ML17329A071

From kanterella
Jump to navigation Jump to search
Safety Insp Repts 50-315/91-12 & 50-316/91-12 on 910603-07. Violation Noted.Major Areas Inspected:Quality Verification Program,Including Peer Insp Process
ML17329A071
Person / Time
Site: Cook  American Electric Power icon.png
Issue date: 06/24/1991
From: Langstaff R, Lougheed V, Phillips M
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML17329A069 List:
References
50-315-91-12, 50-316-91-12, NUDOCS 9107010044
Download: ML17329A071 (11)


See also: IR 05000315/1991012

Text

U.S.

NUCLEAR REGULATORY COMMISSION

REGION III

Reports

No. 50-315/91012 (DRS); 50-316/91012 (DRS)

Docket Nos. 50-315;

50-316

Licenses

No. DPR-58;

DPR-74

Licensee:

Indiana Michigan Power

Company

1 Riverside Plaza

Columbus,

Ohio 43216

Facility Name:

Donald C.

Cook Nuclear Power Plant:

Inspection At:

Donald C.

Cook Plant Site,

Bridgman, Michigan

Inspection

Conducted:

June 3-7,

1991

Inspectors:

R. A. Langstaff

Da e

V. P.

Lo

eed

D te

Approved By:

M. P. Phil ips, Chief

Operational

Programs

Section

g z<t~(

Date

Ins ection

Summar

Ins ection

on June

3-7

-1991

Re orts No. 50-315

91012

DRS

. No.

50-316

91012

DRS

Areas Ins ected:

Routine unannounced

safety inspection of the

licensee

s quality verification program,

including the peer

inspection process.

This inspection utilized NRC inspection

module 35702.

Results:

One violation and two unresolved

items were identified.

The violation involved personnel

not being trained in their skill

area

as required by the licensee's

quality assurance

program

(Paragraph

3).

The unresolved

items dealt with the apparent

lack

of independence

of personnel

performing verification activities

for instrumentation

and control

(I6C) work (Paragraph

4),

and the

qualification of plant personnel to Regulatory Guide 1.8 and

ANSI N18.1

(1971)

(Paragraph

3).

Two weaknesses

were identified in the licensee's

program.

These

entailed:

(1) the lack of procedures

addressing qualification

requirements

for peer inspectors

in the I&C department,

and

(2) the ability of the Quality Control Department surveillances

to identify the above concerns with the peer inspections

process.

5'107010044

giOh24

PDR

ADOCK 05000315

6

PDR

These weaknesses

are discussed

in Paragraphs

2 and 5,

respectively.

DETAILS

1 ~

Persons

Contacted

Indiana Michi an Power

Com an

American Electric Power Service

Cor oration

AEPSC

A. Blind, Plant Manager

R. Allen, Regulation Supervisor,

Maintenance

K. Baker, Assistant Plant Manager,

Production

P. Carteaux,

Safety

& Assessment

Superintendent

L. Gibson, Assistant Plant Manger, Projects

E. Kincheloe, Training Superintendent

J. Rutrowski, Assistant Plant Manager,

Technical Support

T. Wagoner,

Maintenance

Supervisor

M. Wiederwax, Safety and Assessment,

QC/NDE Supervisor

K. Worthington,

AEPSC Site Quality Assurance

U.S. Nuclear

Re ulator

Commission

NRC

J.

Isom, Senior Resident Inspector

D. Passehl,

Resident Inspector

2 ~

All of the above personnel

attended

the exit meeting held on

June

7,

1991.

The inspectors

also interviewed other licensee

employees

during the course of the inspection.

ualit

Verification Procedures

The licensee controlled its quality verification program in

accordance

with its Quality Assurance

Program Description

(QAPD) Chapter 1.7.10,

"Inspection," dated

December

1990.

Specific implementation requirements

were addressed

in

Plant- Manager Instruction PMI-7090, ."Plant Quality Control

Program," dated June

1990.

The

QAPD provided an overview of the inspection process.

It

stated,

in part, that inspections

are performed by personnel

other than those

who perform the activity; inspections

are

performed by qualified personnel;

I&M personnel

who inspect

work are qualified in accordance

with Regulatory Guide 1.8

and ANSI N18,.1 (1971),

and are periodically trained in their

skill area using

INPO accredited training; and that peer

inspection personnel

are independent

in that they do not

perform or directly supervise

the work being inspected,

but

may be from the

same work group.

