Forwards Insp Repts 50-250/88-08 & 50-251/88-08 on 880325-0425.Violation Not Cited Because All Criteria for Categorization of licensee-identified Violations Met
ML17345A219
Person / Time
Site: Turkey Point  
Issue date: 05/25/1988
From: Wilson B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Conway W
FLORIDA POWER & LIGHT CO.
Shared Package
ML17345A220 List:
References
NUDOCS 8806070291
Download: ML17345A219 (3)


See also: IR 05000250/1988008

Text

MAY Z 5

1S&8

Docket Nos.

50-250,

50-251

License

Nos.

DPR-31,

DPR-41

Florida Power

and Light Company

ATTN:

Mr.

W.

F.

Conway

Senior Vice President

- Nuclear

Nuclear Energy Department

P. 0.

Box 14000

Juno

Beach,

FL

33408-0420

Gentlemen:

SUBJECT:

NRC

INSPECTION

REPORT

NOS. 50-250/88-08

and 50-251/88-08

This refers

to the Nuclear Regulatory

Commission

(NRC) inspection

conducted

by

D. R. Brewer on March 25,

1988 through April 25,

1988.

The inspection

included

a review of activities

authorized

for your Turkey Point facility.

At the

conclusion of the inspection,

the findings were discussed

with those

members of

your staff identified in the enclosed

inspection report.

Areas

examined

during the inspection

are identified in the report.

Within

these

areas,

the inspection

consisted

of selected

examinations

of procedures

and

representative

records,

interviews with personnel,

and

observation

of

activities in progress.

The inspection

findings indicate that certain activities

appeared

to violate

NRC requirements.

However,

because

all of the criteria for categorization

of

licensee-identified

violations were met, the violation is not being cited.

The

details

pertaining

to the licensee-identified

violation are described

in the

enclosed

Inspection Report.

In accordance

with Section

2.790 of the

NRC's

"Rules of Practice,"

Part 2,

Title 10,

Code of Federal

Regulations,

a copy of this letter and its enclosure

will be placed in the

NRC Public Document

Room.

The responses

directed

by this letter and its enclosures

are not subject to the

clearance

procedures

of the Office of Management

and Budget

as required

by the

Paperwork Reduction Act of 1980,

PL 96-511.

Should you have

any questions

concerning this letter,

please

contact us.

Sincerely,

Original signed

by

R.

V. Crlenjak (for)

Bruce A. Wilson, Chief

Reactor Projects

Branch

2

Division of Reactor Projects

Enclosure:

(See

page

2)

8806070291

880525

PDR

ADQCK 05000250

O

DCD

Florida Power

and Light Company

MAY 2 5

1988

Enclosure:

NRC Inspection

Report

cc w/encl:

J.

ST

Odom, Vice President

Turkey Point Nuclear Plant

J. Cross,

Plant Manager

Turkey Point Nuclear Plant

L. W. Bladow, Plant equality Assurance

Superintendent

J. Arias, Jr., Regulatory

and Compliance

Supervisor

bcc w/encl:

G.

E. Edison, Project Manager,

Project

Directorate II-2, Division of Reactor

Projects,

NRR

NRC Resident

Inspector

DRS Technical Assistant

Document Control

Desk

~I

CChristensen:lb

05/W/88

J rlenjak

05/z)/88