ML17334B724

From kanterella
Jump to navigation Jump to search
Insp Repts 50-315/98-05 & 50-316/98-05 on 980121-0227 & 0319.Violations Noted.Major Areas Inspected:Maint & Engineering
ML17334B724
Person / Time
Site: Cook  American Electric Power icon.png
Issue date: 04/10/1998
From: James Gavula
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML17334B723 List:
References
50-315-98-05, 50-315-98-5, 50-316-98-05, 50-316-98-5, NUDOCS 9804170065
Download: ML17334B724 (72)


See also: IR 05000315/1998005

Text

U.S. NUCLEAR REGULATORYCOMMISSION

REGION III

Docket Nos:

License Nos:

50-315; 50-316

DPR-58; DPR-74

Report Nos:

50-315/98005(DRS); 50-316/98005(DRS)

Licensee:

Indiana Michigan Power Company

Facility:

Donald C. Cook Nuclear Generating Plant

Location:

1 Cook Place

Bridgman, Ml 49106

Dates:

January 21 through February 27 and March 19, 1998.

Inspectors:

B. Bartlett, Senior Resident Inspector, D. C. Cook

D. Jones, Reactor Engineer

M. Hoimberg, Reactor Engineer

Approved by:

J. A. Gavula, Chief

Engineering Specialists Branch

1

Division of Reactor Safety

9804i70065 9804i0

PDR

ADQCK 050003i5

6

PDR

i

EXECUTIVE SUMMARY

D. C. Cook, Units 1 and 2

NRC Inspection Reports 50-315/98005; 50-316/98005

This nonroutine inspection focused on the conduct of past surveillance testing, corrective

actions and maintenance of the design basis for the ice condenser

in each Unit. The following

specific observations were made:

MairaMe~nn p

~

Eight apparent violations of 10 CFR 50 Appendix B (three Criterion V, four Criterion XI,

and one Criterion Vll)and two violations of technical specifications (TS) were identified

pertaining to inadequate surveillance testing of the ice condenser.

Specifically, these

. violations pertained to inadequate instructions, inadequate acceptance

limits,

inadequate control of contractors, failure to implement TS requirements and entry into

an unanalyzed condition for ice condenser surveillance testing.

(Section M1.1)

~

Two examples of an apparent violation of 10 CFR 50 Appendix B, Criterion V were

identified for the licensee's failure to followthe procedure change process for changes

made to completed surveillance tests.

(Section M1.1)

~

Collectively, the apparent violations associated

with surveillance testing activities

represented

a breakdown in the surveillance testing program for the ice condenser.

(Section M1.1)

~

Three apparent violations of 10 CFR 50 Appendix B, Criterion XVIwere identified for the

licensee's failure to identify conditions adverse to quality. Conditions not previously

identified by the licensee in the ice condenser included:

blocked flow passages,

missing

ice segments,

dented/buckled basket webbing, unweighable ice baskets, and

nonencapsulated

insulation.

(Section M2.1)

~

The ice condenser was degraded to a poor state of materiel condition such that the

operability of the ice condenser was in question.

(Section M2.1)

~nein

e~rin

~

Four apparent violations of 10 CFR 50 Appendix B, Criterion XVIwere identified for the

licensee's failure to identify and correct conditions adverse to quality on ice condenser

components.

Specifically, these violations pertained to the licensee's failure: to

implement prompt corrective actions for missing ice basket sheet metal screws, to

implement effective corrective actions for preventing the recurrence of loose U-bolt nuts

and separated

ice baskets, and to take appropriate corrective actions for the ice baskets

with defective hold down bar welds.

(Section E2.1)

~

Collectively, the apparent violations identified in Sections M2.1 and E2.1 represent a

breakdown in the licensee's corrective action program for the ice condenser.

(Section E2.1)

Seven apparent violations of 10 CFR 50.71(e) were identified pertaining to the

licensee's failure to update the Final Safety Analysis Report (FSAR) Appendices J and

M,.which contained the detailed description and design basis for the ice condenser.

(Section E7.1)

Four apparent violations of 10 CFR 50 Appendix B, Criterion III were identified

pertaining to the licensee's failure to follow the established design control process for ice

basket modifications. (Section E7.1)

Collectively, the apparent violations identiTied in Section E7.1 represent a programmatic

breakdown in the maintenance of the design basis for the ice condenser.

(Section E7.1)

TABLE OF CONTENTS

M1

Conduct of Maintenance

M1.,1

Ice Condenser Surveillance Testing

M1.1.b.1

b.1.1

b.1.2

b.1.3

M1.1.b.2

b.2.1

b.2.2

b.2.3

b.2.4

b.2.5

M1.1.b.3

b.3.1

M1.1.b.4

b.4.1

M1.1.c

Ice Condenser Flow Passage

Surveillance Testing

.

Inadequate

Instructions for Visual Examination of Flow Passages

..

No Systematic Method for Selection of Flow Passages ..........

Lack of Margin to Analysis Limitfor a Degraded Ice Condenser

Ice Weight Surveillance Testing

.

Lack of Margin to Analysis Limitfor Maximum Ice Basket Weight ..

Unanalyzed Condition Authorized

Procedure Change Process not Followed

Nonrepresentative

Selection of Ice Baskets ..

Ineffective Control of Contractors

Ice Basket Inspection Surveillance Testing

TS Requirement for Ice Basket Inspection not Met..............

Ice Condenser Door Surveillance Testing

Lack of Margin for Ice Condenser Door Surveillance Acceptance

Criterion

Conclusions on Surveillance Testing ..

6

6

6

6

7

7

8

8

9

9

10

11

12

12

12

12

13

M2.1.b.1

M2.1.b.2

M2.1.b.3

M2.1.b.4

M2.1.b.5

M2.1.b.6

M2.1.c

Blocked Ice Bed Flow Passages

Missing Ice Segments

in Lower Sections of Ice Baskets .........

Dented/Buckled Ice Basket Webbing Condition is Outside Design

Basis

Unidentified Nonencapsulated

Insulation ..

Unweighable Ice Baskets with Tom, Creased,

Dented, or Buckled

Webbing Damage.......

Ice Form Different Than as Described in the FSAR .............

Conclusions on Ice Condenser Materiel Condition ..............

M2

Maintenance and Materiel Condition of Facilities and Equipment

M2.1

Ice Condenser Materiel Condition ..

14

14

14

14

15

16

17

17

18

E2

Engineering Support of Facilities and Equipment

.

E2.1

Corrective Actions for Ice Condenser Component Damage

E2.1.b.1

Failed and Missing Ice Basket Sheet Metal Screws

b.1.1

Corrective Actions Process not Implemented for Ice Basket

Sheet Metal Screws

.

b.1.2

Unanalyzed Condition for Plant Operation with Missing Sheet

Metal Screws

E2.1.b.2

Loose and Missing U-bolt Nuts

E2.1.b.3

Separated

Ice Baskets

E2.1.b.4

Failed Fillet Welds at the Ice Basket Bottom Hold Down Bar

.

E2.1.c

Conclusions on Corrective Actions for Ice

Condenser'omponents

~

~

~

.18

. 18

18

18

19

20

21

21

23

'TABLEOF CONTENTS

(continued)

E7

Quality Assurance in Engineering Activities.

E7.1

Maintenance of the Ice Condenser Design Basis

.

E7.1.b.1

Design Basis for Ice Condenser not Updated

E7.1.b.2

Unauthorized Modification of Ice Basket Assemblies ..........

E7.1.b.3

Surveillance Procedure Used to Modifyand Remove Ice Basket

Cruciform Supports

E7.1.c

Conclusions on the Maintenance of the Ice Condenser Design

Basis

E7.2

Operability in Question for the As-Found Ice Condenser Condition

24

24

24

26

27

27

28

E8

Miscellaneous Engineering issues

X1

Exit Meeting Summary

.

28

29

M1

Conduct of Maintenance

M1.1

Ic

C nd

n

r

rveill nce T stin

a.

Ins ection

co

617

Inspectors reviewed completed surveillance tests, interviewed licensee staff and

contractors that conducted surveillance testing, and reviewed condition reports

pertaining to surveillance testing of the ice condenser.

b.

0

a

'

n

Fin 'n

b.1

Ice

ond

n

r Fl w P

sa

urv illanc T stin

b.1.1

In

uat

t

ion f rVi

IEx min

i n fFI wP

The licensee completed surveillance test procedure 12 EHP 4030 STP.250 "Inspection

of Ice Condenser Flow Passages,"

Revision

1 on January 5, 1998, for Unit 1 and on

November 15, 1997 for Unit 2. During these surveillances, 48 flow passages

in each

Unit were verified to be free of ice buildup greater than 3/8 inch thick.

On January 22, 1998, inspectors identified blocked flow passages

in each Unit (Section

M2.1.b.1), which prompted a licensee inspection of all flow passages

in both Units.

From this inspection, the licensee identified that 8 of the 48 flow passages

inspected

during the January 5, 1998 performance of the 12 EHP 4030 STP.250 for Unit 1, were

partially obstructed with ice greater than 3/8 inch thick. Additionally, 13 of the 48 flow

passages

previously inspected during the November 15, 1997 performance of STP.250

on Unit 2 were subsequently found partially obstructed with ice greater than 3/8 inch

thick. The contractor and an ice condenser system engineer that performed these

inspections, had used a six volt flashlight to verify the flow passages

free of

obstructions.

Step 3.2 of 12 EHP 4030 STP.250 stated that portable lights will be obtained as

necessary to inspect ice condenser passages.

No other explicit instructions were given

for the conduct of this visual examination.

This procedure did not require: the visual

examinations to be conducted from above and below the flow passages,

the installed

lighting in the lower ice condenser to be turned on, the use of special lighting methods

demonstrated

to be adequate

(e.g. narrow tube lighting lowered into the flow passage).

Further, this procedure did not require inspection personnel to pass a visual examination

nor did it invoke a visual examination qualification standard (e.g. American Society of

Mechanical Engineers Code VT-2'qualification).

'

The instructions provided in step 3.2 of 12 EHP 4030 STP.250 were inappropriate for

the circumstances

in that, the ice blockage had not been detected using the existing

instructions.

Failure to ensure appropriate instructions for the circumstances were

included in 12 EHP 4030 STP.250 is an apparent violation of 10 CFR 50 Appendix B,

Criterion V (EEI 50-315/98005-01(DRS);

EEI 50-316/98005-01(DRS)).

b.1.2

S

t ma i

Meth

for Selection

f Fl w Pas

es

The inspector noted that the blocked flow passages

recently identified (see section

M2.1.b.1) were predominantly adjacent to radial row 1 and/or row 2 ice baskets in each

bay. The ice condens'er system engineer reported that past flow passage

selection did

not include preferentially selecting these areas for inspection, nor were flow passages

previously inspected in past surveillances excluded.

Step 3.3 of 12 EHP 4030 STP.250 required that the Lead Test Engineer identify the flow

passages

to be inspected.

The Test Engineer's selection process was arbitrary, in that

it did not include preferential selection of bay areas with a history of blockage problems

nor did it exclude flow passages

inspected during prior surveillances.

