October 6, 1998 Mr. Robert P. Powers, Senior Vice President Indiana Michigan Power Company Nuclear Generation Group 500 Circle Drive Buchanan, Ml 49107
SUBJECT:
DONALDC. COOK NUCLEAR PLANT, UNITS 1 AND 2 - WITHDRAWALOF AN AMENDMENTREQUEST TO INCREASE UNIT 2 THERMALPOWER AND ASSOCIATED TECHNICALSPECIFICATIONS FOR UNIT 1 (TAC NOS. M96363 AND M96364)
Dear Mr. Powers:
By letter dated July 11, 1996, you applied for an amendment to the Donald C. Cook Nuclear Power Plant Units 1 and 2 Facility Operating License Nos. DPR-58 and DPR-74. The proposed change would have modified the'facility technical specifications pertaining to a thermal power increase for Unit 2 and other associated changes for Unit 1. Subsequently, by letter dated September 22, 1998, you requested the NRC to suspend its review, and withdrew the amendment.
We willconsider the application to be withdrawn and close this action.
Sincerely, Docket Nos. 50-315 and 50-316 cc: See next page Origina1 signed by:
John F. Stang, Senior Project Manager Project Directorate III-3 Division of Reactor Projects - III/IV Office of Nuclear Reactor Regulation
~Dtstribu to
.'Docket-FileQ OGC PUBLIC J. Stang (2)
PDIII-3 Reading EGA1 G. Grant, Rill R. Bellamy DOCUMENT NA To receive a copy of this d (DCCOOK(uprate.wi e
. Indicate in the box:
C Copy without attachment/enclosure E" ~ Copy with attachment/encIosure N
~ No copy OFFICE P:P E
LA PD33 E
(A)PD: PD33 NAME JS DATE
~/
EBarnhill 98 OFFICIAL REC RD COPY RBellamy
/98
'ti8iOi302iQ 'II8iOOb PDR ADOCK 050003i5 P
~
~
October 6, 1998 Mr. Robert P. Powers, Senior Vice President Indiana Michigan Power Company Nuclear Generation Group 500 Circle Drive Buchanan, Ml 49107
SUBJECT:
DONALDC. COOK NUCLEAR PLANT, UNITS 1 AND2-WITHDRAWALOF AN AMENDMENTREQUEST TO INCREASE UNIT2 THERMALPOWER AND ASSOCIATED TECHNICALSPECIFICATIONS FOR UNIT 1 (TAC NOS. M96363 AND M96364)
Dear Mr. Powers:
By letter dated July 11, 1996, you applied for an amendment to the Donald C. Cook Nuclear Power Plant Units 1 and 2 Facility Operating License Nos. DPR-58 and DPR-74. The proposed change would have modified the facilitytechnical specifications pertaining to a thermal power increase for Unit 2 and other associated changes for Unit 1. Subsequently, by letter dated September 22, 1998, you requested the NRC to suspend its review, and withdrew the amendment.
We willconsider the application to be withdrawn and close this action.
Sincerely, Docket Nos. 50-315 and 50-316 cc: See next page
~ifjrf~~i Original signed by:
John F. Stang, Senior Project Manager Project Directorate III-3 Division of Reactor Projects - III/IV Office of Nuclear Reactor Regulation Docket File OGC PUBLIC J. Stang (2)
PDIII-3 Reading EGA1 G. Grant, Rill R. Bellamy DOCUMENT NAg G:t~DCCOOK)uprate.wi To receive s copy of this dbc err', Indicate In the botu "C" ~ Copy without attachment/enclosure "E
~ Copy with sttschment/enclosure N
~ No copy OFFICE P:P LA:PD33 E
(A)PD: PD33 NAME DATE JS ri'i/'8 EBarnhill 98 OFFICIAL REC RD COPY RBellamy
/98
gP,8 RE00 v +
Cy gO
++*++
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, O.C. 2055&4001 October 6, 1998 Mr. Robert P. Powers, Senior Vice President Indiana Michigan Power Company Nuclear Generation Group 500 Circle Drive Buchanan, Ml 49107
SUBJECT:
DONALDC. COOK NUCLEAR PLANT, UNITS 1 AND 2 - WITHDRAWALOF AN AMENDMENTREQUEST TO INCREASE UNIT.2 THERMALPOWER AND ASSOCIATED TECHNICALSPECIFICATIONS FOR UNIT 1 (TAC NOS. M96363 AND M96364)
Dear Mr. Powers:
By letter dated July 11, 1996, you applied for an amendment to the Donald C. Cook Nuclear Power Plant Units 1 and 2 Facility Operating License Nos. DPR-58 and DPR-74. The proposed change would have modified the facilitytechnical specifications pertaining to a thermal power increase for Unit 2 and other associated changes for Unit 1. Subsequently, by letter dated September 22, 1998, you requested the NRC to suspend its review, and withdrew the amendment.
We willconsider the application to be withdrawn and close this action.
Sincerely, Docket Nos. 50-315 and 50-316 cc: See next page ohn F. Stang, Sen g Project Manager Project Directorate III-3 Division of Reactor Projects - III/IV Office of Nuclear Reactor Regulation
a v
Robert P. Powers Indiana Michigan Power Company e
CC:
Donald C. Cook Nuclear Plant Units 1 and 2 Regional Administrator, Region III U.S. Nuclear Regulatory Commission 801 Warrenville Road Lisle, IL 60532-4351 Attorney General Department of Attorney General 525 West Ottawa Street Lansing, Ml 48913 Township Supervisor Lake Township Hall P.O. Box 818 Bridgman, Ml 49106 U.S. Nuclear Regulatory Commission Resident Inspector's Office 7700 Red Arrow Highway Stevensville, Ml 49127 Jeremy J. Euto, Esquire 500 Circle Drive Buchanan, MI 49107 Mayor, City of Bridgman P.O. Box 366 Bridgman, MI 49106 Special Assistant to the Governor Room 1 - State Capitol Lansing, Ml 48909 Drinking Water and Radiological Protection Division Michigan Department of Environmental Quality 3423 N. Martin Luther King Jr Blvd P.O. Box 30630 CPH Mailroom Lansing, Ml 48909-8130 Jeb Kingseed Indiana Michigan Power Company Nuclear Generation Group 500 Circle Drive Buchanan, MI 49107 David A. Lochbaum Union of Concerned Scientists 1616 P Street NW, Suite 310 Washington, DC 20036-1495
0 pA
~
~
~
~
y p
V li