Forwards Structural & Geotechnical Engineering Branch SER on IE Bulletin 80-11 Re Masonry Wall Design.Requests Info Re Completion of All Necessary Mods.Tacs 42869 & 42870 Completed
ML17346A709
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 01/04/1985
From: Varga S
Office of Nuclear Reactor Regulation
To: Williams J
FLORIDA POWER & LIGHT CO.
Shared Package
ML17346A710 List:
References
IEB-80-11, TAC-42869, TAC-42870, NUDOCS 8501140524
Download: ML17346A709 (6)


Text

Docket Nos.

50-250 and 50-251 January 4, 1985 DISTRIBUTION ramme ORB)/1 Rdg L PDR CParrish DEisenhut ACRS 10 JPartlow

~ke Gray 1

e PDR DMcDonald OELD EJordan Mr. J.

W. Williams, Jr., Vice President Nuclear Energy Department Florida Power and Light Company Post Office Box 14000 Juno Beach, Florida 33408

Dear Mr. Williams:

Reference:

TAC Nos.

42869 and 42870

SUBJECT:

MASONRY WALL DESIGN, 1E BULLETIN 80-11, TURKEY POINT PLANT UNITS 3 AND 4 By letters dated July 24,

1980, November 4,
1980, February ll, 1981 and April 3, 1981, you provided your response to 1E Bulletin 80-11 which required all licensees and applicants to review their safety-related masonry walls and document the results.

Your initial responses were supplemented on May 27,

1983, November 7, 1983, January 24, 1984 and February 1,

1984.

We have reviewed your submittals which included the initial design rationale; reevaluation criteria with supporting analysis; modifications including additional grout, rebar and supports and; tests of in-place materials in the"e'xisting safety-'related masonry walls to verify the assumed values for material properties.

We understand that approximately seventy-five percent of the necessary modifications have been implemented and the remaining work i,s~ currently scheduled

',for completion in July of this year.

The details of our review are incl'uded in the enclosed Safety Evaluation (SE) and supporting Technical Evaluation Report (TER) prepared by our technical con'sultant, Franklin Research Center.

Appendix A of the TER provides the criteria used by the staff in determining the acceptability of safety-related masonry walls in nuclear power plants.

Based on our SE and supporting~TER, the requirements of 1E Bulletin 80-11 have been met by the, analysis per'formed, materials tests, modifications completed and modifications currently being implemented.

Therefore, we conclude'hat, there is reasonable assurance that the safety-related masonry walls at'he Turkey Point Plant, Units 3 and 4 will withstand the specified design load conditions without impairment of wall integrity or the performance of required safety functions.

I' t

It t

t I

l)

I'r.

J.,W. llilliams 2

January 4, 1985 This completes our, review effort related to the above referenced TAC numbers.

However, we woul'd like to be informed when all of the necessary modifications have been'ompleted.

fl The reporting and/or-recordkeeping requirements of this letter affect fewer than ten respondents;

'therefore, OMB clearance is not required Under P.L.96-511.

Sincerely,

/s/SVarga

Enclosure:

As stated Steven A. Varga, Chief Operating Reactors Branch 81 Division of Licensing cc w/enclosure:

See next page ORB81:

L McDonald;ps f ls/85

- RBPl:DL a

/

/85

0

  • t 1

If 1.

4

J.

W. Williams, Jr.

Florida Power and Light Company Turkey Point Plants Units 3 and 4

cc:

Harold F. Reis, Equire Newman and Holtziner P.C.

1615 L Street, N.W.

Washington, DC 10036 Bureau of Intergovernmental Relations 660 Apalachee Parkway Tallahassee, Florida 33130 Norman A. Coll, Esquire

Steel, Hector and Davis 4000 Southeast Financial Center Miami, Florida 33131-2398 Mr.

Ken N. Harris, Vice President Turkey Point Nuclear Plant Florida Power and Light Company P.O.

Box 013100 Miami, Florida 33101 Mr. M. R. Stierheim County Manager of Metropolitan Dade County Miami, Florida 33130 Resident Inspector Turkey Point Nuclear Generating Station U.S. Nuclear Regulatory Cormission Post Office Box 57-1185 Miami; Florida 33257-1185 Regional Radiation Representative EPA Region IV 345 Courtland Street, N.W.

Atlanta, GA 30308 Mr. Jack Shreve Office of the Public Counsel Room 4, Holland Building Tallahassee, Florida 32304 Administrator Department of Environmental Regulation Power Plant Siting Section State of Florida 2600 Blair Stone Road Tallahassee, Florida 32301 James P. O'Reilly Regional Administrator, Region II U.S Nuclear Regulatory Commission Suite 2900 101 Marietta Street
Atlanta, GA 30303 Martin H. Hodder, Esquire 1131 N.E. 86th Street Miami, Florida 33138 Joette Lorion 7269 SW 54 Avenue Miami, Florida 33143 Mr. Chris J. Baker, Plant Manager Turkey Point Nuclear Plant Florida Power and Light Company P.O.

Box 013100 Miami, Florida 33101 Attorney General Department of Legal Affairs The Capitol Tallahassee, Florida 32304 Mr. Allan Schubert, Manager Public Health Physicist Department of Health and Rehabilitative Services 1323 Winewood Blvd.

Tallahassee, Florida 32301