PNP 2017-070, NRC Confirmatory Order, EA-15-039
ML17341A039 | |
Person / Time | |
---|---|
Site: | Palisades |
Issue date: | 12/07/2017 |
From: | Hardy J Entergy Nuclear Operations |
To: | Louden P Document Control Desk, Office of Nuclear Reactor Regulation, NRC/RGN-III |
References | |
EA-15-039, PNP 2017-070 | |
Download: ML17341A039 (1) | |
Similar Documents at Palisades | |
---|---|
Category:Confirmatory Order
MONTHYEARCNRO-2018-00051, Grand Gulf Nuclear Station, Palisades Nuclear Plant, River Bend Station, Pilgrim Nuclear Station and Waterford 3 - Entergy Response to Confirmatory Order EA-17-132/EA-17-153, Element K2018-12-28028 December 2018
[Table view]Grand Gulf Nuclear Station, Palisades Nuclear Plant, River Bend Station, Pilgrim Nuclear Station and Waterford 3 - Entergy Response to Confirmatory Order EA-17-132/EA-17-153, Element K PNP 2017-070, NRC Confirmatory Order, EA-15-0392017-12-0707 December 2017 NRC Confirmatory Order, EA-15-039 IR 05000255/20150132016-05-16016 May 2016 EA-15-039, Palisades, Confirmatory Order Related to NRC Report No. 05000255/2015013; and Investigation Report 3-2012-021; Palisades Nuclear Plant ML16021A2232016-01-21021 January 2016 Entergy One-Year Status Notification in Response to Confirmatory Order, EA-14-013 IR 05000333/20110092012-01-26026 January 2012 EA-10-090, EA10-248, EA-11-106 Fitzpatrick/Entergy - Confirmatory Order (Effective Immediately) and Notice of Violation, Investigation Report Nos. 1-2009-041, 1-2010-019 and 1-2010-031, Inspection Repot No. 05000333-11-009 ML12026A3832012-01-25025 January 2012 EA-11-214, Palisades, Confirmatory Order ML11224A2552011-08-24024 August 2011 Confirmatory Order Modifying Licenses (Effective Immediately) ENOC-10-00015, Response to NRC Confirmatory Order EA-09-060 from Entergy Nuclear Operations, Inc2010-04-22022 April 2010 Response to NRC Confirmatory Order EA-09-060 from Entergy Nuclear Operations, Inc ML0931303612009-11-10010 November 2009 EA-09-060 Federal Register Notice Confirmatory Order (Effective Immediately) (Palisades Nuclear Plant) NRC-2009-0505, EA-09-060 Federal Register Notice Confirmatory Order (Effective Immediately) (Palisades Nuclear Plant)2009-11-10010 November 2009 EA-09-060 Federal Register Notice Confirmatory Order (Effective Immediately) (Palisades Nuclear Plant) ML0636303362007-01-0303 January 2007 Nuclear Management Company, LLC Ltr. Douglas E. Cooper Confirmatory Order (Effective Immediately) 2018-12-28 Category:Letter type:PNP MONTHYEARPNP 2023-030, License Amendment Request to Revise Renewed Facility Operating License and Permanently Defueled Technical Specifications to Support Resumption of Power Operations2023-12-14014 December 2023
[Table view]License Amendment Request to Revise Renewed Facility Operating License and Permanently Defueled Technical Specifications to Support Resumption of Power Operations PNP 2023-035, Withdrawal of License Amendment Request - Revise License Condition to Eliminate Cyber Security Plan Requirements2023-12-12012 December 2023 Withdrawal of License Amendment Request - Revise License Condition to Eliminate Cyber Security Plan Requirements PNP 2023-028, Application for Order Consenting to Transfer of Control of License and Approving Conforming License Amendments2023-12-0606 December 2023 Application for Order Consenting to Transfer of Control of License and Approving Conforming License Amendments PNP 2023-026, Pre-Submittal Meeting Presentation - Palisades Nuclear Plant License Transfer Application to Support Resumption of Power Operations2023-09-28028 September 2023 Pre-Submittal Meeting Presentation - Palisades Nuclear Plant License