Text

FPLTQAR ~-76A (PPL-NQA-100A)

REVISION 11 MAY 10, 1988 o ica LIB I SSLII'QACe

-8806 DOCK 05000250 160303 8806077 DCD P

FLORIDA POWER 5 LIGHTCCNPANY

TOPICALQUALITYASSURANCE REPORT Rev.

FLORIDA POWER It LIGHTCOMPANY ABSTRACT pate 3une 10, 1980 Page 1

of Florida Power 2 Light Company (FPL) has established and implemented a Quality Assurance Program to provide assurance that the design, procurement, modification and operation of nuclear power plants conforms with applicable regulatory requirements.

The FPL Quality Assurance Program described in this Topical Report is in compliance with the requirements of Appendix B to 10 CFR Part 50.

The FPL Quality Assurance Program meets the requirements provided by the NRC Regulatory Guidance and Industry Standards as listed in Appendix C of this Topical Quality Assurance Report.

0

qO~ ~~CD l/

"o g

Q I 0

/p +a*<<+

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 101 MARIETTA ST R E ET, N.W.

ATLANTA,GEORGIA 30323 July 20, 1987 Florida Power and Light Company ATTN:

Mr. C. 0.

Woody Group Vice President Nuclear Energy Department P. 0.

Box 14000 Juno

Beach, FL 33408 RECENED AUG 3 Sd7 Nuclear UcensIng Gentlemen:

SUBJECT:

FLORIDA POWER AND LIGHT (FPL)

EQUALITY ASSURANCE PROGRAM UPDATE Your letter dated June 10,

1987, (L-87-241) transmitted FPL's Topical guality Assurance Report (FPL TAHAR 1-76A)

Revision 10, in accordance with 10 CFR 50.54(a).

This report provides the current quality assurance program description for Turkey Point and St. Lucie (Docket Nos. 50-250, 50-251, 50-335, and 50-389).

Your letter dated July 7, 1987, (L-87-283) provided clarifications to Revision 10 as discussed between FPL and NRC Region II personnel during a

telephone conversation conducted on July 1, 1987.

Our review of this information indicates that your quality assurance program continues to meet the requirements of 10 CFR 50 Appendix B and is therefore acceptable.

Please contact me if you have any questions concerning this letter.

We appreciate your timely submittal and prompt response to our questions regarding the information required by 10 CFR 50.54(a).

Sincerely, Caudle A. Julian, Chief Operations Branch Division of Reactor Safety cc:

K. N. Harris, Vice President St. Lucie Nuclear Plant C.

M. Wethy, Vice President Turkey Point Nuclear Plant C. J. Baker, Plant Manager Turkey Point Nuclear Plant J.

G. Boissy, Plant Manager St. Lucie Nuclear Plant J.

B. Harper, Site gA Superintendent L.

W. Bladow, Plant gA Superintendent J. Arias, Jr., Regulatory and Compliance Supervisor

TOPICAL QUALITY ASSURANCE REPORT TABLE OP CONTENTS Rev.

11 Date May 10, 1988 Page 1

of REVISION DATE ID CO N

0DC

'0 O

TQR 7.0 TQR 8.0 Control of Purchased Items

& Services 4

Identification

& Control of Materials, 2

Parts

& Components TQR 9.0 Control of Special Processes TQR 10 '

Inspection TQR 11.0 Test Control TQR 12.0 Control of Measuring

& Test Equipment TQR 13.0 Handling, Storage

& Shipping TQR 14.0 Inspection, Test

& Operating Status TQR 15.0 Nonconforming Materials, Parts or Components TQR 16.0 Corrective Action TQR 17.0 Quality Assurance Records TQR 18.0 Audits Title Page Abstract NRC Staff Evaluation Letter Table of Contents Policy Statement Introduction Topical Quality Requirements TQR 1.0 Organization TQR 2.0 Quality Assurance Program TQR 3 '

Design Control TQR 4 '

Procurement Document Control TQR 5.0 Instruction, Procedures

& Drawings TQR 6.0 Document Control May 10, 1988 June 10, 1984 May 10, 1988 May 10, 1988 June 10, 1987 May 10, 1988 June 10, 1987 June 10, 1986 June 10, 1986 June 10, 1986 June 10, 1986 June 10, 1986 June 10, 1986 June 10, 1986 May 10, 1988 June 10, 1986 June 10, 1985 June 10, 1986 June 10, 1986 May 10, 1988 June 10, 1986 June 10, 1986 June 10, 1986 z

Ol

~V C4 P

0IL

TOPICAL QUALITY ASSURANCE REPORT TABLE OF CONTENTS Rev.

11 Date May 10.

1 Page 2

Of 2

REVISION DATE Appendices A - Organizations 6 Figures Figure l-l: Organization of Departments Affecting Quality B - Qualification 6 Experience Requirements for QA Personnel C - Baseline Document Matrix D - Cancelled E - List of Corporate QA Procedures (QPs)

F - Topics to be Addressed in Safety Analysis Reports 10 May 10, 1988 June 10, 1986 June 10, 1984 May 7, 1982 May 10, 1988 May 7, 1982 D

'5 vl C0Z Ol C4 E

0 U.

TOPICAL QUALITYASSUR1LRCE REPORT QUALITYASSURANCE PROGMM POLICY Rev.

May 10, 1988 Page 1

of To avoid undue risk to the health and safety of the public and company employees, it is necessary to

design, construct, operate and modify nuclear power plants with a high degree of functional integrity, quality and reliability.

STATEMENT OF POLICY It is the policy of Florida Power 6 Light to design, construct, operate and modify nuclear power plants of a

quality level that will meet or exceed government regulations and will merit public confidence by providing electricity in a reliable, efficient and safe manner.

RESPONSIBILITY The President of Florida Power 6 Light Company is responsible for the execution of the Quality Assurance Program for Florida Power

& Light Company nuclear power plants.

The authority for developing and verifying execution of the Program is delegated to the Director of Quality Assurance, through the Vice President of Nuclear

Energy, the Senior Vice President Nuclear and the Executive Vice President responsible for power generation and delivery.

The head of each organization performing quality related activities is responsible for:

identifying those activities within his organization which are quality related as defined by the QA Program; establishing and clearly defining the duties and responsibilities of personnel within his organization who execute those quality-related activities; and planning, selecting, and training personnel to meet the requirements of the QA Program.

R. E. Talion, President Florida Power 6 Light Company

't t

I l

f I

I t

TOPICAL QUALITY ASSURANCE REPORT INTRODUCTION Rev.

June 10, 1987 Page 1

Of 2

The Topical Quality Assurance Report (FPLTQAR 1-76A) contains the description of the Florida Power 6

Light Company (FPL) Quality Assurance Program relative to its nuclear power plants.

This report consists of three parts:

The Introduction, which delineates the purpose and summarizes the scope and applicability of the Topical QA Report.

The second part, Topical Quality Requirements (TQRs),

which delineate QA Program requirements and summarizes the FPL approach to activities related to materials, parts, components,

systems, and services included in the Quality Assurance Program.

The third part, Appendices, which provide supporting statements, tabulations, and technical analyses or deviations which are

not, in themselves, the subject of the report.

The Topical QA Report shall be an integral part of the corporate Quality Assurance Manual (FPL-NQA-100A),

and shall delineate'he generic requirements and responsibilities by which FPL implements the corporate QA Program.

Revisions and changes to this Report will be made in a'ccordance

'ith a Quality Procedure as outlined in TQR 2.0.

The remainder of the QA Manual is comprised of Quality Procedures (QPs) which serve as the documents which describe how the interfacing of tasks between departments or organizations is achieved.

The Quality Procedures also cover those technical elements which require a common corporate position for interfaces or resolution of problem areas.

In addition to the Quality Assurance Manual, Quality Instructions (QIs) are developed as required by each of the implementing plants and departments.

Quality Instructions describe the measures to be used to implement the quality requirements of the QA Manual.

The Quality Instructions describe actions and responsibilities to be performed within a

department or organization and address the requirements of the appropriate Topical Quality Requirements, and Quality Procedures.

TOPICAL QUALITY ASSURANCE REPORT INTRODUCTION Rev.

.Date June 10, 1987 Page 2

Of The FPL Quality Assurance Program meets the requirements provided by the NRC Regulatory Guidance and Industry Standards as listed in Appendix C of this Topical Quality Assurance Report.

The requirements of this Topical QA Report apply to safety related materials,

parts, components, systems and structures; and to services employed for
design, procurement, construction, operation, maintenance, refueling, repair, and modification.

The safety related systems for each plant are specified in the respective plant Safety Analysis Report.

The FPL Quality Assurance Program fully addresses the requirements of Appendix B to 10 CFR Part 50.

The Topical QA Report, shall be applicable to all existing nuclear plants, those under construction, and supporting FPL departments, and will be referenced in the Safety Analysis Report (SAR).

For future

plants, the description of activities, requirements, and organizational structures that are unique to a particular plant shall be addressed in the respective SAR document.

D ector of Quality Assurance Ib CV K

Ih C02 Ch CV E

OIL

TOPICAL QUALITY ASSURANCE REPORT TQR 1.0 Rev.

11 ORGANIZATION May 10, 1988 Page 1

Of 32 GENERAL RE UIREKKTS The FPL organizational structure shall be defined such that the responsibilities for establishment and implementation of the Quality Assurance Program are clearly identified.

The authority and duties of individuals and organizations performing quality assurance and quality control functions shall be described, and shall illustrate the organizational independence and authority necessary to identify problems; to initiate, recormnend, or provide solutions; and to verify implementation of solutions.

In

addition, the description shall illustrate that persons or groups responsible for verifying the correct performance of an activity are independent of the person or groups responsible for performing the activity.

1.2 IMPLEMENTATION The President of Florida Power 6 Light is ultimately responsible for the execution of the Quality Assurance Program for Florida Power R

Light Company (FPL) nuclear power plants.

The authority for developing and verifying execution of the program is delegated to the Director of Quality Assurance, through the Vice President of Nuclear Energy

, the Senior Vice President Nuclear and the Executive Vice President.

The reporting relationship of each department involved with the Quality Assurance Program is shown in Appendix A, Figure 1-1.

lO CO CV O

IZ l7 To provide for a review and evaluation of QA Program policies and activities, the President has established the QA Conmittee, chaired by the Executive Vice President.

This organization's responsibilities are defined in Section 1.2.1.

0Z Ch r

Ol E

0 U.

TOPICAL QUALITY ASSURANCE REPORT Rev.

TQR 1.0 ORGANIZATION May 10, 1988 Page 2

of 32

1.2 IMPIB9KNTATION

(Cont')

In addition, a Quality Assurance Program Review Committee (QAPRC)

(formerly the QA/QC Coordinators) has been established to review changes to the QA Program and to provide an interface for quality matters in each department affecting quality.

This organization's responsibilities are defined in Section 1.2.2.

The head of each department or organization performing quality related activities is responsible for:

a) identifying those activities within the organization which are quality related as defined by the QA Program; b) establishing and clearly defining the duties and responsibilities of personnel within his organization who execute those quality related activities; and c)

planning, selecting, and training personnel to meet the requirements of the QA Program.

The responsibility, authority, and organizational relationship for performing quality related activities within each organization shall be established and delineated in organizational charts and written job or functional descriptions.

A QA Program Review Committee (QAPRC) Member shall be designated by the head of each department or organization except for the Quality Assurance Committee, since this committee is a policy forming body (of which the Director of Quality Assurance is a member).

The QAPRC Member is the prime interface for coordination of quality related matters within the member's department, with the QA Department, and with other departments.

Ol C

'5 C0Z Ol Ol C

0 U.

The organization chart, Appendix A,

Figure 1-1, illustrates the lines of authority and areas of responsibility for each of the organizations that are involved in quality related activities.

The

TOPICAL QUALITY ASSURANCE REPORT TQR l. 0 Rev.

ORGANIZATION May 10, 1988 Page 3

of 32 1.2 IMPLEMENTATION (Cont'd)

Project Management organization shown in this figure is applicable during design, procurement, construction, repairs and preoperational start-up and testing of power plant and modifications of power plants (determined by management on a

case-by-case basis) as described in Section 1.2.4.

Below are listed the departments and organizations that have Quality Assurance responsibilities.

Specific organizational responsibilities for implementation of the Quality Assurance Program are described in the corresponding section numbers.

1.2.1

1. 2. 2.

1.2.3 Quality Assurance Committee Quality Assurance Program Review Committee Nuclear Energy Department

-Nuclear Power Generation

-Nuclear Corporate Staff 1.2 '

Construction 1.2.10 Power Supply 1.2.11 Inventory Resources 1 ~ 2'2 Company Nuclear Review Board 1.2.13 Nuclear Fuel 1.2.14 Corporate Records Services 1.2.4 1.2.5 1.2.6 1.2.7 1.2.8 Project Management Department 1.2.15 Documentary Files Corporate Contracts Department Environmental Affairs Power Plant Engineering Purchasing 1.2. 1 Quality Assurance Committee The Quality Assurance Committee, chaired by the Executive Vice President,'s comprised of executive level members of management with responsibilities for the execution of the Quality Assurance Program within their responsibilities.

This

TOPICAL QUALITYASSURANCE REPORT Rev.

TQR

1. 0 ORGANIZATION Date Nay 10 19SS

~age 4

of 32 1.2.1 Quality Assurance Committee (Cont'd)

Committiee's composition is delineated in its current charter and it's reporting relationship is shown in Appendix A, Figure 1-1.

The Quality Assurance Committee is responsible for reviewing and evaluating QA Program policies and activities.

Policy changes shall be initiated when Committee findings indicate the necessity.

Quality Assurance Program status reports shall be periodically prepared by the QA Department and routed to the members of the QA Committee for their review.

In

addition, QA Committee meetings shall be held by the Executive Vice President to keep members apprised of conditions including significant problems that require management attention.

The Quality Assurance Committee shall be the final authority for resolution of contested quality policies, differences of

opinion, and stop-work or other corrective action requests when lower level agreement cannot be reached between QA or QC and other departments.

Periodic audits of the Quality Assurance Department shall be performed by a team independent of the QA Department, which is selected and approved by the Chairman of the Quality Assurance committee.

The results of this audit are presented to the QA Committee.

ID CO Ol 0'.

C02 Ol Ol 6

O 1.2.2 Quality Assurance Program Review Committee (QAPRC)

The QAPRC (formerly the QA/QC Coordinators) was formed as an organization with the responsibility to review and resolve recommended changes to the QA Program.

This committee is administered by the QA Services group.

QA Program changes reviewed by the QAPRC are reviewed and signed by the department

TOPICAL QUALITY ASSURANCE REPORT TQR 1.0 ORGANIZATION Rev.

11 Date May 10.

1988 Page 5

of 32 1 ~ 2.3 Nuclear Energy Department heads or individuals listed on each Quality Procedure. Nuclear Energy responsibility for the plant begins with the Department's acceptance of a system or portion thereof from FPL Project Management.

Throughout the remainder of plant life, Nuclear Energy maintains control of and responsibility for any plant modifications coordinated by Nuclear Energy and for the preoperational and start-up testing, operation, maintenance, refueling, and modification of the plant in accordance with written and approved procedures.

The organizational structure of Nuclear Energy is shown in Appendix A, Figure 1-1.

The Senior Vice President Nuclear has overall responsibility for Nuclear Energy's activities.

The Senior Vice President Nuclear is designated as the Senior Corporate Nuclear Officer of Section 6.0, Administrative Controls, of each Unit's Technical Specifications.

Reporting to the Senior Vice President Nuclear are:

The Site Vice President

- St.

Lucie, the Site Vice President Turkey Point and the Vice President Nuclear Energy.

1.2.3.1 Nuclear Power Generation The Site Vice President-St.

Lucie and Site Vice President-Turkey Point are accountable for the operation, maintenance, and modification of their respective nuclear

plant, as well as the selection, development and direction of the assigned staff.

They will act as liaison between the plants and corporate headquarters, and are accountable for ensuring that company policies and procedures are properly implemented and continued at the nuclear site.

TOPICAL QUALITY ASSURANCE REPORT TQR 1.0 Rev.

11 ORGANIZATION Date May 10, 19SS Page 6 <<32 1.2.3.1 Nuclear Power Generation (Cont'd)

The Plant Manager (Plant Manager Nuclear at PTN) through the Vice Presidents Turkey Point and St.

Lucie Plants (as applicable) is responsible for the operation of the nuclear plant.

The plant manager is additionally responsible for the establishment and implementation of plant QC policy which implements the quality control aspects of the Quality Assurance Program.

Reporting directly to the Plant Manager is the plant Quality Control Supervisor who has the authority and freedom to administer the plant Quality Control program

and, when necessary, to stop activities adverse to quality.

The QC Supervisor, his staff, and personnel performing QC inspection functions are required to be independent of groups or persons performing activities that they may be required to verify or inspect.

QC effort includes preparation and review of plant procedures,

PCMs, quality related instructions and procurement documents; QC personnel are also responsible for inspection, monitoring, surveillance, and review of plant activities to verify compliance with the provisions of the facility operating license and the Quality Assurance Manual.

The QC Supervisor shall take corrective action for deficiencies identified, where applicable',

and shall follow up on corrective action taken by other organizations until close out.

He shall receive quality program direction from the Director of Quality Assurance.

OI D

C02 Ol OI s

0 U.

The Plant Nuclear Safety Committee (PNSC) at Turkey Point Plant or the Facility Review Group (FRG) at the St. Lucie Plant is comprised of key plant management and staff personnel as des-

TOPICAL QUALITy ASSURANCE REPORT TQR 1.0 ORGANIZATION Rev.

ll Date May 10 19SS Page 7

of 32 1.2.3.1 Nuclear Power Generation (Cont'd) cribed in the plant Technical Specifications.

The PNSC/FRG serves the plant manager in a technical advisory capacity for the review of 'all safety related procedures and activities that impact on plant safety and the facility operating license.

1.2.3.2 Nuclear Corporate Staff The Vice President Nuclear Energy is responsible for the selection,

staffing, training and development of personnel required for supervisory and operating continuity of staff groups supporting nuclear power generation.

Reporting to the Vice President Nuclear Energy are the Maintenance Manager

Nuclear, Manager Nuclear Energy
Services, the Manager of Nuclear
Training, the Director of Quality Assurance, the Director of Nuclear Licensing and the Manager of Planning and Control.

The Maintenance Manager Nuclear is responsible for directing activities in support of major plant maintenance projects, modifications and upgradings, as well as the development of work methods, specifications and systems to promote increased productivity.

ED CO CV D

The Manager Nuclear Energy Services is accountable for technical staff support to the generating department and certain centralized special functions.

This group consists of section supervisors and technical specialists, with functions including Health

Physics, Chemistry, Radiological
Waste, Emergency Planning, Plant
Support, and Materials, Codes and Inspections.

TOPICAL QUALITY ASSURANCE REPORT TQR 1.0 ORGANIZATION Rev.

11 Date May 10.

1gS Page S

of 32 1.2.3.2 Nuclear Corporate Staff (Cont'd)

The Manager of Nuclear Training establishes company policy regarding nuclear training and secure the necessary resources to ensure that Nuclear Energy personnel are adequately trained.

They must have adequate technical and job related skills to provide safe and efficient operation while complying with NRC requirements.

The Quality Assurance Department shall be responsible for administering the FPL Quality Assurance Program.

This includes developing and verifying implementation of corporate policies,

plans, requirements, and procedures affecting quality.

This is accomplished through the Quality Assurance Department.

The Quality Assurance Department retains responsibility for delegated portions of the QA Program by performing initial evaluation and subsequent periodic audits of the contractors'A Programs.

The QA Program responsibility further extends to the performance of audits within the Company to assure management that the established requirements and procedures are being implemented, and that the Program complies with the baseline document requirements.

OlI C

'5 Ca2 Cl OI E

0 The organizational freedom of the QA function is accomplished through the corporate structure, illustrated in Appendix A, which provides independence from those departments responsible for

design, procurement, engineering, construction and operation.

With Quality Assurance as the sole function of this organizationally independent department, the Director of Quality Assurance and his staff, both on-site and offsite, are completely free from the cost and scheduling pressures of

TOPICAL QUALITY ASSURANCE REPORT TQR 1.0 Rev.

ORGANIZATION May 10, 1988 Pege 9

of 32 0

1.2.3.2 Nuclear Corporate Staff (Cont'd)

design, procurement, construction and operation.

The Quality Assurance Department has the freedom and authority to:

a) identify quality problems; b) initiate, recommend or provide corrective action; c) verify implementation of the corrective action; and d) recommend the stoppage of work or operations adverse to quality, when necessary.

The Director of Quality Assurance reports to the Vice President Nuclear Energy with direct communication access to the Senior Vice President Nuclear.

He is responsible for the technical direction and the administrative control (e.g., performance appraisal, salary review, hire/fire, position assignment) of all members of the Quality Assurance Department.

The Manager of Quality Assurance

Services, the Manager of Quality Assurance Procurement 6 Reliability, the Superintendent of Quality Assurance St.

Lucie and the Superintendent of Quality Assurance - Turkey Point report administratively and functionally to the Director of Quality Assurance.

The Superintendents of QA receive technical direction from the Manager of QA Services.

ID CO N

~IC O

The Director of Quality Assurance, the Senior Vice President

Nuclear, and the Vice President Nuclear Energy are each members of the Quality Assurance Committee.

This reporting relationship and memberships on the QA Committee assure that the QA Department has direct access to the levels of management necessary to assure effective implementation of the QA Program.

Further, the Operations QC Supervisors of both Turkey 02 Ol OI E

0 U.

TOPICAL QUALITY ASSURANCE REPORT TQR 1.0 Rev.

ORGANIZATION May 10, 198 pe9e 10 of 32 1.2.3.2 Nuclear Corporate Staff (Cont'd)

Point and St. Lucie receive quality program direction from the Director of QA.

The Manager of QA Services directs and administers the Corporate Quality Assurance

Program, including developing and verifying implementation of policies,
plans, requirements, procedures and audits which assure compliance with the baseline documents listed in Appendix C

of this Topical Quality Assurance Report.

The duties, responsibilities, and authorities of each Quality Assurance group are described in the sections which follow.

a.

Quality Assurance Services Group lO N

lh CaZ Cl C4 E

04.

Quality Assurance Services is responsible for the development and maintenance of the overall QA Program, including the followi'ng:

o Develop and maintain the QA Department Quality Instructions, QA Department Training 6 Organization

Manual, and the corporate QA Manual; including the administration of the QA Program Review Committee (QAPRC) o Assist other departments in the development of Quality Instructions by review and comment and through interpretation of corporate Quality Assurance requirements; o

Develop and implement a

Quality Assurance indoctrination program for FPL supervisory personnel,

TOPICAL QUALITy ASSURANCE REPORT TQR

1. 0 Rev.

11 ORGANIZATION Date May 10, 19SB pa9e 11 Of 32 1.2.3.2 Nuclear Corporate Staff (Cont'd) and a

training program for the Quality Assurance Department; o 'repare reports on Quality Assurance Program activities for presentation to the Quality Assurance Committee by the Manager of Quality Assurance Services; o

Maintain a file system for documentation of quality assurance activities performed by the QA Department; o

Review Regulatory

Guides, Codes, SAR Document Commitments and Standards for impact on the Quality Assurance Program and recommend appropriate program changes; o

Review documents submitted to the Company Nuclear Review Board (CNRB) as requested by the QA Department CNRB member; o

Plan, coordinate and implement a comprehensive system of periodic internal audits with support from the other Quality Assurance

groups, when necessary; o
Initiate, recommend or provide solutions and verify implementation of solutions for quality problems identified; o

Review FPL originated design specifications for inclusion of appropriate quality requirements.

b.

