculation books.
In response
to this concern,
a review of the calculations
for
the
containment
platforms
was
conducted
by
a
Region II
structural
engineer
to
make
a
more
detailed
evaluation
concerning
the
adequacy
of
the
CB platform
steel
design.
Specif'ically,
several
highly-stressed
beams
(as
determined
by
CP&L and
EBASCO to have Interaction
Equation
values
exceeding
0.85)
were
checked
to verify design
procedures,
including
assumptions,
load combinations
and factors,
allowable stresses,
and structural
configuration.
Also, the calculations
for the
connections,
including welds, clip angles,
and
embedded
plates,
of
the
respective
beams
were
examined.
The
beams
checked
included
514,
515,
517 of the
Load Verification Calculation,
LV54,
Volume 4.
In
addition,
calculation
number
CAS15,
"Containment
Building
Platform
Static
Analysis
- Revised
Stresses,"
which is
a compilation
of
beams
which
EBASCO
was
unable
to
qualify
when
using
the
original
design
load
assumptions,
was reviewed.
(3)
The
preliminary
conclusion
reached
upon
completion
of this
evaluation
is that
the calculations
have
been
performed
in
a
manner consistent
with professional
standards
of practice
and
satisfy
design
and
requirements.
However,
additional
review of the structural
steel
design
concerns will be conducted
by
NRC
Region II in closeout
of Violation Item 400/86-77-01,
following completion
of the
licensee's
independent
review of
structural
steel
design
concerns
discussed
in paragraph
3.b.
Findings
The
concerns
expressed
by
the
alleger
had
been
previously
documented
by the licensee
in various internal
CP&L documents,
or had
been
previously identified by
NRC.
These
concerns will
be
further
evaluated
by
NRC
following
completion
of
the
independent
review being conducted
by the
licensee,'uring
review of calculation
LV-54, the inspectors
noted that
thermal
loads were'valuated
using
methods
specified
in
ANSI
N690-1984,
Steel
Structure - Design.
This design
is based
on
steel ductility and local effects of thermal
stresses.
During
review of the
FSAR, the inspectors
noted that this ANSI standard
was
not referenced.
The
inspectors
discussed
with licensee,
engineers
the
need
for
referencing
this
standard
in
the
appropriate
FSAR Section
(Section 3.8.3.2)
when
the next
'.'j.:; amendment is submitted to
NRC the Licensee.
This was identified
- -",to the licensee
as
Inspector
Followup Item 87-41-01,
Add ANSI
';:.,;,...;N690-1984
ta
List
of
Applicable
Codes,
Standards
and
Specification in
FSAR Section 3.8.3.2.
c.
- Undersized
Melds on Structural
Steel
Connections
Concern
Compounding
the
concerns
discussed
in
Paragraph
5.b.,
above,
there
are
an
unknown
number of undersized
on structural
steel
connections.
As
an
example,
the
alleger
stated
that
undersized
were
found in
126 of 187 connections
examined
on the
CB platform steel.
The connections
had to
be modified
because
of the undersized
(2)
Discussion
The
licensee
examined
92 of the
highest
stressed
beams
for
possible effect of undersized
This was in response
to
concerns
expressed
by
NRC Region II during the
September
4-11,
1986
inspection
which
are
documented
in
Inspection
Report
Number 50-400/86-69.
In addition to these
184 connections
(92
beams
x
2 connections
per
beam
= 184),
the
licensee
evaluated
three
other individual connections
which were considered
to be
critical and highly stressed
(Note:
Highly Stressed
is defined
as
a
beam
loaded to greater
than 0.85 fy).
In order to perform
the evaluation,
a detailed as-built sketch
was prepared of each
on
each connections.
These
weld sketches
were attached
to
number
86-0542.
Review of weld
sketches
showed
that at
least
one
was
undersized
on
126
of
the
connections.
However, in all but
a
few cases,
the effect of the undersized
was offset
by oversized
in other
parts
of the
connection.
The
inspectors
examined
the
design
document
(design
change
notices,
field
change
requests,
and
modification
packages)
listed below which were issued to modify the
CB platform steel
connections.
The
inspectors
also
examined
the calculations
associated
with the modification
packages.
