Rev 3 of Pump Inservice Test Program.
ML17334B482
Person / Time
Site: Cook  American Electric Power icon.png
Issue date: 04/02/1993
From:
INDIANA MICHIGAN POWER CO. (FORMERLY INDIANA & MICHIG
To:
Shared Package
ML17331A916 List:
References
PROC-930402, NUDOCS 9308020136
Download: ML17334B482 (4)


Text

DONALD C. COOK NUCLEAR PLANT UNITS NO. 1 AND 2 ASHE B 8. PV CODE SECTION XI Pump Inservice Test Program A. The pump test program shall be conducted in accordance with Section XI, Subsection IMP of the 1983 Edition of the ASHE Boiler and Pressure Vessel Code through Summer 1983 Addenda, except for specific code relief, requested in accordance with 10 CFR 50.55a(g)(5)(iii). Exemptions or amendments are identified in Code Relief Request I.

B. This pump test program is for the 2nd ten year inspection/test interval commencing July 1, 1986 for both Unit 1 and Unit 2.

C. The pump test program was developed employing the classification guidelines contained in Regulatory Guide 1.26, Revision 2 for guali ty Groups B and C, and the definition of the reactor coolant system boundary contained in 10 CFR 50.2 (v) for Group A. (guality Groups A, B, and C are the same as ASNE Class 1, 2, and 3, respectively). Using these guidelines and IWP-)100, the pump list attached as Table A was developed.

Table A identifies the following:

i. The pump number and service it performs along with the drawing identification number on which it is found. .

ii. The applicable test parameters:

1. Speed
2. Inlet Pressure
3. Differential Pressure determined as the difference between discharge and suction pressures
4. Flow Rate
5. Vibration Amplitude
6. Bearing Temperature 1

iii. The test frequency required.

Revision 3 Page 1 of 4 4/2/93 9308020f36 930727 PDR "ADOCK 05000315 P PDR

DONALD C. COOK NUCLEAR PLANT UNITS NO. 1 AND 2 PUMP INSERVICE TEST PROGRAM TABLE A PROGRAM

SUMMARY

TEST PARAMETERS Pump Inlet Differential Flow Vibration Bearing Test Service Pump Speed Pressure Pressure Rate Amplitude Temperature Frequency

{Drawing No.) Number N P. DP V Tb (1)

Auxiliary PP-3W No Yes Yes Yes Yes Yes Quar ter ly Feedwater PP-3E No Yes Yes Yes Yes Yes Quarterl (5106A) PP-4 Yes Yes Yes Yes Yes Yes Quar te Essential PP-7W No Yes Yes Yes Yes Yes Quarterly Service PP-7E No Yes Yes Yes Yes Yes Quarterly Water (5113)

Centrifugal PP-50W No Yes Yes Yes Yes Yes Quarterly Charging PP-50E No Yes Yes Yes Yes Yes Quarterly (5129)

Boric Acid PP-46-1 No Yes Yes Yes Yes Yes Quarterly Transfer PP-46-2 No Yes Yes Yes Yes Yes Quarterly (5131) PP-46-3 No Yes Yes Yes Yes Yes Quarterly PP-46-4 No Yes Yes Yes Yes Yes Quarterly Component PP-10W No Yes Yes Yes Yes Yes Quarterly Cooling PP-10E No Yes Yes Yes Yes Yes Quart Water (5135A)

Safety PP-26N No Yes Yes Yes Yes Yes Quarterly Injection PP-26S No Yes Yes Yes Yes Yes Quarterly

{5142)

Residual PP-35W No Yes Yes Yes Yes Yes Quarterly Heat Removal PP-35E No Yes Yes Yes Yes Yes Quarterly (5143)

Revision 3 Page 2 of 4 4/2/93

TEST PARAMETERS Pump Inl et Di fferenti al Fl ow Vibrati on Bearing Test Ser vice Pump Speed Pressure Pressure Rate Amplitude Temperature (Dr awing No.) Number N P. DP V Tb Frequency'ontainment PP-9M No Yes Yes Yes Yes Yes quarterly Sp.ay (5144) PP-9E No Yes Yes Yes Yes Yes quarterly Diesel Fuel gT-106-ABl No No No Yes 1 Yes No quarterly Oil Transfer gT-106-AB2 No No No Yes 1 Yes No quarterly (5151A & C) gT-106-CDI No No No Yes 1 Yes No quarterly gT-106-CD2 No No No Yes 1 Yes No quarterly Spent Fuel Pit PP-31N No Yes Yes Yes Yes Yes quart Cooling (5136) PP-31S No Yes Yes Yes Yes Yes quarter y Jacket Hater gT-130-AB1 No Yes Yes Yes Yes Yes quarter ly (5151B & D) gT-130-AB2 No Yes Yes Yes Yes Yes (}uarterly gT-130-CDI No Yes Yes Yes Yes Yes. quarterly gT-130-CD 2 No .Yes Yes Yes Yes Yes quarterly a These pumps are tested on test, bypass or minimum flow loops per Section XI Subarticle IMP-1400.

b Inlet pressure is in head of liquid, ft.

c Bearing temperatures will be measured annually, per Section XI IWP-3300, except as noted.

d These positive displacement pumps are tested in full accordance with ASME/ANSI OMa-1988 Addenda to ASME/ANSI Stan OM-1987, "Operation and Maintenance of Nuclear Power Plants", Part 6. Under Part 6, differential pressure and be g temperatures are not required test parameters for positive displacement pumps. Per Table A, Inservice Test Parameters, discharge pressure is the required test parameter rather than differential pressure for this type of pump. Reference values will be established for discharge pressure only. Code relief request for exemption from bearing temperature measurement is rescinded. Testing in accordance with Part 6 of ASME/ANSI OH-1987 is allowed per Regulatory Guide

1. 147, "Inservice Inspection Code Case Acceptability": Code Case N-465, "Alternate Rules for Pump Testing Section XI, Division 1".

(1) Refer to Code Relief Request I Revision 3 Page 3 of 4 4/2/93

DONALD C. COOK NUCLEAR PLANT UNITS NO. 1 AND 2 PUMP INSERVICE TEST PROGRAM CODE RELIEF REQUEST I Duration of Tests Request that the duration of pump operation for testing, per Section XI Subarticle IMP-3500, be amended for the Diesel Fuel Oil Transfer Pumps.

These pumps supply the diesel generator fuel oil day tank. A conservative level is maintained in the tank to meet the minimum capacity per Technical Specification requirements. Due to the limited capacity of this tank, the t test range is restricted. It is requested to record test parameters immediately after pump operation has stabi ize .

Revision 3 Page 4 of 4 4/2/93