Thus, inspectors

concluded that the arbitrary selection process used was inadequate to ensure that a

degraded condition would be detected

in the ice condenser prior to reaching an

inoperable condition.

The instructions provided in Step 3.3 of 12 EHP 4030 STP.250 were inappropriate for

the circumstances,

in that the Test Engineer was allowed to use an arbitrary process,

vice a systematic process for selection of ice condenser flow passages

for inspection.

Failure to ensure appropriate instructions for the circumstances were included in 12

EHP 4030 STP.250 is an apparent violation of 10 CFR 50 Appendix B, Criterion V (EEI

50-315/98005-02(DRS);

EEI 50-316/98005-02(DRS)).

b.1.3 L c

Ma

i

i

i f

D

A 15 percent blockage limitwas used in the analytical input value for groupings of bays

modeled in the Westinghouse analysis WCAP 11902 "Reduced Temperature and

Pressure Operation for Donald C. Cook Nuclear Plant Unit 1 Licensing Report," dated

October 1988.

Inspectors identified that the ice condenser could be considered

operable using criterion in procedure 12 EHP 4030 STP.250 and returned to service

with blocked flow passages

above the maximum assumed

in this analysis.

Option 2 of Step 7.1.3 and Step 7.2.3 "Operability Determination" of 12 EHP 4030

STP.250, authorized the licensee to consider the ice condenser operable, ifthe as-left

percentage of total upward flow area per bay blocked was less than 15 percent.

The

licensee searched surveillance records back to 1990 and identiTied that Option 2 had

been used for Unit 2 in January of 1994 and again in Aprilof 1996. The licensee stated

that the method used to determine the percentage blockage in each bay during these

past surveillances was based entirely on engineering judgement (e.g., no formal

calculations were performed).

Inspectors concluded that the licensee's reliance on

engineering judgement and lack of a required quantifiable calculation methodology (e.g.,

4

independent calculations comparing areas blocked with available bay flow passage

area) would result in a wide error margin.

The instructions provided in Step 7.1.3 and 7.2.3 of 12 EHP 4030 STP.250 did not

adequately incorporate the assumed analysis limitof 15 percent flow blockage.

Specifically, the 15 percent acceptance

criterion used in Steps 7.1.2 and 7.2.3 did not

account for surveillance measurement

errors. These measurement

errors, when

considered, would result in a flow passage

blockage acceptance

criterion in excess of

that analyzed.

Failure to adequately incorporate the acceptance

limits assumed

in the

accident analysis (WCAP 11902) for the percent of flow passage

blockage into 12 EHP

4030 STP.250 is an apparent violation of 10 CFR 50 Appendix B, Criterion XI (EEI

50-315/98005-03(DRS);= EEI 50-316/98005-03(DRS)).

b.2

rv ill n

T

tin

I3.2.1

L

o

r in

An

I si

imitf r

m

B

e

i

From data provided in the FSAR, Appendix M, Table 4.3-1, the maximum analyzed

combined ice basket with ice weight (gross ice basket weight) assumed

in accident

analysis was 1776 pounds (Ibs). On March 1, 1990, the licensee accepted the

Westinghouse analysis

"Indiana Michigan Power D.C. Cook Nuclear Power Plant Ice

Condenser Seismic Load Study New Ice Basket Design," dated February 28, 1990, that

evaluated an increase in gross ice basket weight of up to 1877 lbs. Inspectors identified

that ice baskets with gross weight in excess of this analysis limitcould be accepted by

the licensee during the performance of 12 EHP 4030 STP.21'1 "Ice Condenser

Surveillance," Revision 2 and returned to service.

Attachment 4 of'12 EHP 4030 STP.211 allowed a maximum acceptable gross ice basket

weight of 1877 lbs. This 1877 Ibs limitdid not incorporate a margin for error associated

with the measurement

uncertainty in performing the basket weighing surveillance.

Further, repetitive weighing and averaging weights for the same ice basket was required

by the procedure to get an accurate ice basket weight, which indicated a substantial

margin of measurement

uncertainty.

Thus, inspectors concluded, that surveillance

measurement

errors, when considered, would result in a maximum gross ice basket

weight acceptance

criterion in excess of that previously analyzed.

The instructions provided in Attachment 4 of 12 EHP 4030 STP.211 did not adequately

incorporate the assumed analysis limitof 1877 Ibs for the gross ice basket weight.

Specifically, the 1877 Ibs gross ice basket weight acceptance

criterion used in

Attachment 4 did not account for surveillance measurement

errors, which when

considered, would result in a gross ice basket weight in excess of that analyzed.

Failure

to adequately incorporate the acceptance

limits assumed

in the accident analysis

(Indiana Michigan Power D.C. Cook Nuclear Power Plant Ice Condenser Seismic Load

Study New Ice Basket Design," dated February 28, 1990) for gross ice basket weight

into 12 EHP 4030 STP.211

is an apparent violation.of 10 CFR 50 Appendix B, Criterion

XI (EEI 50-315/98005-04(DRS);

EEI 50-316/98005-04 (DRS)).

b.2.2

nanal zed Co

itio

hori

Table 6.0-1 of Appendix M of the FSAR lists a design basis loss of coolant accident

(DBA), uplift force of 2536 Ibs for the ice baskets.

To resist this force, the bottom of

each ice basket is pinned to the support structure using a clevice pin.. During a DBA the

forces generated

on unpinned ice baskets could cause them to be expelled upward out

of the ice bed, which would create an unanalyzed missile hazard.

Step 4.8 of. EHP 4030 STP.211, Revision 2, allowed up to 60 ice baskets to be unpinned

in operating Modes 3 and 4 to support ice basket weighing operations.

The earlier

version of this procedure (e.g., step 4.7 of 12 THP 4030 STP.211 "Ice Condenser

Surveillance," Revision 17) authorized unpinning of up to 60 ice baskets in operating

Modes

1 through 4. These procedure steps lacked instructions to implement the

TS 3.6.5.1 Action statement for an inoperable ice condenser.

Inspectors identified that

the ice condenser should have been considered inoperable during this step, because

unpinning of multiple ice baskets as allowed in EHP 4030 STP.211 represented

an

unanalyzed condition.

The instructions provided in Step 4.8 of 12 EHP 4030 STP.211 were inappropriate for

the circumstances,

in that no analysis existed to support operation with 60 unpinned ice

baskets and this step lacked instructions to implement the TS 3.6.5.1 Action statement

for an inoperable ice condenser.

Failure to ensure appropriate instructions (e.g., to

declare the ice condenser inoperable at step 4.8) were included in 12 EHP 4030

STP.211 is an apparent violation of 10 CFR 50 Appendix B, Criterion V (EEI

50-315/98005-05(DRS);

EEI 50-316/98005-05 (DRS)).

As of February 25, 1998, the licensee had not located an analysis to bound the

unpinning of ice baskets authorized and performed during past surveillance testing.

On

February 25, 1998, the licensee notified the NRC of this potentially unanalyzed condition

pursuant to the reporting requirements of 10 CFR 50.72(b)(2)(i) ~

b.2.3

On December

1, 1997, the licensee completed 12 EHP 4030 STP.211, Revision 2

through steps 7.5 for Unit 2. Inspectors identified hand written changes in the left hand

margin next to steps 7.1 through 7.5 on the completed copy of. this procedure.

These

changes, signed and dated on December

1, 1997, incorporated the newly proposed TS 4.6.5.1 acceptance

criterion for ice weight inventories.

The licensee intended to use this

change to meet the revised TS 4.6.5.1 acceptance

criterion authorized by the NRC on

January 2, 1998.

The licensee had made the change described above to the procedure acceptance

criterion without following the change process described in procedure PMI-2010

"Instructions, Procedures,

and Associated Indexes Policy," Revision 24. Specifically,

Section 4.6 of PMI-2010 required in part, the use of a procedure change sheet and a

review by personnel holding a Senior Reactor Operating License, neither of which

occurred in this case.

Failure to followthe procedure change process as described in PMI-2010 for changes

made on December 1, 1997, to 12 EHP 4030 STP.211, Revision 2 is an example of an

apparent violation of 10 CFR 50 Appendix B, Criterion V (EEI 50-315/98005-6a(DRS)).

On January 6, 1998, the licensee completed 12 EHP 4030 STP.211, Revision 2 through

steps 7.5 for Unit 1. Inspectors identified hand written changes in the left hand margin

next to steps 7.1 through 7.5 on the completed copy of this procedure.

These changes,

signed and dated January 6, 1998, incorporated the recently changed TS 4.6.5.1

acceptance

criterion for ice weight inventories.

The licensee had made the change described above, to the procedure acceptance

criterion, without following the change process described in procedure PMI-2010

"Instructions, Procedures,

and Associated Indexes Policy," Revision 24. Specifically,

Section 4.6 of PMI-2010 required in part, the use of a procedure change sheet and a

review by personnel holding a Senior Reactor Operating License, neither of which

occurred in this case.

Failure to follow the procedure change process as described in PMI-2010 for changes

made on January 6, 1998 to 12 EHP 4030 STP.211, Revision 2 is an example of an

apparent violation of 10 CFR 50 Appendix B, Criterion V (EEI 50-316/98005-6b(DRS)).

b.2.4Nnre

r

nt

iv

S

ct'

Ic

B

k

TS 4.6.5.1.b.2 required in part, that the licensee select a representative

sample of 144

ice baskets for weighing from radial rows 1,2,4,6,8 and 9. A software computer program

ICE-PICK is used by the licensee to randomly select a basket within each of the radial

basket rows (1,2,4,6,8,9) to meet the "representative" ice basket selection required.

However, this program excluded azimuthal rows 1,5 and 9 from the selection process

and did not exclude baskets weighed during previous surveillance tests.

The licensee

reported that an average of at least 23 baskets were repetitively selected for the 1996

and 1997 surveillances used to calculate ice inventory for each Unit.

Historical data provided by the licensee, indicated that 223 Unit 1 and 171 Unit 2 ice

baskets had never been weighed since original plant construction and start of

commercial operation.. These ice baskets were predominantly the azimuthal row 5 ice

baskets.

The licensee had excluded ice baskets in azimuthal rows 1,5 and 9 in their

normal selection process, because of interference with intermediate deck door support

structures, which are not normally removed due to the extensive restoration required.

In

August of 1997, the licensee selected and weighed a test sample of 54 Unit 2 ice

baskets in azimuthal row 5 and identified "light"ice baskets (e.g., ice baskets containing

less than 1333 Ibs of ice). Of these baskets, 40 contained less than the current TS

surveillance minimum 1333 Ibs of ice and 13 of these baskets contained less than the

preceding TS minimum of 1220 Ibs of ice. The lightest azimuthal row 5 basket

contained only 800 Ibs of ice. Thus, the licensee's sampling process which excluded

azimuthal row 5 ice baskets did not represent this population of "light"ice baskets.

10

1

Inspectors identified that percentages

of ice baskets in radial rows

1 and 9 had not been

weighed as frequently as baskets in other radial rows.