Quality Assurance Procurement and Reliability Group ID CO N

DC The Manager of Procurement and Reliability is responsible for assuring the quality of safety related items and

services, and their vendors, including the following:

C0z Ol Pt Ol E

04

TOPICAL QUALITY ASSURANCE REPORT Rev.

TQR l.0 ORGANIZATION May 10, 1988 Pege

.12 0

32 1.2.3.2 Nuclear Corporate Staff (Cont'd) o Assist in the development and implementation of policies, plans, requirements and procedures for the reqgisition and purchase of materials, equipment and services related to nuclear power plants and to the acceptance and storage of equipment and material; o

Perform appropriate surveillance of hardware during manufacture; o

Develop and implement a

program for auditing of supplier QA/QC programs including architect/engineer/

NSSS Suppliers; o

Review and approve FPL procurement documents and changes to these documents to assure 'hat the necessary quality requirements are imposed; o

Assist other FPL departments in the identification of quality problems associated with procurement and storage; initiate, recommend, or provide solution; and verify implementation of solutions; o

Review, approve and periodically audit the execution of FPL contractor quality assurance programs; o

Maintain a file system for documentation of quality assurance activities performed by the QA Procurement group; o

Evaluate the Quality Assurance capability of suppliers requested by Purchasing and Corporate Contracts and maintain the Quality Assurance Department "Approved Suppliers List".

Ol OC I/l C0Z Ch OI E

0 The responsibility of this group, in terms of phases of procurement, begins with the preparation of the procurement

document, extends through bid evaluation,

TOPICAL QUALITY ASSURANCE REPORT Rev.

TQR

1. 0 ORGANIZATION May 10, 1988

~~9~

13

~~

32 1.2.3.2 Nuclear Corporate Staff (Cont'd) vendor selection, fabrication and shipment; and ends upon receipt af shipment at the operating plant or warehouse.

This group, through audits and surveillances, assures that the contractor's organizations performing QA functions have sufficient authority and organizational freedom to implement effective QA programs.

c.

Quality Assurance Group - Turkey Point The Superintendent of QA-Turkey Point has responsibility for on-site development and implementation of the Quality Assurance

Program, including the following:

ID 00 Ol inspection and

testing, procurement of spare/replacement
parts, material
storage, health
physics, chemistry, plant security and fire protection; o

Coordinate in the development and implementation of

policies, plans, requirements, and procedures for portions of the quality assurance program related to the operation and modification of nuclear power plants at Turkey Point Units 3 and 4 (PTN);

o Perform audits, assessments and other observations at PTN to verify compliance with QA Program commitments, identify quality problems and ensure timely corrective actions are taken in the areas of plant operation, system

turnover, modification and maintenance; including such areas as refueling, inservice Z

Ol C4 6

04.

TOPICAL QUALITY ASSURANCE REPORT TQR 1.0 Rev.

ORGANIZATION Date May 10, 1988 Page 14 of 32 1.2.3.2 Nuclear Corporate Staff (Cont'd)

N OC Vl C0Z Ol

<<4 CV s

0 U.

o Identify requirements, ensure inclusion of commitments in documents and verify implementation of the Quality Assurance Program during the backfit activities at PTN through audits of FPL and contractor organizations; o

Recommend stoppage of work or operations adverse to quality at PTN in'accordance with the appropriate Quality Procedures; o

Review and comment on Quality Instructions or equivalent quality related administrative procedures prior to

issue, with respect to the requirements of the FPL Quality Assurance
Program, the PTN Final Safety Analysis
Report, and the PTN Technical Specifications; o

Assure that the status is tracked for all PTN open items identified by the FPL QA Turkey Point group, and inform appropriate management when there is an indication that a commitment will not be met on time; o

Maintain a file system for documentation of quality assurance activities performed by the Turkey Point group; o

Assure design related activities performed by the Architect/Engineer meet the quality aspects of the contract; o

Review backfit procedures with respect to the FPL QA Program (for procedure review requirements see TQR 5.0);

o Review site generated FPL procurement documents and changes to procurement documents in accordance with the appropriate Quality Procedures;

TOPICAL QUALITY ASSURANCE REPORT TQR 1.0 Rev.

11 ORGANIZATION Date May 10.

1988 Page 15 of 32 1.2.3.2 Nuclear Corporate Staff (Cont'd) o Perform audits of PTN architect engineer and NSSS suppliers both on-site and off-site, in conjunction with QAPGR.

The interface with the QA Procurement 6 Reliability group ends with the receipt of a

shipment of nuclear safety related equipment at the plant site.

The Quality Assurance program for the shipment is then within the purview of the QA Turkey Point group.

Off-site interfaces for the resolution of quality related problems and NRC items are with Project Management, Power Plant Engineering, Nuclear Corporate Staff and the architect engineer and NSSS Quality Assurance Department.

This group is called upon to audit the Turkey Point operating plant.

The Turkey Point group interfaces with the Site Vice President and his staff on-site by assisting in the resolution of quality related problems.

d.

Quality Assurance Group - St. Lucie (PSL)

The Superintendent of QA St. Lucie has responsibility for on-site development and implementation of the Quality Assurance

Program, including the following:

ID 00 Ol C

D 0Z Ol

~V C4 6

0 U.

o Coordinate in the development and implementation of

policies, plans, requirements and procedures for portions of the quality assurance program xelated to the operation or modification of St.

Lucie Unit 1

G Unit 2 (PSL);

TOPICAL QUALITY ASSURANCE 'EPORT TQR

1. 0 Rev.

ORGANIZATION Date May 10 198 Page 16 <<32 1.2.3.2 Nuclear Corporate Staff (Cont'd)

ID Ol C

CO2 Ol Ol s

0 U.

o Perform audits, assessments and other observations at PSL to verify compliance with QA Program commitments, identify quality problems and ensure timely corrective action are taken in the areas of plant operation, system turnover,'modification and maintenance; including such areas as refueling, inservice inspection and

testing, procurement of spare/replacement
parts, material
storage, health
physics, chemistry, plant security and fire protection; o

Identify requirements, ensure inclusion of commitments in documents and verify implementation of the Quality Assurance Program during the backfit activities at PSL through audits of FPL and contractor organizations; o

Maintain a file system for documentation of quality assurance activities performed by the St.

Lucie Projects-QA group; o

Assure design related activities performed by the Architect Engineer meet the quality aspects of the contract; o

Review backfit procedures with respect to the FPL QA Program (for procedure review requirements see TQR 5.0);

o Review site generated FPL procurement documents and changes thereto, 'n accordance with appropriate Quality Procedures; o

Perform audits of PSL architect/engineer/NSSS suppliers both on-site and off-site, in conjunction with QAPGR;

TOPICAL QUALITY ASSURANCE REPORT ORGANIZATION TQR 1.0 Rev.

11 Date May 10, 1gS8 Page 17 of 32 1.2.3.2 Nuclear Corporate Staff (Cont'd) o Recommend stoppage of work or operations adverse to quality at PSL in accordance with the appropriate Quality Procedures; o

Review and comment on Quality Instructions or equivalent quality related administrative procedures prior to issue, with respect to the requirements of the FPL Quality Assurance

~ Program, the PSL Final Safety Analysis Reports and the plant Technical Specifications; o

Assure that the status is tracked for all PSL open items identified by FPL St. Lucie Projects QA group, and inform appropriate management when there is an indication that a commitment will not be met on time; The interface with the QA Procurement 6 Reliability group ends with the receipt of a

shipment of nuclear safety related equipment at the plant site.

The Quality Assurance program for the shipment is then within the purview of the St. Lucie Projects QA group.

Off-site interfaces for the resolution of quality related problems and NRC items are with Project Management, Power Plant Engineering, Nuclear Corporate Staff and the architect engineer and NSSS Quality Assurance Department.

This group is called upon to audit the St. Lucie operating plant.

The St. Lucie Projects QA group interfaces with the Site Vice President and I

his staff on-site by assisting in the resolution of quality related problems.

TOPICAL QUALITYASSURANCE REPORT TQR 1.0 Rev.

ORGANIZATION Date May 10.

1988 Page 18 of 32 1.2.3.2 Nuclear Corporate Staff (Cont'd)

The Director of Nuclear Licensing is responsible for coordinating the NRC interface, distributing NRC documents requiring actions, evaluating potential impact and responding to all NRC action items.

He's also responsible for assuring that the status is tracked for all open items identified by the NRC or other

federal, local and state agencies and for informing appropriate management when there is an indication that a commitment will not be met on time.

1.2.4 Project Management Department ID Ol D

C0Z Ch P4 C4 0

U.

The Project Management Department, through the Project General

Manager, exercises management control of assigned projects.

This management control begins when a Project is assigned to the Project Management Department and continues until the facility is accepted for operation or the project is complete.

This management control includes the responsibility for coordination of specifications and requisitions,

repair, construction and may include preoperational start-up and testing of power plant modifications.

The Project Management Department organization is shown in Appendix A, Figure 1-1.

S I

The Director of

Projects, reporting to the Senior Vice President, has overall responsibility for the activities of the Project Management Department.

A Project General

Manager, reporting to the Director

. of

Projects, is responsible for completing the assigned project in compliance with technical

TOPICAL QUALITY ASSURANCE REPORT TQR

1. 0 Rev.

11 ORGANIZATION Date May 10, 1988 Page 19 Of 32 1.2.4 Project Management (Cont'd) and other project specifications, and for the application of the provisions of the Quality Assurance Manual during the project.

The Project General Manager is responsible for obtaining corrective action from any contractor's management when corrective action cannot be obtained at the project site management level

and, when necessary, can exercise his authority to stop work on project activities adverse to quality.

The overall responsibility for Plant Changes and Modifications to operating plants is defined in each plant's Technical Specifications.

However, frequently the work of installation and administration of Plant Changes and Modifications is assigned to FPL Project Management Department.

The Project Site Manager will report to the appropriate nuclear site Vice President but will also receive guidance and advice from the Project General Manager.

The Project Site Manager is additionally responsible for the functional direction of construction QC for the purpose of coordinating inspection activities which implement the quality control aspects of the quality assurance program for modifications of projects assigned to project management.

Activities affecting quality may be performed by FPL or contracted.

Should any of these functions be contracted, the contractor may perform the activities under his own Quality Assurance

Program, which must have prior approval by FPL Quality Assurance, or the contractor may directly adopt the requirements of the FPL Quality Assurance Manual. If the contractor implements the Quality Control function directly to the FPL QA Manual requirements, z

Ol C4 E

TOPICAL QUALITY ASSURANCE REPORT TQR 1.0 Rev.

ORGANIZATION Date May 10.

1988 Page 20 Of 32 1.2.4 Project Management (Cont'd) the contractor's Quality Control Supervisor shall have the authority and freedom to administer the Quality Control program.

Project Team Members are appointed by their home department heads as the departmental representative on the respective

project, when requested by the Project General Manager.

Team Members, other than Quality Assurance and Stores Department, report functionally to the Project General Manager, or the Project Site Manager, but continue to receive administrative support and technical direction from their home department.

Team members are responsible to the Project General Manager for home department support to the Project.

1.2.5 Corporate Contracts Department ID Ol DC Vl C0Z Cll Ol E

0 U.

The Corporate Contracts Department is responsible for generation, negotiation and issuance of Contracts over specified time periods and dollar limits for turbine generators, steam generators, nuclear steam supply systems (NSSS),

new

items, repairs, constructors, construction
managers, and Architect Engineer (A/E) and consulting services.

Corporate Contracts is also responsible for assuring that technical and quality requirements developed by others are incorporated in such contracts, as appropriate, and that these contracts have the required approvals.

Details of the activities of the department in fulfillingthis responsibility shall be delineated in the appropriate Quality Procedures.

The Manager of Corporate Contracts reports to the Director of Corporate Contracts.

The Corporate Contracts Organization is shown in Appendix A, Figure 1-1.

TOPICAL QUALITY ASSURANCE REPORT TQR 1.0 Rev.

ORGANIZATION Date May 10 1988 Page 21 of 32 1.2.6 Environmental Affairs Environmental Affairs is responsible for obtaining the federal and state environmental permits required for FPL facilities and operations.

Environmental Affairs is responsible for overall coordination of non-radiological environmental monitoring (federal and state) programs at the nuclear power plant sites.

The Manager of Environmental Technical Services, the Manager of Environmental Resources and Planning and the Manager of Environmental Permitting and Programs report to the Director of Environmental Affairs as illustrated in Appendix A, Figure 1-1.

The Director of Environmental Affairs has overall responsibility for implementation of the Environmental Technical Specifications and Environmental Protection Plans at nuclear power plant sites.

ID CO OlIC

'0 The Environmental Affairs Department through its management of the Company Environmental Review Group (CERG) is responsible for overall coordination of environmental monitoring programs and requirements related to the Environmental Technical Specifications and Environmental Protection Plans.

The CERG provides review of proposed changes to the Environmental Technical Specifications and Environmental Protection Plans, review of any violations of monitoring and/or limitation requirements and review of proposed plant changes and modifications for environmental impact effects as requested by the plant manager(s).

C02 Cll rN 0

U.

TOPICAL QUALITY ASSURANCE REPORT TQR 1.0 Rev.

ORGANIZATION

>>te May 10, 1988 page 22 Of 32 1.2.6 Environmental Affairs (Cont'd)

The CERG provides information to the Director of Environmental Affairs and the Chairman of the CNRB on environmental matters for which requirements are included in the Environmental Technical Specifications and Environmental Protection Plans.

1.2.7 Power Plant Engineering The Power Plant Engineering Department (JPE) is responsible for power. plant design related aspects of the FPL QA Program throughout all phases of plant life except as specified for the Fuel Resources Department in

-Section 1.2.13.

This responsibility extends from initial engineering evaluations of plant design related site characteristics, through preliminary and detailed

design, construction, operation and decommissioning.

Ol C

'5 C0Z Ol Ol E

0

'LL.

JPE performs design related activities and delegates design related activities to qualified contractors.

For activities performed by JPE, the work is governed by FPL's QA Program, and JPE is responsible for approval of the design output.

Delegated activities are performed in accordance with an FPL approved QA Program and the contractor is responsible for approval of design output.

JPE is responsible for defining the scope of delegated activities and the responsibilities of the contractor.

Prior to the release of design outputs by contractor organizations, JPE ensures that the contractor is technically qualified to perform the design related activity.

TOPICAL QUALITY ASSURANCE REPORT TQR 1.0 Rev.

11 ORGANIZATION Date May 10.

19SS Page 23 of 32 1.2.7 Power Plant Engineering (Cont'd)

JPE is responsible for development and maintenance of the design control program governing design related activities performed by JPE and for providing technical support to the Quality Assurance Department for assessing the

adequacy, implementation and effectiveness of contractor design control programs.

JPE is responsible for the preparation, revision, approval and distribution of plant design drawings that are identified to be maintained as "asconstructed" drawings during plant operation.

The Chief Engineer

Power Plants reports to the Senior Vice president as shown in Appendix A, Figure 1-1.

1.2.8 Purchasing The Purchasing Department is responsible for the purchase of materials and services by FPL for its nuclear power plants with the exception of those materials and services secured by Corporate Contracts and Nuclear Fuels.

Materials and services for nuclear safety related application are secured only from approved suppliers, or as commercial grade, as applicable.

'P DC

'0 The Department is responsible for assuring that technical and quality requirements developed by others are reviewed and approved by the designated quality departments, as applicable, are incorporated in the procurement document which the departments authorizes't is responsible for maintaining 02 Ol CV

TOPICAL QUALITY ASSURANCE REPORT TQR 1.0 Rev.

ORGANIZATION Date May 10.

1988 Page 24 Of 32 1.2.8 Purchasing (Cont'd) traceability of purchase 'ecords from acceptance of requisitions through payment, of the purchase order invoices.

The Manager of Purchasing reports to the Director of Procurement and Materials Management who reports to the Vice President of Corporate

Services, Chief Financial Officer as shown in Appendix A, Figure 1-1.

1.2.9 Construction The Juno Construction Management Department (JCM) is responsible for providing direction and coordination regarding construction, supervision and management, equipment utilization, quality

control, welding, NDE and other construction support activities.

The Director of Construction reports directly to the Vice President of Engineering, Projects and Construction.

He is responsible for directing and administering effective

.management of the department to ensure compliance to the corporate policies, practices and procedures.

Reporting to the Director of Construction Management are the Manager of Plant Construction and the Manager of Construction QC, Welding and NDE.

C

'0 C02 Ol

~i C4 s.

0 U

The Manager of Plant Construction is responsible for providing qualified construction support personnel to the Project Site Manager.

Reporting administratively to the Manager of-Plant Construction are the Construction Superintendents.

TOPICAL QUALITY ASSURANCE REPORT TQR 1.0 Rev.

11 ORGANIZATION Date May 10, 1998 Page 25 of 32 1.2.9 Construction (Cont'd)

The Construction Superintendent is responsible for conformance of project construction activities to the requirements of specifications,

codes, regulations and site procedures.

He supervises the construction personnel assigned to the project, coordinates construction activities including the scheduling of construction personnel requested by the Project Site Manager.

The Manager of Construction Quality Control, Welding and NDE is responsible for directing and administering the Construction QC and Welding Programs and for the technical direction and administrative control of all personnel within the Construction QC and Welding organizations.

This includes the development and implementation of policies, plans and procedures to meet the requirements of the QA program, codes and standards.

Reporting to the Manager of Construction QC, Welding and NDE are the site Project QC Supervisors, NDE Level III Supervisor, FPL Welding Superintendent and a staff of QC Coordinators.

ID CO C4 Construction QC is responsible for providing inspections as

required, to assure that backfit activities meet the requirements of engineering drawings, specifications, codes and standards.

This responsibility extends from receipt inspections of material on-site to acceptance of the installed items prior to turnover to the Nuclear Energy Department.

It also includes verification of conformance of an item or activity accomplished during this period to quality requirements (e.g.,

records review, NDE, inspections).

TOPICAL QUALITY ASSURANCE REPORT TQR 1.0 Rev.

ORGANIZATION Date May 10, 1988 Page 26 of 32 1.2.9 Construction (Cont'd)

Each nuclear power plant is assigned a Project Quality Control Supervisor, who directs the on-site backfit QC organization.

The Project QC Supervisor reports administratively and technically to the Manager of Construction Quality Control, Welding and NDE, however, he also reports functionally to the Project Site Manager for the purpose of coordinating and scheduling inspection activities.

The functional/

administrative reporting roles provide the necessary independence of the site Construction Quality Control organization and also maximizes the communication between the Construction staff, the QC staff and the Nuclear Energy staff.

Ol OC C0z Ol lh CV sI0 U.

The Project QC Supervisor is responsible for first line verification of the conformance of backfit activities to quality requirements, specifications, codes and local, State and Federal regulations.

He directs on-site implementation of the Construction QC Program which includes supervision, and daily coordination, and scheduling of inspection activities, and review of inspection results.

The freedom and independence of the on-site QC organization to assure the effectiveness of the QC Program from pressures of cost and scheduling is derived from the Project QC Supervisors administrative and technical reporting relationship to the Manager of Construction QC, Welding and NDE..

Both the Manager of Construction Quality

Control, Welding and
NDE, and the Project Quality Control Supervisor have the authority to stop work or operations adverse to quality if the need arises.

TOPICAL QUALITY ASSURANCE REPORT TQR 1.0 Rev.

ORGANIZATION May 10, 1988 Page 27 of 1.2.9 Construction (Cont'd)

The NDE Level III Supervisor is responsible for directing and monitoring the NDE activities performed under the control of the Construction Management Department.

He is responsible for preparation, revision and implementation of NDE procedures, and the training, testing and qualification of the NDE personnel performing these activities.

He is also responsible for providing the programs and direction for performance of NDE activities meeting the

ASME, AWS and other NDE code requirements.

The Quality Control Coordinators provide staff technical and administrative support to the Manager of Construction QC, Welding and NDE in the preparation,

review, issue and monitoring of the Construction QC program to ensure effective implementation.

lO EO CV IX l7 0z Oi Ol s

U.

The FPL Welding Superintendent reports to the Manager of Construction QC, Welding and NDE. His responsibilities are to develop, maintain and control the FPL Welding Control Manual, with assistance from Power'Plant Engineering, to originate and qualify welding procedure specifications and qualification of welders and welding operators to meet the applicable code requirements.

He provides administrative and technical direction to the personnel within the FPL welding control program to meet engineering welding standards and code requirements.

Reporting to the FPL Welding Superintendent are the Welding Supervisors at each Nuclear site.

The organization structure of the Construction Management Department is illustrated in Appendix A, Figure 1-1.

TOPICAL QUALITY ASSURANCE REPORT TQR 1.0 ORGANIZATION Rev.

11 Date May 10, 1988 Page 28 of 32 1.2.10 Power Supply Within the Power Supply Department only equipment and services provided by the System Protection Group and Power Supply Technical Services are subject to the requirements of the Quality Assurance Program.

Appendix A Figure 1-1 illustrates the'eporting relationship.

System Protection is responsible for test, calibration and maintenance of certain high voltage electrical protective relays for safety related systems of the nuclear plant.

Activities of System Protection include final wiring connection checks, preoperational check-out and test of system protection devices and providing inspection of equipment under their cognizance.

Power Supply Technical Services is responsible for providing to System Protection certain setpoint and checkpoint values for protective devices.

1.2.11 Inventory Resources ID OI DC l5 l/l Caz Ol OI E

0 U

The Inventory Resources Department is responsible for the

receipt, handling,
storage, shipping and issue of items received at the plant site for control by Inventory Resources.

This responsibility encompasses spare and replacement parts and components for plant equipment through all phases of plant life.

TOPICAL QUALITY ASSURANCE REPORT TQR 1.0 Rev.

ORGANIZATION May 10, 1988 Page 29 Df 32 1.2.11 Inventory Resources (Cont'd)

During operations, Inventory Resources also performs additional quality related activities such as handling and segregation for nonconforming items received for stores control.

The Manager of Power Plant Stores reports to the Manager of Inventory Resources who reports to the Director of Procurement and Material Management as shown in Appendix A, Figure 1-1 ~

1.2.12 Company Nuclear Review Board The Company Nuclear Review Board (CNRB) reviews or directs the performance of reviews of activities concerning the technical aspects of the operating nuclear power plant insofar as they impact on plant safety, the health and safety of the public, and laws, regulations and licensing commitments.

In addition, audits of these areas are performed under the cognizance of the CNRB.

Where necessary, the Board may use consulting services to perform required reviews.

The management level to which the CNRB reports is illustrated in Appendix A, Figure 1-1.

Its composition is delineated in Section 6.0 of each facility's Technical Specifications.

The Senior Vice President responsible for Power

Delivery, Construction, Power Plant Engineering, and Projects will perform his CNRB membership duties as Acting Group Vice President.

Ib CO Ol o

IZ Subjects within the purview of the Board are listed in the appropriate plant Technical Specifications.

The CNRB has the authority to carry out its responsibilities by way of written action

letters, verbal direction, minutes of meetings or appointed subcommittees.

C0z Ol C4 F

0 U.

TOPICAL QUALITY ASSURANCE REPORT TQR 1.0 Rev.

ORGANIZATION Date May 10 19 Page 30 of 32 1.2.13 Nuclear Fuel The Nuclear Fuel Section (FRN) of the Fuel Resources Department's responsible for the procurement, management, and accountability of FPL's nuclear fuel assets, and for providing technical support to fuel users within FPL.