O

PMI-7090 expanded

upon the requirements

of the

QAPD. It

defined the terms verification, independent verification,

inspection,

and inspection hold point,

and outlined the

requirements for each.

For example, verifications were to

be performed by someone

other than the one who performed the

activity or otherwise established

the condition that was

being verified.

However,

a verifier could be a 'qualified

member of the

same work group.

For independent verifications,

PMI-7090 stated that the

person performing the independent verification was to be

disassociated

from those performing the task:by not being in

the area at the'ime the activity or condition was being

performed.

For cases

where two person

teams

were required

to perform the activity,

a second

team was required to do

the independent verification.

PMI-7090 further delineated

when an independent verifier was required

as

compared to a

verifier.

Examples

were:

removal

and return to service of

equipment

and systems

required by technical specifications

or equipment described in the safety analysis report and

credited with controlling the reactor or preventing or

mitigating an accident or transient.

Guidance regarding

who could perform a peer inspection

was

contained in Maintenance

Head Instruction MHI-7090,

"Maintenance

Department Inspection Hold Point Program,"

dated August 1987.

This procedure

only applied to the

inspection hold point portion of the peer inspection

process.

It specified that inspection hold points could

only be performed by:

a)

an independent

supervisor,

same

discipline,

b)

an independent

supervisor, different

discipline,

c)

an independent

maintenance

mechanic

A, same

discipline,

d)

an independent

maintenance

mechanic

A,

different discipline,

e)

an independent

maintenance

mechanic

B, or f) an independent

maintenance

engineer.

The applicability of these

requirements to other portions of

the peer inspection process

(verification, independent

verification, or inspections)

was not directly described in

either this procedure or other working level documents.

Additionally, the applicability to instrumentation

& control

(I&C) activities

(which were not covered under the

maintenance

department)

was not defined.

Lack of specific

lower level procedural

guidance

was considered to have

contributed to the deficiencies

found by the inspectors

regarding

I&C department

implementation of the peer

inspection

program

and was

a weakness

in the licensee's

program.

Trainin

and

uglification of Personnel

Performin

Peer

Ins ections

The inspectors

reviewed training records for selected

individuals whom the inspectors

had observed

performing

independent verification activities.

The inspectors

observed

performance of four I&C surveillances

on June

3 and

4,

1991.

For all of these surveillances,

the independent

verifications were performed by individuals who had not

completed the accredited training program as documented

on

their training matrix.

As part of the peer inspection process,

the licensee,

in its

QAPD, required all individuals performing quality

verification activities to be periodically trained in their

skill area using an accredited training program,

and to be

qualified in accordance

with ANSI-N18.1 (1971).

The accredited

program consisted of classroom

course work

followed by on-the-job training for specific tasks.

When

both sets of training had been completed,

the individual was

considered qualified.

Some individuals,

due to length of

service time when the program was initiated,

were waived

,from either the classroom training, the on-the-job training,

or both.

The status of an individual s qualifications was

tracked through

a training matrix.

The matrix indicated

whether

a person

was qualified through performance or

simulation of a specific task,

was waived,

had completed the

classroom training, or was unqualified.

10 CFR Part 50, Appendix B, Criterion II, "Quality Assurance

Program" states,

in part, that the licensee shall establish

a quality assurance

program which complies with the

requirements

of Appendix B.

This program shall be

documented

by written policies, procedures,

or instructions,

and shall be carried out throughout plant life in accordance

with those policies, procedures,

or instructions.

It

further states that the program shall take into account the

need for verification of quality by inspection

and test

and

shall provide for indoctrination and training of personnel

performing activities affecting quality as necessary

to

assure that suitable proficiency is achieved

and maintained.

The Indiana

and Michigan Power

Company Quality Assurance

'rogram

Description

(QAPD) is the policy by which Criterion

II is carried out.

Section 1.7.10.2.4 of the

QAPD, states,

in part, that personnel

who inspect work are qualified in

accordance

with Regulatory Guide 1.8 and ANSI N18.1 (1971),

and are periodically trained in their skill area.

The lack of completed training for these individuals is

considered

an example of a violation of the requirements

of

10 CFR Part 50, Appendix B, Criterion II, as implemented

by

the licensee's

QAPD.

(315/91012-01;

315/91012-01).

Interviews with I&C supervisors

revealed that the

supervisors

recognized that personnel

who performed

and

oversaw surveillances

needed to be qualified.

However, they

did not consider

such qualification necessary

for personnel

who performed the independent verifications,

and,

as such,

the practice of using personnel

who had not completed the

applicable qualification training for performing independent

verifications was accepted.