From data taken since 1994 on

Unit 1, an average of 48 percent of radial row 1 baskets and 51 percent of radial row 9

baskets had not been weighed.

These percentages

of unweighed baskets were

significantly higher in row 1 and 9 than for any other radial row. Further, the ice baskets

which had not been weighed recently in radial row 1 and 9 may correlate with ice

baskets which had larger segments of missing ice in the lower part of the ice basket

(Section M2.1.b.2). Thus, repetitive weighing of the same ice baskets in radial row 1

and 9 from one surveillance to the next, created a nonrepresentative

sample, in that the

potentially "light"nonweighed baskets with missing ice were not represented.

Based on the information discussed above, inspectors concluded that the licensee had

been selecting a nonrepresentative

sample of ice baskets when performing ice weight

surveillances.

The selected ice baskets constituted a nonrepresentative

sample, in that

azimuthal row 5 ice baskets were exclude, which were "lighter" than other azimuthal

rows. Further, the selection was nonrepresentative

in that the same ice baskets were

repetitively weighed (particularly in radial rows

1 and 9) between sequential

surveillances due to the failure to track and exclude previously weighed ice baskets.

Failure to select a representative

sample of ice baskets to weigh is an apparent violation

of TS 4.6.5.1.b.2 (EEI 50-315/98005-07(DRS);

EEI 50-316/98005-07 (DRS)).

The licensee had completed 12 EHP 4030 STP.211 on December 1, 1997 for Unit 2 and

on January 6, 1998 for Unit 1. The licensee used these procedures to establish that ice

inventory requirements for average bay group ice weight of 1333 Ibs and total ice

inventory met TS 4.6.5.1.b.2.

However, these calculations of ice inventory did not

include an adjustment for the recent data collected on "light"azimuthal row 5 baskets.

On February 11, 1998, the licensee notified the NRC (pursuant to requirements of 10 CFR 50.72(b)(2)(i)) that the ice weights used to determine TS compliance that may not

constitute a representative

sample and potentially represented

an unanalyzed condition.

The licensee also documented the concern as to whether the ice weights used to

demonstrate TS compliance constituted a representative

sample in CR 98-500.

b.2.5 Ineffectiv

r

f

tr

t

Damage to numerous Unit 1 and Unit 2 ice baskets had been documented

in

condition/problem reports CR 98-388, CR 97-3244, PR 88-914, CR 12-05-85-1036, CR

1-08-83-771 and CR 1-07-83-647.

This ice basket damage, typically tom ice basket

webbing, creased

ice baskets and bent upper ice basket rims, potentially rendered the

affected ice baskets unweighable or incapable of sustaining the original ice basket

. design loadings.

The licensee attributed this damage to activities performed by

contractors during the ice basket weighing surveillance test.

Historically, the licensee had used contractor services to perform the ice basket

weighing for surveillance procedure 12 EHP 4030 STP.211 (formerly 12 THP 4030

STP.211).

10 CFR 50 Appendix B, Criterion Vllrequires in part, that the licensee

assess

the quality by contractor services at intervals commensurate

with the nature of

11

the work. In this case, the licensee controls were ineffective to assess

and control the

quality of work performed by contractors performing the ice basket weighing surveillance

testing.

As a consequence

of this failure, a,large number of ice baskets had sustained

damage over many years, some of which put ice baskets outside the original design

basis.

Failure to adequately assess

the control of quality for contractor services for ice

condenser surveillance testing is an apparent violation of 10 CFR 50 Appendix B,

Criterion Vll (EEI 50-315/98005-08(DRS);

EEI 50-316/98005-08(DRS)).

b.3

B

k tin etin

rvilln

T

in

b.3.1 TS Re uire

ent

Ice Baske

s ection not M t

TS surveillance requirement 4.6.5.1.d required in part, that the licensee visually inspect

accessible portions of at least two ice baskets from each 1/3 of the ice condenser and

verify that the ice baskets are free of detrimental wear, cracks, corrosion or other

damage.

A visual inspection of the accessible portions of the lower basket assembly

was not required by 12 EHP 4030 STP.212 "Ice Condenser Basket Inspection,"

Revision 0.

On March 21, 1997, the licensee completed 12 EHP 4030 STP.212 "Ice Condenser

Basket Inspection," Revision 0 for Unit 1. This inspection included a visual examination

to identify damage on six ice baskets in accordance with TS 4.6.5.1.d requirements.

During this inspection, ice basket 6-3-4 was visually examined, found free of damage

and returned to service.

However, on February 14, 1998, the licensee identified that

Unit 1 ice basket 6-3-4 had a 3 inch by 8 inch dent in the webbing

1 foot above the

bottom of this basket and a missing sheet metal screw in the bottom basket rim.

b.4

The damage identified on February 14, 1998, for ice basket 6-3-4 had not been

identified during the prior surveillance test, because

12 EHP 4030 STP.212 did not

include an inspection requirement for the lower ice basket area.

Further, based on a

scoping test completed by the licensee on a dented/buckled basket on February 12,

1998 (Section M2.1.b.3), the dented webbing could potentially decrease

the

compressive strength of this basket below the original design strength of a new basket.

Thus, the licensee failed to identify potentially detrimental damage in ice basket 6-3-4

during the March 21, 1997 inspection as required by TS 4.6.5.1.d.

Failure to include

requirements in 12 EHP 4030 STP.212 to perform inspection of accessible areas of the

lower ice basket is an apparent violation of TS 4.6.5.1.d (EEI 50-315/98005-09(DRS);

EEI 50-316/98005-09(DRS)).

Ice Con en e

Do

Surv 'lian

T

tin

b.4.1

rD

ill

A

t n

C'he

door operability acceptance

criteria were at the maximum values allowed by TS 4.6.5.3 in procedures

12 EHP 4030 STP.207 "Ice Condenser Lower Inlet Doors,"

Revision 0 and 12 EHP 4030 STP.245 "Inspection of Ice Condenser Intermediate Deck

Doors," Revision 0. A margin for error associated

with the measurement

uncertainty in

12

]

'l

~l

performing the door surveillance testing had not been incorporated into the acceptance

criteria used in these procedures.

Surveillance procedure 12 EHP 4030 STP.207 specified a lower ice condenser door

maximum opening torque of 675 inch-pounds and 195 inch-pounds (at 40 degrees

open).

These values did not account for surveillance measurement

errors, which when

considered would result in acceptance

criteria in excess of the limits specified in TS 4.6.5.3.1.b item

1 and 2. Failure to adequately incorporate the acceptance

limits

specified by TS 4.6.5.3.1.b item

1 'and 2 into 12 EHP '4030 STP.207 is an apparent

violation of 10 CFR 50 Appendix B, Criterion XI (EEI 50-315/98005-10(DRS);

EEI

50-316/98005-10 (DRS)).

Surveillance procedure 12 EHP 4030 STP.245 specified ice condenser intermediate

deck door maximum opening resistance forces of 37.4 Ibs, 33.8 Ibs, 31.8 Ibs and 31.0

lbs. These values did not account for surveillance measurement

errors, which when

considered would result in an acceptance

criterion in excess of the limits specified in

TS 4.6.5.3.2.b.

Failure to adequately incorporate the acceptance

limits specifie by TS 4.6.5.3.2.b into 12 EHP 4030 STP.245 is an apparent violation of 10 CFR 50 Appendix

B, Criterion XI (EEI 50-315/98005-11(DRS);

EEI 50-316/98005-11

(DRS)).

b.4.2 NRC inspection report 50-369/97-16; 50-370/97-16 documented that 10 of 48 lower ice

condenser inlet doors had failed to meet TS surveillance requirements for opening

torque and were therefore rendered inoperable at the McGuire facility Unit 2. This

problem was caused by the door flashing dragging against the floor. The floor had been

raise 0.75 inches above the original grade level, due to freeze thaw cycles which

introduced water into the concrete flooring.

For D.C. Cook, the licensee staff stated that the ice beds had never been "melted out"

and thus water had not been introduced into the lower wear slab.

No condition reports

had been issued that documented

a lower inlet door surveillance failure attributed to this

condition nor were any visual indications present to indicate ice condenser floor

movement.

Thus, inspectors concluded that this problem had not occurred at D.C.

Cook.

I 'son Surv ill n e

estin

Inspectors identified eight apparent violations of 10 CFR 50 Appendix B (three Criterion

V, four Criterion XI, and one Criterion Vll)and two apparent violations of TS. These

violations pertained to inadequate instructions, inadequate acceptance

limits,

inadequate control of contractors, failure to implement TS requirements and entry into

an unanalyzed condition for ice condenser surveillance testing.

Further, two examples

of an apparent violation of 10 CFR 50 Appendix B, Criterion V were identified for the

licensee's failure to followthe procedure change process for changes made to

completed surveillance tests.

Collectively, these apparent violations represent a

breakdown in the surveillance testing program for the ice condenser and contributed to

a questionable state of operability for the as-found condition of the ice condenser.

13

M2

Maintenance and Material Condition of Facilities and Equipment

M2.1<

Ice

nd ns r Mat ri

I Condition

a.

In

cti

S

27

Inspectors performed walkdowns of the ice condenser for each Unitto evaluate the

materiel condition.

rvations

nd Fin in

b.1

BI

d I

Bed Fl

P

Areas between ice baskets (flow passages)

allow steam released

in a loss of coolant

accident to travel through the ice bed and condense which reduces the post accident

containment pressure.

On January 22, 1998, inspectors identified multiple flow

passages

obstructed by ice in Unit 2. As a corrective action for this finding, the licensee

initiated an inspection of flow passages

in every bay of both Units to identify blockage.

On January 27, 1998, the licensee identified blocked flow passages

in every bay for

both Units and estimated that 10 to 20 percent of the ice condenser flow passage

area

was blocked by ice. The plant design basis analysis (Westinghouse WCAP-11902

"Reduced Temperature and Pressure Operation for Donald C. Cook Nuclear Plant Unit

1 Licensing Report" dated October 1988 ) had assumed

15 percent of the flow passage

area blocked in groups of ice bays.

The licensee declared the ice condensers

inoperable on January 28, 1998 and documented the condition in CR 98-0326.

Both

Units were in cold shut down at the time and the ice condenser operability was not

required until hot plant operation (e.g., Modes 1-4). These blocked passages

likely

existed during past plant operation and had not been identified due to inadequate

surveillance testing (Section M1.1.b.1.1).

On January 28, 1998, the licensee notified the NRC (pursuant to requirements of

10 CFR 50.72(b)(2)(i)) of the blocked ice condenser flow passages,

that potentially

represented

an unanalyzed condition. Because of this condition and other unanalyzed

conditions identified herein, the licensee staff reportedly intended to complete a detailed

analysis to demonstrate that the ice condenser was capable of performing its design

function during previous operating periods (Section E7.2).

b2

i

m nt

in Lower Se

ti ns

Ic

B

The TS 4.6.5.1 basis for operability of the ice condenser assumed that ice is evenly

distributed through the containment bays.