The Nuclear Fuel Section is under the direction of the Manager of Nuclear Fuel who has the responsibilities described below:

ID CO Ol D

CC C02 Ol Ol E

O U.

o Forecasting FPL's nuclear fuel requirements and the availability and price of nuclear fuel; o

Preparing the procurement specifications for components of the nuclear fuel cycle;,

o Determining sources of supply and evaluating alternatives; o

Making commercial arrangements, including contract negotiations with vendors for acquisition, processing and delivery of nuclear fuel and related services for the nuclear fuel cycle; o

Assuring that technical and quality requirements including inputs from other FPL departments are incorporated in fuel contracts and letters of authorization and that these documents have the necessary approvals; o

Administering and managing contracts for nuclear fuel and related services to assure that contractual obligations are met, and serving as FPL liaison in all matters of nuclear fuel and fuel related contracts; o

Performing audits and coordinating accountability reporting on all nuclear fuel; o

Providing support to the QA Department for their auditing of nuclear fuel design and fuel assembly manufacturing;

TOPICAL QUALITY ASSURANCE REPORT TQR 1.0 Rev.

ORGANIZATION Date May 10, 3.989 Page 31 of 32 1.2.13 Nuclear Fuel (Cont'd) o Performing fuel management and safety analyses of nuclear cores to support plant licensing; o

Development and/or review of fuel and nuclear physics design; o

Performing the project management function with respect to nuclear fuel; o

Provide and maintain benchmarked computer codes and procedures available for Fuel Resources line functions and other departments for daily use in maintaining records, performing safety analysis and core design, reporting of off-site nuclear fuel management activities and providing economic data; o

Maintain effective and controlled computer access to Nuclear applications systems; o

Develop and

provide, to appropriate FPL
groups, information necessary to determine FPL's fuel related costs and to finance fuel related expenditures; o

Reviewing core related changes to Safety Analysis Reports and Technical Specifications for compliance with design criteria and regulatory requirements; o

Participating in start-up physics tests and providing other technical support for operating nuclear power plants; o

Planning, maintenance and implementation of the Corporate Special Nuclear Materials program.

OK 17a The Manager of Nuclear Fuel reports to the Director of Fuels as shown in Appendix A, Figure 1-1.

Ch Ol E

0 U.

TOPICAL QUALITY ASSURANCE REPORT TQR 1.0 Rev.

11 ORGANIZATION May 10, 1988 Pege 32

~f 32 1.2.14 Corporate Records Services The Manager of Corporate Records Services is responsible for:

ensuring the QA records program activities are managed in accordance with applicable laws and regulations; assisting with the development and implementation of effective and compatible records and micrographics programs; developing, approving and maintaining record retention schedules; establishing parameters for indexing in the corporate records computerized Record Management System (RMS);

locating acceptable record storage areas when requested;

storage, retrieval and control of records/documents as reqested by other departments; leading the evaluation of specially designated "QA approved" storage facilities and maintaining the records of this evaluation.

The Corporate Records Services organization is shown in Appendix A, Figure 1-1.

1.2.15 Documentary Files The Supervisor of Documentary Files is responsible for receiving, maintaining, retrieving and storing the QA records in connection with licenses, and contracts received from other departments.

The Documentary Files organization is shown in Appendix A, Figure 1-1.

ID Ol

~IC Vl C02 Ol cv 0L

TOPICAL QUALITY ASSURANCE REPORT TQR 2.0 QUALITY ASSURANCE PROGRAM Rev.

Date June 10, 1987 page 1

of 8

2. 1 GENEKG RE UIREMENTS Florida Power 6 Light Company has established a Quality Assurance Program which complies with the criteria of 10 CFR 50 Appendix B, and meets the requirements of Regulatory Guides and Industry Standards referenced in Appendix C

of this report.

The Topical Quality Requirements and attached Policy Statement, together with the Quality 'Procedures and Quality Instructions document the Program and the FPL policy with regard to Quality Assurance.

This Program shall be instituted for each plant site in a schedule consistent with accomplishing the required activity and shall be carried out throughout the life of FPL nuclear plants.

The requirements of the FPL Quality Assurance Program shall only apply to nuclear safety related structures,

systems, and components as identified in the Safety Analysis Report for each nuclear unit.

Additionally, the requirements of the FPL Quality Assurance Program shall apply to all

FPL, contractor, or consultant organizations performing activities affecting the quality of safety related structures,
systems, and components of FPL nuclear power plants.

Documented procedures shall require and define indoctrination and training of personnel performing activities affecting quality as necessary to assure that suitable proficiency is achieved and maintained.

Periodic program reviews of the status and adequacy of the FPL Quality Assurance Program shall be accomplished by the independent audit team described in Section 1.2.1 and by QA Department audits.

TOPICAL QUALITYASSURANCE REPORT TQR 2.0 QUALITY ASSURANCE PROGRAM Rev.

Date June 10, 1987 Page 2

of 8

2.1 General Requirements (Cont'd)

Management of organizations outside Florida Power 6 Light Company participating in the Program shall be required to regularly review the status and adequacy of that part of the FPL Quality Assurance Program which they are executing.

The FPL Quality Assurance Department shall review and concur in the QA Program of contractors.

2.2 IMPLEMENTATION 2.2.1 Goals and Objectives As stated in the Policy Statement of the President of Florida Power 6 Light Company, the goal of the FPL Quality Assurance Program is to maintain quality levels in an effective and efficient manner, and to assure the high degree of functional integrity and reliability of nuclear safety related structures,

systems, and components.

To meet this goal, the following objectives of the FPL Quality Assurance Program have been defined:

a 0 b.

Define through documented

'procedures and instructions the quality activities that apply to the design, fabrication, procurement, modification,

testing, operation, refueling, maintenance, and repair of nuclear power plants; Establish,
assign, and document the responsibilities for those activities affecting quality of safety related structures, co
systems, and components; Establish confidence that the
design, fabrication, IDZ CV C0Z Ol Ol 0

U.

policies by assuring quality by responsible personnel; related activities are performed modification, and operation of nuclear power generation facilities are performed in a

manner consistent with FPL

TOPICAL QUALITY ASSURANCE REPORT TQR 2.0 QUALITY ASSURANCE PROGRAM Rev.

June 10, 1987 Page 3 of 9

2.2.1 Goals and Objectives (Cont'd) d.

Apprise management of unresolved problems and trends which could have a significant effect on nuclear power plant safety; and e.

Prevent schedule delays and high cost due to poor quality.

2.2.2 Program Documentation The Topical Quality Assurance

Report, which defines the policy,
goals, and objectives regarding the Quality Assurance Program, shall be contained in the FPL Quality Assurance
Manual, and used as guidance for the development of corporate level Quality Procedures which are also contained in the Quality Assurance Manual.

Revisions to the Topical Quality Assurance Report will be made, as

needed, to reflect current FPL program requirements and descriptions of activities.

These revisions shall be made in accordance with a Quality Procedure.

If a program revision reflects a reduction of the commitments from the baseline documents contained in Appendix C, the revision shall be submitted to and approved by the NRC prior to implementation.

In all other cases, amendments to the Topical QA Report will be submitted to the NRC to reflect implemented program revisions on an annual or more frequent basis.

lO CO Ol IX V0 Quality Procedures shall be written by the department with major responsibilities for an

activity, or by the Quality Assurance Department when requested.

These procedures shall be reviewed by all the departments with responsibility for some portion of that procedure, and shall be approved by the major implementing departments with co-approval by the Director of Quality Assurance.

A listing of corporate level Quality Procedures is contained in Appendix E.

TOPICAL QUALITY ASSURANCE REPORT TQR 2.0 QUALITY ASSURANCE PROGRAM Rev.

Date June 10, 3.997 Page 4

of 8

2.2.2 Program Description (Cont'd)

Each Quality Procedure shall be written to further address criteria contained in the Topical Quality Requirements and to further define the FPL QA policies, plans, and program where action is required by more than one department.

Each department head shall have the responsibility for implementation of the Quality Assurance

Program, which includes compliance with procedure requirements applicable to his department.

In

addition, he

, shall be responsible for the preparation,

approval, and distribution of Quality Instructions, operating procedures, testing procedures, or other instructions where further guidance is necessary for implementat.ion of the QA Program requirements within his department.

Quality Instructions shall be reviewed by the Quality Assurance Department at each revision.

2.2.3 Structures,

Systems, and Components The requirements of the FPL Quality Assurance Program shall apply to nuclear safety related structures,
systems, and components, as defined in the SAR.

Safety related structures,

systems, and components are listed as those necessary to assure the integrity of the reactor coolant boundary, the 'capability to shutdown the reactor and maintain it in a safe shutdown condition, or the capability to prevent or mitigate the consequences of accidents which could result in off-site exposures comparable to the guideline exposures of 10 CFR 100.

Ol C

COZ Ol E

0 U.

TOPICAL QUALITY ASSURANCE REPORT TQR 2.0 QUALITYASSURANCE PROKVLM Rev.

Date June 10, 3.987 Page 5

of 8

2.2.3 Structures, Systems and Components (Cont'd)

Control over activities affecting the quality of safety related structures,

systems, and components shall be to the extent consistent with their importance to safety.

Such control shall include use of appropriate equipment, establishment of suitable environmental conditions, and assurance that all prerequisites for a given activity have been satisfied.

The Program shall provide for controls over special processes and skills necessary to attain the required

quality, and the need 'or verification of quality by inspection and test.

Advance planning is required, for the control of management and technical interfaces between FPL and contractors, during the phase-out of design and construction and during preoperational testing and plant turnover.

This is achieved through periodic meetings of concerned organizations and the development of procedures which define responsibilities and interfaces, and control the testing and turnover of plant systems to FPL.

2.2.4 Participating Organizations The FPL organizations with responsibilities for activities affecting quality of nuclear safety related structures,

systems, and components are identified in TQR 1.0, which also briefly describes their assigned responsibilities.

Florida Power G Light Company may delegate activities to contractor organizations and equipment vendors.

Delegated activities are subject to the external organization's FPL approved QA Program or the FPL QA Program, or some FPL approved combination thereof.

TOPICAL QUALITY ASSURANCE REPORT TQR 2.0 QUALITY ASSURANCE PROGRAM Rev.

Date June 10, 1987 2.2.4 Participating Organizations (Cont'd)

However, FPL shall retain overall responsibilities for the QA Program.

Procurement documents shall define the scope of delegated activities, as well as QA Program requirements that shall govern these activities.

The Quality Assurance Department shall review and approve the QA Program governing contracted activities prior to award of contract except for activities for which the output is of a conceptual and/or prototype nature.

In all cases, final approval shall occur at a point in the process to ensure that the output complies with the requirements of the FPL approved QA Program.

The object of this review shall be to verify that the program is in compliance with the applicable requirements of Appendix B,

10CFR50, and ANSI N45.2.

Audits shall be conducted periodically to verify the acceptable implementation of the contractor's FPL approved QA Program governing delegated activities.

The Quality Assurance Department is responsible for conducting these audits.

The initial review and periodic audits shall be performed by qualified Quality Assurance Department personnel,

. and as appropriate, by technical specialists from other FPL departments and contractor organizations.

2.2.5 Indoctrination and Training tD Ol OK C0Z Ol C4 C

O U

A program shall be established and maintained for quality assurance indoctrination, and for training which assures that the required level of personnel competence and skill is achieved and maintained in the performance of quality related activities.

Quality Procedures shall delineate the requirements for an indoctrination program to assure that personnel responsible for performing quality activities are instructed in the purpose,

scope, and implementation of the quality related
manuals, instructions, and procedures and that compliance to these documents is a mandatory requirement.

TOPICAL QUALITY ASSURANCE REPORT TQR 2.0 QUALITY ASSURANCE PROGRAM Rev.

Date June IP, igS7 Page 7

of S

2.2.5 Indoctrination and Training (Cont'd)

Quality Procedures shall also require the head of each department (including the QA Department) to be responsible for a training plan which assures that personnel performing quality related activities are trained in the principles and techniques of the activity being performed.

This training shall maintain the proficiency of personnel in the skills necessary for the quality related activities through retraining, requalification or reexamination, as appropriate.

When personnel are assigned to perform their functions under the direction of personnel from other than their home department, the department head of the organization providing direction is resporisible for the indoctrinaton and training of personnel who perform quality related activities under his direction.

Quality Procedures shall specify the requirements for documenting indoctrination and training

sessions, including a

course description, attendance,

location, and date.

2.2.6 Management Participation In addition to the involvement of department heads in implementing the QA Program within their departments and the involvement of the Director of Quality Assurance and the Manager of QA Services in the development, coordination, and review of the

Program, the Quality Assurance Committee shall be apprised of the status and adequacy of the Quality Assurance Program on a periodic basis.

The following

TOPICAL QUALITY ASSURANCE REPORT TQR

2. 0 QUALITYASSURANCE PROGRAM Rev.

Date June IP, yg87 Page 8

Of 8

2.2.6 Management Participation (Cont'd) actions shall be instituted to assure that the Quality Assurance Committee remains informed and meets its Program responsibilities:

a 0 b.

C ~

The Committee shall review a

summary of the results of management level QA audits of FPL Departments.

The Quality Assurance Department shall circulate monthly reports of quality related activities to members of the QA Committee and affected department heads.

The monthly reports may include such items as the status of audits, a summary of audit

findings, the status of development
projects, and descriptions of policy matters or problems requiring management attention.

The Quality Assurance Committee shall review the status of the QA Program on a

semiannual basis.

The review will include assessment of the accomplishments.

Program

goals, objectives, and d.

Periodic audits of the QA Department and Program shall be conducted by an independent audit group under the direction of the Chairman of the Quality Assurance Committee.

This audit group shall employ FPL audit procedures and shall distribute the audit report to the QA Department, and to the Quality Assurance Committee for review of findings and corrective action.

Auditor certifications of independent audit teams will be retained by the Quality Assurance Department.

CC IA CaZ CV 0

The programs of contractor organizations that perform quality related activities shall be reviewed by Quality Assurance to assure that their management regularly reviews the status and adequacy of that part of, the FPL Quality Assurance Program which they are executing.

TOPICAL QUALITYASSURANCE REPORT Rev.

FLORIDA POWER 8 LIGHTCOMPANY DESIGN CONTROL Date 3une 10 1986 Page of 1

6 3.1 GENERAL RE UIREMENTS A

Quality Assurance Program shall be established for design related activities.

This design control program shall ensure that the design is defined, controlled and verified; that applicable design inputs are specified and correctly translated into design output documents; that design interfaces are identified and controlled; that design adequacy is verified by persons other than those who designed the item; and that design changes, including field

changes, are governed by control measures commensurate with those applied to the original design.

Design records shall be developed to provide evidence that the design process and design verification were performed in accordance with the requirements of FPL's Quality Assurance Program.

The design organization (the Power Plant Engineering Department, the Fuel Resources Department or designated contractor organization) shall be responsible for the content of these records.

Design records shall include design output documents and the important steps in the design effort.

The intent of this documentation is to allow a technically qualified person to understand how the design was developed, and to allow that person to verify the design based on the design documentation and engineering data sources referenced therein.

3.2 IMPLEMENTATION The design organization's Quality Assurance Program for design control shall be approved by the FPL Quality Assurance Department prior to the release of approved design output by the design organization.

The design organization is the organization responsible for approval of design output.

TOPICAL QUALITYASSURANCE REPORT TQR 3.0 FLORIDA POWER 8 LIGHTCOMPANY DESIGN CONTROL Rev.

Date 3une 10, 1986 Page 2

of 6

3.2 Implementation (Cont'd)

Quality Procedures and Quality Instructions shall be developed to delineate design control requirements governing design related activities performed by the Power Plant Engineering Department and the Fuel Resources Department and for their delegating activities to contractor organizations.

3.2.1 Design Process The design organization shall specify and document its design activities to the level of detail necessary to permit the design to be developed in a correct manner and to permit verification that design output documents satisfy design input requirements.

Design methods, materials, parts, equipment and processes, including those associated with commercial grade items that are essential to the function of the structure, system or component shall be selected, reviewed and approved for suitability of application by the design organization.

Design inputs shall be identified, documented, reviewed and approved by the design organization.

They shall be specified to the level of detail necessary to permit the design activity to be carried out in a correct manner, and to provide a consistent basis for making design related decisions, performing design verification and evaluating design changes.

Changes to approved design

inputs, including the reason for the
changes, shall be
approved, documented and controlled by the design organization.

The design organization shall identify aspects of manufacture, construction, inspection and testing critical to achieving the function of the structure, system or component.

Quality standards and quality requirements shall be specified on design output or procurement documents.

Changes from

TOPICAL QUALITYASSURANCE REPORT Rev.

T R 3.0 FLORIDA POWER 5 LIGHTCOMPANY DESIGN CONTROL Date 3une 10, 1986 Page of 3.2.1 Design Process (Cont'd) approved quality related requirements specified in design output, including the reason for the changes, shall be approved, documented and controlled by the design organization.

Design analyses shall be controlled and documented.

Approved design output documents and approved changes thereto shall be relatable to the design input by documentation in sufficient detail to permit verification.

The design organization shall establish procedures to review industry design experience.

As appropriate, this experience shall be made available to cognizant design personnel.

3.2.2 Design Change Control Changes to approved design output documents, including field changes, shall be justified, subjected to control measures commensurate with those applied to the original design, and shall be reviewed and approved by the same design organization that approved the original design unless other organizations are specifically designated.

Where a significant design change is necessary because of an incorrect design, as appropriate, Power Plant Engineering or Fuel Resources shall determine the cause of the incorrect design.

As necessary, design and verification procedures shall be reviewed and modified to correct the cause of the incorrect design.

During the operations

phase, design changes shall also be reviewed by operating plant management including plant Quality Control.

The intent of this review is to ensure that implementation of the design change is coordinated with any necessary changes to operating procedures and practices, and required QC Surveillance activities.

In accordance with plant

TOPICAL QUALITYASSURANCE REPORT TQR 3.0 FLORIDA POWER 8 LIGHTCOMPANY DESIGN CONTROL Rev.

Date 3une 10, 1986 Page 0

of 6

3.2.3 Design Change Control (Cont'd) technical specification requirements, nuclear safety related design changes are reviewed by the Plant Nuclear Safety Committee (PNSC) or Facility Review Group (FRG) and the Company Nuclear Review Board (CNRB).

3.2.3 Design Interface Control The'esign organization shall be responsible for identification, control, resolution and documentation of design interface requirements.

Procedures shall establish interface controls between participating organizations and between the various technical disciplines within the design organization.

These procedures shall include the assignment of responsibility, and be in sufficient detail to cover the preparation,

review, approval,
release, distribution and revision of design output documents.

For interdisciplinary

design, approval documentation of each involved discipline of the design organization shall appear on the design output document or on a separate document directly traceable to the design output.

The design organization shall designate a

discipline(s) responsible for resolution of the comments of participating organizations.

The designated discipline(s) approval of a design output shall also document resolution of the comments of participating organizations.

3.2.0 Design Verification Design control measures shall be established to independently verify the design

inputs, design
process, and that design inputs are correctly incorporated into design output.

The design organization shall develop procedures that govern design verification.

These procedures shall require that the design organization identify and document the verification method utilized and that the documentation clearly identify those individuals performing the design verification.

TOPICAL QUALITYASSURANCE REPORT Rev.

FLORIDA POWER 8 LIGHTCOMPANY DESIGN CONTROL Date 3une IO 1986 Page of 5

6 3.2.0 Design Verification (Cont'd)

Design verification shall be performed by technically qualified individual(s) or group(s) other than those who performed the design.

The original designers and verifiers may both be from the design organization.

Design verification by the designer's immediate supervisor shall be limited to those instances where the supervisor is the only qualified individual available within the 1

design organization.

These instances are further restricted to designs where the supervisor did not specify a singular design approach, or did not restrict design methods or alternatives, or did not specify design inputs (unless the specified design inputs have already been independently verified).

3ustification for verification by the designer's immediate supervisor should be documented along with the extent of the supervisor's involvement in the design.

The design organization shall be responsible for determining the extent of design verification and methods to be employed.

"The methods may include one or more of the following: the performance of design reviews, the use of alternate calculations, or the performance of qualification tests.

This shall apply to original design and to changes to approved design output.

Where reverification is not required for a

design change the bases shall be documented by the design organization.

Cursory supervisory reviews and mathematical checks for calculation accuracy do not satisfy the independent design verification requirement.

Design verification shall normally be completed prior to release of design output for procurement, manufacture or release by the design organization for use in design activities by a participating organization.

Verification shall be conducted based on the status of design at the time of release of design documents.

Where this timing cannot be met, verification may be deferred provided that the unverified portion of the design output, and all design output 0z 0>

I CV e

04.

TOPICAL QUALITYASSURANCE REPORT TQR 3.0 FLORIDA POWER It LIGHTCOMPANY DESIGN CONTROL Rev.

Date 3une 10, 1986 Page 6

of 6

3.2.0 Design Verification (Cont'd) documents, structures, systems and components based on the unverified portion of design are identified and controlled.

In all cases verification shall be completed prior to relying on any affected items to perform their design functions.

3.2.5 Computer Codes Organizations utilizing computer codes as a method for design shall maintain instructions or procedures to effect the following:

1.

That such codes are verified for their particular use using benchmark

problems, alternate calculations, comparison with other code or experimental results, design review or similar methods, 2.

That such codes have been qualified for their specific application sufficient to ensure valid results, 3.

That such codes are provided with user instructions sufficient for a technically competent individual to follow, That configuration controls are provided to assure that such code changes or modifications are documented and controlled.

FLORIDA POWER 5 LIGHTCOMPANY TOPICAL QUALITYASSURANCE REPORT PROCUREMENT DOCUMENT CONTROL TQR 0.0 Rev.

2 Da~e June 10, 1936 Page 1

of 3

0.1 GENERAL RE UIREMENTS Procurement of items and services shall be performed in accordance with procedures which assure that applicable regulatory requirements, design

bases, code requirements, and other requirements necessary to assure quality shall be included or invoked by reference in the procurement document.

These procedures shall delineate the sequence of actions to be accomplished in the preparation,

review, approval, and control of procurement documents.

Changes to procurement documents shall be subjected to the same degree of control as utilized in the preparation of the original documents.

0.2 IMPLEMENTATION 0.2.1 Procurement Document Provisions Quality Procedures and Quality Instructions shall identify the responsibilities and actions required of the organizations originating, reviewing, approving, and controlling procurement documents.

These procedures shall require the procurement documents to specify:

ao b.

c, d.

The scope of work to be performed.

Technical requirements (by specifying or referencing) which shall include the applicable components and materials identification requirements, drawings, specifications, procedures, instructions, codes, and regulations and provide for identification of applicable

test, inspection and acceptance requirements, or special process instructions.

QA Program requirements to be imposed on contractors which shall include the applicable portions of 10 CFR 50, Appendix B.

Right of access which provides, as appropriate, for access to contractor facilities and records for inspection or audit by FPL or its designated representative, and to access for events such as witness and hold points.

TOPICAL QUALITYASSURANCE REPORT Rev.

T R

0.0 FLORIDA POWER 8, LIGHTCOMPANY PROCUREMENT DOCUMENT CONTROL Date 3une 10 1986 Page of 0.2.1 Procurement Document Provisions (Cont'd) e.

The documentation required to be

prepared, maintained, and/or submitted to FPL or its representative for review, approval, or historical record.

The time of submittal of this documentation and the retention and disposition of quality assurance records which will not be delivered to FPL shall be prescribed.