In contrast,

interviews with

supervisors

and training personnel

outside of the I&C

department

revealed that personnel

who performed independent

verifications in the maintenance

department

had to be

qualified in the task being verified.

In addition to the skill area training described

above,

specific training on peer inspections

was conducted for

maintenance

mechanics

and electricians.

This training was

comprised of a four hour classroom

course

and included

discussions on'lant commitments, qualifications necessary

to perform inspections,

independent

inspections,

and

condition/problem reports.

Similar. training was not

provided for I&C personnel,

as this department

was

considered

separate

from the maintenance

department at the

time of the training.

The inspectors

were unable to ascertain

from the training

records

reviewed,

whether

I&C personnel

had been trained in

accordance

with ANSI N18.1 (1971),

as required by QAPD

paragraph

1.7.10.2.4 for licensee

personnel

performing

inspections.

The licensee

was requested,

during the exit

meeting, to provide additional documentation to demonstrate

how this

QAPD requirement

was being met.

Pending

a review

of the results, this issue will be tracked

as

an unresolved

item (315/91012-02;

315/91012-02)

.

Inde endent Verification of Surveillance Activities

The inspectors

were concerned that the surveillance

activities performed within the IIC department

may not be

sufficiently independent

from the performance of the work

to meet regulatory

and

QAPD requirements.

The inspectors

observed

several

I&C surveillances

being

performed

on June

3 and 4,

1991 where the independent

verifications were performed by a member of the team doing

the work.

The majority of the surveillances

witnessed

were

routine technical specification surveillances;

however,

one

was performed following maintenance

on an inoperable

technical specification

component.

The inspectors

noted

that the normal practice for performance of independent.

verifications involved having one person

(of a two member

work team) monitor an indicator while the other team member

performed the activity, such

as racking in a breaker

on

'

back panel.

In the majority of cases

observed

by the

inspectors,

the independent verifier was in communication

with the person

who performed the activity, and was being

told what to expect by the person performing the work.

In

addition, the independent verifier did not have

a copy of

the procedure

step that was being verified.

The licensee

considered this to be independent

since the indicator was in

a different location than the breaker being manipulated.

In one case,

the lead technician stopped

work and informed

the junior technician that he would have to step out of

sight of the panel

so that the junior technician could

independently verify the lead

s activity.

The junior

technician

stepped

behind the panel

as told, returned

when

.called,

checked the switch position,

and then signed

as the

independent verifier.

The manner in which this activity was

performed led the inspectors to question whether the

technicians

were sufficiently qualified to perform

independent verification activities

(see Paragraph

3 above).

The inspectors

were also concerned

about the independence

of

the junior technician since

he clearly was taking direction

from the senior technician performing the work, and up to

that step,

had been working directly under the supervision

of the lead technician.

The inspectors

also observed

an example of maintenance

work

on a control circuit.

In this case,

two senior'evel

technicians

performed trouble-shooting activi'ties to

determine

why spiking was occurring.

Upon determining that

the leads to a potentiometer

needed to be removed, cut,

and

resoldered

in order to provide

a better connection,

the two

technicians

accomplished

the task with one holding the wire

in place while the other soldered.

In order to show that

the maintenance

had been effective, the technicians

then ran

a surveillance procedure,

which included independent

verification of the return to service of the component.

One

of the technicians

became the independent verifier by

watching the indicator light as the other technician racked

in the breaker to return the component to service.

Because

both technicians

had been actively involved in the

maintenance

work, the inspectors

did not, believe that they

could be considered

independent for this one step.

There

was no specific verification performed for the resoldering

activity.

The use of members of the team doing the work for inspection

activities did not appear to meet the licensee's

requirements

for ensuring that inspection personnel

not

perform or directly supervise

the work being inspected.

In the I&C department,

both supervisors

and personnel

repeatedly

stated that it was

common,

and acceptable,

to use

members of the

same

team for independent verification

activities.

Supervisors

and training personnel for the

mechanical

and electrical maintenance

department

indicated

that in their areas of responsibility independent

verifications were performed by individuals other than

members of the work team or their supervisor.

The

verification aspects

were considered to be separate

from the

requirements for inspections specified in Criterion X

of'ppendix

B to 10 CFR Part 50.

However, section 1.7.10.2.4

of the licensee's

QAPD specified that inspection personnel

not perform or directly supervise

the work being inspected.

As such,

the use of members

o'f the team doing the work for

inspection activities appeared to be contrary to this

QA

program requirement.