A
summary
of the,
design
documents
reviewed
by the inspectors
is listed below.
DCN 650-960,
issued
on March 19,
1986,
by
EBASCO to modify
connections
on
CB steel
platforms due to increases
in loads
from attachments
to platforms.
This
DCN involved the more
highly stressed
beams
which
had
been identified by
EBASCO
prior
to
the
time
the
structural
st'eel
design
was
transferred
from EBASCO to the
CP8 L onsite
HPES unit.
FCR AS-10481
issued
on
May 28,
1986 to revise details
on
DCN 650-960 for modifications to connections
on elevation
261
CB platform at azimuths 5'-9', 266',
30',
and
345'.
The
FCR
was
required
due
to field conditions
and
interferences.
FCR-AS-10546,
issued
on June
12,
1986, to revise details
on
DCN 650-960 for modification to connections
on elevation
286 at azimuths
330
and
345
.
The
FCR was required
due to
field conditions
and interferences.
Field Modification (FM)
C 6525,
issued
October 5,
1986, to
modify four connections
to increase
capacity of connections
to carry additional vertical loads.
10
FM
C
6526,
issued
October 4,
1986,
to
modify five
connections
due to torsional
loads.
FM
C
6527,
issued
October
5,
1986,
to
modify three
connections
due
to
loads
from the
main
steam
line whip
restraints.
One of these
connections
number 236-C3822N-188
had
been
undersized.
The
specified
weld size
(per
the
original design drawing) was 0.3125 inches.
The "as-built"
weld size
was 0.281 inches.
The required weld size,
due to
the increased
loads
was 0.345 inches.
FM
C 6529,
issued
October 4,
1986, to modify one connection
by installation of two 7/8
inch diameter
high
strength
bolts.
Modification was
due to increase
in loads acting
on
CB platform due to attachments.
FM
C
6531,
issued
October 7,
1986
to
modify five
connections
due to increased
loads
from attachments
to the
CB structural
steel
platforms.
The modifications involved
increasing
weld sizes
(beyond those originally specified),
or addition of high strength bolts to the connections
FM
C
6535,
issued
October 8,
1986,
to
modify
two
connections
due to torsional
loads
and to add seat plate to
one
connection
due
to
increased
vertical
loads
due
to
attachments.
The original designed
weld on this connection
was overstressed
due to new attachment
loads.
FM
C
6539,
issued
October 9,
1986,
to
modify
two'onnections
due to torsional
loads.
FM
C
6542,
issued
October 30,
1986,
to
modify
two
connections
due
to
increased
loads,
and
to
remove
the
modifications
installed
under
DCN 650-960
on
one
connection.
The
removal
consisted
of cutting the plates
attached
to the flanges
on Connection
Number 261-C3822N-575
so the connection
would behave
as pinned connection rather
than
a fixed connection after the plates
were installed.
The fixed connection
was undesirable
since
high stresses
were transferred
from the
beam into the
embed plate at this
connection.
FM
C
6543
modified
once
connection
due
to construction
problem
(nuts
were
not
tightened
on
bolts
and
w'ere
inaccessible
due to interferences
added
since the bolt were
installed).
Review of the calculations
and modifications listed above
showed
that the welds were modified (enlarged)
due to changes
in loads
during final platform steel
design 'verification
program,
not
because
of undersized
11
(3)
Findings
The
concern
was
not substantiated.
Although undersized
existed
on
some
connections,
modifications
to
the
welds/connections
were
not required
because
of the undersized
welds, but as
a result of additional
loads
from new attachments
~ to
the
structural
steel
platforms.
The
analysis
of
the
additional
attachment
loads
were part of a planned
systematic
design
program.
d.
Design of Welded Pipe Attachments
Concern
Problems
were identified with design of welded pipe attachment.
The criteria
used
to
design
the
attachments
(e.g.,
lugs,
trunnions,
etc)
was
inconsistent
and
was
not
properly
documented.
(2)
Di scussion
This is similar to the concern
expressed
in guality Check 9950.
An
evaluation
of welded
pipe
attachment
(WPA) calculations
disclosed
inconsistencies
in use of various coefficients (e.g.
Beta factors
and load coefficients).