Consideration shall be given to the need for special requirements in the preparation and review of procurement documents.

Procedures and instructions shall be prepared and implemented for special on-site handling or storage requirements.

The receiving department shall be responsible for on-site implementation of the special

handling, shipping, and storage requirements for items received and controlled by their organization.

Special

handling, preservation,
storage, cleaning, packaging, and shipping requirements shall be specified, as appropriate, in the design documents or purchase orders.

The requirements established in the design documents or purchase orders shall be consistent with industry accepted standards, the importance of equipment or material to nuclear safety, and the material or equipment's sensitivity to damage.

The preparation of these design documents or purchase orders may be delegated by FPL to other organizations.

The preparation and control of design documents and purchase orders is described in TQR 3.0.

0.2.2 Procurement Document Review Procurement documents shall be reviewed for correctness, and inspectability and controllability of quality requirements in accordance with Quality Procedures and Quality Instructions to assure that the appropriate provisions

TOPICAL QUALITYASSURANCE REPORT Rev.

FLORIDA POWER 5 LIGHTCOMPANY PROCUREMENT DOCUMENT CONTROL Date 3une 10 1986 Page of 3

3 0.2.2 Procurement Document Review (Cont'd) of Section 0.2.1 are included. This review shall be documented and performed by designated technical and quality evaluators, and shall assure that the procurement document was prepared, reviewed and approved as required.

Spare or replacement parts for safety related structures,

systems, and components are subject to technical or quality requirements equivalent to or better than those used for the original equipment.

Changes to procurement documents, whether initiated by FPL or their representative, are subjected to the same degree of control as that utilized in the preparation of the original document.

0.2.3 Selection of Procurement Sources The Purchasing, Fuel Resources or Corporate Contracts Department, as applicable, shall verify that the procurement document has been reviewed and

approved, and that the supplier has been approved prior to issuing the purchase order for safety related materials or services.

Supplier approval is not necessary if the important characteristics of the item can be verified by inspection or test.

The overall procurement requirements including those related to planning, bid evaluation, and review and concurrence of suppliers QA programs are described in Quality Procedures and Quality Instructions.

TOPICAL QUALITYASSURANCE REPORT TQR 5.0 FLORIDA POWER 8 LIGHTCOMPANY INSTRUCTIONS, PROCEDURES, AND DRAWINGS Rev.

6 Date 3une 10, 1936 Page 1

of 3

5.1 GENERAL RE UIREMENTS Activities affecting quality of nuclear safety related structures,

systems, and components shall be prescribed by documented instructions, procedures, or drawings of a type appropriate to the circumstances and shall be accomplished in accordance with these instructions, procedures, or drawings.

These documents shall include appropriate quantitative criteria such as dimensions, tolerances, and operating limits, and qualitative criteria such as comparative workmanship

samples, to assure that the quality assurance activity has been satisfactorily accomplished.

5.2 IMPLEMENTATION 5.2.1 Quality Assurance Program Documents The FPL Quality Assurance Manual described in TQR 2.0 contains corporate Quality Procedures which comply with the criteria of 10 CFR 50, Appendix B.

Quality Procedures and department level Quality Instructions provide direction for activities.affecting quality.

The Quality Assurance Department reviews and comments on Quality Instructions written by other departments.

Comments concerning compliance with corporate QA commitments and requlatory requirements are resolved prior to issuance.

The Quality Assurance Department receives controlled copies of Quality Instructions issued by other departments.

5.2.2 Procedures and Instructions Instructions and procedures for activities affecting quality shall be prepared,

reviewed, and approved in accordance with written Quality Procedures or Quality Instructions.

FLORIDA POWER 8 LIGHTCOMPANY TOPICAL QUALITYASSURANCE'EPORT INSTRUCTIONS, PROCEDURES, AND DRAWINGS TQR 5.0 Rev.

6 3une 10, 1986 Page 2

of 3

. 5.2.2 Procedures and Instructions (Cont'd)

For plant operations, on-site plant procedures shall be prepared, reviewed, and approved in accordance with written instructions which includes a review for concurrence by Quality Assurance or Quality Control personnel.

These plant procedures include operating procedures, off-normal and emergency procedures, test procedures, and calibration procedures.

Also included are maintenance and repair procedures for subcontracted maintenance and repair activities which are outside the normal scope of plant craft capability.

For backfit activities, contractors shall be required to have Quality Assurance Programs which contain written instructions for preparation, review, and approval of procedures, instructions, and drawings affecting quality.

In

addition, Contractor's site procedures and Quality Control inspection procedures shall be approved by FPL Project Site Manager, or his designee, following reviews by Quality Assurance or Quality Control personnel to assure compliance with Corporate commitment and regulatory requirements.

During the

design, modification, and procurement
phases, the Architect/Engineer or other contractors may be delegated responsibility. for maintaining, issuing and verifying the implementation of appropriate program documents.

In this

case, Quality Assurance Department audit and/or Construction Quality Control surveillance activities shall assure that such measures are established and implemented.

Contractor programs shall clearly delineate the actions to be accomplished in the preparation, review and control of instructions, procedures and

drawings, and the methods for complying with the appropriate criteria of 10 CFR 50, Appendix B.

A plant change or modification of a magnitude requiring the assignment of a Project General Manager - Nuclear shall be subject to the QA Program as discussed in above.

TOPICAL QUALITYASSURANCE REPORT TQR 5.0 FLORIDA POWER & LIGHTCOMPANY INSTRUCTIONS, PROCEDURES, AND DRAWINGS Rev.

6 oate June 10, l986 Page 3

of 3

5.2.3 Drawings The design organization is responsible for review and approval of drawings.

For delegated design activities, as appropriate, the Power Plant Engineering Department or the Nuclear Fuel Department may approve changes to drawings.

The technical control of drawings, i.e., review and approval of the drawing and all changes thereto shall be governed by procedures.

A means shall be developed and updated as required to identify approved drawings and revisions thereto.

A Master Drawing List is the normal means used for this.

5.2.0 Acceptance Criteria Quality Procedures and Quality Instructions require that quality related instructions, procedures, and drawings include adequate quantitative and qualitative acceptance criteria, as appropriate, for determining satisfactory work performance and quality compliance.

These acceptance criteria requirements apply to important activities such as design, operations, test control, inspection, and plant modifications.

TOPICAL QUALITYASSURANCE REPORT Rev.

TQR 6.0 FLORIDA POWER 5 LIGHTCOMPANY DOCUMENT CONTROL 3une 10, 1986 Page 1

of 3

6.1 GENERAL RE UIREMENTS The distribution of documents such as instructions, procedures, and drawings which provide guidance, specifications, or requirements affecting the quality of nuclear safety related structures,

systems, and components shall be controlled.

These documents shall be prepared, reviewed for adequacy, and approved for release by authorized personnel in the effected organization.

These documents shall be distributed to locations where the activity is performed.

Changes to controlled documents shall be so identified and shall be reviewed and approved by the same organization that performed the original review and approval unless otherwise specified in the implementing procedures.

In addition, procedures shall provide for controlling obsolete documents to preclude the possibility of use of outdated documents.

6.2 IMPLEMENTATION 6.2.1 Responsibility Quality Procedures shall delineate the control measures for controlled documents including direction for the review for adequacy, approval by authorized personnel, distribution of controlled documents and verification that changes are received.

These control measures shall apply to documents affecting the quality of nuclear safety related structures,

systems, and components such as:

a.

design speci fications; b.

design, manufacturing, construction, and installation drawings; c.

quality program manuals, procedures, and instructions;

TOPICAL QUALITYASSURANCE REPORT TQR 6.0 FLORIDA POWER 8 LIGHTCOMPANY DOCUMENT CONTROL Rev.

Date 3une 10, 1936 Page 2

of 3

6.2.1 Responsibility (Cont'd) d.

inspection, manufacturing, and test procedures and instructions; e.

plant operating and maintenance procedures; plant Safety Analysis Reports and related design criteria documents.

The requirements for control of procurement documents are contained in TQR 0.0.

During all phases of the plant life, it shall be the responsibility of each organization issuing and using controlled documents to use document control procedures.

Procedures shall document the responsibility for review,

approval, maintenance and distribution of documents including assuring revisions are initiated to interfacing documents within their organization.

During the design and construction phase and for operating plant changes under their cognizance, the Architect/Engineer, Nuclear Steam Supply System

vendor, and other contractors shall be responsible for assuring that all revisions required as a

result of FPL

comments, nonconformances, or engineering work are incorporated into revised documents.

6.2.2 Distribution of Controlled Documents Quality Procedures shall specify that controlled documents and revisions be distributed to locations where the activity is performed.

TOPICAL QUALITYASSURANCE REPORT Rev.

T R 6.0 FLORIDA POWER & LIGHTCOMPANY DOCUMENT CONTROL Date 3une 10, 1986 Page of 6.2.3 Drawing Control FPL assumes control of the drawings and Master Drawing List after initial operation of the facility or delegates this activity to a qualified contractor.

The Power Plant Engineering Department shall require that participating design organizations update the drawings and Master Drawing List to reflect the as-built conditions of the facility prior to FPL's acceptance of these documents.

Maintenance, distribution and control of the drawings and the Master Drawing List by FPL during the operation phase shall be assigned to a drawing custodian.

Revision to drawings shall be approved prior to release by the drawing custodian, approval shall be by, as appropriate, Power Plant Engineering, Nuclear Fuel, or a design organization designated by one of these departments.

During the operation phase a system shall be established to provide ready access and availability of drawings to engineering and operations personnel; to identify drawings affected by approved plant design changes; and to update drawings and the Master Drawing List to reflect implemented design changes.

6.2.0 Instruction 2 Procedure Control Participating organizations shall be responsible for development, maintenance and control of those documents identified in paragraph 6.2.1 issued by them as controlled documents.

Each organization shall be responsible for the adequacy of their procedures.

6.2.5 Obsolete Documents Controls established by Quality Procedures and Quality Instructions shall assure that outdated copies of controlled documents are not inadvertently used.

TOPICAL QUALITYASSURANCE REPORT TQR 7.0 Rev.

FLORIDA POWER & LIGHTCOMPANY CONTROL OF PURCHASED ITEMS AND SERVICES Date 3une 10, 1936 Page 1

of 3

7.1 GENERAL RE UIREMENTS Measures shall be established to assure that safety related items or services purchased by or for FPL conform to the requirements of the procurement document.

These measures shall include documented evidence of source selection, verification activities and examination of items or services to assure compliance with the procurement document.

The effectiveness of the control of quality by contractors and subcontractors shall be assessed at intervals consistent with the importance, complexity, and quantity of the product or service.

7.2 IMPLEMENTATION 7.2.1 Initial Evaluation of Suppliers Procurement source evaluation and selection measures shall be specified in Quality Procedures and Quality Instructions which shall identify the responsibility of qualified individuals for determining supplier capability. The evaluation may require integrated action involving Quality Assurance and one or more organizations (e.g.,

Engineering, Construction, Fuel Resources or Purchasing) based upon the item or service being procured.

This evaluation is to ensure that the FPL contractors comply with the applicable portions of 10 CFR 50, Appendix B.

Documented evidence of the evaluation, and the acceptance of the contractor's quality program and procedures shall be retained in the Quality Assurance Department files.

The determination of supplier approval shall be based on such factors as prior performance, historical quality performance data, source surveys or audits, and evaluation of the supplier's QA Program.

The basis shall be consistent with the importance, complexity, and quality required foi the items or services involved.

TOPICAL QUALITYASSURANCE REPORT Rev.

TQR 7.0 FLORIDA POWER 5 LIGHTCOMPANY CONTROL OF PURCHASED ITEMS AND SERVICES 3une IO, 1986 Page 2

of 3

7.2.2 Verification Activities Quality Procedures shall define the requirements for verification activities such as surveillance, inspection, or audit to assure conformance of procured items and services to identified requirements.

These verification activities shall be performed in accordance with written procedures, procurement documents and their references, which specify the documentation required and the characteristic or process to be witnessed, inspected, verified, or accepted.

FPL verification activities shall be accomplished by qualified personnel to verify that the supplier complies with quality requirements, and depending on the importance/complexity, shall be performed on those items where verification of procurement requirements cannot be determined upon receipt.

7.2.3 Receiving Inspection Quality Procedures and Quality Instructions shall delineate requirements and responsibilities for the performance of receiving inspection.

This inspection shall verify that suppliers have fulfilled their contractual obligation and that the procured items meet the appropriate quality requirements.

Receiving inspection shall include, as appropriate:

ao b.

c, d.

Measures for verifying that the shipment is

complete, properly identified, undamaged, and corresponds with the purchase order documentation; Measures for inspection of the item and review of supporting documentation (e.g., mill test reports, NDE reports) as required by the purchase documents; Measures for disposition of items to inspection instructions; Measures for identifying and controlling items including identification of inspection status prior to release from the receiving inspection area;

TOPICAL QUALITYASSURANCE REPORT Rev.

FLORIDA POWER & LIGHTCOMPANY CONTROL OF PURCHASED ITEMS ANDSERVICES Date 3une 10 1986 Page 3

3 of 7.2.3 Receiving Inspection (Cont'd) e.

Measures to ascertain that inspection records or Certificates of Conformance are available prior to release.

7.2.0 Supplier Furnished Records Records required to be furnished by the supplier shall be specified in the procurement document.

Certifications or documentation verifying conformance provided by the supplier shall identify the specific procurement requirements met (either by reference to the purchase order or by referenced requirements therein).

Such certification shall identify any procurement requirements which have not been met and provide a description of those nonconformances dispositioned "accept as is" or "repair".

0

TOPICAL QUALITYASSURANCE REPORT Rev.

T R

8.0 FLORIDA POWER 4 LIGHTCOMPANY IDENTIFICATIONAND CONTROL OF MATERIALS,PARTS, AND COMPONENTS Date 3une 10 1986 Page 1

of 2

8.1 GENERAL RE UIREMENTS Materials, parts, and components, including partially fabricated assemblies, shall be identified and controlled as required throughout fabrication, receipt, handling, storage, installation, and use of the item.

The identification of the item shall be maintained by heat number, part number, serial number, FPL MRS number, or other suitable

means, and shall be physically marked on the item or on records traceable to the item.

The object of these controls shall be to prevent the use of incorrect or defective materials, parts, and components.

(The FPL Material and Supplies MRS number is a number given to each unique type of item in inventory to distinguish it from each other type of item in inventory).

8.2 IMPLEMENTATION Quality Procedures and Quality Instructions shall establish the responsibilities and requirements for the identification and control of materials, parts and components.

The procedures and instructions used by all organizations shall assure that identification and control is maintained throughout fabrication, receipt, handling, storage, installation and use of items.

Provisions include:

ao b.

c, d.

Requirements for traceability to appropriate documentation, such as:

procurement documents, manufacturing documents, drawings, specifications, inspection and test records, and nonconformance reports.

Controls to assure that the correct identification of an item is verified and documented prior to fabrication, receipt, handling, storage, installation and use.

Requirements which assure that the method or location of markings do not affect the function or quality of an item.

Establishment of identification requirements by specifications,

drawings, procurement documents, instructions or procedures during initial planning.

TOPICAL QUALITYASSURANCE REPORT Rev.

TQR 8.0 FLORIDA POWER 8 LIGHTCOMPANY IDENTIFICATIONAND CONTROL OF MATERIALS,PARTS, AND COMPONENTS Date 3une 10, 198 Page 2

of 2

8.2 Implementation (Cont'd)

FPL may delegate any portion of the implementation of the identification and control program to the Architect/Engineer, Constructor, Nuclear Steam Supply System vendor or other contractors.

If delegated, contracts shall require that the contractor establish an identification and control program which meets the requirements of this TQR.

TOPICAL QUALITYASSURANCE REPORT TQR 9.0 FLORIOA POWER & LIGHTCOMPANY CONTROL OF SPECIAL PROCESSES Rev.

6 Date 3une 10, 1986 Page 1

of 3

9.1 GENERAL RE UIREMENTS Measures shall be established to assure that special processes such as welding, heat treating, and nondestructive examination, are controlled and accomplished by qualified personnel using qualified procedures and equipment in accordance with applicable

codes, standards, specifications,
criteria, and other special requirements.

9.2 IMPLEMENTATION The Power Plant Engineering Department, or the Fuel Resources Department or the delegated contractor organization, as appropriate, shall include special process requirements in their design outputs and changes thereto.

Special processes used during plant operations shall be the responsibility of the plant

manager, who shall ensure that procedures are developed, reviewed, approved and controlled, and that personnel and equipment are qualified.

9.2.1 Identification of Special Processes Special processes are those processes which must be qualified and controlled where quality is highly dependent on close control of process variables or operator skills, and objective verification (inspection, examination or testing) of end quality is difficult.

As a further clarification, special processes identified as such by applicable codes and standards shall be controlled, qualified, and implemented in accordance with those codes and standards.

Examples of special processes include (but are not limited to) welding, heat treating, and nondestructive L

examination.

Others, i.e., flushing, protective coating, plating applications and nuclear cleaning should be reviewed to determine if they are special processes.

TOPICAL QUALITYASSURANCE REPORT Rev.

TQR 9.0 FLORIOA POWER a LIGHTCOMPANY CONTROL OF SPECIAL PROCESSES 3une 10, 198 Page 2

of 3

9.2.2 Procedure Qualification and Control Process control procedures written by FPL organizations or their contractors shall be used and qualified as required by applicable specifications, codes, or standards.

'IVhere FPL assigns work to outside contractors, the contractors shall make their procedures and personnel qualifications available for review to FPL prior to the start of work.

The Architect/Engineer, Nuclear Steam Supply System vendor, or other organization designated by FPL shall be responsible for the evaluation and acceptance of on-site contractor special process procedures, and shall interface with the appropriate FPL department, as necessary, to resolve review comments with the contractor.

The contractor shall also be responsible for the control and approval of sub-contractor procedures.

9.2.3 Personnel Qualification and Certification Procedures or instructions shall specify personnel qualification and certification requirements.

Personnel responsible for the performance and verification of special processes shall be trained, tested, and certified as required by applicable specifications, codes and standards.

Requirements for the period of certification, retesting, and recertification of personnel shall also be specified.

Contractors shall qualify personnel and maintain records of qualified personnel in accordance with applicable

codes, standards, specifications, and contract or procurement document requirements.

9.2.0 Special Process Records The Plant Manager is responsible for the review and retention of records.

Records shall provide objective evidence that special processes were performed in compliance with approved procedures by qualified personnel and C0z Ol Iee E

04

TOPICAL QUALITYASSURANCE REPORT Rev.

TQR 9.0 FLORIDA POWER 4 LIGHTCOMPANY CONTROL OF SPECIAL PROCESSES 3une 10, 1986 Page 3

of 3

9.2.0 Special Process Records (Cont'd) equipment.

Records shall also be maintained for verification activities when required by procedure, code or specification.

Results of nondestructive examinations shall be recorded in accordance with applicable specifications, codes and standards.

These records shall be retained by the vendor or supplied to FPL as required by contract or purchase orders.

If records are to be retained by the vendor, the contract or purchase order shall specify the retention period and instructions for final disposition of such records.

For backfit activities, the Construction Quality Control organization is responsible for the review of nondestructive examination documents for acceptance.

The Project Site Manager is responsible for assuring that documents for special processes utilized for modifications are properly collected, reviewed, accepted and transmitted for retention of records.

TOPICAL QUALITY ASSURANCE REPORT TQR 10.0 INSPECTION Rev.

8 Date May 10, 1988 Page 1

of 5

10. 1 GENERAL RE UIREMENTS A program for inspection shall be established and executed by or for FPL to, verify conformance with the documented instructions, procedures and drawings for accomplishing an activity.

Such inspections shall be performed by individuals or groups other than those who performed the activity being inspected.

Examinations, measurements and tests of materials or products processed shall be performed for each work operation, where necessary, to assure conformance to established requirements.

If direct inspection of processed materials or products is impossible or disadvantageous, indirect control by surveillance or monitoring shall be provided.

Mandatory inspection,

witness, or hold points beyond which work shall not proceed without the consent of FPL or a designated representative shall be indicated in the appropriate documents'0.

2 IMPIJBKNTATION 10.2.1 Inspection Responsibilities lO CO Ol For plant operations activities, a program for on-site inspection of activities affecting quality shall be established by the Nuclear Energy Department.

Nuclear Energy shall perform inspections, surveillance and monitoring of plant activities and plant operations as required by established

plans, schedules and/or procedurally required inspection, witness or hold points.

In all

cases, the personnel performing the inspection shall be independent of the group performing the work.

TOPICAL QUALITYASSURANCE REPORT TQR 10.0 INSPECTION Rev.

Date May 10, 1988 Page 2

of 5

10.2.1 Inspection Responsibilities (Cont'd)

For plant modifications assigned to Project Management Department or when requested by the Plant

Manager, a

program for on-site inspection of these activities affecting quality shall be established and executed by the Construction Management Department to ensure conformance with documented instructions, procedures and drawings.

For these plant modifications, the Construction Management Department may delegate the establishment and execution of this program to a contractor or other designated FPL representative, but shall retain ultimate responsibility for the program.

For preoperational start-up and testing of plant modifications, Nuclear Energy personnel may report functionally to the Project Site Manager and establish plans, schedules and procedurally required inspection, witness or hold points.

In all cases, the personnel performing the inspection shall be independent of the group performing the work.

The Construction Management Department shall also be responsible for performing receiving and process verification inspections for work under the jurisdiction of the Project General

Manager, or as requested by the Plant Manager.

The System Protection Group may perform inspections of equipment within their purview during operations.

Inspections shall be performed in accordance with

approved, written procedures by qualified personnel.

Ol D

C0Z Ch Cll 0

U.

Quality Procedures and Quality Instructions shall be written which delineate the requirements and responsibilities for the performance of inspections.

TOPICAL QUALITY ASSURANCE REPORT TQR 10.0 INSPECTION Rev.

8 Date Nay 10.

19SS Page 3

of 5

10.2.2 Inspection Plans and Schedules Documented inspection plans may be either a separate document or an integral part of work instruction documents.

The plans shall be based on design specifications, procurement documents,

drawings, other specifications or previous experience, as appropriate.

Inspections shall be scheduled to assure that sufficient time and resources are available, and to assure inspections are not inadvertently omitted or bypassed.

i 10.2.3 Inspection Personnel a 0 Inspections shall be performed by individuals other than those who performed or directly supervised the activity being inspected.

Inspection personnel shall be qualified and certified in accordance with appropriate

codes, standards and/or company training programs.

Qualifications and certifications shall be kept current.

b.

Prior to performing inspections, inspection personnel shall have access to the

drawings, procedures, specifications or other documented criteria necessary for performance of the inspection.

10.2.4 Inspection Procedures ID CO CV L

a 0 Required inspection, surveillance or monitoring activities shall be performed and documented according to

written, approved instructions or procedures.

Inspection procedures, instructions or checklists shall contain the following:

TOPICAL QUALITY ASSURANCE REPORT TQR 10.0 INSPECTION Rev.

Date May 10.

1988 Page 4

of 5

10.2.4 Inspections Procedures (Cont'd) 0 0

0 0

Identification of characteristics to be inspected; Identification of tive individual or groups responsible for performing the inspection; Acceptance criteria or reference to the acceptance criteria; A description of the method of inspection; Verification of completion and certification of inspection.

b.

