Responds to NRC Re Violation Noted in IE Insp Repts 50-250/79-41 & 50-251/79-41.Corrective Actions:Charts Listed in Findings Stamped & Labeled Per Administrative Procedure 103.2
ML17339A990
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 03/03/1980
From: Robert E. Uhrig
FLORIDA POWER & LIGHT CO.
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
Shared Package
ML17339A989 List:
References
L-80-69, NUDOCS 8005050220
Download: ML17339A990 (4)


Text

85050 2.>+ p I

FLORIDA POWER 5 LIGHTCOMPANY March 3, 1980 L-80-69 Mr. James P. O'Reilly, Director, Region II Office of Inspection and Enforcement U.S. Nuclear Regulatory Commission 101 Marietta Street, Suite 3100 Atlanta, Georgia 30303

Dear Mr. O'Reilly:

RE:

RII:

RVL 50-250/79-41 50-251/79-41 Florida Power

& Light Company has reviewed the subject inspection report and a response is attached.

There is no proprietary information in the report.

Very truly yours, Robert E. Uhrig Vice President Advanced Systems 6 Technology REU/MAS/pa, Attachment I

cc:

Harold Reis, Esquire

.0 g~wpIQ~ QQPV+~

PEOPLE... SERVING PEOPLE

ATTACHMENT RE:

RII:RVL 50-250/79-41 50-251/79-41

~F1ndin As required by Technical Specification 6.8.1, written procedures and ad-ministrative policies shall be implemented.

Paragraph 8.4.6.1.1 of Ad-ministrative Procedure 0103.2 requires that all recorder charts be stamped with the date and identification.

Contrary to the above, recorder charts

454, 455, 456 associated with the steam generator parameters gathered during and subsequent to the 1:37 a.m.

Unit 4 reactor trip on December 19, 1979, were neither stamped or labeled with any identification or dates.

As corrective action, the charts listed in the finding have been stamped and labeled as required by Administrative Procedure 0103.2.

In order to prevent recurrence, discussions were held with the appropriate Nuclear Match Engineer and Nuclear Supervisor on the importance of full compliance with Administrative Procedure 0103.2.

Compliance was achieved on February 19, 1980.

~