Inspectors performed a sample inspection of

portions of several bays in the Unit 1 and 2 lower ice condenser and identified ice

baskets with missing ice segments

(6 to 18 feet in height). The predominant number of

ice baskets with larger missing ice segments appeared

to exist for ice baskets in radial

rows 8 and 9. Inspectors reviewed the dates when the licensee had last weighed four

Unit 2 ice baskets (in radial rows 8 and 9) with 12 feet or more of missing ice. Of these

14

four Unit 2 ice baskets, two had not been weighed in over 10 years and two had no

recorded weight since the beginning of plant operation.

Ice baskets are not refilled

unless they are weighed and found to be "light." Thus, ice baskets not recently weighed

with observed missing ice segments were potentially "lighter" than the average basket

weights specified by the TS. Further, light ice baskets potentially affected the

assumption that the ice was evenly distributed through ice condenser bays and

impacted the methodology used to select a representative

sample of ice baskets for

weighing (Section M1.1.b.2.4).

As a corrective action for the missing ice segments,

the licensee performed a visual

inspection of the lower segments of all accessible ice baskets and identified missing ice

segments

in every bay. On February 11, 1998, the licensee documented

in CR 98-500

that radial row 8, 9 and azimuthal row 5 ice baskets showed visual evidence of ice loss

due to sublimation. The sublimation of ice in the ice condenser has been demonstrated

to be less than five percent per year. Thus, the ice baskets with significant missing.ice

segments

(as discussed above) had developed over many years without identification or

evaluation by system engineers or other members of the licensee staff during ice

condenser walkdowns. The ice condenser performs a passive safety function and

licensee staff reported that the ice condenser historically had not been considered a

"system."

The licensee is required by 10 CFR 50 Appendix B, Criterion XVI, to establish measures

to ensure that conditions adverse to quality are promptly identified and corrected.

In this

case the licensee had failed to promptly identify, evaluate or implement corrective

actions for the missing ice segments, which is an apparent violation of 10 CFR 50

Appendix B, Criterion XVI (EEI 50-315/98005-12(DRS);

EEI 50-316/98005-12(DRS)).

b.3

D nte

Buckl d lce B

ket W bb'

ii ni

t id

the D

i n B sis

An ice basket profile roundness tolerance (reference WCAP 8887 and 8304) is specified

for basket fabrication. Changes to the basket roundness profile potentially affect the

ability of the ice basket to sustain a compressive load. Under design basis accident

conditions the ice baskets are subject to compressive loadings.

On February 4, 1998, the inspectors identified seven Unit 2 ice baskets with a six-inch

long horizontal crease or buckled area of webbing approximately

1 foot above the

bottom of the basket.

This buckled webbing changed the ice basket roundness profile

and potentially affected the ice basket design compressive strength.

As a corrective

action, the licensee included a search for dented/crumpled

ice baskets in the inspections

of all accessible lower basket assemblies

in each unit to identify missing screws.

From

this inspection, the licensee generated

a preliminary list of damaged baskets.

In excess

of 40 Unit 1 baskets and in excess of 100 Unit 2 baskets were identified with dents or

buckled/crushed

areas in the lattice webbing near the bottom of the basket.

The licensee staff stated that the likely cause of the dented/buckled damaged to the ice

baskets was dropping of the baskets, or jacking the baskets from below, in an attempt to

loosen the baskets for surveillance testing.

Based on observed corrosion at buckled

15

L

0

webbing locations (protective coating was damaged) and the number of damaged ice

baskets, the inspectors concluded that the damage had occurred over an extended

period of time. Further, these dented/buckled ice baskets were readily visible and yet

this damage had heretofore not been identified during ice condenser walkdowns by

system engineers."

In this instance, the licensee staff had numerous opportunities to identify and correct

the dented baskets during past surveillance testing or ice condenser walkdowns.

Failure to promptly identify, evaluate or implement corrective actions for the

Unit 1 and 2 ice baskets with dented/buckled webbing located near the bottom ice

basket rim assembly,

is an apparent violation of 10 CFR 50 Appendix B, Criterion XVI

(EEI 50-315/98005-13(DRS);

EEI 50-316/98005-13(DRS)).

On February 12, 1998, the licensee conducted a scoping test on a Unit 1 ice basket,

which contained a dented/buckled section of webbing approximately

1 foot above the

bottom of the basket.

This test was, intended to apply a compressive axial and lateral

load equivalent to that used to qualify the design basis (dead load combined with

operational basis earthquake) of an undamaged

basket (reference WCAP 8304). This

basket began to fail with plastic deformation (crumple) under a compressive load of less

than half that used to qualify the design of an undamaged

basket.

On February 12,

1998, the licensee notified the NRC (pursuant to reporting requirements of.10 CFR 50.72(b)(2)(i)) that this ice basket, represented

a condition outside the plant's design

basis.

b.4

U ide

i

Nn

Section 3.1.6 "Loose Insulation" of Appendix M of the FSAR discusses

the use of an

airtight polyethylene bag to encapsulate

insulation, to prevent loose insulation during a

DBA. Loose insulation could be returned to the sump and potentially clog emergency

core cooling system suction strainers following a DBA.

On February 19, 1998, inspectors identified a blanket of "loose" (nonencapsulated)

fiberglass insulation between the entry doorway bulkhead and the bay 24 east wall in

the Unit 1 lower ice condenser.

Inspectors estimated that this nonencapsulated

insulation was potentially a 10 feet by 10 feet piece of fiberglass insulation with cutouts

for the door and structural support materials.

This condition had likely existed since

original plant construction.

On February 20, 1998, the licensee issued CR 98-0634 to

document and evaluate this condition applicable to both Units.

In this instance, the licensee staff had numerous opportunities to identify and evaluate

the nonencapsulated

insulation during past surveillance testing or ice condenser

walkdowns.

Failure to promptly identify, evaluate or implement corrective actions for

the nonencapsulated

insulation in the Unit 1 and 2 ice condensers,

is an apparent

violation of 10 CFR 50 Appendix B, Criterion XVI(EEI 50-315/98005-14(DRS);

EEI 50-316/98005-14(DRS)).

16

I ~

4

i~,

Ijj

b.5

Unw i habl

B

t

'hT r

D nt

rB

k

W

in

D ma

Inspectors noted tom'ligaments, bent rims and missing screws at the upper rim

area of ice basket assemblies.

The licensee had previously identified (reference

CR 2-12-88-1719 and CR 1-04-89-702) in excess of 200 Unit 2 ice baskets and in

excess of 300 Unit 1 ice baskets with damage to upper areas of ice baskets

(predominantly tom webbing and bent rims).

In some cases, this damage to the

upper rim areas prevented the use of test equipment to liftthe ice basket for the ice

basket weight surveillance, which rendered the ice basket unweighable.

The licensee could not readily identify the damaged ice baskets in service that had been

rendered unweighable, because

this type of information was not tracked.

The licensee

initiated actions to visually inspect and map the ice baskets still. in service with damage

near the upper rim areas.

The licensee stated that the probable cause of the ice basket damage in upper areas of

the basket was rough handling (e.g., attempts to free baskets frozen in) during past

surveillance. weighing activities (M1.b.2.5.).

Inspectors identified that damaged

unweighable ice baskets in radial rows 1,2,4,6,8,9 could affect the ability of the licensee

to perform representative

sampling of ice baskets (Section M1.b.2.4). Inspectors

identified that during the April 24, 1996 performance of EHP 4030 STP.211 for Unit 2,

sixteen radial row nine and ten radial row one ice baskets could not be weighed due to

damaged rims or being frozen in. Additionally, unweighable baskets cannot be refilled

without repairs, since baskets loaded without subsequent weighing could potentially

exceed the maximum allowable ice basket weights assumed

in the design basis

analysis.

b.6

I eF

Di

n

Section 1.1 of the FSAR, Appendix M, described the form of ice used to fillthe ice

baskets as 2 inch by 2 inch by 1/8 inch flake ice. Further, Section 5.3.3 of the FSAR

stated that long-term ice storage tests have shown that the ice can be stored without

significant weight loss or physical distortion. Contrary to this description, inspectors

observed that ice baskets recently filled contained a course loose granular form of ice

and that ice baskets not recently filled had sublimated into a solid mass of ice.

To address this change in ice form, the licensee provided a letter from Westinghouse

dated February 10, 1998, which referenced Westinghouse testing conducted in 1960

that tested ice in the form of chips, cubes, blocks and spheres.

These tests reportedly

demonstrated

that ice condenser performance was insensitive to extreme changes

in

ice heat transfer surface area.

Additionally, a 1973 Westinghouse test was referenced

which included 0.75 Ibs of water per foot per basket.

The water was added to represent

the Iong term storage condition of the ice. The licensee also referenced the Atomic

Energy Commission (AEC) questions and responses

on this subject during the initial

plant licensing.

Licensee responses

to the AEC for this concern included, "Ice storage

17

tests have shown that ice can be stored for long periods without significant degradation"

and "Results of these tests show no significant difference in the properties of various

forms of ice."

Based on the information discussed

above, the existing changes

in ice form appeared

to

be bounded by tests and evaluations reviewed during initial plant licensing.

However,

the licensee's failure to update the description of the ice form changes in the FSAR was

considered an apparent violation of 10 CFR 50.71(e) requirements and is discussed

in

section E7.1.

Conclusions on Ic

Con

n

r Mat ri

I C

n iti

Inspectors identified three apparent violations of 10 CFR 50 Appendix B, Criterion XVI

for the licensee's failure to identify conditions adverse to quality. Conditions not

previously identified by the licensee in the ice condenser included: blocked flow

passages,

missing ice segments,

dented/buckled basket webbing, unweighable ice

baskets, and nonencapsulated

insulation.

Further, these conditions had existed for an

extended period of time, without identificatio by system engineers or licensee staff.

Collectively, these problems contributed to a poor state of materiel condition in each ice

condenser, such that the ability of the ice condenser to perform its design function was

in question.

E2

Engineering Support of Facilities and Equipment

E2.1

C rre tive Actions

rlc

Cond nse

Com one

Dama

e

i n

72

Inspectors interviewed engineering staff and reviewed engineering corrective actions

documented

in problem/ condition reports for damaged

ice condenser components..

b.

rv tion

nd F'ndin

b.1

F iled

ndMi

in

B

k t

h

t

I

rw

b.1.1

rre tiv A ti n

roc

not I

I men

f rl e B

k t

h et

tal

rew

Ice baskets segments (typically 12 feet in length) are coupled together using sheet

metal screws arranged in pairs at 60 degrees intervals around the circumference of the

ice basket.

Twelve screws on each basket segment are installed at the coupling joint.

Missing screws at the intermediate or lower coupling joints could allow an ice basket to

separate and become a missile hazard under design basis accident loads.

NRC

18

inspection report 50-390/97-04; 50-391/97-04 documented that broken ice basket sheet

metal screws had been found in the ice melt tank at another ice condenser plant (Watts

Bar).

For D.C. Cook, an ice condenser system engineer identified four ice basket sheet metal

screw heads in the ice melt system filteron January 22, 1998. The licensee had not

initiallyrecorded these screws missing from ice baskets, nor others found in prior

outages on condition reports.

The system engineer estimated that approximately two

dozen sheet metal screw parts had been found in the ice melt system filters since 1991.