Inspection records shall identify:

0 0

0 0

0 Inspector or data recorder; Method or type of observations; Test or inspection results; Statement of acceptability; Date of observation; Deficiencies and nonconformances, and the action taken in connection with these deficient conditions, either by inclusion or by reference to other documents.

c ~

Inspection procedures shall be reviewed by QC personnel to determine the need for an independent inspection and the degree and method if such an inspection is required, and to assure the identification of inspection personnel and the'ethod of documentation of inspection results.

~I Cf.

C0z Ol e4II OI C

0 U.

d.

Written approved instructions shall specify surveillance or monitoring of processing

methods, or testing and operation of equipment when inspection is impossible, inaccessible or not applicable.

TOPICAL QUALITY ASSURANCE REPORT TQR 10.0 INSPECTION Rev.

May 10, 1988 Page 5

of 5

10.2.4 Inspections Procedures (Cont'd) e.

Modification,

repair, replacement or rework items shall be inspected in accordance with original inspection requirements or acceptable alternatives.

10.2.5 Inspection,

Witness, and Hold Point Identification Appropriate inspection, witness or hold points shall appear in process documents (e.g.,

construction,

testing, operating and maintenance procedures).

These process procedures are subject to the review of the appropriate Quality Control organization for adequacy of inspection,

witness, and hold points.

Mandatory hold points shall be used when witnessing and inspecting must be performed and signed-off by the responsible personnel before work can proceed.

FPL shall indicate FPL witness or hold points applicable during the manufacture of an item in procurement documents.

A distinction shall be made between witness points and mandatory hold points.

lO CO C4 0D0!

O

FLORIDA POWER & LIGHTCOMPANY TOPICAL QUALITYASSURANCE REPORT TEST CONTROL TQR 11.0 Rev.

2 3une 10'986 Page 1

of 3

11.1 GENERAL RE UIREMENTS A test program shall be established to assure that testing required to demonstrate that structures, systems and components willperform satisfactorily in service is identified, accomplished, and documented in accordance with written procedures.

The test program shall include, as appropriate, proof tests, prior to installation, preoperational tests, start-up tests, and operational tests, and retest following repairs, replacements or modifications.

11.2 IMPLEMENTATION 11.2.1 Test Program Testing requirements shall be identified in the engineering/design documents, SAR documents, procedures, or procurement documents, as appropriate.

Retest following repairs, replacements, or modifications shall be performed in accordance with the original design and test requirements or acceptable alternatives.

Retest shall be performed when the original test results are invalidated.

Quality Procedures and Quality Instructions shall be written which delineate the methods and responsibilities for controlling, accomplishing, and documenting testing.

FPL may delegate the implementation of all or any part of the test program to other organizations but shall retain ultimate responsibility for the program.

The contractor shall be required to control, perform and evaluate tests in accordance with written procedures and shall be required to prepare a written test program detailing the testing required.

FLORIDA POWER 8 LIGHTCOMPANY TOPICAL QUALITYASSURANCE REPORT TEST CONTROL TQR 11.0 Rev.

2 Date June 10, 1986 Page 2

of 3

11.2.2 Test Procedure Preparation and Test Performance Testing shall be accomplished in accordance with written approved test procedures which incorporate or reference the requirements and acceptance limits in the applicable design and procurement documents.

The test procedure or test program documents shall include the following as a

minimum:

a.

Instructions for the testing method used; b.

Required test equipment and instrumentation; c.

Test requirements and acceptance criteria; d.

Hold, witness, inspection and data collection points; e.

Test prerequisites such as:

calibrated instrumentation;

trained, qualified, and licensed or certified personnel; preparation, condition and completeness of item to be tested; suitable and controlled environmental conditions.

f.

Methods for documenting or recording test data and results; g.

Test records shall identify:

1)

Inspector or data recorder;-

I 2)

Method or type of observations; 3)

Test or inspection results; 0)

Statement of acceptability; V)

COz Ch ICll C

0

TOPICAL QUALITYASSURANCE REPORT TQR 11.0 Rev.

FLORIDA POWER I LIGHTCOMPANY TEST CONTROL Oate 3une 10, 1986 Page 3

of 3

11.2.2 Test Procedure and Test Performance (Cont'd) 5)

Date of observation; and 6)

Deficiencies and nonconformances, and the action taken in connection with these deficient conditions, either by inclusion or by reference to other documents.

11.2.3 Evaluation of Test Results The documented test results shall be evaluated against the predetermined acceptance criteria by a

group or individual having appropriate qualifications.

The acceptance status of the test shall be documented.

Deficiencies noted during the evaluation shall be documented and dispositioned in accordance with approved Quality Procedures or Quality Instructions.

The evaluation of the test results may be delegated to other organizations;

however, FPL shall retain the responsibility for the evaluation.

The evaluating organization shall be required to use qualified personnel, evaluate the data against predetermined criteria, and document the results of the evaluation and acceptance status of the test.

FLORIDA POWER 5 LIGHTCOMPANY TOPICAL QUALITYASSURANCE REPORT CONTROL OF MEASURING AND TEST EQUIPMENT T

R 12.0 Rev.

3 3une 10, 1983 Page 1

of 12.1 GENERAL RE UIREMENTS Tools, gauges, and other measuring and testing equipment used as the basis for acceptance in activities affecting quality shall be properly controlled, periodically calibrated, and adjusted to assure that accuracy is maintained within limits necessary to verify that design requirements have been met.

It is the responsibility of each department maintaining calibrated instruments to provide for the calibration and control of such instruments.

12.2 IMPLEMENTATION 12.2.1 Control of Measuring and Test Equipment Procedures shall be written to delineate the methods and responsibilities for the control, maintenance, and calibration of measuring and test equipment (MdcTE).

MRTE control procedures or calibration program documents shall contain the following:

a.

A listing of MATE to be controlled; b.

Frequency of calibration of listed MATE. The frequency may be based on calendar time or relate to usage, and be based on such factors as experience, inherent stability, instrument purpose, or accuracy required; c.

A method for controlling issue and recall of portable MATE; d.

A method to identify controlled MATE (e.g.,

labeling) required calibration frequency and calibration test data applicable to the MRTE; e.

Method to document and maintain the status of MATE.

TOPICAL QUALITYASSURANCE REPORT Rev.

T R

120 FLORIDA POWER & LIGHTCOMPANY CONTROL OF MEASURING AND TEST EQUIPMENT Date 3une 10, 1985 Page of 12.2.1 Control of Measuring and Test Equipment (Cont'd)

FPL may delegate the control and/or calibration of MRTE to other organizations.

FPL, however, retains ultimate responsibility for control and calibration, and the contractor shall meet the requirements of this TQR or an acceptable alternative program as required by the procurement document for the contracted services.

12.2.2 Calibration Procedure MATE shall be calibrated in accordance with written approved procedures.

The calibration procedures shall contain, as a minimum:

a.

Identity of MATE to which the procedure applies; b.

Calibration equipment and reference standards to be used; c.

Acceptance criteria; d.

Sequence of operations and special instructions; e.

Documentation and data collection requirements; f.

A requirement that MdcTE be checked and results recorded before adjustments or repairs are made; g.

Calibration frequency required.

CC O

CO C0Z Ch CV e

O4

FLORIDA POWER 8 LIGHTCOMPANY TOPICAL QUALITYASSURANCE REPORT CONTROL OF MEASURING AND TEST EQUIPMENT TQR 12.0 Rev.

3une 10, 1985 Page 3

of 12.2.3 Calibration Standards MRTE shall be calibrated using reference standards whose calibration has a known, documented, valid relationship to nationally recognized standards or accepted values of natural physical constants.

If no national standard exists, the basis for calibration shall be documented.

Standards and reference standards shall have an accuracy

level, range and stability which are adequate to verify that the equipment being calibrated is within tolerance and adequate for the programmatic requirements of the equipment being calibrated.

MRTE shall be calibrated against working standards having an accuracy of at least four times the required accuracy of the equipment being calibrated.

When this is not practical, working standards shall have an accuracy that assures that the MRTE being calibrated will be within required accuracy tolerances and that the basis of acceptance is documented and authorized by designated responsible management.

The meaning of this paragraph may be diagrammed as follows:

NATIONAL BUREAU OF STANDARDS (NBS)/NBS Certified Laboratory "greater than" tolerance PRIMARY STANDARD(if applicable)

"greater than" tolerance SECONDARY STANDARD(if applicable)

"greater than" tolerance WORKING STANDARD "1:0 ratio" tolerance (except as noted above)

MRTE (installed instruments and measuring and test equipment used for inspection, maintenance, etc.)

TOPICAL QUALITYASSURANCE REPORT Rev.

T R

12.0 FLORIDA POWER & LIGHTCOMPANY CONTROL OF MEASURING AND TEST EQUIPMENT Date 3une 10, 1935 Page

~

of 12.2.3 (Cont'd)

The accuracies of MRTE and reference standards shall be chosen such that the equipment being calibrated can be calibrated and maintained within the required tolerances.

12.2.0 "Out of Tolerance" Control MATE and reference standards, when found out of tolerance, shall be so identified and removed from service.

An investigation shall be conducted to determine the validity of previous inspection or test results gained through use of the instrument, and of the acceptability of items previously inspected or tested.

TOPICAL QUALITYASSURANCE REPORT TQR 13.0 FLORIDA POWER 5 LIGHTCOMPANY HANDLING,STORAGE AND SHIPPING Rev.

3une 10, 1986 Page 1

of 2

13.1 GENERAL RE UIREMENTS

)Vritten instructions or procedures shall be established and implemented for the cleaning, shipping, storage, preservation, packaging, and handling of specified items.

These instructions and procedures shall delineate measures which prevent degrading an item through damage or deterioration.

)Vhen necessary for particular

products, special protective environments such as inert gas atmosphere, specific moisture content levels, and temperature levels shall be specified and provided.

13.2 IMPLEMENTATION 13.2.1 General Instructions or procedures shall be written to define the requirements and responsibilities for the cleaning, packaging, preservation, handling, storage, and shipping of equipment and material, and shall require implementation of the established design and specification requirements by personnel having appropriate qualifications.

FPL may delegate any portion of the responsibility for handling, storage and shipping of material and equipment, but shall retain ultimate responsibility.

5Vhere any of the functions in the section which follow is delegated to a contractor, the contractor shall be required to adhere to the FPL requirements stated herein.

13.2.3 Handling, Storage, and Shipping Procedures Materials and equipment which are to be incorporated into a safety related system of a nuclear power plant shall be handled,

stored, and shipped in accordance with written procedures, where necessary, to implement the design document and purchase order requirements.

These procedures shall assure that cleaning, handling, storing, packaging, shipping, and preserving

TOPICAL QUALITYASSURANCE REPORT Rev.

TQR 13.0 FLORIDA POWER & LIGHTCOMPANY HANDLING,STORAGE AND SHIPPING Date June 10, 193 Page 2

Gf 13.2.3 Handling, Storage, and Shipping Procedures materials, components and systems will preclude

damage, loss, or deterioration by environmental conditions, such. as temperature or humidity.

The preparation and/or implementation of these procedures may be delegated to other organizations, but FPL shall retain the ultimate responsibility for proper material handling, storage, and shipping.

13.2.0 Verification of Proper Handling, Storage, and Shipping.

The Quality Assurance Department shall be responsible for verification of proper

handling, storage and shipping at vendor facilities.

The Plant Manager and the QA Department shall be responsible for verification of proper handling, storage, and shipping at the plant.

TOPICAL QUALITYASSURANCE REPORT TQR 10.0 FLORIDA POWER K LIGHTCOMPANY INSPECTION, TEST, AND OPERATING STATUS Rev.

6 Date 3une 10, 1986 Page 1

of 2

10.1 GENERAL RE UIREMENTS Measures shall be established to indicate by the use of markings such as stamps, tags, labels, routing cards or other suitable means, the status of inspections and tests performed on material, equipment, or systems.

These measures shall provide for the identification of items which have satisfactorily passed required inspections and tests.

Measures shall also be established for indicating the operating status of structures, systems and components to prevent inadvertent operations.

10.2 IMPLEMENTATION 10.2.1 General For operations activities, the Nuclear Energy Department is responsible for establishment and maintenance of a suitable system for identifying the inspection, test, and operating status of materials, equipment, systems, and components.

For plant modifications assigned to Project Management Department or when requested by the Plant

Manager, the Project Site Manager is responsible for establishing a suitable system for identifying, inspecting and testing for material, equipment, systems and components which is approved by Nuclear Energy Department.

Each system shall be established, implemented and maintained in accordance with written Quality Procedures and Quality Instructions.

The Architect/Engineer or Contractors shall develop and implement procedures to comply with contractual responsibilities, and applicable codes, standards, specifications, and criteria governing the status identification of procurement items being

tested, installed, or fabricated.

The Architect/Engineer (where applicable),

suppliers and contractors shall be required to maintain a

system for identifying the inspection, test and processing status of materials, parts, and

TOPICAL QUALITYASSURANCE REPORT Rev.

TQR 10.0 FLORIDA POWER & LIGHTCOMPANY INSPECTION, TEST, AND OPERATING STATUS Date June 10, 1986 Page 2

of 10.2.1 General (cont'd) components.

Elements of this system require that suppliers and contractors have a controlled manufacturing and test operation in order to preclude the inadvertent bypassing of processing, inspections or test, and to provide a positive identification of component status throughout all phases of manufacturing, testing, and inspecting, by means of tagging, routing cards,

stamping, manufacturing or test
reports, labeling or other appropriate methods.

The Vice Presidents - Turkey Point or St. Lucie and the Quality Assurance Department shall verify adequacy of the controls established and implemented, as appropriate for their site.

10.2.2 Status Identification and Control Quality Procedures and Quality Instructions shall describe control of the application and removal of markings such as stamps, tags, labels, routing

cards, and other suitable means to indicate the status of non-operational, nonconforming, or malfunctioning nuclear safety related structures, systems and components to prevent inadvertent operation, and to prevent omission of inspections,
tests, or other critical operations.

These procedures and instructions shall delineate the requirements, methods and responsibilities for indicating the status of the affected items.

These procedures will clearly delineate the individuals or groups responsible for application and removal of status indicators.

TOPICAL QUALITY ASSURANCE REPORT TQR 15.0 NONCONFORMING MATERI2KSi PARTS OR COMPONENTS Rev.

Date May 1P, 19S8 Page 1

of 4

15. 1 GENERAL RE UIREMENTS Measures shall be established to control materials, parts, or components which do not conform to requirements in order to prevent their inadvertent use or installation.

These measures shall

include, as appropriate, procedures for identification, documentation, segregation, disposition and notification to affected organizations.

Nonconforming items shall be reviewed and accepted,

rejected, repaired or reworked in accordance with documented procedures.
15. 2 IMPLEMENTATION 15.2. 1 Program Quality Procedures and Quality Instructions shall define the responsibilities and methods for identifying, documenting, segregating and dispositioning nonconforming items.

For procedure review requirements, see TQR 2.0 and TQR 5.0.

Each department shall be responsible for the identification, control and disposition of nonconformances within the scope of their departmental responsibilities.

ED CO CV Throughout plant life, FPL may delegate any portion of the identification and control of nonconforming items and services to an Architect/Engineer (A/E),

constructor, NSSS vendor or other contractors.

In any

case, FPL retains the responsibility for assuring that requirements are
met, and shall assure that the contractor's actions conform to requirements set by FPL.

TOPICAL QUALITY ASSURANCE REPORT NONCONFORMING MATERItLLS, PARTS OR COMPONENTS TQR 15.0 Rev.

7 May 10, 1988 Page 2

of 4

15.2.2 Documenting and Controlling Nonconformances All nonconformances in safety related items shall be documented and reported for corrective action.

Measures shall be delineated in Quality Procedures and Quality Instructions which control further processing, installation, or operation of nonconforming items.

These measures shall include:

a.

Physical identification of the item as nonconforming.

b.

Segregation of nonconforming items until properly dispositioned.

Where physical segregation is not practical, suitable tags, marking or documentation shall be used to assure control.

15.2.3 Documentation Documentation of the nonconforming item shall:

identify the item; describe the nonconformance; show disposition of the nonconformance and inspection requirements; and include the signature of the person approving the disposition.

15.2.4 Evaluation and Disposition CO CV DC C0z Ol P4 C4 0

U.

Power Plant Engineering, Nuclear

Fuel, Nuclear Energy or the delegated contractor organization, as specified by procedure, shall evaluate nonconformances and disposition them based on the results of the evaluations.

These evaluations and dispositions shall be

reviewed, approved and documented in accordance with procedures.

TOPICAL QUALITYASSURANCE REPORT NONCONFORMING KLTERIALS, PARTS OR COMPONENTS TQR 15.0 Rev.

7 May 10, 1988 Page 3

Of 4

15.2.4 Evaluation and Disposition (Cont'd)

An evaluation to determine the disposition of nonconforming items shall be performed.

The evaluation shall determine whether an item is to be accepted as-is,

repaired, reworked or rejected.

A technical evaluation shall be performed when an item is accepted as-is or is repaired to an acceptable condition.

Records of the disposition of these items shall be made part of the nonconformance report.

This evaluation shall assure that the final condition does not adversely effect safety, operability or maintainability of the item, or of the component or system in which it is installed.

The A/E, or other contractors on-site, shall be required to inform the FPL Construction Management or Nuclear Energy Department prior to use or installation of a

nonconforming item.

The nature and extent of a nonconformance and the reason for proposing its use or installation shall be justified.

Nonconforming items dispositioned "accept as-is",

or repaired to an acceptable condition, shall be so identified.

Nonconformance reports for those items shall be made part of the item records and forwarded with the material to FPL.

The determination of the need and the advisability of releasing nonconforming materials or

items, is made by the Power Plant Engineering, Construction Management or Nuclear Energy Departments.

The following factors may be appropriate considerations in making this determination:

a.

Effect on the orderly progress of,work if material or items are released; b.

Safety of personnel;

TOPICAL QUALITY ASSURANCE REPORT Rev.

TQR 15.0 NONCONFORMING MATERIALS, PARTS OR COMPONENTS Date May ]p. 1988 Page 4

of 4

15.2.4 Evaluation and Disposition (Cont'd) co d.

e.

Suitability of material or items in "as-is" condition, i.e.,

probability of eventual satisfactory resolution of the nonconformance without repair, rework, or replacement; Accessibility of material or items after release; Cost of removal and repair of replacement should material or items eventually have to be removed, repaired, or replaced; Impact on plant safety.

Items shall be reworked or repaired in accordance with documented procedures and shall be verified by reinspecting the item as originally inspected or by a documented method which is at least equal to the original inspection method.

Quality Assurance or Quality Control personnel shall periodically review nonconformance reports to identify quality trends.

The results of these analyses shall be reviewed with appropriate members of upper level management.

ID N

D Vl C0Z Ol C4 04.

TOPICAL QUALITYASSURANCE REPORT TQR 16.0 FLORIDA POWER 8 LIGHTCOMPANY CORRECTIVE ACTION Rev.

5 Date 3une 10, 1936 Page 1

of 3

16.1 GENERAL RE UIREMENTS Documented measures shall be used to assure that conditions adverse to quality such as failures, malfunctions, deficiencies, deviations, defective material and equipment, and nonconformances, are promptly identified and corrected as soon as practicable.

In the case of significant conditions adverse to quality, the cause of the condition shall be determined and action taken to preclude repetition.

The identification of significant conditions adverse to quality, the cause of the condition, and the corrective action taken shall be documented and reported to appropriate levels of management.

16.2 IMPLEMENTATION 16.2.1 Corrective Action and Follow-Up Quality Procedures and Quality Instructions shall define responsibilities and methods for identifying and correcting conditions adverse to quality.

)Vhen an adverse condition is detected, a

determination shall be made by plant supervision, Quality Control, or Quality Assurance personnel as to whether immediate or routine corrective action is required.

"Immediate Corrective Action" applies to conditions which pose a threat to plant safety or to the health and safety of the public, which could result in major equipment and material

damage, or could, if not corrected, produce defects of significantly greater consequences than those immediately resulting from the condition.

"Immediate Corrective Action" is accomplished through stop-work requests/orders to appropriate levels of management, requiring that work be stopped, the plant be shut down or other appropriate actions be taken.

TOPICAL QUALITYASSURANCE REPORT Rev.

TQR 16.0 FLORIDA POWER & LIGHTCOMPANY CORRECTIVE ACTION Date 3une 10, 19g6 Page 2

of 3

16.2.1 Corrective Action and Follow-Up (Cont'd) b.

"Routine Corrective Action" applies to conditions which do not require immediate corrective action.

Routine corrective action is assured through the distribution and disposition associated with inspection reports, surveillance reports, nonconformance reports, and audit reports; and the investigation analysis and action associated with reportable conditions.

Follow-up to verify implementation of corrective action and close-out of corrective action documentation is accomplished by the QA or QC organization responsible for verifying the corrective action.

The Quality Assurance Department shall

track, follow-up, and close-out open items identified by QA Department audits and vendor surveillances.

The respective department or plant shall track those items charged to its operating license by the NRC. Each department shall be responsible for follow-up and close-out of corrective action resulting from their departmental inspections,

tests, or operations.

If corrective action is inadequate or not timely, the follow-up organization shall request corrective action from management, as delineated in procedures.

The Quality Assurance Committee is the final authority in the event that agreement is not reached at lower levels regarding stop work requests or other corrective action.

V/here corrective action is required of contractor personnel, FPL shall define in procedures and contracts the corrective action interface between FPL and the contractor.

FPL shall require, the A/E, NSSS vendor, constructor and other suppliers of safety related materials and services to have a documented corrective action system.

TOPICAL QUALITYASSURANCE REPORT TQR 16.0 FLORIDA POWER 8 LIGHTCOMPANY CORRECTIVE ACTION Rev.

Date 3une 10, 1986 Page 3

of 3

16.2.2 Recurrence Control It is the responsibility of the organization which identifies the significant condition a'dverse to quality to verify that corrective action description not only corrects the immediate condition, but also precludes the condition from recurring.

The organization(s) that provide(s) the corrective action disposition and implementation is responsible to assure that the corrective action taken not only corrects the immediate condition, but also precludes recurrence.

16.2.3 Incidents and Reportable Occurrences Reporting Operating Reportable Occurrences and reports of incidents shall be investigated, documented as to cause and corrective action, and reported to the NRC in accordance with the applicable plant Technical Specifications.

Reportable Occurrences and reports of incidents that result in damage or are otherwise safety related, shall be forwarded to the Company Nuclear Review Board (CNRB) for review.

Conditions adverse to quality are reported to operating plant management through:

distribution of QA audit reports, QC inspection

reports, corrective action
requests, and the investigation and reporting of Reportable Occurrences in accordance with plant Technical Specifications.

TOPICAL QUALITYASSURANCE REPORT TQR 17.0 FLORIDA POWER 8 LIGHTCOMPANY QUALITYASSURANCE RECORDS Rev.

Date 3une 10, 1986 Page 1

Gf 2

17.1 GENERAL RE UIREMENTS Sufficient records shall be maintained to furnish documented evidence of the quality of safety related structures,

systems, and components, and of activities affecting their'quality.

The records shall include, as appropriate, data such as qualifications of personnel, procedures, and equipment; and other documentation such as inspection or test acceptance criteria, and the action taken in connection with deficiencies noted during inspection.

The records required to furnish documentary evidence of quality, herein called quality assurance

records, shall be identifiable and retrievable.

These records shall be maintained in facilities that provide a suitable environment to minimize deterioration or damage and to prevent loss.

The requirements and responsibilities for quality assurance record control, transmittal, retention, and maintenance shall be established and documented.

These record requirements shall be consistent with applicable

design, manufacturing, and installation codes and standards, and with procurement document requirements.