To respond to the (}uality
Check,
licensee
engineers
conducted
a review of 125 pipe
hanger
designs
which included
a welded pipe attachment.
This review
disclosed that there
were inconsistencies
in selection
of load
coefficients
and
Beta
factors.
However,
all
calculations
reviewed were found to
have
used
acceptable
load coefficients,
although
in
some
cases
they
result
in
higher
calculated
stresses.
The review disclosed
that in
some calculations
very
conservative coefficients were
used
in calculating
load stresses
in the pipe wall at the
WPA, while in othe'r cases,
the correct
value listed in various Beta and/or load coefficient tables
was
used
in
the
calculation.
Use
of
the
conservative
load
coefficient
values
resulted
in calculation
of higher
local
stresses
in the pipe welds.
For'example,
since
pipe stress
is
-'~'--,.'.based
on the
load coefficient or Beta factor multiplied by the
applied
loads acting
on the pipe at
the
WPA,
use
of
a
Beta'actor
or load coefficient of 0.4 when the correct value
was 0.3
would result in a
33 percent
increase
is calculated
stresses
in
the pipe (0.4/0.3
= 1.33).
Therefore
even
though
an incorrect
factor
was
used
in
the
analysis,
its
use
had
no
safety
significant
since
the
errors
were
always
in the conservative
direction.
During review of the
125 calculation
packages,
minor errors were
found
in eight
supports
calculations.
These
errors
were
not
associated
with the
Beta
factor s or load coefficients.
The
12
,':l,icensee
issued
NCR 87-096
to document
and disposition
these
minor errors.
Correction
of the
problems
resulted
in minor
revisions
to the calculation
packages.
No work was required to
modify the hangers
affected
by the minor calculation errors.
In order to assure
that consistent
values for load coefficients
would
be
used
in future design of welded pipe attachments,
the
licensee
issued
NED
Design
Guide
No. DG-II.12,
Design
and
Analysis of Welded Pipe Attachments for the Harris Project.
The
inspector
reviewed this design
guide
and
found that it clearly
establishes, requirements
to
be
used
in calculation
of local
stresses
in pipe walls at the
WPA.
(3)
Finding
The concern
was substantiated
in that criteria used in design of
welded pipe attachments
was inconsistent.
However this problem
had
been previously identified and resolved
under the licensee's
guality Check Program.
Although inconsistencies
were identified
in
some calculations,
these
inconsistencies
did not result
in
nonconservative
piping designs.
The inconsistent
use of load
coefficients resulted
in more conservative
calculated
stresses
and thus did not affect any hardware.
Thus, this substantiated
concern
has
no safety significance.
Previously Identified Inspector
Follow-up Items
a.
(Closed) IFI 400/86-69-02,
Reinspection
of Shared Electrical Supports
for Deleted Conduit
During the September
4-11,
1986
NRC inspection,
a Region II inspector
examined
the
shared
conduit
support
problems
identified
on
86-0444.
The
NCR documented
discrepancies
identified by the licensee
during
walkdown
inspections
of non-nuclear
safety-related
(NNS)
conduits
which disclosed
that installation of
NNS conduit supports
that
share
supports
with
safety-related
raceway
had
not
been
inspected
for seismic attributes.
The cause
of this problem was due
to'insufficient instructions
in
CP&L Procedure
Inspection
of
Non-,Safety
Related Electrical
Raceways,
to assure
that installation
of,"'.NNS conduits that shared
supports with safety-related
(SR) conduit
would be inspected
to verify that seismic installation requirements
were completed
as noted
on Sheet
14 of Drawing number
CAR 2166-B-060.
'n order to correct this problem,
the licensee
amended
Revision
7 of
procedure
TP-51 with
a
procedure
change
notice
(PCN) to clearly
specify that
NNS conduit that shares
supports with SR conduit are to
be inspected
to assure installation conforms to seismic
requirements.
The
NNS conduits
listed
in
NCR 86-0444
were reinspected.
Conduit
found with unacceptable
seismic
installations
were
reworked
and
reinspected.
Some
of
the
rework
involved
removal
of
temporary
conduits that
had been installed for construction,
and other conduit
13
no longer required
due to design
changes
and thus were scheduled
to
be
removed.