The licensee staff had believed that the source of these screws was the top basket rim

or separated

baskets, which had been restrained through modifications and thus had no

safety significance.

Inspectors'uestions

into the definitive source and significance of

these missing sheet metal screws prompted a licensee inspection of ice baskets in each

Unit for missing screws (Section E2.1.b.1.2).

The licensee's failure to promptly identify

and initiate corrective actions for the ice basket sheet metal screws found in the ice melt

cleanup system filters during previous outages is an apparent violation of 10 CFR 50

Appendix B, Criterion XVI (EEI 50-315/98005-15(DRS);

EEI 50-316/98005-15(DRS)).

U

al z

C d't'PI

i nw'thMi

in

h

t

I

r ws

The scope of the licensee's ice basket inspection for missing sheet metal screws

consisted of a visual inspection of accessible areas of the bottom basket coupling rings

for ice baskets

in both Units. The accessibility of the bottom basket coupling ring area

of some ice baskets was limited by ice buildup or physical interferences with ice

condenser components.

For example, of the 81 ice baskets per bay, the licensee was

not able to perform a complete inspection on up to 22 baskets per bay in Unit 2 and up

to 18 baskets per bay in Unit 1

~ In addition to the bottom basket areas, the licensee

performed a camera aided visual examination of the intermediate coupling joints and

stiffening rings on ice baskets in each unit (a population of 60 to 100 baskets for each

Unit was planned).

From the inspections discussed above, in excess of 40 Unit 1 and in excess of 90 Unit 2

ice baskets were identified with missing sheet metal screws at the lower ice basket

coupling ring. In addition, several ice baskets had been identified to have one or two

missing screws at intermediate coupling rings in the ongoing full length camera aided

inspections.

The licensee had Westinghouse complete an evaluation (documented in a

memorandum dated February 13, 1998) of the missing sheet metal screws.

In this

evaluation Westinghouse concluded that the ice basket column would continue to meet

the design function (based on allowable shear stress in the sheet metal screws) with 8

of 12 screws on a basket segment at the coupling union on a case by case basis.

At the

19

conclusion of the inspection period the licensee had identified the following ice baskets

with more than 4 missing sheet metal screws at the bottom basket coupling ring.

Unit

No.

Basket No. (Bay, Azimuthal Row, Radial Row)

No. Of Missing Screws

2-1-6

3-4-8

24-4-8

8-2-9

14-6-8

19-7-9

22-8-9

11 of 12

12 of 12

9of12

6 of 12

9 rivets and 3 screws

12 of 12

5 of 12

On February 14, 1998, the licensee notified the NRC (pursuant to requirements of

10 CFR 50.72(b)(2)(i)) that two Unit 1 baskets missing more than 4 sheet metal screws

represented

an unanalyzed condition outside the plant's design basis.

At of the

conclusion of the inspection period, the licensee had not determined the cause of the

failed sheet metal screws.

b.2

Lo se and

is's

On November 2, 1990, the licensee documented

in PR 90-1639 a broken U-bolt and 19

missing nuts from Unit 1 ice baskets and 12 missing U-bolt nuts from Unit 2 ice baskets.

The cause of the missing fasteners was attributed to loosening of the nuts caused by

vibrating tools used during the ice basket emptying process.

Licensee corrective

actions included replacing missing nuts and inspecting a selection of basket nuts to

identify any loose or missing fasteners.

Preventative actions included revising 12 THP

4030 STP.211 to require all baskets which are vibrated to be inspected for broken

U-bolts, and loose or missing nuts..

On April 23, '1992, the licensee documented

in PR 92-0360 that 10 percent of all Unit 2

U-bolt basket nuts were loose and 5 Unit 2 baskets had missing U-bolt nuts. Again, the

cause of the loose fasteners was attributed to vibrating tools used during ice basket

emptying.

On August 19, 1992, the licensee identified in PR 92-1386, missing nuts and an

unspecified number or percentage of loose nuts for Unit 1. The cause of the loose and

missing nuts was documented as unknown. The preventative action was to continue to

do inspection of nuts during 12 THP 4030 STP.211.

Step 4.17 of EHP 4030 STP.211 (formerly 12 THP 4030 STP.211) allowed replacing

loose or missing fasteners from the bottom ice basket U-bolts without restrictions or

20

instructions.

Step 5.4.3.3 required missing or broken U-bolts to be documented on a

condition report and Attachment 4 of this procedure.

However, this step only required

documenting loose nuts in Attachment 4, vice on a condition report. Thus, inspectors

were concerned that loose U-bolt nuts could be an ongoing problem for a number of ice

baskets and not identified in condition reports.

Loose or missing U-bolt nuts can allow the ice baskets to be displaced horizontally

under design basis accident loads such that other baskets may be contacted,and

damaged.

The licensee's preventative actions implemented in PR 90-1639 did not

prevent recurring loose and missing U-bolt nuts.

Further, existing surveillances

requirements did not require repeat occurrences of this condition adverse to quality

to be entered into th'e corrective action process.

Failure to implement corrective

actions which preclude recurrence of this significant condition (loose U-bolt nuts)

adverse to quality is an apparent violation of 10 CFR 50 Appendix B, Criterion XVI

(EEI 50-315/98005-16(DRS);

EEI 50-316/98005-16(DRS)).

b.3

rated

B

s

In 1983, the licensee identified separation of sections of the Unit 1 ice baskets 17-2-9,

20-6-8 and 20-8-8 and documented this condition in CR 1-07-83-647 and

CR 1-08-83-771.

The bay 20 ice baskets had failed during weighing activities with

less than 1000 Ibs of liftingforce applied.

This amount of force was below the

design forces for the basket and the licensee had not determined the cause for these

basket section failures in response to these condition reports.

On February 28, 1997, during surveillance testing, the top three feet of ice basket

20-9-8 had separated.

The licensee documented this condition in CR 97-554, and did

not identify a definitive cause, nor implement preventative actions for this condition.

These ice baskets, which failed below the design loadings, could have separated under-

DBA blowdown loadings and become missile hazards.

Failure to implement corrective

actions for these separated

Unit 1 ice baskets, which precluded repetition of this

significant condition adverse to quality, is an apparent violation of 10 CFR 50

Appendix B, Criterion XVI (EEI 50-315/98005-1 7(DRS)).

b.4

Fill

W

I

h

B

B tt

IdD

B

On July 22, 1992, the licensee had identified 22 Unit 1 and 3 Unit 2 ice baskets which

had settled (bottom rim displaced relative to the hold down bar) and documented this

condition in PR 92-1181.

Two ice baskets had been removed to examine the inner

bottom basket rim area, which was not directly accessible to an in-situ examination.

This examination revealed that the filletweld joining the bottom basket (/~ inch by 4 inch

by 11.6 inch) hold down bar had failed allowing separation of this bar from the bottom

basket rim.

The cause of these weld failures was determined to be manufacturing induced flaws,

vice service induced.

The metallurgical report (Gelles Laboratories, Inc. dated

21

August 1992) conclusions stated "No evidence of service caused failure was found" and

"..the galvanizing operation may not have been done correctly" and "The lack of fusion

appears to be caused by improper joint cleaning." Further, this report had

recommended

that the licensee perform mechanical testing of selected ice baskets to

ascertain the capability of these baskets.

The licensee's corrective actions for the known (settled) ice baskets with failed fillet

welds included installing restrainer bars over the failed Unit 2 baskets and replacing

the bottom rims for the Unit 1 baskets.

However, corrective actions documented

in

PR 92-1181 did not include identificatio of the full scope of ice baskets with failed fillet

welds caused by manufacturing defects.

The licensee chose not to attempt to identify

other ice baskets with flawed/failed filletwelds due to in-situ accessibility limitations.

Instead, the licensee performed analyses and evaluations to accept this condition.

In a licensee memorandum dated July 27, 1992, the licensee evaluated the effect of the

broken filletwelds on the ice basket during a DBA. In this evaluation, the licensee

stated in part, that the stiffness of the end grid is several orders of magnitude lower than

the stiffness of the bottom rim and of the Y~ inch bar, causing it to deflect out of the way

during a DBA uplift condition and causing the bar to engage the lower rim inner lip with

minimal displacement and no impact. The evaluation success

criteria established

by the

licensee were that bending and shear stresses of the bottom rim would remain within

allowable values, for the material.

Based on this evaluation, the licensee concluded that

the ice baskets could resist all loads despite the broken weids.

On 'July 27, 1992, Westinghouse expressed

a concern pertaining to the dynamic effects

of a DBA blowdown on baskets with broken weids that had settled.

For baskets in a

settled position, the lip of the bottom rim of the basket would be subject to additional

loads due to the impact on the /~ inch bar as the baskets is accelerated

upwards by the

blowdown forces generated

by the DBA. Westinghouse could not provide reasonable

assurance

that the settled baskets would not become missile hazards when subject to a

DBAplus design basis earthquake loads.

On August 13, 1992, the licensee performed another evaluation and developed a

mathematical model of the dynamics of the ice basket loadings to address the

Westinghouse concern discussed

above.

The licensee reportedly incorporated the

blowdown loads provided by Westinghouse and the displacement load/resistance

curves (developed from a single static pull test performed on August 8, 1992) into their

mathematical model of dynamic loads.

For the design ice basket weights, the model

reportedly established:

whether the bottom basket rim assembly would stop the motion

of the dropped baskets, how much displacement is required, what residual capacity of

the assembly is to resist static blowdown forces and the dynamic forces on the support

structure.

Based on the results of this test and calculation of kinetic energy to which the

baskets could be exposed, the licensee concluded that ice baskets would not become

missile hazards.

The FSAR Appendix M, Section 3.1.4 provided the original design criterion and load,

factors for the ice baskets.

The licensee testing and analysis had accepted plastic

22

ll

deformation (displacement) of the ice basket bottom rim assembly without applying

design bases lateral loads, which was outside the original ice basket design basis

described in Appendix M of the FSAR. Further, the licensee analysis incorporated the

results from a single load test, which may not represent the bounding case, nor provide

an adequate statistical design basis.

Section 3.1.5 of Appendix M required in part, that

the licensee obtain AEC (now NRC) approval for analysis criterion other than previously

accepted by the AEC in Section 3.1.4 of Appendix M. As of February 27, 1998, the

licensee had not submitted their July 27 and August 13, 1992 analysis for ice baskets

with failed filletwelds to the NRC for evaluation.

Inspectors concluded that as of February 27, 1998, the licensee had not taken adequate

corrective actions as discussed above for this condition adverse to quality. Specifically,

the licensee failed to apply the applicable FSAR design criteria or seek NRC approval of

the alternative analysis used in the engineering evaluation (dated July 27 and August

13, 1992) that accepted the affected ice baskets.

Failure to implement adequate

corrective actions for this condition (ice baskets with flawed/failed filletwelds) adverse to

quality is an apparent violation of 10 CFR 50 Appendix B, Criterion XVI

(EEI 50-315/98005-18(DRS);

EEI 50-316/98005-18(DRS)).