17.2 IMPLEMENTATION 17.2.1 Records Identification Quality Procedures shall define the quality assurance records necessary to furnish documentary evidence of the quality of safety related structures,

systems, and components; and activities affecting quality.

These records shall include plant operating logs; results of design

reviews, inspections, tests, audits, and material analyses; qualification of personnel, procedures, and equipment; design records such as drawings and specifications; procurement documents; calibration records; and nonconformance or corrective action reports.

FLORIDA POWER & LIGHTCOMPANY TOPICAL QUALITYASSURANCE REPORT QUALITYASSURANCE RECORDS TQR 17.0 R ev.

2 Date 3une 10, 1986 Page 2

of 17.2.2 Responsibilities Responsibilities shall be established and documented for the

control, transfer, maintenance, and retention of quality assurance records.

Quality Procedures shall provide guidance for determining the retention requirements of quality assurance records.

Each organization responsible for the conduct of a quality activity shall be responsible for the maintenance of the subsequent quality assurance records unless retention responsibilities have been transferred by a

prearranged agreement.

In any

case, the organization initiating the quality assurance records shall be responsible for their validity and approval.

17.2.3 Retrieval Quality Procedures shall require that quality assurance records submitted for retention be legible, completely filled out, and adequately identifiable and retrievable for each item.

The records shall be filed in the storage area or facility using a

documented system to provide retrievability.

Quality Procedures additionally require control of corrections and supplements issued for quality assurance records that are previously approved and filed, and that documented methods for control and accountability of records removed from the storage area be instituted.

17.2.0 Storage Specified in the Quality Procedures are the construction features and location requirements for record storage facilities which assure that quality assurance records are protected from possible destruction by causes such as

fire, flooding,
theft, tornadoes,
insects, rodents, and from possible deterioration by a combination of extreme variations in temperature and humidity.

Specific instructions regarding the storage area are given for special processed records and for temporary storage facilities.

TOPICAL QUALITYASSURANCE REPORT TQR 18.0 FLORIDA POWER 8 LIGHTCOMPANY AUDITS Rev.

5 Date 3une 10, 1986 Page 1

of 5

18.1 GENERAL RE UIREMENTS A comprehensive system of planned and periodic audits shall be carried out to verify compliance with all aspects of the quality assurance program and to determine the effectiveness of the program.

The audits shall be performed in accordance with the written procedures or checklists by appropriately trained personnel not having direct responsibilities in the areas being audited.

Audit results shall be documented and reviewed by management having responsibility in the area audited.

Follow-up action, including reaudit of deficient areas, shall be taken, where necessary.

18.2 IMPLEMENTATION A comprehensive program of audits is carried out by the Quality Assurance Department during the design, procurement, construction, and operations phase of nuclear power plants.

These audits are performed to verify that all safety related activities associated with nuclear power plants are carried out in accordance with the requirements of the FPL QA Program, and that the implementation is effective.

18.2.1 Personnel Quality Procedures provide instructions for the training of QA Department personnel who perform audit activities, to assure that they are adequately indoctrinated and traine'd, and that they are qualified to carry out these activities.

Quality Procedures provide for personnel qualified as Lead Auditors to be formally certified by Quality Assurance Department management.

Certification shall be based on education, experience, training and other specified criteria.

TOPICAL QUALITYASSURANCE REPORT Rev.

TQR 18.0 FLORIDA POWER 8 LIGHTCOMPANY AUDITS 3une 10, 1986 Page 2

of 5

18.2.2 Planning and Scheduling Quality Procedures and Quality Instructions provide requirements for written audit plans and schedules.

The audits are planned and scheduled on the basis of the following requirements, as appropriate:

a.

Activities shall be audited as early in their life as practicable.

Auditing shall be initiated early enough to assure effective quality assurance during the design, procurement and contracting activities.

b.

Applicable elements of the internal and on-site QA Programs shall be audited at least once every two years during the operation phase of plant life following initial fuel loading.

For other plants'hases, the applicable. elements shall be audited at least once every year or once within the life of a quality related activity, whichever is shorter.

c.

An annual evaluation of suppliers'uality performance history shall be performed to determine reaudit requirements.

Reaudit requirements for suppliers shall be based on the supplier's quality performance and the complexity and criticality of the equipment or service being procured.

A facility evaluation (audit) willbe performed at least every three years and shall be conducted in accordance with Quality Procedures and Quality Instructions for supplier evaluations.

d.

Audits shall be regularly scheduled for on-going activities.

e.

Regularly scheduled audits shall be supplemented, as required to cover unforeseen events or changes in requirements.

The scope of audit activities shall include, as a minimum:

TOPICAL QUALITYASSURANCE REPORT TQR 18.0 FLORIDA POWER a LIGHTCOMPANY AUDITS Rev.

5 DaIe 3une 10, 1986 Page 3

of 5

18.2.2 Planning and Scheduling (Cont'd) a.

The determination of site features which affect plant safety (e.g., core sampling, site preparation, and meteorology).

b.

The preparation, review, approval, and control of the SAR, designs, specifications, procurement documents, instructions, procedures, and drawings.

c.

Evaluation of bids.

d.

Indoctrination and training programs.

e.

Receiving and plant inspections.

f.

Operation, maintenance/repair and modification.

g.

The implementation of operating and test procedures.

h.

Allcriteria in Appendix B to 10 GFR Part 50.

i.

Validity of Certificates of Conformance.

External audits shall be performed by the Quality Assurance Department on Architect/Engineers, NSSS

vendors, constructors, and other suppliers of safety related materials and services to evaluate their QA programs, procedures and activities.

Procurement documents require that FPL suppliers and contractors in turn perform audits on their sub-tier suppliers and contractors.

TOPICAL QUALITYASSURANCE REPORT TQR 18.0 FLORIDA POWER & LIGHTCOMPANY AUDITS R ev.

5

~

>><<3une 10, 1986 Page g

of 5

18.2.3 Conduct of Audits Quality Procedures and Quality Instructions shall delineate requirements for the conduct of audits. These procedures and instructions shall require that:

a.

Audits be conducted by trained and qualified personnel.

b.

Personnel conducting audits shall not have direct responsibility in the area audited.

c.

Checklists or procedures shall be used to ensure depth and continuity of audits.

d.

Objective evidence shall be examined for compliance with quality assurance program requirements.

This shall include examination of procedures and activities to assure that documented objective evidence is meaningful and in compliance with the overall Quality Assurance Program.

e.

Audits shall include evaluation of work areas, activities, processes and items; and the review of documents and records.

18.2.0 Reporting of Audit Findings Audit findings shall be documented in written reports.

Audit reports shall be distributed to the responsible management of the audited FPL organization within thirty calendar days after completion of the audit.

TOPICAL QUALITYASSURANCE REPORT TQR 18.0 FLORIDA POWER L LIGHTCOMPANY AUDITS Rev.

Date 3une 10, 1986 Page 5

of 5

18.2.5 Follow-up Responsible management of the audited organization shall take action to correct the deficiencies identified in the audit report and provide a written response within thirty calendar days after receipt of the report.

This response shall include action taken and/or planned to correct deficiencies and to prevent recurrence of the deficiencies, and commitment dates for actions not yet complete.

The mechanism for evaluation and follow-up of corrective action is described in TQR 16.0.

The status of correction of deficiencies shall be followed until the corrective actions have been accomplished and verified.

18.2.6 Reports to Management Quality Assurance Program status reports are periodically prepared by the QA Department and routed to the members of the QA Committee for their review.

This status report summarizes the results of QA Department audit activities for the period, keeps all Committee members apprised of current conditions and program effectiveness, and when necessary, directs management attention to significant trends and problems.

PACSIOCNT CICCUTIVI VICC PACSIOCNT CItCUTIVt VICC tattfotNT SCNIOI VICC PACSIOCNT VICC MCSIOCNT COAOA1TC StAYICC~

1NO CHltP

~ INANCIAL OffICta SCNI 01 VICC tatSIOCNT CoatANY NVCLCAA ACYICV SOMO OVALITT ASSVAANCC CONHIITCt SINf01 VICC PACSIOCNT NVCLCM DIRCCTOA~

CORP OA1 IC CONTAACfS YICC PACSIOCNT OIACCTOA Of taocvatNKNT ANO NATC1IAL NSNf VICC taCSIOCNT toYCA DCLI'YCAY DIRCCTOA Of FUCL'0 NANASC1 OF NUCLtaA SVKL DIACCTOA POVCA SUPPLY OtRCCTOA OF CONSTAVCTION NANASCA Of PLANf CONSTAVCTION CONST1VCTION SVPCAINTCNDCNf CONSIAVCTION ttASONNKL NANAOtA CONSTAVCIION Oc VCLOINO ANO NDK STAFF OC COORDINATOR taoJCCT OC SVPCAYISOA CHICf CNSINCCA fofta PLANT OVTS IDC CONSVLfANTS CICCUTIVC 1'ISISTANf DIACCTOA OF PAOJCCTS PAOJCCT OCNCAAL NANASCA tAOJCCT Ttaa I

I I

I I

I I

I l

I I

I I

I I

I I

I I

I HANAOta Of COAPOAATC CONIAAC IS coapoaATt SCCACTMT NANASCA OF COAPOAAIC RCCOAOS StAYICCS OIRCCTOA Of CNYI10NNCNIAL Aff1 I1$

CoatANY CNYIAONNCNT1L ACYICV OAOVP NANACCA Of CNYIAONNCNTAL CCHNICAL SCAYICCS NANAOCA OF CNVIAONNCNTAL acsovaccs 0

Pl ANNtNS Haaasca of CNVIAONNCNTAL tta Nl 'I1 INS

~

t1001ANS tVPCAYISM Ot OOCVNCNTMY SILKS NANASCA OF tlNCHAS INO HANASCA Of INVCNIOAT ACSOVACCS NANASCA Of tofta tLANI SIOACS NANASCR SYSftN PAOTCCTION NANASCA Of POVKA SVttLT TCCHNICAL SCAVICCS NOC LCVCL III SVPCAYISOA VCI.OINO SVttalNTCNOCNT SITC VICC tatSIOCN TVMtf POINf NUCLCAA SPCCIFIC SITC OAOANIIATION la fl~ I-t YICC PACSIDCNT SITC vlcc PACSIOCN Nvcaaaa actasr Sf LUCIS SPCCIFIC SITC OASANIIATION INSI~ I I NANASCA tLANNINO AND CON'fAOL N1N1OCA NVCLCAA CNCAOT SCAVICCS DIACCTOA OVALflT ASSVAANCC NANASCA NVCLCAA CNC1ST NAINTCNANCC HANAOKA NUCLCAA TRAHINS D IRCCTOA NVCl.tAA LICCNS INS CVVCNICCfla KICK

~vtaAtaftaotaf OA ST ~ LVCIC NANASCA SVftalNTCNDCNT OVALlffASSVAANCC OA SKAYICCS TVRICY tolNT NANASCA PAOCUACNCNT ~

ACLIAOILITY TOPICAL OUALITY ASSURANCE REPORT 0101HI1A'IION OF DtfaafNCNIS AfftCIINS OVALITT FIOVAC I I APFKNOIX 1 KT I I Selt~

~KC Nl OVAL I 'IY 1SSURANCC tAOOAAN 1tYICV Colull'I'fC l01taC I CAD OC OA f CISSIRS

SITE VICE ~ AESIOENI TUMKT to INT tLMT NANASKA NVCLEM SKAYICct NANASKA NVCLKAA 5 ITK tADIECT NANASEA SITE ENSINCCAINS NANASK1 tL1NT SKCUAIIV SUVKAYISOA flAK taolcCTION 5WKAYI501 afcll caslaccalas

~tout CH1IANAN tL1NI NVCLEAA tafcrr CONNIITEE OtlAATIONS 5utcalNTKNOENT NVCLKM ouALII1 CON110L SWKAYISOA IECIVIICAI.

OEYMTNENT SUVKAVltoh TAAININS 5UtcAVISOA NAINTKNANCK SutKAINIKNDENT NVCLKAh HEALTH tNYSICt SVtcaVISOA AEACTOA Sutf all SON OAKAATTONS SWEATISM CHC NI5 11 1 5utK1 1 I501 TKCNNICAL 5IAff INSTAVNCNT AND CONTAOL SUYKAVISOA 1$ $ ISIANT SVAEAINTKNDENT NICNANICAL NAINIKNANCK NVCLEAh AS ISIANI tUtca NTKNDENI ELEC'IA ICAL NAINTKNANCE NVCLEM AAOI1TION taOTKCTION NAN AE ACT OA fNS INEKA

~LANI SWEAT1501 NVCLKM Ithol 11010 CHENISI SHIf1 TECHNICAL AOYISM NUCLKAA NATCH ENSINKca 1510)

NVCLKAA CONTAOL CENTKA OYEAATOA 1101 uNLICKNsco OtcAA'1015 C40 OC 64 7-K29S240 TOPICAL QUALI'TY ASSURANCE REPORT TURKEY POlNT NUCLE4R SITE ORGANIZATION FI6URE I 2 APPEHOTX A AEV DATE 5/Io/SS tASC Al

sl'lC vlcc tactlocal 5T ~ LUCIS tLANT NANASCI 5CIYICCS NANASCI ADAINIS TAITIYC 5UtCIYISON FIAC taOTCCTION SUtCAYISOA tLANT SCCUAI'IY SUFCAYISOA OttIATIONS SVttalNICNOCNT TAAININO SUFCIYISOA TCCHNICAL DCFAAINCN'I SUttIYISON OVALITY CONIAOL 50tCa YISOA NAINltNANCC 5VtfII NIC NO III NCALTN tNYSICS 5UtCIYISOS ICACTOI SUttAYISOI OttIATIDNS SVtCAYISOI ISIOI CNCNISTAY SUttAYISOI TCCHNICAL STAFF INSTAUACNT ANO CONTAOL SUttAYISOA A55ISIANI 5WCAINICNOCNT NtCNANICAL NAINICNANCC ASS I5 TANI 5VI'tIINTt NOT NI CLCCTAICAL NAINICNANCC ICACIOA CNSINCCI NUCLCAA tL*NT SUtCAYltOI ISIS I 5HIFT

'ItCNNICAL AOYISON A55I IANI NUCLCAA ttaal SUFI AYISOI ISAOI CON AOL CtNICA OFCAAIOA IIOI UNLICCNSCO OttAAIOAS CAO OC 64-7-629SSAO TOPICAL QUALITY ASSURANCE REPORT ST. LUCIE PLANT~ UNITS I 6 2 SITE ORSANIZATION FIGURE 1-6 APPENOIX A ICY.

0 SAIC a

5/IO/SS FASC

~I

TOPICAL QUALITYASSURANCE REPORT Rev.

FLORIDA POWER 8 LIGHTCOMPANY QUALIFICATIONAND EXPERIENCE REQUIREMENTS FOR FPL QUALITY ASSURANCE PERSONNEL Date 3une 10 1986 Page of 1

1 TITLE Manager of Quality Assurance Services and Superintendents

- QA EDUCATION AND BACKGROUND EXPERIENCE+

Shall satisfy the following set of requirements:

Graduate of a four year accredited engineering or science college or university, plus seven years of industrial experience, including five (5) years in positions of leadership such as lead engineer, project engineer, audit team leader, etc.

At least two (2) years of this five (5) years experience shall be nuclear power plant experience in the implementation of the Quality Assurance Program.

Six (6) months of the two (2) years experience shall be obtained within a Quality Assurance organization.

A masters degree in engineering or business management is considered equivalent to two (2) years of general industry experience.

Assistant Manager of Quality Assurance Shall satisfy one of the following sets of requirements:

Graduate of a four year accredited engineering or science college or university, plus seven years of industrial experience including three years in positions of leadership, such as lead engineer, project engineer, audit team leader, etc.

At least two years of this experience should be associated with nuclear facilities.

A masters degree in engineering or business management is considered equivalent to two years of experience.

Completion of college level work leading to an associates degree in a related discipline plus fifteen years of industrial experience including three years in positions of leadership, such as project

engineer, audit team
leader, supervisor, etc.

At least five years of this experience should be associated with nuclear facilities.

High school

graduate, plus twenty years of industrial experience, including three years of positions of leadership, such as project
engineer, audit team
leader, supervisor, etc.

At least five years of this experience should be associated with nuclear facilities.

CO2 Ol e

04 The education and experience requirements should not be treated as absolute when similar training or an outstanding record will provide reasonable assurance that a person can perform the required tasks.

FLORIDA POWER 4 LIGHTCOMPANY TOPICALQUALITYASSURANCE REPORT BASELINE DOCUMENT MATRIX APPENDIX C Rev.

7 3une 10, 198ff Page 1

of This topical report contains the program requirements for Florida Power R Light Company's Quality Assurance Program.

The Quality Assurance Program is described in detail in the Florida Power 2 Light Company Quality Assurance Manual.

The Regulatory Guides, codes, and standards specifically listed in the matrix of this appendix (on page 2) represent the baseline documents used in the preparation of FPL's QA Manual and this topical report.

These documents, therefore, provide the basis for the FPL QA Program, but they are not considered to be part of the QA Program unless specifically addressed in the applicable SAR, technical specifications, etc.

The FPL Quality Assurance Program meets the requirements of the documents referenced in this appendix.

'Any alternatives or clarifications made to the requirements contained in these documents are stated on pages subsequent to the second page of this appendix.

FLORIDA POWER a LIGHTCOMPANY TOPICALQUALITYASSURANCE REPORT BASELINE DOCUMENT MATRIX APPENDIX C Rev.

7 3une 10, 1980 Page 2

of GOVERNMENT DOCUMENT 10 CFR PART 50, APPENDIX B 10 CFR PART 50;55a 2/19/75 ANSI-N05.2 1971 ASME BRPV Code Specified in the Section IIIR SAR document of XI the respective plant REFERENCE INDUSTRY DRAFT REV.

DATED STANDARD ISSUED DATE Regulatory Guide 1.8 Rev.

1 Regulatory Guide 1.28 Regulatory Guide 1.30 Regulatory Guide 1.33 Rev. 2 Regulatory Guide 1.37 Regulatory Guide 1.38 Rev. 2 Regulatory Guide 1.39 Rev. 2 Regulatory Guide 1.58 Rev.

1 Regulatory Guide 1.60 Rev. 2 Regulatory Guide 1.7'egulatory Guide 1.88 Rev. 2 Regulatory Guide 1.90 Rev.

1 Regulatory Guide 1.116 Regulatory Guide 1.123 Rev.

1 Regulatory Guide 1.100 Rev.

1 Regulatory Guide 1.106 9/75 6/7/72 ANSI-N18.1 ANSI/ANS 3.1 ANSI-N05.2 2/78 ANSI-N18.7 3/16/73 ANSI-N05.2.1 5/77 9/77 9/80 6/76 2/70 10/76 O/76 6/76 7/77 9/80 8/80 ANSI-N05.2.2 ANSI-N05.2.3 ANSI-N05.2.6 ANSI-N05.2.11 ANSI-N05.2.10 ANSI-N05.2.9 ANSI-Nff5.2.5 ANSI-N05.2.8 ANSI-N05.2.13 ANSI-N05.2.12 ANSI-N05.2.23 8/11/72 ANSI-N05.2.4 1971 1978 1971 1972 1976 1973 1972 1973 1978 1970 1973 1970 1970 1975 1976 1977 1978

TOPICALQUALITYASSURANCE REPORT APPENDIX C FLORIDA POWER 8 LIGHTCOMPANY BASELINE DOCUMENT MATRIX Rev.

7 Date 3une 10, 1980 Page 3

of 23 Florida Power R Light Company position regarding conflicting guidance and exceptions:

T AR A endix C Clarification ANSI/ANS 3.1 - 1978 (PSL-2)

The Regulatory Guides and industry standards listed in Appendix C to the Topical Quality Assurance Report take precedence over any Regulatory Guide or industry standard which may be referenced in any one of these documents.

Re ulator Guide 1.8 Rev.

1 ANSI N18.1-1971 ANSI/ANS 3.1 (PSL-2)

ANSI N18.1 describes the training and education requirements for plant staff positions and is endorsed by Reg. Guide 1.8 with an exception.

That exception is the requirements for the Supervisor - Radiation Protection.

ANSI N18.1 is invoked by Technical Specifications (Appendix A of the Facility Operating License) at the Turkey Point plants and PSL-1. ANSI/ANS 3.1-1978 is invoked by Technical Specification at PSL-2.

Reg. Guide 1.8 is also invoked by Technical Specifications at our St. Lucie plant and a license amendment has been approved for our Turkey Point plant to specify the Health Physics Supervisor qualifications addressed in Reg. Guide 1.8.

To avoid duplication of requirements, FPL will address Plant Staff Qualifications in only the Technical Specif ications.

Re ulator Guide 1.30 ANSI N05.2.0-1972 ANSI N05.2.0-1972, Paragraph 2.3 addresses installation specifications and requires the inclusion of inspection and'test objectives.

FPL maintains that test values and inspection scope are inherently contained in the applicable procedures.

ANSI N05.2.0-1972, Paragraph 6.1.2 requires that the inspection of installed equipment verify that "good and proper workmanship" has prevailed.

FPL maintains that acceptable parameter compliance with codes and standards along with company preference is the verification of "good and proper workmanship".

FLORIDA POWER 8 LIGHTCOMPANY TOPICALQUALITYASSURANCE REPORT BASELINE DOCUMENT MATRIX APPENDIX C Rev.

7 3une 10, 1980 Page f

of Re ulator Guide 1.33 Rev. 2 ANSI N18.7-1976 FPL's method of addressing Paragraphs 0.0, 5.2.2, 5.2.15 and 5.3 of ANSI 18.7 - 1976 as modified by Regulatory Guide 1.33, Rev. 2 is covered in Section 6 of each individual plant's Technical Specifications.

ANSI N18.7-1976, Section 0.3, requires that personnel performing the independent review and audit be specified in number and technical discipline. This standard is invoked by the Technical Specifications (Appendix A of the Facility Operating Licenses) which have been approved for the FPL nuclear plants at St. Lucie and Turkey Point. Specifically this function is performed by the Company Nuclear Review Board (CNRB) identified in Section 6.5.2 of the Technical Specif ications.

To avoid duplication of requirements, FPL will address the personnel and functions of this independent review and audit only in the Technical Specifications.

FPL's method of addressing Section 5.2 of ANSI N18.7-1976, as modified by Regulatory Guide 1.33, Rev. 2, is by administratively controlling licensed operator hours on shift and by our Duty Call Supervisor system.

Further, FPL has developed a response to NUREG 0650 which provides staffing availability; FPL's method of addressing Paragraph 5.2.8 of ANSI N18.7-1976, as modified by Regulatory Guide 1.33, Rev. 2, is covered in Section 0 of each plant's Technical Specifications.

FPL's method of addressing Paragraph 5.2.9 of ANSI N18.7-1976, as modified by Regulatory Guide 1.33, Rev. 2, is covered in 10 CFR 73 and each plant's Security Plan, and as such is not included in the Quality Assurance Program.

FLORIDA POWER It LIGHTCOMPANY TOPICAL QUALITYASSURANCE REPORT BASELINE DOCUMENT MATRIX APPENDIX C Rev.

7 Date gune 10 Paga 5

of Chemical cleaning is not presently. controlled as a special process per se; however, the requirements of ANSI N05.2.1-1973 and Regulatory Guide 1.37 dated 3/16/73 are part of the FPL QA Program and are met in our program.

FPL proposes these requirements to be an alternative to the requirements of ANSI N18.7-1976, Paragraph 5.2.18.