These
conduits
are referred
to
as
"deleted
conduit".
During
the
September
4-11,
1986
inspection,
an additional
conduit
number
17129K,
on
a
shared
support
was
identified
which
lacked
inspection
records
to verify compliance
with seismic
attributes.
This problem was documented
on
NCR 86-0555.
To correct this problem,
conduit
17129K
was
inspected
for seismic
installation attributes.
The
installation
was
found
to
be
acceptable.
The
licensee's
corrective
actions to resolve
the shared
support
problems
included
a
detailed
walkdown program to identify all
NNS and "deleted"
conduits
which share
supports with SR conduit,
review of inspection
records
to
verify NNS conduit
on
shared
supports
had
been
inspected,
necessary
rework
to
correct
shared
support
problem
identified
during
inspection,
removal
of
"deleted"
conduit
where
required,
and
documentation
of inspection
of
NNS conduit
on
shared
supports
when
records
were
found to
be
incomplete.
In addition,
the
Regulatory
Guide
1.29
walkdown program,
discussed
in paragraph
6.d below,
was
another
program
conducted
in'dependent
of
the
resolution
of
86-0444
and
86-0555
to identify potentially inadequately
supported
non-safety
related
equipment
which could affect
SR equipment.
The
inspectors
examined
documentation
supporting closeout of NCR 86-0444
and
-0555
and the following memorandums
which
summarize
corrective
actions
to resolve
shared
support problems:
Memorandum
to
A. H. Rager
from
V. Cox/J. Martin
dated
September
22,
1986, Subject:
Deleted Conduits
Memorandum
to
M. Holveck
from
V. Cox,
dated
October 3,
1986,
Subject:
Response
to
Concern
Related
to Deleted
Conduits Installed
on Shared
Supports
Memorandum
to
V..Cox
from J. Frantz,
dated
October
28,
1986, Subject: 'hared
Support Walkdown
Memorandum
to
File
HXDE-2XX-XXX-516 from
J. Martin /
M. Bodnar,
dated
November 24,
1987,
Subject:
Deleted
Conduit
Subsequent
to closeout
of
NCR 86-0444
and -0555,
NCR OP-86-0121
was
issued
on
October 24,
1986,
regarding
identification
of
two
addi.tional
conduits,
numbers
19567K
and
16231U,
which
had not
been
inspected
for seismic attributes
during original installation.
The
conduits
were
inspected
for
seismic
attributes
to
resolve
this
problem.
Conduit
16231U
was
acceptable
while conduit
19567K
was
found to
be
unacceptable
and
required
further evaluation.
After
evaluation
by HPES, this conduit was found to be acceptable.
Further
review
by the
licensee
resulted
in cancellation
of
NCR OP-86-0121
since
the
walkdown inspection
program
being
conducted
to identify
these
problems
was
in
progress.
The
inspector
concurs
with
cancellation
of this
NCR.
Based
on review of the licensee's
program
for reinspection
of shared
supports,
IFI 400/86-69-02 is closed.
(Closed) IFI 86-77-04,
Resolution of Cable Tray Riser Design Concerns
An engineer,
designated
Individual
E in Inspection
Report
Number
50-400/86-77,
involved with the analysis of the containment
building
cable tray riser structures
re'signed
his position at the Harris site
to accept
other
employment.
Since
he
had only partially completed
the cable tray riser analysis,
Individual
E prepared
a list of his
pending
concerns
regarding
the analysis
and
submitted this list to
his supervisor.
The licensee
addressed
these
concerns
in calculation
number
LV-66,
Cable
Tr ay
Ri ser
Frame
(Final
Verification) .
The
-inspectors
reviewed
calculation
LV-66 to determine if the
design
engineer's
concerns
were
resolved.
During
review
of
this
calculation,
the inspectors
noted that the change
in temperature
(hT)
used
in calculation of thermal
stress
in the structure
was
assumed
to
be
60OF
not
the
value
of
148
F
used
in the
CB structural
steel
platform analysis.
This error appeared
on page
67 of the calculation
and
was
used
in recalculation
of thermal
stresses
after
use of the
correct
bT value of
148
F resulted
in
an interaction
equation
of
2.47, which considerably
exceeds
the acceptable
value of 1.0.