The licensee

was requested

to provide its justification for

the practice of utilizing persons

from the

same work team to

perform the work to also conduct the verification activities

met the requirements

of the

QAPD and Appendix

B to 10 CFR Part 50.

This is considered

an unresolved

item.

(315/91012-03;

316/91012-03).

ualit Verification Activities

In addition to the peer inspection process,

the licensee

maintained

a corporate Quality Assurance

(QA) function as,

well as

a plant Quality Control

(QC) capacity.

The role of

the corporate

group was to provide an overview of quality

assurance

programs at both the site and corporate offices.

The

QC group performed inspections

on any work performed by

organizations

other than the licensee (i.e., all work

performed by contractor personnel

was verified by the

QC

department rather than through the peer inspection process).

Additionally, the

QC department

performed periodic

surveillances

of specific work activities to monitor the

implementation of the peer inspection process.

The inspectors

reviewed the annual

QA audits of the site

inspection processes

for 1989 and

1990

(QA-89-12 and 90-12).

The audits were of acceptable

scope

and depth

and noted

several deficiencies,

especially in regard to training and

independent verification.

The inspectors

also reviewed

a

sample of twelve

QA surveillances

performed in the last six

months.

These surveillances

were more limited in scope,

and

tended to provide an overview of a specific work activity

rather than just the inspection process.

The

QA audits

and

surveillance'ppeared

to be adequate

in their overview

capacity.

However, the licensee's

Quality Control Department

surveillance activities associated

with the peer inspection

process failed to identify the concerns

found during this

inspection,

even though identical activities had been

inspected.

The inspectors

revi'ew of the 1991

QC

surveillances

determined that they had been performed

through use of an approved checklist.

The final

documentation of each individual activity inspected

(including the peer inspection process)

was

a two-line entry

into a computer program.

Although the surveillance

forms

provided

a concise description of what the

QC department

did, they did not provide any judgement

on the activities

being witnessed other than

a single letter indicating

whether the activity was acceptable,

conditional, or

unacceptable.

The inspectors

noted that over

98% of the

activities observed,

reviewed,

or verified by the

QC

department,

including the reviews performed of I&C

Department activities,

were considered satisfactory.

None

of these surveillances identified the lack of training in

the skill area

as unsatisfactory.

Additionally the inspectors

observed that

QC routinely noted

that verifications were performed by C-level personnel

(i.e., trainees)

in the I&C areas;

however, in the

-electrical

and mechanical

maintenance

areas,

verifications

were performed

by A-level personnel

(senior level).

Because

the I&C activities were considered satisfactory

by QC, it

appeared that the fact that trainees

were performing the

work was never followed up to determine if it met the

requirements

of the licensee's

QAPD.

This is considered to

be

a weakness

in the licensee's

quality verification

program.

Unresolved

Items

An unresolved

item is

a matter about which more information

is required to ascertain

whether it is an acceptable

item,

a

deviation, or a violation.

Two unresolved

items were

disclosed during this inspection

and are discussed

in

paragraphs

3 and 4.

Exit Interview

The inspectors

met with licensee

representatives

(denoted in

Paragraph

1) at the conclusion of the inspection

on June

7,

1991.

The inspectors

summarized the scope

and findings of

the inspection.

The inspectors

also discussed

the likely

informational content of the inspection report with regards

to documents

or processes

reviewed by the inspectors

during

the inspection.

The licensee did not identify any such

documents

or processes

as proprietary.

After discussion during the exit meeting regarding the

qualifications of I&C personnel

performing inspection

activities, the plant manager

committed to only allow use of

personnel

who were qualified,

as denoted

on their training

matrix, to perform verifications.

The plant manager

informed the inspectors that this change

would take place

immediately and would continue until plant management

could

determine

and document the skill level necessary

to perform

verifications in the I&C area.

During the exit meeting, plant management

agreed with the

inspectors'bservations

regarding

how independent

verifications were performed in the I&C area,

but disagreed

with the inspectors'haracterizations.

Plant management

indicated that mechanical

and electrical maintenance,

because

of the nature of the work, required

a second

independent

person to perform 'the verification.

However, in

the I&C or operations

area,

the independent verification was

actually provided by the indication (the light going out

when the breaker

was racked in, for example)

rather than by

the individual.

Management

indicated that since this

approach

had been

implemented,

the number of errors in the

operations

and I&C areas

had been reduced.

Therefore,

use

of a team member to ensure that the indication had responded

was considered

by plant management

to be an acceptable

form

of independent verification.

10