Further, TQR 9.0, Paragraph 9.2 explains the review of potential special processes and determination of their status as special processes.

FPL meets the intent of Section 5.2.19.3 of ANSI N18.7-1976 as modified by Regulatory Guide 1.33, Rev. 2, as applied to significant changes to operating procedures, by the technical review of the procedure change by knowledgeable plant professionals, by the safety review of the procedure change by the on-site facility review group, by the regulatory and QA review of the procedure by plant Quality Control, by training the licensed operators in the change through the training report system, and by trained, licensed operators using the revised operating procedure and observing the proper result.

In addition, procedure changes will be reviewed to assure 10 CFR 50.59 requirements are met.

Paragraph 5.3.5(0) - Clarification - When FPL uses vendor manuals and drawings which provide adequate instructions for maintenance, these documents are attached or referenced with Plant Work Orders which are reviewed and approved by Supervisory and Quality Control personnel and are considered to be adequate procedures in themselves.

These vendor manuals and drawings, when received at site, are controlled documents and changes to the applicable sections and instructions of these documents require the same level of review and approval as the operating procedures.

Appendix A of Regulatory Guide 1.33 lists "typical safety related activities which should be covered by written procedures".

Regulatory Guide 1.33 is invoked by the Technical Specifications at FPL Nuclear Plants.

In order to avoid duplication of requirements invoked in our licensing documents, the FPL Quality Assurance Program does not list those required operating procedures specified in Appendix A.

FLORIDA POWER 8 LIGHTCOMPANY TOPICAL QUALITYASSURANCE REPORT BASELINE DOCUMENT MATRIX APPENDIX C Rev.

7 oate gune 1P, 19gg Page 6

Of 23 Re ulator Guide 1.37/ANSI N05.2.1-1973 ANSI N05.2.1-1973, Paragraph 5 states in part that, "Fitted and tackwelded joints (which will not be immediately sealed by welding) shall be wrapped with polyethylene or other non-halogenated plastic film until the welds can be completed".

The FPL QA Manual shall require that the weld be covered to prevent entry of moisture and contaminants but willnot specify the material to be employed.

Materials employed to cover openings shall meet the requirements of Regulatory Guide 1.37, Position 0.

ANSI N05.2.1-1973, Paragraph 7.1 states in part, "provisions shall be made to collect leakage and protect insulation from being wetted".

FPL Quality Assurance Program includes the above requirements.

However, FPL's program allows the wetting of metallic type insulations which are not adversely affected by wetting.

ANSI N05.2.1-1973, Paragraphs 7.2.2, 7.2.3, and 7.3 address specific cleaning methods (Alkaline, Chelate, Acid) and make recommendations associated with several types of cleaning methods.

FPL's QA manual does not specifically delineate these paragraphs.

However, the procedure developed per Paragraph 2.2 of ANSI N05.2.1 will ensure that any specific cleaning method chosen willbe properly considered and controlled.

FLORIDA POWER It LIGHTCOMPANY TOPICAL QUALITYASSURANCE REPORT BASELINE DOCUMENT MATRIX APPENDIX C Rev.

7 Date gune 1P, 198'age 7

of 23 Re ulator Guide 1.38 Rev. 2 ANSI N05.2.2-1972 FPL will meet the requirements of Reg. Guide 1.38, Rev. 2, Position 2C, D and E for safety related applications during preoperational and operational activities.

Restrictions imposed for tapes to be color constrasting will only be applied to the extent that these colors are dissimilar or otherwise distinguishable.

This does not preclude using other tapes when precuations are taken to ensure these tapes do not come in contact with austentic stainless steel or nickel alloy materials.

Vapor barrier material (other than metal) shall be colored to contrast with or be otherwise distinguishable from safety related systems to prevent undisclosed entry into the system.

These requirements do not apply to components in storage which would require removal of such tapes and barriers to effect installation.

ANSI N05.2.2-1972 Section 2.7 requires that items governed by this standard be classified into one of four levels by the buyer or the contractor.

FPL intends to consider what care is appropriate for each item individually rather than generically classifying the material into protection levels and providing care required of that level.

The following shall be considered when determining the handling, storage, and shipping requirements:

1.

The vendor's recommended handling, shipping, and storage standards.

2. =- Environmental requirements which may include such requirements as inert gas

~ - atmosphere, humidity limits, temperature limits, chemical requirements, acceleration (g force) requirements.

3.

Special tools or equipment which are provided and controlled as necessary to ensure safe

'nd adequate handling.. These tools or equipment shall be inspected and tested at specified times to verify that they are adequately maintained.

FLORIDA POWER 8 LIGHTCOMPANY TOPICALQUALITYASSURANCE REPORT BASELINE DOCUMENT MATRIX APPENDIX C Rev.

7 3une 10, 1980 Page 8

of 0.

Packaging, covering or coatings required to meet environmental requirements such as barrier and wrap material, desiccants, pipe caps, plugs, contact preservatives, etc.

5.

Container, crating, skids of sufficient strength to support the item (including stacking).

6.

Cushioning, blocking, bracing, and anchoring to prevent movement during shipment or handling.

7.

Special handling or storage procedures for unique situations.

8.

Marking and identification of the item and its packaging.

9.

Anticipated "shelf life"of the item.

FPL considers this to be a more effective approach since the quantity of spare and replacement

material, parts and components governed by this standard will be afforded protection commensurate with the recommendations of Section 2.7 of this standard.

ANSI N05.2.2-1972 Sections 3.0, 0.0, and the Appendix address all the requirements applicable to the packaging and shipping of material.

FPL in general does not package or ship material governed by this standard.

Suppliers of material are required by purchase order'to provide adequate packaging and shipping protection.

Isolated cases of material packaging or shipping are treated on a case-by-case basis and receive protection comparable to that required by the manufacturer of that material.

Loading, rigging and handling precautions identified in Section 0.3 are applied to material unloaded by FPL from a transport vehicle.

ANSI N05.2.2-1972 Section 5.2 requires that specific attributes of material and components received by FPL be inspected.

For plants with operating licenses FPL verifies conformance to procurement documents during receipt inspections.

Any of these attributes identified in these procurement documents are verified during this inspection.

ll O

Po COZ Cb 0V e

O Ja

FLORIDA POWER & LIGHTCOMPANY TOPICAL QUALITYASSURANCE REPORT BASELINE DOCUMENT MATRIX APPENDIX C Rev.

7 Date June 10, 193ff, Page 9

of 23 ANSI N05.2.2-1972 Section 5.2, paragraph 5.2.1, requires certain preliminary inspections to be done "prior to unloading" of material which is received.

We believe that the sequence specified in the standard is to facilitate commercial claims, and should these preliminary inspections occur "after unloading" that control of materials quality would not be degraded.

Accordingly, required shipping damage inspections may be performed after unloading.

The requirements of ANSI N05.2.2, Paragraph 7.2 for items that require special handling instructions is clarified by FPL to be limited to those items covered in the scope of NUREG 0612, entitled "Control of Heavy Loads at Nuclear Power Plants".

ANSI N05.2.2-1972, Paragraph 7.0 requires that an inspection program be established for handling equipment and rigging, including methods for identifying acceptable and nonconforming items.

In lieu of having a program of periodic, documented inspections of rigging and handling equipment, FPL's practice is to have the individual user determine the equipment's acceptability prior to each use.

This prior-to-use inspection is exactly the same as that required during periodic inspections, and uses criteria identified in ANSI N05.2.2-1972, paragraph 7.0.

This practice also precludes the need for a system to indicate the acceptability of rigging and handling equipment.

Implementation of this prior-to-use inspection will be assured through periodic surveillances and audits performed by Quality Assurance and Quality Control.

Cranes are inspected on a periodic basis and willnot be subjected to this prior-to-use inspection.

Certain mechanical components of the PSL-2 nuclear unit have been designed for a service environment of the site area because portions of the plant are exposed to the temperature, humidity, and ocean salt spray during operations.

Extreme air temperature variations, snow or slush are not encountered during operations or in the out-of-doors storage environment.

As an alternative to the rigid requirements of storage levels B and C in paragraph 6.1 of ANSI N05.2.2-1972, FPL proposes to store these particular mechanical components

outdoors, but within controlled areas, with sufficient periodic surveillances and inspections to minimize the possibility of damage or lowering of quality due to corrosion, contamination, deterioration, or physical damage.

In cases where special environmental conditions are present (i.e. hurricanes, paint sprays, concrete pours, etc.) precautions or additional steps will be taken to further protect the items.

TOPICALQUALITYASSURANCE REPORT APPENDIX C Rev.

7 FLORIDA POWER a LIGHTCOMPANY BASELINE DOCUMENT MATRIX oate June 1P, 198th

>>ga 1P Re ulator Guide 1.39 Rev. 2 ANSI N05.2.3-1973 For FPL's operating nuclear plants, alternative methods are followed to achieve equivalent objectives for the below listed sections of ANSI N05.2.3-1973:

The zone designations of Section 2.1 of N05.2.3 and the requirements associated with each zone are not consistent with the FPL Housekeeping requirements at our operating nuclear units.

In lieu of the zone designation, cleanliness is maintained at a level consistent with the work being performed, so as to prevent the entry of foreign material into safety related systems.

Documented cleanliness inspections are performed immediately prior to system closure.

Control of personnel, tools, equipment, and supplies is established with approved procedures when the safety function of a system, component, or item may be jeopardized and also while the reactor system is opened for inspection, maintenance, or repair.

Re ulator Guide 1.58 Revision 1 ANSI N05.2.6-1978 ANSI N05.2.6-1978, Paragraphs 1.1, 3.1, 3.2.2(a) and 0 (Table-1) identify requirements which apply to personnel who perform inspections, tests or nondestructive examinations or who participate in the approval of procedures, the handling of data or test results, or the control of reports and records.

FPL proposes an alternative to capability requirements for those who participate in:

(1) the approval of procedures, (2) the handling of data or test results and (3) the control of reports and records.

FPL accomplishes this by having personnel determined to be qualified and competent by management through consideration of education, training, and experience.

The Florida Power dc Light Company position on the scope of ANSI N45.2.6-1978 is that personnel participating in testing who take data or make observations, where special training is not required to perform this function, need not be qualified in accordance with ANSI N05.2.6 but need only be trained to the extent necessary to perform the assigned function.

C0z Cb Ol E

O U

FLORIDA POWER It LIGHTCOMPANY TOPICAL QUALITYASSURANCE REPORT BASELINEDOCUMENT MATRIX APPENDIX C Rev.

7 Date June 10, 198$

23 For leak testing conducted as part of the preoperational and operational testing programs, FPL considers that the qualification requirements of Regulatory Guide 1.8 (ANSI N18.1-1971) and ANSI N05.2.6-1978, Paragraph 3.0 to be an acceptable alternative to SNT-TC-lA-1975 requirements for leak testing, except for leak testing defined in and performed under Section III of the ASME Code, where in such cases, the Code shall govern.

For preoperational and operational inspection, examination and testing by Quality Control Inspectors, FPL considers that Position C.l of Regulatory Guide 1.58, Revision 1 and ANSI N05.2.6-1978, Paragraph 3.0 are acceptable requirements for training and qualification, except for inspections, tests and examinations defined in and performed under Section III of the ASME Code, where in such cases, the Code shall govern.

For all other preoperational and operational inspection, examination and testing performed by operating plant and support personnel, FPL considers that training and qualification to the requirement of ANSI N18.1-1971 and Regulatory Guide 1.8 are sufficient for the type and scope of activities performed and that qualifications to ANSI N05.2.6-1978 is unnecessary and redundant.

These preoperational and operational inspection, examination tests shall be supervised or directed by personnel qualified to Position C.l of Regulatory Guide 1.58, Revision l.

FPL shall comply with Position C.10 of Regulatory Guide 1.58, Revision 1, effective with Revision 0 of the Topical Quality Assurance Report, in that all new certifications issued for personnel shall meet the education and experience requirements or shall document objective evidence demonstrating that the individual indeed does have comparable or equivalent competence to that which would be gained from having the required education and experience.

FPL's position on ANSI N05.2.6-1978, Paragraph 2.3 is that an initial and periodic review (not to exceed two years) of personnel shall determine the capabilities in his qualified area.

If during this review or at any other time, it is determined that the individual's capabilities are not in accordance with the specified requirements, that individual shall be removed from that activity until the required capability has been demonstrated.

In addition, during this review a

determination shall be made that an individual has been actively involved in the inspection process in his qualified area.

FLORIDA POWER 8 LIGHTCOMPANY TOPICALQUALITYASSURANCE REPORT BASELINE DOCUMENT MATRIX APPENDIX C Rev.

7 June 10, 1980 Pe9e 12 af 23 Re ulator Guide 1.60 Rev. 2 ANSI N05.2.11-1970 FPL's exception to Regulatory Guide position C.2 is as follows:

Design verification shall be performed by technically qualified individual(s) or group(s) other than those who performed the design.

The original designers and verifiers may both be from the design organization.

Design verification by the designer's immediate supervisor shall be limited to those instances where the supervisor is the only qualified individual available within the design organization.

These instances are further restricted to designs where the designs where the supervisor did not specify a singular design approach, or did not restrict design methods or alternatives, or did not specify design inputs (unless the specified design inputs have already been independently verified).

Justification for verification by the designer's immediate supervisor should be documented along with the extent of the supervisor's involvement in the design.

ANSI N05.2.11-1970, Paragraph 11.0 requires that "audits shall include an evaluation of design quality assurance policies, practices, procedures and instructions...."

FPL's design quality assurance (and all other QA elements) policies, procedures and instructions are included in FPL's Quality Assurance Program documentation.

The Quality Assurance Department evaluates all of this documentation in reviews performed during its development and revision. Accordingly, FPL does not require subsequent (and redundant) evaluations of these Quality Assurance Program policies, procedures and instructions during audits.

FPL audits will include evaluations of the adequacy of the practices which are the implementation of these policies, procedures and instructions.

Re ulator Guide 1.68 (11 73)

Regulatory Guide 1.68 (ll/73) entitled "Preoperational and Initial Start-up Test Programs for Water Cooled Power Reactors" is addressed in Section 10.2.1 of the St. Lucie Unit 2 FSAR which states in part, "The start-up test program is developed using the recommendations of Regulatory Guide 1.68".

To avoid duplication of requirements, FPL will address Regulatory Guide 1.68 in the FSAR.

FLORIDA POWER 5 LIGHTCOMPANY TOPICALQUALITYASSURANCE REPORT BASELINE DOCUMENT MATRIX APPENDIX C Rev.

7 3une 10, 1980 Pege 13 0f 23 Re ulator Guide 1.70 ANSI N05.2.10 - 1973 ANSI N05.2.10 -

1973 identifies terms and their definitions important to the uniform understanding of the intent of required quality assurance practices for the construction of nuclear power plants.

Regulatory Guide 1.70 (2-70) endorses these terms and definitions and extends them through the operational phase and includes a clarification of procurement documents.

FPL has developed a glossary of terms and their definitions as part of the Quality Assurance Manual which is being used throughout its nuclear construction and operating plant activities.

The following definitions are currently listed in our glossary and are alternatives or clarifications to those listed in the ANSI Standard and Regulatory Guide:

Assembly A combination of subassemblies or components or both, fitted together to form a workable unit.

Audit A

documented activity performed in accordance with written procedures or checklists to verify, by examination and evaluation of objective evidence, that applicable elements of the quality assurance program have been developed, documented and effectively implemented in accordance with specified requirements.

An audit does not include surveillance or inspection for the purpose of process control or product acceptance.

Guidelines Particular provisions which are considered good practice but which are not mandatory in programs intended to comply with Standards.

1 The term "should" denotes a guideline; the term "shall" denotes a

requirement; and the word "may" denotes permission, neither a

requirement nor a recommendation.

TOPICAL QUALITYASSURANCE REPORT APPENDIX C Rev.

7 FLORIDA POWER 4 LIGHTCOMPANY BASELINE DOCUMENT MATRIX Date gune lo, i98q Page lq Gf Inspector (Owner's or Installer's)

A qualified inspector employed by the Owner or Installer, whose duties include the verification of quality related activities on installations.

Inspection Examination, observation, or measurement to determine the conformance of materials,

supplies, components,
parts, appurtenances,
systems, processes, or structures to predetermined requirements.

Procurement Documents Contractually binding documents, including such documents as contracts, letters of intent, work orders, purchase orders or proposals and their acceptances which authorize the seller to perform services or supply equipment,

material, or facilities on behalf of the purchaser.

Qualification (Personnel)

The characteristics or abilities gained through training or experience or both as measured against established requirements such as standards or tests that qualify an individual to perform a required function.

Quality Assurance All those planned and systematic actions necessary to provide adequate confidence that a.structure, system or component will perform satisfactorily in service.

Quality Assurance includes quality control.

Quality Control Those quality assurance actions related to the physical characteristics or material, structure, component or system, which provide a means to control the quality of the material, structure, component or system to predetermined requirements.

TOPICAL QUALITYASSURANCE REPORT APPENDIX C Rev.

FLORIDA POWER 8 LIGHTCOMPANY BASELINE DOCUMENT MATRIX

>>9e 3une 10, 1980 Storage That period following the release of an item for shipment until turnover for start-up preoperational testing.

This would include in-place storage.

System An integral part of a nuclear power plant comprised of electrical, electronic, or mechanical components (or combinations thereof) that P

may be operated as a separate entity to perform a specific function.

Testing Performance of those steps necessary to determine that systems or components function in accordance with predetermined specif ications.

"Re uirements" Clarification for Glossar A mandatory action, denoted by the word shall.

(See "Guidelines" )

Requirements are generally based on statutes or regulations, but may be internally generated within the company.

"Shall" is therefore used for both

external, legally enforceable actions and internal requirements not enforceable under current NRC practices.

Re ulator Guide 1.88 Rev. 2/ANSI N05.2.9-1970 ANSI N05.2.9-'1970, Section 3.2.5 requires Quality Assurance records be classified as lifetime or non-permanent and further defines lifetime and non-permanent in Section 2.2 of the Standard.

FPL provides the following definitions as an alternative to the above.

Lifetime Records:

Records which are required by the NRC facility operating license, the NRC construction permit, applicable parts of 10CFR, the FSAR, or other NRC commitments to be retained for the life of the plant.

FLORIDA POWER 8 LIGHTCOMPANY TOPICAL QUALITYASSURANCE REPORT BASELINE DOCUMENT MATRIX APPENDIX C Rev.

7 Da<e brune 10 193q Paoe

] 6 G~

23 Non-permanent Records:

Records which are required by the NRC facility operating license, the NRC construction permit, applicable parts of 10CFR, the FSAR, or other NRC commitments to be retained for periods of time less than the life of the plant.

ANSI N45.2.9-1970, requirements for Section 5.6, "Facility", are clarified by FPL as follows:

QA records shall be stored in a manner as to protect contents from possible destruction by causes such as fire, flooding, tornados,

insects, rodents, and from possible deterioration by a combination of extreme variations in temperature and humidity conditions.

A QA Record Storage Evaluation Team (QARSET) shall be responsible for determining methods utilized to assure that QA Records are adequately stored and protected.

The QARSET shall consist of the following:

the Manager of Quality Assurance, the Loss Prevention Engineer, and the Manager of Corporate Record Services, who shall be responsible for maintaining records of evaluations and establishing schedules to assure that reevaluations are performed every two (2) years.

If necessary, the above QARSET Committee may delegate appropriate designees to serve as team members.

As part of their responsibility, the QARSPT shall evaluate the status of existing facilities and the adequacy of additional records facilities prior to the construction of a new facility or the conversion of existing structures.

Preferably, such evaluations should be performed during the design phase.

ANSI N05.2.9-1970 will be utilized in the evaluation of potential record storage facilities.

Section 5.6 "Facilities" is modified as follows and shall be the basis for QARSET approved QA Record Storage Facilities.

1.

A 2-hour vault meeting NFPA No. 232 without additional provisions.

COz Cb Cll e

0 CC 2.

2-hour rated fire resistant file room as defined in NFPA No. 232-1930 if the following additional provision are provided:

FLORIDA POWER 8 LIGHTCOMPANY TOPICAL QUALITYASSURANCE REPORT BASELINE DOCUMENT MATRIX APPENDIX C Rev.

7 oate June 10, 1980 Pa9e 17 Of 23 a.

Early warning fire detection and automatic fire suppression shall be provided, with electronic supervison at a constantly monitored central station.

b.

Records shall be stored in fully enclosed metal cabinets.

Records shall not be permitted on open steel shelving.

No storage or records shall be permitted on the floor of the facility.

Adequate access and aisle space shall be maintained at all times throughout the facility.

c.

Work not directly associated with records storage or retrieval shall be prohibited within the storage facility.

d.

Smoking and eating/drinking shall be prohibited throughout the records storage facility.

e.

Ventilation, temperature, and humidity control equipment shall be provided with approved fire dampers where they penetrate fire barriers.

3.

Other conditions from the above may be approved by the QARSET if in their judgement the condition meets the established level of protection defined above.

There are two acceptable alternatives to the establishment of an approved QA record storage facility:

1.

The maintenance of duplicate QA Records stored in separate locations which are not subject to the same destructive force at the same time.

2.

The use of QARSET approved factory built record protection equipment, such as insulated record containers, fire-resistive safes, and insulated filingdevices.

Where a specially constructed storage room is maintained to store the only copy of QA records, at least the following features should be considered in its construction:

FLORIDA POWER 8 LIGHTCOMPANY TOPICAL QUALITYASSURANCE REPORT BASELINE DOCUMENT MATRIX APPENDIX C Rev.

7 June 10, 1980 Pege 18 Of 23 (1)

Reinforced concrete, concrete block, masonry, or equal construction.

(2)

Concrete floor and roof with sufficient slope for drainage; if a floor drain is provided, a check valve (or equal) shall be included.

(3)

Structure, doors, frames and hardware should be fire-rated with a recommended two hour minimum rating.

(0)

Sealant applied over walls as a moisture or condensation barrier.

(5)

Surface sealant on floor providing a hard-wear surface to minimize concrete dusting.

(6)

Foundation sealant and provision for drainage.

(7)

Forced-air circulation with filter system.

(8)

Adequate fire detection and/or suppression system.

(9)

No pipes other than those providing fire protection to the storage facility are to be located within the facility.

Re ulator Guide 1.116 ANSI N05.2.8-1975 ANSI N05.2.8-1975, Paragraph 2.3 requires that Measuring and Test Equipment (MRTE) used for inspection be identified on the Inspection Report.

FPL may, as an option, employ a MATE issue log which provides traceability between MRTE and the applicable inspections.

CC CO C0Z Cb Icv E

O 4

ANSI N05.2.8-1975, Paragraph 0.6 addresses care of items to the extent that temporary use of equipment or facilities to which the standard applies that are to become part of the completed project may be desirable.

FLORIDA POWER a LIGHTCOMPANY TOPICAL QUALITYASSURANCE REPORT BASELINEDOCUMENT MATRIX APPENDIX C Rev.

7 Date gune 10, 198$

19 0

23 The following clarification applies to the above statement.

For FPL plants in the construction phase (to the point of plant operation license) temporary use of equipment and facilities may be used according to need and/or situation.

In this case, authorization for usage shall be provided along with all the documents, conditions, safeguards and evaluations to verify permanent plant equipment adequacy.

In the operations phase all equipment, including temporary equipment, is subject to identical controls to preclude adverse effects on safety and suitability for use.

Re ulator Guide 1.123 Rev. 1/ANSI N05.2.13-1976 ANSI N05.2.13-1976 Section 1.1 states that the extent to which the individual requirements of this standard willapply willdepend upon the nature and scope of the work to be performed and the required quality of the items or services purchased.