The change
in the
hT value from 148'o 60'F constitutes
a change
in
a specified design input, specifically, the accident
temperature
used
to
calculate
thermal
stresses.
This
change
was
not
properly
identified, approved,
documented
or controlled in accordance
with the
licensee's
approved
program
or
Appendix B,
Criterion III. This was identified to the licensee
as Violation Item
400/87-41-02,
Uncontrolled Change to Design Input.
After the inspector identified the
problem regarding
the
change
in
design
input for
hT,
licensee
engineers
conducted
a
review of
calculation
LV-66.
This
review disclosed
that incorrect allowable
stresses
had
been
used
in
some
portions
of the calculations
to
qualify
some
members for the operating
base
design
loads.
These
problems,
the
incorrect
hT
and
the
incorrect
allowable
stresses,
were
documented
on
NCR 87-51.
During resolution of the
NCR,
which
involved
an
extensive
revision
to calculate
LV-66,
licensee
engineers
discovered
some errors in geometry in the computer
model of the riser structure
analyzed
in the original calculation
LV,.-'66.
As
a result,
licensee
engineers
conducted
an extensive
design
re;.."evaluation of the riser structure.
This re-evaluation
was still
ongoing at the conclusion of the inspection.
Based
on review of calculation
LV-66, the inspectors
determined that
Individual E's concerns
regarding
the cable tray riser frame analysis
were
addressed
in calculation
LV-66, although
the errors
discussed
above will result
in revision of the calculation.
A
summary
of
Individual E's concerns
and their resolutions
follows below:
4
15
Concern
No frequency calculations
for attaching
conduit
and instrument
supports
were performed.
Resolution
(2)
A frequency analysis
was performed
and considered
in analysis of
attachment
of conduit
and
instrument
supports
to the riser
frame.
The attachments
were
checked
for
a
reduced
frequency
determined
from
an
updated
static
analysis,
based
on actual
column properties.
'Concern
The
column
properties
input
in
the
EBASCO
analysis
were
incorrect.
The
moment
of inertia
( I) input in the
EBASCO
analysis
assumed
the
2
C9 x 15
members
were
adjacent
to
each
other
and
behaved
as
a
beam without consideration
of actual
riser configuration
(Channels
spaced
approximately
15
inches
center-center
with cross-braces
consisting
of horizontal tie
plates
connecting
the
channels).
The
same
condition
also
applies to the internal bracing (built-up 4 x 4 x 3/8 angles).
Resolution
The actual "as-built" riser configuration of the riser structure
(channels
connected
by the plates)
was
modeled
in the analysis
and
an
equivalent
moment of inertia
was
computed 'or
these
members.
The equivalent
moment of inertia
was
used
in
the
analysis.
The internal
bracing
was
also
analyzed
using
the
correct
moment of inertia.
(3)
Concern
There
were
no calculations
performed to determine
stresses
in
on internal connections.
Resolution
A,N
Calculation were performed to check weld stresses
in connections
on tie plates,
double angle cr'oss braces,
and the
W8 braces.
(4)
Concern
There
were
no stress
calculations
performed for the tie pipes.
The
main concern
here
was that the material
grade
used for the
pipe
had
a yield stress
of 25
Ksi
(ASTM A53,
Type
F,
Grade
B)
which
was
substituted
for the original
pipe material
which
specified
a yield stress
of 36 ksi.
16
Resolution
The
pipe material
originally specified
was
not available
in
either
E or S,
Grade
B (yield stress
of
36 ksi).
Therefore,
the material
with the
25
ksi yield
stress
was substituted.
Stress
calculations
were performed for
1',-inch diameter pipes with a
25 ksi yield stress.
The analysis
showed that the materials
used were acceptable.
(5)
Concern
Additional attachments,
e.g.
nonscheduled
conduit, to the riser
structure
were not considered
in the analysis.
Resolution
Loads
from
additional
attachments
were
considered
in
the
reanalysis
(calculation LV-66).
(6)
Concern
The
model
used
in the original analysis
had bracing in rear of
structure at azimuth
217 -30'hen
actual
structure
has "x" type
bracing
in front.