Transfer Application to Support Resumption of Power Operations PNP 2023-025, Request for Exemption from Certain Termination of License Requirements of 10 CFR 50.822023-09-28028 September 2023 Request for Exemption from Certain Termination of License Requirements of 10 CFR 50.82 PNP 2023-023, Special Report High Range Noble Gas Monitor Inoperable2023-08-0909 August 2023 Special Report High Range Noble Gas Monitor Inoperable PNP 2023-018, 2022 Annual Non-Radiological Environmental Operating Report2023-04-25025 April 2023 2022 Annual Non-Radiological Environmental Operating Report PNP 2023-007, and Big Rock Point, 2022 Annual Radioactive Effluent Release and Waste Disposal Reports2023-04-19019 April 2023 and Big Rock Point, 2022 Annual Radioactive Effluent Release and Waste Disposal Reports PNP 2023-008, 2022 Radiological Environmental Operating Report2023-04-18018 April 2023 2022 Radiological Environmental Operating Report PNP 2023-002, 6 to Updated Final Safety Analysis Report2023-03-31031 March 2023 6 to Updated Final Safety Analysis Report PNP 2023-006, Report of Changes to Security Plan, Revision 202023-03-29029 March 2023 Report of Changes to Security Plan, Revision 20 PNP 2023-012, Presentation on Regulatory Path to Reauthorize Power Operations2023-03-16016 March 2023 Presentation on Regulatory Path to Reauthorize Power Operations PNP 2023-001, Regulatory Path to Reauthorize Power Operations2023-03-13013 March 2023 Regulatory Path to Reauthorize Power Operations PNP 2023-004, Report of Changes to Palisades Nuclear Plant Technical Specification Bases2023-03-0808 March 2023 Report of Changes to Palisades Nuclear Plant Technical Specification Bases PNP 2023-005, Response to Palisades Nuclear Plant - Request for Additional Information Related to the Post-Shutdown Decommissioning Activities Report2023-03-0101 March 2023 Response to Palisades Nuclear Plant - Request for Additional Information Related to the Post-Shutdown Decommissioning Activities Report PNP 2022-037, Report of Changes to Security Plan, Revision 192022-12-14014 December 2022 Report of Changes to Security Plan, Revision 19 PNP 2022-036, Response to Request for Additional Information Regarding License Amendment Request for Proposed Permanently Defueled Emergency Plan and Permanently Defueled Emergency Action Level Scheme2022-11-0808 November 2022 Response to Request for Additional Information Regarding License Amendment Request for Proposed Permanently Defueled Emergency Plan and Permanently Defueled Emergency Action Level Scheme PNP 2022-035, International - Notification of Commitment Cancellations for Remaining Activities Related to Beyond-Design-Basis Seismic Hazard Reevaluations2022-11-0202 November 2022 International - Notification of Commitment Cancellations for Remaining Activities Related to Beyond-Design-Basis Seismic Hazard Reevaluations PNP 2022-026, Request for Exemption from 10 CFR 50.54(w)(1) Concerning Onsite Property Damage Insurance2022-10-26026 October 2022 Request for Exemption from 10 CFR 50.54(w)(1) Concerning Onsite Property Damage Insurance PNP 2022-024, Request for Exemption from 10 CFR 140.11(a)(4) Concerning Primary and Secondary Liability Insurance2022-10-26026 October 2022 Request for Exemption from 10 CFR 140.11(a)(4) Concerning Primary and Secondary Liability Insurance PNP 2022-031, License Amendment Request, Revise License Condition to Eliminate Cyber Security Plan Requirements2022-09-14014 September 2022 License Amendment Request, Revise License Condition to Eliminate Cyber Security Plan Requirements PNP 2022-025, Report of Changes to Palisades Nuclear Plant Security Plan, Revision 