In a letter dated August 31, 1992, the licensee documented that a four hour event

notification pursuant to 10 CFR 50.72(b)(2)(i) requirements was made on August 4,

1992 for the ice baskets found in this condition.

In this letter the licensee also stated

"Since duplicate reporting is discouraged by the NRC, a separate

Part 21 Notification

was not made." The licensee concluded that their analysis demonstrated

that the

baskets'with degraded welds would not become missile hazards and thus, this condition

was not reportable and recommended

retraction of the NRC notification made on

August 4, 1992.

However, as discussed above, this condition was outside the original

design basis for the ice baskets and the 10 CFR 50.72 event notification appeared

valid. Thus, for the failed basket welds caused by manufacturing defects, inspectors

were concerned that 10 CFR 50.72 and 10 CFR 21 reporting requirements had not

been properly evaluated.

Inspectors considered this an unresolved item pending

review of the licensee basis of the applicability of these requirements to this

issue'URI

50-315/98005-19(DRS);

URI 50-316/98005-19(DRS)).

Conclu 'ons

n Corrective Actions for Ice Cond nser C m

ts

Inspectors identified four apparent violations of 10 CFR 50 Appendix B, Criterion XVI,

for the licensee's failure to identify and correct conditions adverse to quality on ice

condenser components.

Specifically, these violations pertained to the licensee's failure

to: implement prompt corrective actions for missing ice basket sheet metal screws,

implement effective corrective actions to prevent recurrence of loose U-bolt nuts and

separated

ice baskets, and take appropriate corrective actions for the ice baskets with

defective hold down bar welds.

Collectively, the corrective action violations identified in

Sections M2.1 and this section represent a breakdown in the corrective action program

for the ice condenser..

23

(J

l

j,',

fl

E7

Additionally, the inspectors identified an unresolved item pertaining to the licensee's

application of 10 CFR 50.72 and 10 CFR 21 reporting requirements associated with the

failed basket hold down bar filletwelds.

Quality Assurance in Engineering Activities

E7.1

in

n

fh

I

n

B

In

in

77

Inspectors reviewed select analyses and modifications made to ice condenser

components since original construction and reviewed the current description of the ice

condenser in Section 5.3.3 and Appendix J and M of the FSAR.

b.

rv tin

n

Fin

b.1

D

i Ba'fr

C

10 CFR 50.71(e) requires in part that the licensee periodically update the FSAR as

originally submitted in the application for an operating license.

Appendix J and M of the

FSAR were submitted as part of the FSAR in the original license application for D.C.

Cook.

Inspectors identified that these appendices

had not been updated over the life of

the plant. The licensee issued CR 98-0444 to document the failure to update the FSAR,

Appendix M..

The cover page for Appendix J and M of the FSAR stated that "The appendix is

presented as information current during the OL [Operating License) review, and is

reproduced as an historical record." These appendices

contained the detailed original

design description and analysis for the ice condenser.

Due to the licensee's failure to

maintain these appendices

current, the design basis and descriptions of ice condenser

components had become out of date.

Inspectors identified specific analysis and

modifications affecting the design basis or original ice condenser component

descriptions, which had not been incorporated into Appendix J or M of the FSAR as

discussed

below.

b.1.1 WCAP-11902 "Reduced Temperature and Pressure Operation for Donald C. Cook

Nuclear Plant Unit 1 Licensing Report," dated October 1988, was used as the basis to

establish an upper allowable limitfor ice condenser fiow passage

blockage, which the

licensee incorporated into 12 THP 4030 STP.211 (currently 12 EHP 4030 STP.211).

As of February 27, 1998, the analysis limits established

in WCAP 11902 for the ice

condenser had not been incorporated into Appendix M or J of the FSAR. Failure to

incorporate ice condenser flow passage

blockage limits as established

in

WCAP-11902 into the FSAR is an apparent violation of 10 CFR 50.71(e)

(EEI 50-315/98005-20(DRS);

EEI 50-316/98005-20(DRS)).

b.1.2 The FSAR, Appendix M, Figure 6.4.1 details the configuration of the ice basket bottom

rim assembly.

A bolted rectangular tube support is depicted in this drawing, vice the as-

24

built solid hold down bar support attached with filletwelds for ice baskets in the plant.

As of February 27, 1998, the licensee has not updated Figure 6.4.1 to match the as-built

configuration.

Failure to update the FSAR to incorporate the as-built ice basket

configuration is an apparent violation of 10 CFR 50.71(e) (EEI 50-315/98005-21(DRS);

EEI 50-316/98005-21(DRS)).

b.1.3 The FSAR, Appendix M, Section 1.1 described the form of ice used to fillice baskets as

2 inch by 2 inch by 1/8 inch flake ice. Further, Section 5.3.3 of the FSAR stated that

long-term ice storage tests have shown that the ice can be stored without significant

weight loss or physical distortion. Contrary to this description, since the beginning of

commercial operation, the ice baskets have been refilled with ice in course granular

form, which had sublimated into a solid mass of ice for baskets not recently filled. As of

February 27, 1998, the licensee has not updated these FSAR sections to reflect the

actual form of ice used.

Failure to update the description of the ice form in the FSAR

to match the as-used

ice form is an apparent violation of 10 CFR 50.71(e) (EEI

50-315/98005-22(DRS);

EEI 50-316/98005-22(DRS)).

b.1.4 The licensee modified a Unit 2 ice basket 2-3-8 in February of 1989, by adding 4 pipe

structural supports and a cable under modification 02-MM-032. As of February 27,

1998, the licensee had not updated the ice basket descriptions in Appendix M of the

FSAR to identify this modified Unit 2 ice basket.

Failure to update the FSAR

descriptions for this modified ice basket is an apparent violation of 10 CFR 50.71(e)

(EEI 50-316/98005-23(DRS)).

b.1.5 The licensee modified Unit 1 ice baskets 12-2-4, 12-84, 14-7-8, 3-3-9, 1-7-9, 13-7-9,

16-7-9 and 18-7-9, in July of 1989 by adding 4 pipe structural supports and a cable to

each ice basket under modification 01-MM-048. As of February 27, 1998, the licensee

had not updated the ice basket description in Appendix M of the FSAR to identify these

modified Unit 1 ice baskets.

Failure to update the FSAR descriptions for this modified

ice basket is an apparent violation of 10 CFR 50.71(e) (EEI 50-315/98005-24(DRS)).

b.1.6 Westinghouse letter "Indiana Michigan Power D.C. Cook Nuclear Power Plant Ice

Condenser Seismic Load Study New Ice Basket Design," dated February 28, 1990,

was used as the basis to establish the maximum gross basket weight limitof 1877 Ibs,.

which the licensee incorporated into 12 THP 4030 STP.211 "Ice Condenser

Surveillance" (currently 12 EHP 4030 STP.211).

As of February 27, 1998, the

licensee had not updated data in table 4.3-1 of Appendix M of the FSAR, that reflect a

maximum analyzed gross ice basket weight limitof 1776 lbs. Failure to update the

FSAR sections to incorporate the revised maximum analyzed gross ice basket weight

is an apparent violation of 10 CFR 50.71(e) (EEI 50-315/98005-25(DRS);

EEI 50-316/98005-25(DRS)).

b.1.7 On October 14, 1992, the licensee authorized the use of Westinghouse drawings

1851E35, Revision 7 and 1880E22, Revision 6 to construct replacement ice baskets

from short 2 or 3-foot segments, vice the original 12-foot segments described in

Appendix M of the FSAR. This change in ice basket design resulted in a heavier ice

basket with more coupling joints and sheet metal screws.

As of February 27, 1998, the

25

~

'

lj

licensee failed to revise the FSAR, Appendix M, to incorporate the change made to

replacement Unit 1 and 2 replacement ice baskets fabricated from short ice basket

subassemblies

(2 or 3-foot segments).

'Failure to update the FSAR to incorporate the

replacement ice basket design is an apparent violation of 10 CFR 50.71(e)

(EEI 50-315/98005-26(DRS);

EEI 50-316/98005-26(DRS)).

b.2

Un

hori

M

ifi

ti n fl

B

A

Inspectors identified modiTications to Unit 1 and Unit 2 ice baskets which had been.

installed without following established design control processes.

Between February 14 through 17, 1998, licensee staff conducted inspections of

accessible areas of the lower ice basket to identify damage and nonconforming

conditions in response to missing screws and other basket damage discussed

herein.

From a preliminary list of damaged baskets created by licensee staff during this

inspection, the inspectors identified and visually confirmed unauthorized modifications

made to Unit 1 and Unit 2 ice baskets as discussed

below.

b.2.1 On February 19, 1998, inspectors identified that Unit 1 ice baskets 4-1-9, 5-9-1 and

20-3-6 had a galvanized bolt installed in place of the clevis pin that connected the ice

basket to the support structure.

The licensee was unaware of when this modification

was installed, since it had not been authorized.

Failure to followestablished design

control processes. for this modification to these ice baskets is an apparent violation of

10 CFR 50 Appendix B, Criterion III (EEI 50-315/98005-27(DRS);

EEI 50-316/98005-27(DRS)).

b.2.2 On February 19, 1998, inspectors identified that Unit 2 ice basket 1-7-9 had a six inch

wide curved sheath of sheet metal installed onto the ice basket mesh, beginning just

above the bottom of the ice basket and running vertically upwards as far as could be

seen (greater than 12 feet). The licensee was unaware of when this modification was

, installed, since it had not been authorized. Failure to followestablished design control

processes

for this modification to ice basket 1-7-9 is an apparent violation of 10 CFR 50

Appendix B, Criterion III (EEI 50-315/98005-28(DRS);

EEI 50-316/98005-28(DRS)).

b.2.3 On February 19, 1998, inspectors identified that Unit 2 ice basket 14-6-8 had 9 rivets

installed in place of sheet metal screws in the bottom ice basket rim coupling. The

licensee was unaware of when this modification was installed, since it had not been

authorized.

Failure to follow established design control processes

for this modification

to ice basket 14-6-8 is an apparent violation of 10 CFR 50 Appendix B, Criterion III

(EEI 50-315/98005-29(DRS);

EEI 50-316/98005-29(DRS)).

At the conclusion of the inspection period, the licensee had not determined the potential

safety consequences

for past plant operation with these unauthorized modifications.

26

J

'

b.3

Surv

ill n ePr

ce

r

U edt Mod'nd Rem v

I

B

k t

ru if rmSu

orts

The ice basket cruciform supports attach to the coupling and stiffening ring locations (at

six foot intervals) and prevent ice in the basket's from displacing axially in the event of a

loss of ice by sublimation or due to accident conditions.

On November 18, 1988, the licensee initiated a modification RFC-DC-12-1937 to

change the design or remove cruciform supports from ice baskets in,Unit 1 and Unit 2.

A licensee letter dated January 31, 1990, documented that drawings for ice baskets

modified in this manner would not be updated because

these drawings were not

retained by the licensee and the drawings in this modification package would serve as

the permanent plant record for the affected ice baskets.

After closure of RFC-DC-12-1937, the licensee changed Attachment 4 and 5 of

12 EHP 4030 STP.211 (formerly 12 THP 4030 STP.211) to authorize changing basket

cruciforms or deletion of cruciforms.