The incorrect modeling
may reduce calculated
loads to the structure,
and
may also affect the platform steel.
Resolution
The structure
was
remodeled
using the correct configuration for
the bracing.
The effect of the
loads
from the riser structure
on the
CB platform steel
was included in the analysis
for the
CB
platform (See
paragraph
5.b).
The inspectors will re-examine calculation
LY-66 as part of follow-up
on
corrective
action
for Violation
Item
400/87-41-02 'ince
Individuals
E's
concerns
were
resolved,
IFI
400/86-77-04
is
considered
closed.
(Open) IFI 400/86-77-05,
Painting of Restricted
Embeds
"t +
Diiring construction
of the Harris plant,
the licensee
used adhesive
tags to identify restricted
embed plates.
The restricted plates
were
those to which no
new attachments
could be
made to the
embed without
the explicit approval
of design engineering.
Restricted
embeds
were
identified
on field
change
requests
(FCRs).
At
the
end
of
construction,
licensee
engineering
personnel
conducted
a review of
the restricted
embed
program
and
concluded
that
the
use
of the
adhesive
tags
to identify restricted
plates
was ineffective.
The
licensee
conducted
an indepth review, which included
a field walkdown
and
design
evaluation
of restricted
embeds,
to ascertain
that the
17
re'stri'cted
embeds
were not loaded in excess
of their design capacity.
The:"'1-icensee
also decided
to paint the restricted
embeds
with red
paint to permanently identify them.
During the inspection
documented
in Inspection
Report
Number 50-400/86-77,
the inspector
noted during
a field inspection
of restricted
embeds
that
there
was
apparently
some
confusion
regarding
which
embeds
required painting to identify
them
as
restricted
embeds.
Licensee
engineers
indicated
to
the
inspector that they were coordinating
the restricted
embed painting
program with craft personnel
to assure
that all the restricted
embeds
would be painted.
During the current inspection,
licensee
engineers
indicated that all restricted
embeds
had been painted.
The inspector
selected
the following FCRs which restrict embeds:
FCR AS-6340 (R1),
7066 (Rl), 7067,
7068,
7392,
8665,
8666,
9345 (Rl).
Examination of
the
embeds restricted
by these
FCRs disclosed
the following problems.
(1)
The description
of the location of the
embed restricted
by
FCR
AS-7067
was incorrect
on
page
1 of 4.
The description
stated
that
support/embed
in question
was located 7'-0" east of column
line Fv, when in fact, correct location is 7'0" west of column
line Fv.
(2)
The as-built sketch
on Sheet.7
of 7 of
FCR AS 9345 (Rl) shows
a
conduit support attached
to embed
shown
on top of page,
when in
fact a cable tray support is attached
in this location.
(3)
The incorrect
area
was painted for embed
shown
on
FCR AS-7392.
The as-built sketch of the
embed
was also incorrect.
Following completion of the inspector's
walkdown,
a licensee
engineer
examined
embeds
restricted
on
12
additional
FCRs.
During
the
engineer's
walkdown,
he identified
an
embed
which
had
an attachment
not shown
on the as-built
sketch attached
to the
FCR.
Based
on these
reviews,
the
licensee
concluded
that
an
additional
indepth
examination
of the restricted
embeds
was
necessary.
Pending
the
outcome
of the findings of this reinspection,
and determination
of.
the
safety
significance
of
any
discrepancies
identified,
IFI
400/86-77-05 will remain open.
d.
(Closed) IFI 400/86-77-06,
Review of Discrepancies
Identified in R.G.
1'-;29; Mal kdown Program
fy
The inspector
examined
the discrepancies
in the licensee's
R.G.
1.29
walkdown
program
identified
by
an
NRC
consultant
during
the
inspection
documented
in
Inspection
Report
Number
50-400/86-77.
These
discrepancies
and their corrective
actions
are
summarized
below:
19
(3)
population
size
of the affected
anchor
using
CP&L procedure
CgA-7,
Evaluation
of
Program
Effectiveness.
The
inspector
reviewed the results of the licensee
evaluation of these
anchors
which are
documented
in
CP&L Letter
Number
MS-876316(E)
dated
July 17,
1987, Subject:
CQA.-7 Evaluation of Silver Anchors
Used
in Engineering
Evaluations of Reg.