182022-09-12012 September 2022 Report of Changes to Palisades Nuclear Plant Security Plan, Revision 18 PNP 2022-032, 2022 Evacuation Time Estimate Report2022-09-0707 September 2022 2022 Evacuation Time Estimate Report PNP 2022-023, Report of Changes to Palisades Nuclear Plant Security Plan, Revision 172022-08-15015 August 2022 Report of Changes to Palisades Nuclear Plant Security Plan, Revision 17 PNP 2022-014, Report of Changes to Palisades Nuclear Plant Site Emergency Plan, Revision 342022-07-13013 July 2022 Report of Changes to Palisades Nuclear Plant Site Emergency Plan, Revision 34 PNP 2022-016, License Amendment Request: Proposed Permanently Defueled Emergency Plan and Permanently Defueled Emergency Action Level Scheme2022-07-12012 July 2022 License Amendment Request: Proposed Permanently Defueled Emergency Plan and Permanently Defueled Emergency Action Level Scheme PNP 2022-017, Request for Exemptions from Certain Emergency Planning Requirements of 10 CFR 50.47(b); 10 CFR 50.47(c)(2); and 10 CFR Part 50, Appendix E2022-07-11011 July 2022 Request for Exemptions from Certain Emergency Planning Requirements of 10 CFR 50.47(b); 10 CFR 50.47(c)(2); and 10 CFR Part 50, Appendix E PNP 2022-019, & Big Rock Point - Notification of Expected Date of Transfer of Ownership of Nuclear Plants to Holtec Palisades, LLC; and Notification of Receipt of All Required Regulatory Approvals2022-06-24024 June 2022 & Big Rock Point - Notification of Expected Date of Transfer of Ownership of Nuclear Plants to Holtec Palisades, LLC; and Notification of Receipt of All Required Regulatory Approvals PNP 2022-011, Termination of the Emergency Response Data System (Eros) Link2022-06-13013 June 2022 Termination of the Emergency Response Data System (Eros) Link PNP 2022-010, Certifications of Permanent Cessation of Power Operations and Permanent Removal of Fuel from the Reactor Vessel2022-06-13013 June 2022 Certifications of Permanent Cessation of Power Operations and Permanent Removal of Fuel from the Reactor Vessel PNP 2022-004, 2021 Radiological Environmental Operating Report2022-05-12012 May 2022 2021 Radiological Environmental Operating Report PNP 2022-003, and Big Pock Point Plant - 2021 Annual Radioactive Effluent Release and Waste Disposal Report2022-04-25025 April 2022 and Big Pock Point Plant - 2021 Annual Radioactive Effluent Release and Waste Disposal Report PNP 2022-007, 2021 Annual Non-Radiological Environmental Operating Report2022-04-21021 April 2022 2021 Annual Non-Radiological Environmental Operating Report PNP 2022-012, Response to Request for Additional Information Regarding License Amendment Request to Revise Facility Operating License and Technical Specifications for a Permanently Defueled Condition2022-04-21021 April 2022 Response to Request for Additional Information Regarding License Amendment Request to Revise Facility Operating License and Technical Specifications for a Permanently Defueled Condition PNP 2022-002, Annual Report of Changes in Emergency Core Cooling System Models2022-03-24024 March 2022 Annual Report of Changes in Emergency Core Cooling System Models PNP 2021-012, Report of Changes, Tests and Experiments, and Summary of Commitment Changes2021-10-0707 October 2021 Report of Changes, Tests and Experiments, and Summary of Commitment Changes PNP 2021-029, Pre-Notice of Disbursement from Decommissioning Trust2021-09-0202 September 2021 Pre-Notice of Disbursement from Decommissioning Trust PNP 2021-013, Request for Rescission of Interim Compensatory Measure from Order EA-02-0262021-07-21021 July 2021 Request for Rescission of Interim Compensatory Measure from