Specifically, Attachment 4 and 5 of this procedure

allowed deletion of the bottom three cruciforms from Radial row 7, 8 or 9 ice baskets

and/or the installation of replacement cruciforms of a new design.

These modifications

were not required to be updated on the ice basket drawings.

On February 3, 1998, the inspectors requested

a list of all baskets with cruciform

supports that had been deleted or modified during performance of 12 EHP 4030

STP.211.

As of February 27, 1998, the licensee was unable to compile a list of ice

baskets modified under 12 EHP 4030 STP.211, due to the extensive resources required

to review the previous surveillance test data to identify the modified ice baskets.

The inspectors concluded that the open ended modification process authorized in

12 EHP 4030 STP.211, did not ensure that updated drawings were maintained for the

specific ice baskets with deleted or modified cruciform supports.

10 CFR 50 Appendix

B, Criterion III requires in part that controls will be in place to ensure that modifications

are controlled....

In this case the licensee chose not to maintain current drawings of ice

baskets with the modified cruciform design.

Further, the use of a surveillance procedure

to perform modifications was outside of the licensee's established design control

process.

Failure to followthe existing design control processes

in modification of ice

basket cruciforms is an apparent violation of 10 CFR 50 Appendix B, Criterion III

(EEI 50-315/98005-30(DRS);

EEI 50-316/98005-30(DRS)).

e

'ntnn

t

Ic

on

nerDeinB

is

Inspectors identified seven apparent violations of 10 CFR 50.71(e) pertaining to the

licensee's failure to update the FSAR Appendices J or M which contained the detailed

description and design basis for the ice condenser.

Additionally, inspectors identified

four apparent violations of 10 CFR 50 Appendix B, Criterion III, pertaining to the

licensee's failure to follow the established design control process for ice basket

.

modifications. Collectively, these apparent violations represent a programmatic

breakdown in the maintenance of the design basis for the ice condenser.

27

.~

~

p

~

'

I

E7.2

0

ra ilit in

ti fr eA-F un

n

n

r

nd'i

The ice condenser was degraded to a poor state of materiel condition, such that the

operability of the ice condenser was in question (Section M2.1). The licensee had

issued a condition report 98-0388 to document all damage to ice baskets, including

damage previously identified. As part of the investigation for this condition rep'ort, the

licensee had reportedly contracted with Westinghouse to undertake an assessment

of

the overall ice condenser operability for the as-found condition of the ice condenser.

Pending review of the licensee's evaluation of past plant operation with the ice

condenser

in the as-found state, inspectors considered this an unresolved item

(URI 50-315/98005-31(DRS);

URI 50-316/98005-31(DRS)).

E8

Miscellaneous Engineering Issues (92700)

E8.1

I L'v

L

-

1

4-: Interim LER- Restricted Ice

Condenser Flow Passages

Found to Constitute an Unanalyzed Condition, issued,

February 23, 1998.

This issue was reported to the NRC on January 22, 1998, pursuant to requirements of

10 CFR 50.72(b)(2)(i) and is discussed

in Sections M1.1.b.1 and M2.1.b.1. The impact

of this condition on the as-found condition of the ice condenser for past plant operations

will be assessed

by the licensee and tracked by the NRC in resolution of an unresolved

'tem

(URI 50-315/98005-31(DRS);

URI 50-316/98005-31(DRS)).

Therefore, this LER is

closed.

E8.2

Cl

ed

Li

R

o

LE

-

1

-: InterimLER-Lackof

Adequate Number of Screws in Ice Basket Coupling Rings Determined to Constitute

Unanalyzed Condition, issued February 23, 1998.

This issue was reported to the NRC on February 14, 1998, pursuant to requirements of

10 CFR 50.72(b)(2)(i) and is discussed

in Section E2.1.b.1.2.

The impact of this

condition on the as-found condition of the ice condenser for past plant operations will be

assessed

by the licensee and tracked by the NRC in resolution of an unresolved item

(URI 50-315/98005-31(DRS);

URI 50-316/98005-31(DRS)).

Therefore, this LER is

closed.

E8.3

Clo ed

Lic n e

vent R

L

0-

5

0 6-: InterimLER-Procedure

Option for Weighing of Ice Baskets in Modes 3 and,4 Determined to be a Potentially

Unanalyzed Condition, issued March 3, 1998.

This issue was reported to the NRC on February 25, 1998, pursuant to requirements of

10 CFR 50.72(b)(2)(i) and is discussed

in Section M1.1.b.2.2.

The failure of the

licensee to provide adequate instructions for entry into an unanalyzed condition

(unpinning 60 ice baskets) is considered an apparent violation of 10 CFR 50 Appendix

B, Criterion V (EEI 50-315/98005-05(DRS);

EEI 50-316/98005-05(DRS)).

Corrective

actions will be addressed

by the licensee in resolving this violation, therefore, this LER is

closed.

28

'J

4

p I

Cl

E8.4

I

Li en

Ev n R

rt LER

5 -31 /

0 7-0: Interim LER-Ice Condenser

Weights Used to Determine Technical Specification Compliance Not Representative

This issue was reported to the NRC on February 11, 1998, pursuant to requirements of

10 CFR 50.72(b)(2)(i) and is discussed

in Section M1.1.b.2.4. The failure of the

licensee to select a representative

sample of ice baskets to weigh is a violation of TS 4.6.5.1.b.2 (EEI 50-315/98005-07(DRS);

EEI 50-316/98005-07(DRS)).

Corrective

actions willbe addressed

by the licensee in resolving this violation, therefore, this LER is

closed.

E8.5

Clo e

Li

n e

Ev nt R

o

L R

-

1

9

0 - OFailureof Ice Baskets to

Withstand Simulated Accident Loadings During Testing Results in Unanalyzed Condition

This issue was reported to the NRC on February 12, 1998, pursuant to requirements of

10 CFR 50.72(b)(2)(i) and is discussed

in Section M2.1.b.3. The failure of the licensee

to identify/evaluate buckled webbing in lower section of ice baskets is a violation of TS 4.6.5.1.b.2 (EEI 50-315/98005-13(DRS);

EEI 50-316/98005-13(DRS)).

Corrective

actions willbe addressed

by the licensee in resolving this violation, therefore, this LER is

closed.

X1

Exit Meeting Summary

The inspectors presented the inspection results to members of licensee management at the

conclusion of the inspection on February 27, 1998, and in a final phone exit held March 19,

1998. The licensee acknowledged the findings presented

and did not identify any of the

potential report input as proprietary.

29

III

I

!

I

il

t

0

PARTIALLIST OF PERSONS CONTACTED

Ameri

n

I

ri

P wr

A. Blind, Vice President Nuclear Engineering

J. Boesch, Maintenance Superintendent

D. Cooper, Plant Manager

S. Farlow, Supervisor l&C Engineering

M. Finissi, Supervisor, Electrical Systems

E. E. Fitzpatrick, Executive Vice President Nuclear Generation Group

D. Hafer, Manager, Plant Engineering

M. Kelly, Nuclear Licensing

B. Kovarik, Safety-related Mechanical Systems

F. Pisarsky, Supervisor, Mechanical Component Engineering

J. Sampson, Site Vice President

P. Schoepf, Supervisor, Safety-related Mechanical Systems

D. Sudhoff, Safety-related Mechanical Systems

A. Tetslaff, Safety-related Mechanical Systems

S. Wolf, Performance Assurance

Duk

P w rC

n

B. Lamb

D. Myer

R. Proctor

mri

nN

I

L. Demski

M. Poluhanyiz

We

'n

J. Matusz

S. McKenzie

C. Scrabis

othBnd

i

J. Swidwa

Hrld

II

i

S. Aiken

K. Kamps

N. Lee

30

I

q

F

'I

INSPECTION PROCEDURES USED

IP 37700

IP 61700

IP 62700

IP 92700

IP 92720

Design Changes and Modifications

Surveillance Procedures

and Records

Maintenance Program Implementation

Onsite Review of LERs

Corrective Action

ITEMS OPENED, CLOSED, AND DISCUSSED

ITE

OP

NED

50-315/98005-01(DRS)

50-316/98005-01(DRS)

50-315/98005-02(DRS)

50-316/98005-02(DRS)

50-315/98005-03(DRS)

50-316/98005-03(0RS)

50-315/98005-04(DRS)

50-316/98005-04(DRS)

50-315/98005-05(DRS)

50-316/98005-05(DRS)

50-31 6/98005-06a(DRS)

50-315/98005-06b(DRS)

50-315/98005-07(DRS)

50-316/98005-07(DRS)

50-315/98005-08(DRS)

50-316/98005-08(DRS)

50-315/98005-09(DRS)

50-316/98005-09(DRS),

50-315/98005-10(DRS)

50-316/98005-10(DRS)

50-315/98005-11(DRS)

50-316/98005-11(DRS)

50-315/98005-12(DRS)

50-316/98005-12(DRS)

EEI

EEI

EEI

EEI

EEI

EEI

EEI

EEI

EEI

EEI

EEI

EEI

EEI

Inadequate instructions for inspection of flow

passages

Inadequate instructions for selecting flow

passages

Insufficient margin to analysis limitfor evaluating

a degraded

ice condenser

Insufficient margin to analysis limitfor maximum

gross ice basket weight

Inadequate instructions for entry into an

unanalyzed condition (unpinning 60 ice baskets)

Failure to followthe procedure change process

for a completed surveillance test

Failure to followthe procedure change process

for a completed surveillance test

Failure to select a representative

sample of ice

baskets to weigh per TS 4.6.5.1.b2

Failure to assess

and control the quality of work

by ice condenser contractors

Failure to inspect accessible areas of the lower

ice basket per TS 4.6.5.1.d

Insufficient margin to TS 4.6.5.3.1.b limitfor

lower ice inlet door opening torque

InsUfficient margin to TS 4.6.5.3.2.b limitfor

intermediate deck door opening force

Failure to identify/evaluate missing ice segments

in lower section of ice baskets

31

J

t'

ITEMS OPENED

50-315/98005-13(DRS)

50-316/98005-13(DRS)

50-315/98005-14(DRS)

50-316/98005-14(DRS)

50-315/98005-15(DRS)

50-316/98005-15(DRS)

50-315/98005-16(DRS)

50-316/98005-16(DRS)

50-315/98005-17(DRS)

EEI

EEI

EEI

EEI

EEI

Failure to identify/evaluate buckled webbing in

lower section of ice baskets

Failure to identify/evaluate fibrous material in the

ice condenser

Failure to promptly identify/evaluate missing ice

basket sheet metal screws

Failure to prevent recurrence of loose U-bolt

nuts

Failure to prevent recurrence of separated

ice

baskets

50-315/98005-18(DRS) 'EI

50-316/98005-18(DRS)

Failure to take prompt effective corrective action

ice baskets with failed filletwelds

50-315/98005-19(DRS)

50-316/98005-19(DRS)

50-315/98005-20(DRS)

50-316/98005-20(DRS)

50-315/98005-21(DRS)

50-316/98005-21(DRS)

50-315/98005-22(0RS)

50-316/98005-22(DRS)

50-316/98005-23(DRS)

50-315/98005-24(DRS)

50-315/98005-25(DRS)

50-316/98005-25(DRS)

50-315/98005-26(DRS)

50-316/98005-26(DRS)

50-315/98005-27(DRS)

URI

EEI

EEI

EEI

EEI

EEI

EEI

EEI

EEI

Applicabilityof 10 CFR 50.72 and 10 CFR 21

reporting requirements to the ice baskets with

failed filletwelds

WCAP-11902 analysis not incorporated into the

FSAR per 50.71e

As-built ice basket bottom assembly not

incorporated into the FSAR per 50.71e

As-used ice form not incorporated into the FSAR

description per 50.71e

Ice basket modified by 02-MM-032 not

incorporated into the FSAR description per

50.71e

Ice baskets modified by 01-MM-048 not

incorporated into the FSAR description per

50.71e

Westinghouse

ice basket seismic load study,

dated February 28, 1990 not incorporated into

the FSAR per 50.71e

Revised replacement ice basket design not

incorporated into the FSAR per 10 CFR 50.71e

Unauthorized modification (bolt vice pin) installed

in three Unit 1 ice baskets

32

,

II

<

e

I

ij

I

TEM

QP

NED

50-316/98005-28(DRS)

50-316/98005-29(DRS)

50-315/98005-30(DRS)

50-316/98005-30(DRS)

50-315/98005-31(DRS)

50-316/98005-31(DRS)

EEI

EEI

EEI

URI

Unauthorized modification (sheath of sheet

metal) installed on a Unit 2 ice basket.