Guide 1.29 Interactions.
The'esults
of the
CgA-7
program
showed
that
the
non-g
anchor
program
had proficiency greater
than
97%, identifying only 26
unacceptable
anchors
in the
945 anchors
inspected.
The licensee
concluded
that their non-(} anchor
program
was acceptable.
The
'nspector
concurs with licensee's
conclusions.
Discrepancy
Oversized 2-bolt clamps
were
used
on conduit for Item 69/70 in
Area A-1-190-1.
In addition,
some
clamps
were installed with
only one bolt due to interference with structural
steel
supports
for stairway platforms.
Corrective Action
Normal practice
in installing conduit supports
(clamps) is that
the
ID of the clamp is equal
in size to the
OD of the conduit.
This attaches
the conduit rigidly to the structure.
However,
review of the 'ackage
for this
item
showed
that
oversized
conduit
clamps
were
installed
intentionally
to
prevent
the
conduit
from interacting
with (falling on)
safety
related
equipment
in case
of a seismic
event.
Review of the
sketches
detailing installation of the
clamps
showed that
s'ome
of the
clamps
were
intended
to
have
only
one
anchor.
The
anchor
placement
reports
(APR) attached
to the package
reviewed
by the
NRC Consultant
were
incomplete.
Review of the
completed
APRs
for this item showed'hat
the
number of anchors installed agreed
with the as-built
conditions
in
the field.
No
rework
was
required.
Discrepancy
Incorrect
span
lengths
were
used
in analysis
of supports
for
Item 38 in Area
Package
F-2-236-1.
Also, additional
conduits
',
. were not considered
in analysis.
Corrective Action
The
supports
were re-evaluated
by licensee
engineers
using the
correct
span
lengths
and
considering
all
attachments.
The
inspector
examined the -calculations
and verified that they
had
been corrected.
No rework was necessary.
20
(5)
Summary
The licensee
corrected
the specific
problems identified by the
NRC consultant.
No
rework
was
necessary
to correct
these
problems.
The licensee
also
evaluated
the generic
aspects
of
these
specific
problems
and
conducted
further inspections
and
evaluations
to determine if problems existed with the R.G.
1:29
walkdown program which
had
been
completed
to date
and revised
procedures
to prevent these
same
problems
from occurring again.
Some discrepancies
were identified in other
RE G.
1.29
packages
which required
rework to correct.
The inspector
examined
the
procedures
which controlled the
R.G.
1.29 program
and
conducted
field
walkdown
inspections
to
examine
selected
R.G.
1.29
packages.
The results of these
inspections
are discussed
below.
(a)
Review of R.G.
1.29 Procedures
The inspector
examined
procedures
which controlled the
R.G.
1.29 evaluation
program.
These
procedures
were:
,HPES
Manual
of Instructions
(MOI) 7. 1.F, Guidelines
for
Evaluation
of
Regs
Guide
1.29
Problem
Identification Reports
HPES
MOI
7. 1.G,
Guidelines
for
Evaluation
of
Interdisciplinary Clearance
Problem Identified Reports
HPES
MOI 7 '.B,
Reg.
Guide 1.29
:,-.
- (b)
HPES
MOI
7. 1.A,
General
Design
Guidelines
for
Civil/Structural Engineering Unit
Review of the
above
procedures
disclosed
that
procedure
7. 1.F
was
revised
as
a result
of the
NRC consultant's
finding to emphasize
the
need to accurately
determine
span
lengths
to
be
used
in calculations,
and to
assure
that
required
hardware
was
installed.
Procedure
7 'B
was
revised to require evaluation of field conditions
by
HPES
engineering
personnel.
Review of R.G.
1.29 Generic Calculations
The
inspector
examined
calculation
number
MOI
7. 1. G,
Interdisciplinary
Clearance
Guidelines,
and
Calculation
number
MOI 7. 1.F,
Reg.
Guide
1.29 Evaluation Guidelines.
These calculation
included the following.