Order EA-02-026 PNP 2021-020, Request for Partial Exemption from Record Retention Requirements in 10 CFR 50.122021-06-15015 June 2021 Request for Partial Exemption from Record Retention Requirements in 10 CFR 50.12 PNP 2021-005, License Amendment Request to Revise Renewed Facility Operating License and Technical Specifications for Permanently Defueled Condition2021-06-0101 June 2021 License Amendment Request to Revise Renewed Facility Operating License and Technical Specifications for Permanently Defueled Condition PNP 2021-026, Pre-Notice of Disbursement from Decommissioning Trust2021-05-27027 May 2021 Pre-Notice of Disbursement from Decommissioning Trust PNP 2021-016, 2020 Radiological Environmental Operating Report2021-05-12012 May 2021 2020 Radiological Environmental Operating Report PNP 2021-022, 2020 Annual Non-Radiological Environmental Operating Report2021-04-27027 April 2021 2020 Annual Non-Radiological Environmental Operating Report PNP 2021-015, and Big Rock Point, Submittal of 2020 Annual Radioactive Effluent Release and Waste Disposal Report2021-04-21021 April 2021 and Big Rock Point, Submittal of 2020 Annual Radioactive Effluent Release and Waste Disposal Report PNP 2021-017, Schedule Change to Open Phase Condition Detection Implementation2021-04-0101 April 2021 Schedule Change to Open Phase Condition Detection Implementation PNP 2021-003, 2020 Steam Generator Tube Inspection Report2021-03-25025 March 2021 2020 Steam Generator Tube Inspection Report PNP 2021-010, Annual Report of Changes in Emergency Core Cooling System Models2021-03-19019 March 2021 Annual Report of Changes in Emergency Core Cooling System Models PNP 2021-004, Report - Changes to Palisades Nuclear Plant Technical Specifications Bases2021-03-10010 March 2021 Report - Changes to Palisades Nuclear Plant Technical Specifications Bases PNP 2021-006, Pre-Notice of Disbursement from Decommissioning Trust2021-03-0808 March 2021 Pre-Notice of Disbursement from Decommissioning Trust PNP 2021-001, ASME Section XI 90-Day Owner'S Activity Report2021-01-12012 January 2021 ASME Section XI 90-Day Owner'S Activity Report 2023-09-28 |
Text
~Entergy Entergy Nuclear Operations, Inc.
Palisades Nuclear Plant 27780 Blue Star Memorial Highway Covert, MI 49043 Tel 269 764 2000 Jeffery A. Hardy Regulatory Assurance Manager PNP 2017-070 December 07,2017 Mr. Patrick Louden U. S. Nuclear Regulatory Commission Division of Reactor Projects, Region III 2443 Warrenville Road Lisle, IL 60532
Subject:
NRC Confirmatory Order, EA-15-039 Palisades Nuclear Plant Docket 50-255 License No. DPR-20
Reference:
Letter from Nuclear Regulatory Commission to Entergy Nuclear Operations, Inc.,
"Confirmatory Order Related to NRC Report No. 05000255/2015013; and Investigation Report 3-2012-021; Palisades Nuclear Plant," dated May 16, 2016.
Dear Mr. Louden:
In accordance with the subject Confirmatory Order, Entergy Nuclear Operations, Inc. (ENO) developed a case study addressing lessons learned from the event. The case study was provided in training sessions to site personnel identified in the order. The Oversight Subcommittee of ENO's Safety Review Committee (SRC) developed a report that detailed the effectiveness of the training. The report was provided to ENO's Chief Nuclear Officer.
Pursuant to Section V, Item 1c, of the Confirmatory Order, this letter provides notification that the SRC's Oversight Subcommittee report is available for NRC inspection.
This letter contains no new commitments and no revisions to existing commitments.
JAH/tad cc: Document Control Desk, USNRC Project Manager, Palisades, USNRC Resident Inspector, Palisades, USNRC