For commercial grade items, FPL has determined that certain aspects of the individual requirements of ANSI N05.2.13'need not apply. Commercial grade items are those (1) not subject to design or specification requirements that are unique to facilities or activities licensed by the NRC, and (2) used in applications other than facilities or activities licensed by the

NRC, and (3) to be ordered from the manufacturer/supplier on the basis of specifications set forth in the manufacturer's published product description.

These commercial items are subject to varying degrees of control as indicated in the FPL Quality Assurance Manual.

As a minimum, an evaluation is performed by qualified personnel to assure that the commercial item satisfies the necessary technical and quality requirements and the item is checked upon receipt to assure that the item received was the one ordered, damage was not sustained during shipment, and documentation, if required, was received.

ANSI N05.2.13-1976 Section 1.3 provides a definition of "procurement document" which is different from the definition contained in ANSI N05.2.10-1973 and Regulatory Guide 1.70.

The Florida Power ItL Light (FPL) Quality Assurance Program uses the definition of "procurement document" contained in ANSI N05.2.10-1973 as modified by Regulatory Guide 1.70.

FLORIDA POWER a LIGHTCOMPANY TOPICAL QUALITYASSURANCE REPORT BASELINE DOCUMENT MATRIX APPENDIX C R ev.

oate gune 10, 198'ge 2O ANSI N05.2.13-1976 Section 3.3.a requires that procurement documents be reviewed prior to release for bid and contract award.

The FPL Quality Assurance Program requires procurement document reviews prior to bid and contract award for all safety related purchases with the exception of these accomplished by "Confirming Purchase Order".

A "Confirming Purchase Order" is an order which is initially placed verbally with the supplier and then later confirmed with a written Purchase Order.

A "Confirming Purchase Order" is only used when time restraints would prohibit the normal review and approval cycle.

The following controls are provided in the FPL Quality Assurance Manual to assure that the intent of ANSI N05.2.13 is satisfied for "Confirming Purchase Orders".

(1)

Quality Assurance must be contacted prior to contacting the supplier to place the order unless it is an emergency purchase after normal working hours in which case Quality Assurance is contacted the next working day.

(2)

Prior to verbally placing the order, it must be verified that the intended supplier is on the FPL Quality Assurance Approved Supplier List.

(3)

The verbally placed order must be promptly followed-up (confirmed) with a written procurement document which is subject to all reviews and approvals required for safety related purchases.

Section 8.2 of ANSI N05.2.13 identifies those nonconformances which shall be submitted to the Purchaser.

Florida Power R Light's (FPL) position regarding the nonconformances to be reported is as follows..Suppliers (including A/E's and Contractors) shall submit all nonconformances which consist of one or more of the following:

CO COz a

04 1) 2)

3)

Technical or material requirements are violated.

Requirement in supplier documents which have been approved by the Purchaser is violated Nonconformances which would affect the quality of the item in regard to function of safety related features.

In cases where the supplier cannot make this determination, they shall be submitted to the Purchaser for evaluation.

FLORIDA POWER & LIGHTCOMPANY TOPICAL QUALITYASSURANCE REPORT BASELINE DOCUMENT MATRIX APPENDIX C Rev.

7 Date brune 10, 198/

Page 21 0~

23 This policy assures that all nonconformances affecting safety related functions willbe reviewed and approved by FPL.

In all cases, the supplier's documentation on nonconformances is available for FPL's review.

Re ulator Guide 1.130 ANSI N05.2.0-1972 ANSI N05.2.0-1972, Paragraph 2.5.2 requires that equipment be "suitably marked to indicate date of next required calibration".

In lieu of marking equipment, FPL has chosen to control calibration of installed instrumentation and control equipment by maintaining records for each piece of equipment by instrument tag number (or equivalent) to show that established schedules and procedures for calibration have been followed.

Re ulator Guide 1.100 Rev. I/ANSI N05.2.12-1977 Regulatoi'y Guide 1.100, Positions C.3 aRb, states in part that applicable elements of an organization's Quality Assurance Program should be audited at least annually or at least once within the life of the activity, whichever is shorter.

ANSI N13.7-1972, Paragraph 0.0 (endorsed by Regulatory Guide 1.33) states in part; "Audits of selected aspects of plant operation shall be performed with a frequency commensurate with their safety significance, and in such a manner as to assure that an audit of safety related activities is completed within a period of two years."

FPL has chosen a two year cycle for auditing elements of the internal and on-site QA Program during the operation phase of plant life following initial fuel loading.

FPL's position is that the two year cycle:

(1) allows more in-depth and meaningful audits in each regularly scheduled area, (2) permits more audits of ongoing activities, and (3) in conjunction with the planning and scheduling requirement of TQR 18.0 provides for a comprehensive audit program.

The audit frequency requirements of Regulatory Guide 1.100 willbe followed during other plants'hases.

FLORIOA POWER 5 LIGHTCOMPANY TOPICAL QUALITYASSURANCE REPORT BASELINE DOCUMENT MATRIX APPENDIX C R ev.

7 Date gune 1O, 198E Page 22 Of 23 In the case of suppliers, an annual evaluation of quality performance history shall be performed to determine reaudit requirements.

Reaudit requirements for suppliers shall be based on the quality performance, and the complexity and criticality of the equipment or service being procured.

ANSI N05.2.12, Paragraph

0.3.1 states

"A brief pre-audit conference shall be conducted at the audit site with cognizant organization management.

The purpose of the conference shall be to confirm the audit scope, present the audit plan, introduce auditors, meet counterparts, discuss audit sequence and plans for the post-audit conference, and establish channels of communication."

FPL willnot require the pre-audit conference for audits of limited scope and of specific site activities conducted by the Construction and Operations Groups.

This conference is omitted because the day-to-day contact of the auditors and plant management, the awareness on the part of plant management that these audits are conducted without pre-audit conferences, and the limited scope of the audits meet the intent of a pre-audit conference.

ANSI Standard N05.2.12-1977, Paragraph 0.5.1 states in part "The audited organization shall provide a follow-up report stating the corrective action taken and the date corrective action was completed".

The FPL QA Program requires the QA Department to followup on all action taken by the audited department.

This is documented on the corrective action followup form by the QA Department and closed by the QA Department instead of the audited department.

This assures that all actions taken by the audited department are verified by the QA Department and that the QA Department concurs with the resolution.

We feel that it is appropriate for this to be documented by the QA Department instead of the audited department.

CO COz Cb CV e

0 4

FLORIDA POWER & LIGHTCOMPANY TOPICAL QUALITYASSURANCE REPORT BASELINE DOCUMENT MATRIX APPENDIX C Rev.

7 aune 10, 193e Page 23 of Plannin Clarification ANSI N05.2.0-1972, Paragraph 2.1; ANSI N05.2.6-1973, Paragraph 2.1; ANSI N05.2.13-1976, Paragraph 7.2; ANSI N18.7-1972, Paragraph 5.1.6.3; ANSI N05.2.8-1975, Paragraph 2.1 and Paragraph 2.2 include plans and/or planning as required.

The terms plan and/or planning are included in FPL's activities as indicated in the following clarification:

Planning is considered to be a management process or analytical tool used as an aid to help develop identification and/or development of program requirements, implementation activities, assignments and staffing, inspections, surveillances and audits, controls and other activities to assure completeness of the requirements.

Planning, as such, is not always documented nor addressed as an end item and is considered to be an integral "process" within the developed item.

Plans which are considered to be end type or output type documents have the term "plan" in the title, such as ISI Master Plan, Audit Plan, Start-up Plan, and others, which as such willreflect directly the requirement of these standards in the appropriate documents.

Plans which are not considered to be end type or output type documents do not have the word plan in the title.

However, certain procedures, instructions, flow charts, schedules and checklists may be considered to be plans reflecting planned actions which especially require step-by-step accomplishments.

In these

cases, the term plan may not appear in the title but considered to be a plan only in the indirect sense and identified as a

procedure or other document.

FPL considers the above practice to be in compliance with the "plan" requirements of these standards.

TOPICALQUALITYASSURANCE REPORT Rev.

APPENDIX D

N/A FLORIDA POWER 8 LIGHTCOMPANY GRAY, GREEN, AND ORANGE BOOK MATRIXTO QA PROCEDURES May 7,1982 Pege 1

Gf

'APPENDIX D "GRAY, GREEN, AND ORANGE BOOK MATRIXTO QA PROCEDURES CANCELLED IN ENTIRETY

TOPICAL QUALITY ASSURANCE REPORT Rev.

APPENDIX E 10 LIST OF CORPORATE QUALITY ASSURANCE PROCEDURE Date May 10, 1998 Page 1

of 11 P NUMBER TITLE SECTION DESCRIPTION 1.1 CANCEILED 2.1 CANCEILED (Terms and Definitions contained in the QA Manual Glossary) 2.2 REVISION OF THE TOPICAL QUALITY ASSURANCE REPORT Provides instructions for the revision of the Florida Power Light Company Topical Quality Assurance. Report (FPL TQAR).

2.3 QUALITY ASSURANCE PROGRAM REVIEW 2.4 PREPARATION AND REVISION OF QUALITY INSTRUCTIONS Describes the instructions and methods used for establishing, preparing,

issuing, revising and controlling Quality Procedures employed in supporting quality requirements.

Provides the responsibilities, guidelines and methods used for developing and revising Quality Instructions, based upon QP's, that involve quality activities within a department or organization and are unique to that activity.

2.5 QUALITY ASSURANCE INDOCTRINATION AND DEPARTMENTAL TRAINING Describes the requirements for the indoctrination and training of personnel who

perform, or are responsible for activities that affect quality.

2.6 CANCELLED

TOPICAL QUALITY ASSURANCE REPORT Rev.

APPENDIX E 10 LIST OF CORPORATE QUALITY ASSURANCE PROCEDURE Date May 10, 1988 Page 2

of 11 P NUMBER TITLE SECTION DESCRIPTION 2.7 IDENTIFICATION OF NUCLEAR SAFETY RELATED AND SAFETY RELATED DESIGN

. FEATURE STRUCTURES, SYSTEMS COMPONENTS AND SERVICES Describes the development and approval of documents identifying safety related and safety related design feature structures, systems and components.

2.8 CLEANLINESS CONTROL METHODS Provides criteria for securing good housekeeping.

Assigns responsi-bilities for assuring that the cleanliness of material, systems and structures is maintained.

2.9 QUALIFICATION OF QA AUDIT, QC INSPECTION AND CONSTRUCTION TEST PERSONNEL Describes the personnel INSPECTION qualifications that are required to assure that competent QC inspectors, QA auditors, and construction test personnel perform these respective functions.

2.10 HOUSEKEEPING OPERATING PLANTS Describes the responsibilities and controls for housekeeping at operat-ing nuclear power plants.

2.11 CANCELLED 2.12 FPL QA PROGRAM APPLICABILITY FPL FOR FIRE PROTECTION SYSTEMS Identifies the applicability of the Quality Assurance Program for Fire Protection Systems.

ID Ol OK C0z Ol OI 0

U.

2.13 PROCESSING OF NRC CORRESPONDENCE Describes the system for providing responses to NRC initiated action requests.

TOPICAL QUALITY ASSURANCE REPORT LIST OF CORPORATE QUALITY ASSURANCE PROCEDURE APPENDIX E Rev.

10 Date May 10, 19BB Page 3

of 11 P NUMBER TITLE SECTION DESCRIPTION 2.14 IMPLEMENTATION OF ASME XI 2.17 ENVIRONMENTAL QUALIFICATION (EQ)

OF ELECTRICAL EQUIPMENT Describes the program and responsibilities for controlling activities defined by ASME Section XI.

Delineates the responsibilities and requirements for maintaining the environmental qualifications of nuclear plant components.

3.1 CANCELLED 3.2 IDENTIFICATION AND CONTROL OF DESIGN INTERFACES Describes measures employed for identifying and controlling design interfaces, changes in design interfaces, and modifications that affect documents.

3.4 PLANT CHANGES AND MODIFICATIONS FOR OPERATING PLANTS Establishes measures for controlling design changes or modifications in operating nuclear power plants.

3.5 DESIGN CONTROL AT THE CONSTRUCTION SITE Defines the responsibilities and methods employed for the initiation, review, evaluation, approval and disposition of field initiated design changes and miscellaneous design documents such as field sketches and isometrics.

3.6 CONTROL OF FPL ORIGINATED DESIGN Covers the preparation,

review, and approval of design input documents, design analysis specifications, and design verification for safety related design work originated by FPL.

TOPICAL QUALITY ASSURANCE REPORT LIST OF CORPORATE QUALITY ASSURANCE PROCEDURE APPENDIX E Rev.

10 Date May 10, 1998 Page 4

of 11 P NUMBER TITLE SECTION DESCRIPTION 3.7 EVALUATION AND CONTROL OF CONTRACTOR DESIGN FOR NUCLEAR FUEL AND RELATED SYSTEMS Describes the evaluation and control of contractor designs for fuel related components and analysis.

F 1 CONTROL OF PROCUREMENT ORIGINATED BY OPERATING PLANT PERSONNEL Provides a system to assure that the appropriate technical and quality requirements are placed upon suppliers who provide materials, equipment, and services for operating nuclear plants as requested by operating plant personnel.

4.2 EVALUATION OF CONTRACTOR'S BIDS TECHNICAL Provides the basic evaluation factors for technical evaluations of contractor's bids to supply

material, equipment, or services to FPL or FPL's Architect/Engineer.

4.3 CANCELLED 4.4 REVIEW OF PROCUREMENT DOCUMENTS FOR ITEMS AND SERVICES OTHER THAN SPARE PARTS Applies to all FPL issued purchase orders and contracts relating to a nuclear power

plant, except those originated by operating plant personnel.

4.5 PROCUREMENT OF SAFETY RELATED AND QUALITY RELATED ELECTRICAL EQUIPMENT Provides a system to assure appropriate technical and quality requirements are placed on suppliers of electrical equipment for nuclear plants.

CV PDK IA C02 Ol s

0 U.

TOPICAL QUALITY ASSURANCE REPORT Rev.

APPENDIX E 10 LIST OF CORPORATE QUALITY ASSURANCE PROCEDURE Date May 10, 1988 Page 5

of 11 SECTION DESCRIPTION 5.1 OPERATING PLANT PROCEDURES Describes measures which ensure that instructions and procedures used in operating plants are identified,

prepared, reviewed,
approved, issued and revised in accordance with regulatory and FPL requirements.

5.2 BACKFIT PROCEDURES Describes the generation, review and control of backfit procedures.

6.1 CONTROL OF CONSTRUCTION PROJECT CONTRACTOR DRAWINGS, SPECIFICATIONS/

AND PROCEDURES Defines responsibilities and methods for the control and issue of contractor drawings, specifications and procedures to be used during the construction phase of nuclear power plants.

6.2 CONTROL OF DOCUMENTS ISSUED BY FLORIDA POWER 6 LIGHT COMPANY Instructions are provided for controlling documents issued by FPL which prescribe activities affecting the quality of safety related items.

6.3 CANCELLED 6,4 CANCELLED 6.5 CANCELLED 6.6 DRAWING CONTROL FOR OPERATING NUCLEAR POWER PLANTS Describes the method to be used for controlling and updating nuclear safety related drawings for operating plants after turnover from the design organization.

TOPICAL QUALITYASSURANCE REPORT Rev.

APPENDIX E 10 LIST OF CORPORATE QUALITY ASSURANCE PROCEDURE May 10, 1988 pege 6

of 11 P NUMBER TITLE SECTION DESCRIPTION 6.7 CONTROL OF VENDOR MANUALS AND VENDOR TECHNICAL INFORMATION 7.1 RECEIPT INSPECTION OF MATERIALS, PARTS AND COMPONENTS FOR OPERATING PLANTS 7.2 CANCELLED 7.3 CANCELLED Establishes requirements for controlling technical manuals for operating, maintenance and test equipment.

Provides instructions for receipt inspection of materials, parts and components which have been obtained for use in nuclear safety applica-tions at the operating plant site.

7.4 EVALUATION OF SUPPLIERS OF SAFETY RELATED ITEMS OR SERVICES 7.5 CANCELLED Provides standards,

measures, and guidelines for the evaluation of QA Programs of contractors or suppliers supplying items or services.

ID EO Ol OL I/I E0Z Cl

~V Ol E

OIL 7.6 ACCEPTANCE OF ITEMS 6 SERVICES 7.8 REVIEW AND DISPOSITION OF SUPPLIER DEVIATION NOTICES Describes the responsibilities and requirements for accepting nuclear saf ety related items or services that are being procured for nuclear power plants.

Describes the responsibilities and requirements for the review and disposition of nonconformances identified within a

supplier's facility which have resulted or will result in an item which does not fully comply with the FPL procurement document quality and technical requirements.

This procedure applies to purchased items which have not yet been shipped.

TOPICAL QUALITYASSURANCE REPORT LIST OF CORPORATE QUALITY ASSURANCE PROCEDURE APPENDIX E Rev.

10 Date May 10, 1988 Page 7

of 11 P NUMBER TITLE SECTION DESCRIPTION 7 '

CONTROL OF ON-SITE VENDOR SERVICES This procedure provides a system to assure that vendors who provide on-site services by contract or purchase order to FPL at nuclear power plants are controlled.

8.1 IDENTIFICATION 6 CONTROL OF MATERIALS, PARTS, COMPONENTS AT THE PLANT SITE Delineates measures for assuring traceability, identification and control of items from the time they are received through usage at operating plants.

8.2 CANCELLED 9.1 CONTROL OF SPECIAL PROCESSES Delineates the responsibilities of organizations and personnel, and the control and documentation of special processes that are applied to safety related items.

9.2 CANCELLED (Combined with 9.1) 9.4 CONTROL OF WELDING FOR NUCLEAR POWER PLANTS Delineates responsibilities and requirements for control FPL welding processes for nuclear power plants.

10. 1 CANCELLED

TOPICAL QUALITYASSURANCE REPORT LIST OP CORPORATE QUALITY ASSURANCE PROCEDURE APPENDIX E Rev.

10 Date May 10, 19BB Page 8

of P NUMBER TITLE SECTION DESCRIPTION 10.2 CANCELLED 10.3 INSPECTION AND SURVEILLANCE 10.4 CANCELLED Delineates responsibilities and requirements for the inspection and surveillance of safety related plant maintenance activities, operation of safety related

systems, and fuel handling activities.

10.5 CANCELLED 10.6 CANCELLED 11.1 CANCELLED (Combined with 11.4) 11.2 CANCELLED (Combined with 11.4) 11.3 CANCELLED (Combined with 11.4)

Ol C

COz Ol Ol E

O U.

11.4 TEST CONTROL Defines the measures for control of proof test prior to installation, construction

tests, preoperational
tests, startup
tests, operational tests and retests following
repairs, replacements or modifi-cations for nuclear safety related
systems, structures, and components.

TOPICAL QUALITY ASSURANCE REPORT LIST OF CORPORATE QUALITY ASSURANCE PROCEDURE APPENDIX E Rev.

May 10, 1988

~e9e 9

<<al P NUMBER TITLE SECTION DESCRIPTION 12.1 CALIBRATION AND CONTROL OF MEASURING AND TEST EQUIPMENT Delineates the responsibilities for implementing the described program for maintenance, calibration and control of measuring and test equipment (MRTE).

12.2 CALIBRATION CONTROL OF INSTALLED PLANT INSTRUMENTATION AND CONTROL EQUIPMENT 13.1 HANDLING, STORAGE AND SHIPPING OF MATERIALS, PARTS AND COMPONENTS 13.2 CANCELLED Describes the calibration program, delineates responsibilities, and establishes procedures for control over the calibration of installed instrumentation and plant control equipment.

Establishes responsibilities and procedures to assure that measures are employed by FPL and contractors to:

(1) control the handling, shipping and storage of material; (2) protect the quality of material by using proper handling, shipping, and storage techniques; (3) effectively control the disposition of discrepant items.

13.3 CONTROL OF RESERVED CENTRALLY STORED ELECTRICAL CABLE Provides the requirements for the issuance and controls of centrally stored electrical cable for use in all operating nuclear power plants.

14.1 INSPECTION, TEST, AND OPERATING DURING PLANT OPERATION Specifies the respective STATUS responsibilities of FPL personnel and the measures employed for identifying the status Inspection-Test-Operation) of plant structures, systems and components.

TOPICAL QUALITY ASSURANCE REPORT Rev.

APPENDIX E 10 LIST OF CORPORATE QUALITY ASSURANCE PROCEDURE Date May 10, 1988 Page 10 of 11 P NUMBER TITLE SECTION DESCRIPTION 14.2 INSPECTION TEST AND OPERATING DURING PLANT CONSTRUCTION 1'5. 1 CANCELLED (Combined with 15.2)

Provides requirements and STATUS responsibilities for the identification of the inspection, test and operating status of plant equipment up to turnover of the plant to the operating organization.

15.2 CONTROL OF NONCONFORMING MATERIALS,

PARTS, COMPONENTS AND SERVICES Defines the objectives and PARTS OR responsibilities for controlling nonconforming items or services in order to,prevent their inadvertent use, installation or application to operating nuclear power plants.

16.1 CORRECTIVE ACTION 16.2 CANCELLED (Combined with 16.1)

Establishes the respective responsibilities of FPL personnel and the procedure for assuring that conditions identified by the FPL QA Department as being adverse to quality, are corrected.

16.3 CANCELLED (Combined with 16.1) lO CV D

C0z Ol Ol 0IL 16.4 EVALUATING AND REPORTING OF NONCOMPLIANCES FOR SUBSTANTIAL SAFETY HAZARDS IN ACCORDANCE WITH 10 CFR PART 21 Specifies the measures and DEFECTS 6

responsibilities within Florida Power G Light to assure compliance to 10 CFR Part 21.

TOPICAL QUALITY ASSURANCE REPORT APPENDIX E Rev.

10 LIST OF CORPORATE QUALITY ASSURANCE'ROCEDURE May 10, 1988 Page 11 of P NUMBER TITLE SECTION DESCRIPTION 16 '

CANCELLED 17.1 THE COLLECTION AND STORAGE OF QUALITY ASSURANCE RECORDS FOR NUCLEAR POWER PLANTS 18.1 CONDUCT OF QUALITY ASSURANCE AUDITS Identifies records and documents required to substantiate quality; and, describes measures employed for their maintenance, retention and retrieval.

Provides instructions for conducting audits of FPL Quality Assurance Program activities.

18.2 CANCELLED 18.3 CANCELLED 18.4 CANCELLED

FLORIDA POWER 8 LIGHTCOMPANY TOPICAL QUALITYASSURANCE REPORT TOPICS TO BE ADDRESSED IN SAFETY ANALYSISREPORTS APPENDIX F Rev.

1 Date May 7, 1982 Page 1

Gfi The FPL Topical Quality Assurance Report is the statement of Florida Power Itt: Light Company Quality Assurance Program Requirements which do not vary with plant site.

These stated requirements form a description of the FPL Quality Assurance Program which does not contain identification of the involvement of principal contractors such as the Architect/Engineer, Nuclear Steam Supply System vendor, or Constructor.

The contractor involvement in the Program will be described in the plant Safety Analysis Report.

In addition, other detailed aspects of the Quality Assurance Program vary from plant-to-plant or with plant site.

These aspects will also be described in the plant SAR.

The requirements of the FPL Quality Assurance Program shall apply to the nuclear safety related structures, systems and components as defined in the applicable plant SAR.