Basis for acceptance
of electrical
boxes, wall mounted
transformers,
power
panels,
and
communication
boxes
and speakers
21
4
Allowable conduit loads
on B-Line supports
Fire extinguisher bracket design
Notes
on
Non -g expansion
anchors
Emergency light box support calculations
Basis
for acceptance
of one-inch
diameter air line
supports
Basis
and review of trapeze
supports
(c)
Field Walkdown Inspection of R.G.
1.29
Packages
The inspector
performed
a walkdown inspection
and examined
selected
R.G.
1.29
area
packages/case
numbers.
The
packages
examined
were
those
that
the
licensee
had
reverified
due
to findings of the
NRC consultant.
The
inspectors
also
reviewed
the verification calculations
which formed
the
basis
for acceptance
of the
R.G.
1.29
interactions.
Packages/Items
examined
are listed in the
Table below.
TABLE
R.G.
1.29 Verification Walkdown
Problems
Examined
Area Packa
e Numbers
Case .Numbers
A-1-236-1
A-1-236"1
A-2-236-2
A-1-261-1
A-2-261-1
A-6-261-1
A-1-286-1
A-1-286-1
A-1-286"1
A-2-286-1
A-2-305"1
A-2-305"1
A-2-305-1
A-2-305"2
3 and
4
25
51
8
5 and
6
~ 25
71
89
133
17
26
96
97
6
Examination
of
the
above
items
disclosed
some
minor
discrepancies
in three
of the
packages.
Two of the
errors
involved use of incorrect
span
lengths
in calculation
of the
22
loads
on the
supports
and the other involved
an error in the
sketch of the
support configuration'n
the
walkdown
sketches
which resulted
in
an error
in calculation of the
loads
on one
support.
The inspector
determined
that the errors
were minor
and did not affect the results
of the
walkdown verification.
The
licensee
revised
the
calculation
to correct
the
minor
errors.
These errors
had
no safety significance.
(6)
Conclusions
The
licensee's
R.G.
1.29
walkdown
verification
met
NRC
requirements.
The licensee's
R.
G.
1.29
program
was sufficient
to identify interactions
between
safety
and non-safety
related
equipment,
and
assure
that
the
non-safety
related
equipment
would not collapse
on or interfere with safety-related
equipment
during
a sei smic event.
Although some minor discrepancies
were
identified
by
the.
inspector
during this
inspection,
these
discrepancies
had
no
safety
significance.
The
inspectors
concluded
that
the licensee's
R.G.
1.29
walkdown verification
was thorough
and conservative.
IFI 400/86-77-06 is closed.
e.
(Closed) IFI 400/86-77-07,
Follow-up on Justification for FCR AS-2381
Review
of
the
justification
for
FCR
AS-2381
showed
that
the
calculations
for analyzing
the baseplates
included
shear
and axial
loads
only,
no moments.
The interaction
equation
for these
loads
(shear
and
tension)
equaled
0.99.
The
concern
was
that
since
'attachment
of the structural
members to the baseplate
was with clip
angles
welded
on
three
sides,
the
actual
loads
on
the
baseplate
anchors
would be
in excess
of the allowable
due to
moments
carried
through
the welded connections (i.e.
the interaction equation
would
exceed 1.0).
The inspector
examined
the calculation titled "Addendum to
RAB 315.5
Calculation
Book."
Review
of this
calculation
showed
that
the
licensee
reanalyzed
the platform using
updated
seismic coefficients
for 4 percent
and
7 percent
damping,
and the as-built loads acting
on
the.. platform.
The
analysis
was
performed
by
assuming
the
end
condition for the
connections
to the
baseplates
were
both rigid
(fully fixed) and semi-rigid (one-third fixity).
These
assumptions
resulted
in
moment
transfer
into
the
baseplate;
however,
the
frequency of the platform was also increased
due to the fixity which
permitted transfer of moments.
The overall result was
a reduction in
the
axial
and
shear
stresses
acting
on
the
baseplate.
The
calculation
showed that the
maximum bolt interaction
was
0.314
and
the
maximum principal
stresses
in the plate
were
1085
psi
versus
allowable
of 27,000
psi.
The revised calculation
showed that the
original justification for
FCR
AS-2381
was
based
on conservative
assumptions
and
that
the
baseplate
design
was
acceptable.
I'FI
400/86-77-07 is closed.