Unauthorized modification (rivets vice screws)

installed on a Unit 2 ice basket.

Failure to follow design controls for ice basket

cruciform modifications

As-found operability of ice condenser

in question

for past plant operation

I

E

L

ED

50-315/98004-00

50-315/98005-00

50-315/98006-00

50-315/98007-00

50-315/98008-00

ITEMS D S

S

LER

LER

LER

LER

LER

t

Restricted ice condenser flow passages

found to

constitute an unanalyzed condition

Lack of an adequate number of screws in the ice

basket coupling rings an unanalyzed condition

Procedure option for weighing of ice baskets in

Modes 3 and 4 determined to be a potentially

unanalyzed condition

Ice condenser weights used to determine TS

compliance not representative

Failure of ice baskets to withstand simulated

accident loadings during testing results in an

unanalyzed condition

None

33

4'

J

$ t

(

'i

LIST OF ACRONYMS

CFR

CR

DBA

DRP

DRS

EEI

FSAR

LER

NRC

OL

PDR

PR

STP

TS

FSAR

URI

Code of Federal Regulations

Condition Report

Design Basis Loss of Coolant Accident

Division of Reactor Projects

Division of Reactor Safety

Escalated Enforcement Item

Final Safety Analysis Report

Licensee Event Report

Nuclear Regulatory Commission

'Operating License

Public Document Room

Problem Report

Surveillance Test Procedure

Technical Specification

Updated Final Safety Analysis Report

Unresolved Item

34

lg

f;l

I>

II

PARTIALLIST OF DOCUMENTS REVIEWED

~Proc ~r

EP-10 "Ice Basket Installation Procedure," Revision 2.

12 CHP 5021.MCD.004 "Removal and Replacement of Ice Condenser Baskets," Revision 2.

PMI-2010 "Instructions, Procedures,

and Associated Indexes Policy," Revision 24.

12 EHP 4030 STP.250 "Inspection of Ice Condenser Flow Passages,"

Rebision 1.

12 EHP 4030 STP.211 "Ice Condenser Surveillance," Revision 2.

12 EHP 4030 STP.212 "Ice Condenser Basket Inspection," Revision 0.

12 EHP 4030 STP.207 "Ice Condenser Lower Inlet Doors," Revision 0.

12 EHP 4030 STP.245 "Inspection of Ice Condenser Intermediate Deck Doors," Revision 0.

12 EHP 4030 STP.246 "Inspection of Ice Condenser Floor Drain Valves," Revision 0.

12 THP 6020 CHM.106 "IceCondenser," Revision 0.

Probl

or

nditi n

ort

PR-87-0163- Bay 11 intermediate deck door inoperable due to ice.

PR-87-0176- More than 3/8 inch of ice was found on ice condenser structure in bay 1 and bay

11 rows 8 and 9.

PR-87-0465- In Unit 2 upper containment ice condenser,

two center intermediate deck doors

were frozen shut by accumulated

ice.

PR-87-0466- The intermediate deck doors between air handler units 42A, 43A, 42B, and 43B

were found frozen shut by ice'uildup.

PR-87-0467- Start of ice build-up on Unit 1 ice condenser doors.

PR-87-0804- More than 3/8 inch of ice/frost was found in the ice bed in rows

1 and 9 bays

3,4,8,11 and 17 during flow passage

inspection.

PR-88-0146- During testing of Unit 1 ice condenser intermediate deck doors, 7 of 192 doors

failed to meet the opening acceptance

criteria.

PR-88-0215- More than 3/8 inch of ice/frost was found in bay 4 between rows

1 and 2 baskets.

PR-88-0427- The chemical sections current practice is to analyze an individual sample on a

weekly basis, combining of the samples isn't performed as required by technical specifications.

PR-88-0624- 12 THP 4030 STP.207 did not have proper documentation for declaring the ice

condenser inoperable during the testing of the lower inlet doors.

PR-88-0902- Chemical analysis on the ice condenser indicated that the boron concentration

was below the TS limits.

PR-88-0914- Several ice condenser baskets have webbing damage.

PR-89-0458- Damage to ice condenser baskets caused by ice basket weighing.

PR-89-0908- An ice basket in bay 21 has PH and boron concentration below TS.

PR-89-1 239- Inadequate procedure guidance in 12 THP 4030 STP.211 ice condenser

surveillance.

The maximum basket weight was in error.

PR-89-1368- 6/1 3/86 memorandum incorrectly stated the maximum ice basket weight limit.

PR-90-0313- Loose chunk of ice found on one flow passage.

PR-90-0817- Ice condenser lower inlet doors blew open.

. PR-90-0979- Ice condenser divider barrier seal had numerous cracks.

PR-90-1016- Discrepancy with plant drawings and FSAR concerning installation of ice

condenser divider barrier seals.

PR-90-1 326- Five Unit 1 intermediate deck doors stuck shut.

35

4-'

4'

1z

PR-90-1639- Broken U-bolt and missing nuts in Unit 1 and 2 ice condensers.

PR-90-2064- Ice condenser bed inoperable due to maximum bed temperature above 27

degrees.

PR-91-0171- Lower 95 percent confidence limitof boron concentration less than TS.

PR-91-'0257- Unit 2 ice condenser bed inoperable due to bed temperature above 27 degrees.

PR-91-0330- Flow path bypassing the ice condenser bed would exist during accident.

PR-91-0745- Unit 2 ice condenser intermediate deck doors frozen shut.

PR-91-1206- Areas not inspected for flow blockage during TS surveillance.

PR-92-0360- Two ice baskets found in Unit 2 missing U-bolt nuts.

PR-92-1181- Unit 1 ice basket bottom cross bar displaced into basket bottom on four baskets.

PR-92-1386- Ice condenser basket U-bolt nuts missing or loose.

CR-93-0488- Ice condenser intermediate deck door 4A frozen shut.

CR-93-0524- Ice condenser intermediate deck door frozen shut.

CR-93-1242- Five intermediate deck doors frozen shut.

CR-94-0075- Intermediate deck door frozen shut.

CR-94-0398- Unit 1 debris in ice baskets and basket ligament damage.

CR-94-0427- Five ice baskets exceeded

maximum allowed weight.

CR-94-0744- Ice condenser intermediate deck door 8B failed surveillance test.

CR-94-1825- Debris found in ice condenser floor drains.

CR-94-1894- Calibration documentation not available for ice basket weighing.

CR-94-1902- Three ice baskets exceeded

maximum allowed weight.

CR-95-1482- Debris found in ice condenser floor drain.

CR-95-1666- Ice basket retainer beam unsecured.

CR-96-0253- Ice condenser intermediate deck door 9A failed surveillance test.

CR-96-0355- Debris fell into ice basket.

CR-96-0708- Extra displaced cruciforms found in bottom of ice baskets.

CR-96-0875- Two intermediate deck doors frozen over.

CR-96-1611- Ice buildup behind plexiglass.

CR-96-2114- Loose tape on ice condenser top deck doors.

CR-97-0370- Debris found in ice condenser.

CR-97-0554- Three feet of ice basket separated

during weighing.

CR-97-2010- Unit 2 ice condenser top deck doors inoperable due to blockage by maintenance

equipment.

CR-97-2569- Ice condenser stage working fluid not in accordance with FSAR.

CR-97-2655- Duct tape inside ice condenser.

CR-97-2730- Discrepancy between FSAR and TS value for boron concentration.

CR-97-2806- Gray duct tape in the Unit 2 ice condenser.

CR-97-3244- Damaged Unit 2 ice basket had missing screws in bottom rim.

CR-97-3423- Intermediate deck doors 9A and 20B failed to meet acceptance

criterion.

CR-98-0076- Intermediate deck door 19G failed acceptance

criterion.

CR-98-0077- Debris found in upper ice condenser.

CR-98-0126- Damaged lower inlet door shock absorbers.

CR-98-0268- Gray duct tape found in Unit 2 lower ice condenser.

CR-98-0306- Four ice basket screw heads found in ice melt system filter.

CR-98-0357- Loose tape on ice condenser top deck doors.

M difi

ti n

36

02-MM-032- Repair damaged Unit 2 ice basket 2-3-8.

01-MM-048 - Repair of eight damaged Unit 1 ice baskets.

12-PM-299 - Modify piping on boron solution pump.

RFC-DC-12-762 - Add valve and drain line for air handling units.

RFC-DC-12-943 - Lower ice condenser door seal test.

RFC-DC-01-1272 - Install foam strip to lower ice condenser inlet doors.

RFC-DC-12-1478 - Replace ice condenser door seals.

RFC-DC-12-1576 - Modifyice condenser lower access door.

RFC-DC-12-1670 - Replace ice condenser glycol valves.

RFC-DC-12-1702- Replace ice condenser lower door frame plate.

RFC-DC-01-1762 - Replace lower ice condenser door adjustment spring.

RFC-DC-12-4049 - Replace fabric on ice condenser deck doors.

n

I si

an

Ev

I

ti

WCAP - 8304 "Stress and Structural Analysis and Testing of Ice Baskets," dated May 1974.

WCAP - 8887."Ice Basket Stress Analysis - D.C. Cook," dated March 1977.

WCAP-11902 "Reduced Temperature and Pressure Operation for Donald C. Cook Nuclear

Plant Unit 1 Licensing Report," dated October 1988.

Westinghouse letter "Indiana Michigan Power D.C. Cook Nuclear Power Plant Ice Condenser

Seismic Load Study New Ice Basket Design," dated February 28, 1990.

37

if

Iil