Forwards IE Insp Repts 50-400/79-04,50-401/79-04, 50-402/79-03,50-403/79-03 on 790205-8.No Noncompliance Noted
ML18003A479
Person / Time
Site: Harris  
Issue date: 03/08/1979
From: Murphy C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Jackie Jones
CAROLINA POWER & LIGHT CO.
Shared Package
ML18003A477 List:
References
NUDOCS 7903270281
Download: ML18003A479 (2)


See also: IR 05000400/1979004

Text

~S Afar~

C

C

O~

~e

Yi~

0

++*++

In Reply Refer To:

RII:WBS

50-400/79-4

50-401/79-4

50-402/79-3

50-403/79-3

UNITEDSTATES

NUCLEAR REGULATORY COMMISSION

REGION II

101 MARIETTASTREET, N.W.

ATLANTA,GEORGIA 30303

MAR 0 8 1979

Carolina Power

and Iight Company

Attn:

Mr. J. A. Jones

Executive Vice President

Engineering,

Construction

and Operation

411 Fayettevi'lie Street

Raleigh, North Carolina

27602

Gentlemen:

This refers to the inspection

conducted

by Mr.

W. B.

Swan of this office

on February 5-8,

1979 of activities authorized

by NRC License

Nos.

CPPR-158,

CPPR-159,

CPPR-160

and

CPPR-161 for the Shearon Harris Nuclear

~

~

~

Plant facility, Units 1, 2,

3 and 4,

and to the discussion of our findings

held with Mr. R.

M. Parsons

at the conclusion of the inspection.

Areas

examined during the inspection

and our findings are discussed

in

the enclosed

inspection report.

Within these

areas,

the inspection

consisted of selective

examinations

of procedures

and representative

records,

interviews with personnel,

and observations

by the inspector.

Within the scope of this inspection,

no items of noncompliance

were

disclosed.

In accordance

with Section 2.790 of the NRC's "Rules of Practice",

Part 2, Title 10,

Code of Federal Regulations,

a copy of this letter and

the enclosed

inspection report will be placed in the NRC's Public

Document

Room. If this report contains

any information that you (or

your contractor) believe to be proprietary, it is necessary

that you

make

a written application within 20 days to this office to withhold

such information from public disclosure.

Any such application must

include

a full statement

of the reasons

on the basis of which it is

claimed that the information is proprietary,

and should

be prepared

so

that proprietary information identified in the application is contained

in a separate

part of the document.

If we do not hear from you in this

regard within the specified period, the report will be placed in the

Public Document

Room.

V9082VO P 8(

MAR 0 8 1979

Carolina Power and

Light Company

Should you have any questions

concerning this letter,

we will be glad to

discuss

them with you.

Sincerely,

g<g9~~

Charles

E. Murphy, Chief

Reactor Construction

and

Engineering

Support Branch

Enclosures:

Inspection Report Nos. 50-400/79-4,

50-401/79-4,

50-402/79-3

and

50-403/79-3

cc w/enclosures:

Mr. Roland Parsons,

Site Manager

Shearon Harris Nuclear Power Plant

Post Office Box 101

New Hill, North Carolina

27562