ML17328A912

From kanterella
Jump to navigation Jump to search
Exam Repts 50-315/OL-91-01 & 50-316/OL-91-01 on 910130-0207. Exam Results:One SRO Failed Simulator Portion of Exam & One SRO & One Reactor Operator Failed Job Performance Measure Portion of Exam
ML17328A912
Person / Time
Site: Cook  American Electric Power icon.png
Issue date: 03/05/1991
From: Burdick T, Shepard D
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML17328A909 List:
References
50-315-OL-91-01, 50-316-OL-91-01, NUDOCS 9103130101
Download: ML17328A912 (10)


Text

U.S.

NUCLEAR REGULATORY COHHISSION REGION III Report No. 50-315/OL-91-01 Docket Nos. 50-315; 50-316 Licenses No. DPR-58; No.

DPR-74 Licensee:

Indiana Hichigan Power Company Donald C.

Cook Nuclear Power Plant

Bridgman, HI 49106 Facility Name:

Donald C.

Cook Nuclear Power Plant Examination Administered At:

Donald C.

Cook Nuclear Power Plant Examination Conducted:

January 30 through February 7, 1991 Chief Examiner:

D.Se r

Date Approved By:

T. H. Burdick, Chic Operating Licensing Section 2

Date Examination Summar Examination administered on Januar 30 throu h Februar 7

1991 e ort o.

L-1 Conslste o

written an operating requalification examinations administered to ten reactor operators and ten senior reactor operators using alternative B methodology.

Results:

One senior reactor operator failed the simulator portion of the examination.

One senior reactor operator and one reactor operator failed the Job Performance Heasure (JPN) portion of the examination.

One senior reactor operator failed the written examination.

One senior reactor operator mentioned above failed his second retake examination.

All other operators and all crews passed the examination.

The licensee's requalification program is declared satisfactory in accordance with the program performance criteria in NUREG-1021, ES-601.

9103130101 910305 PDR ADOCK 05000315 PDR

REPORT DETAILS l.

Examiners D. Shepard, NRC, Chief Examiner N. tlaguire-tioffitt, NRC, PNL 2.

Examination Develo ment a.

Written Examination The licensee's proposed written examination contained some items that did not meet the guidance of NUREG-1021 and therefore had to be rewritten by the examination team or deleted from the examination.

The following deficiencies were identified:

The following Part 8 ("Administration Controls/Procedural Limits") questions were determined to be Part A ("Plant and Control Systems-Static Simulator" ). questions:

A015, JC13,

PS8, ES2,
OC8, and ICA43.

Some questions were not at the comprehension or higher cognitive level and were replaced.

Two questions were modified to preclude having two correct answers.

Validation times for Part A questions were determined to be too long.

This required additional questions to be added.

Two questions required changing distractors to be more plausible.

The following strengths were identified:

All questions utilized as replacements were from the facility examination bank.

Over 90% of the facility exam bank were objective type questions.

In general, only minor corrections were made to the facility supplied examination.

b.

D namic Simulator Scenarios The following are observations made by the NRC concerning the.

dynamic simulator scenarios validated for use during the requalification examination:

Some Individual Simulator Critical Tasks (ISCT) were deleted or made less restrictive (increased times given for action).

Simulator'scenarios need to add more requirements to have the senior operator prioritize resources.

c.

Job Performance Heasures (JPH)

The following are examples of deficiencies relating to the requirements of JPH's:

Some non-critical steps were marked as critical.

Some cues were not plant responses (such as "red light lit")

but plant conditions (such as "valve is closed" ).

Two JPH's needed to be revised due to procedure revisions.

The JPH questions needed to have times added.

The following strengths were identified:

The JPH's used covered a variety of systems and types of procedures (normal, abnormal and emergency procedures).

The times assigned to the JPH questions appeared to be reasonable.

3.

Examination Administration The licensee was responsible for examination administratio~

scheduling while the NRC observed and coevaluated the examination which allowed the NRC to evaluate the licensee's requalification program as well as the individual operators.

The following observations were made by the NRC concerning examination administration:

The facility scheduled the written examination and the JPH's to minimize the waiting time which reduced stress on the operators.

Examination security between the various crews was maintained at all times by the facility.

The facility conducted their critiques between the simulator scenarios in an expeditious manner which limited the operators'ait, and therefore, stress between the scenarios.

Evaluation of Faci lit Evaluators In addition to evaluating the operator's performance, the NRC evaluated the licensee evaluators'bility to conduct consistent and objective examinations as well as their ability to'rovide unbiased evaluations of the operators.

The following observations were made by the NRC concerning the facility evaluators:

In general, all of the evaluators performed consistent and objective evaluations of the operators.

All evaluator s were satisfactory with respect to the criteria of NUREG-1021.

There were a few instances where JPH cues were not given as written.

There were a few instances of inconsistent repeat back of answers to JPtl questions, in that the repeat back consisted only of the expected answer portion. of the operator's answer.

The JPH evaluators need to standardize their examination technique:

- do job brief the same for all 'operators;

- no paraphrasing of the questions or task unless asked for by the operator for clarification; and

- hand out sheets for task and questions be the same for all operators.

One JPVi evaluator gave a

cue prior to required action on the part of the operator.

One JPH evaluator asked an inappropriate question after getting an incorrect answer to prompt the operator to give the correct answer.

One JPI< evaluator did not time all answers to JPI1 questions.

One JPt1 evaluator inadvertently handed out the job brief prior to the simulator being set for the JPH.

5.

Examination Evaluations Coevaluation by the NRC examiners and the licensee evaluators of the operators'erformance on the examination was performed.

Coevaluations

provided the NRC with the necessary information to assess the individual operator's performance as well as the licensee's requalification program performance.

a ~

D namic Simulator Examination The dynamic simulator evaluation was performed on the D.

C.

Cook simulator and included 20 individual and five crew evaluations each using two scenarios.

One individual failure was identified by both the NRC and the facility.

The following observations were made by the NRC concerning the dynamic simulator examination:

Electrical safety gear was not used by two of three crews during operation of 4KV breaker knife switches.

During ECA-O.O, "Loss of All AC Power",

two of three crews did not continue beyond step 17 (as required by procedure) while waiting for steam generator levels to increase.

The crews showed excellent control of tripping protective bistables.

The crews performed the immediate action steps of the emergency procedures quickly and accurately.

b.

JPti Examination The JPfi examination was conducted at the D.

C.

Cook Nuclear Plant.

The NRC identified two individual failures.

The facility identified one additional individual failure for a total of three failures.

'he following observations were made by the NRC concerning the JPt4 examination:

c ~

The reactor operators had difficulty determining the differential boron worth for use in calculating shutdown margin.

All operators reviewed the precautions and initial conditions of the procedures prior to use.

Written Examinations Parallel grading of the written examination by the NRC and the licensee resulted in consistent overall evaluations regarding pass/fail decisions for all operators.

One individual failed the written examination as graded by both the NRC and the facility.

The NRC deleted one question from the reactor operator examination'MRX" dealing with offsite dose assessment.

The following observations were made by the NRC concerning the written examination:

Taking into account the question deleted, the grading was identical between the NRC and the facility.

The facility should shuffle the Part A examination questions so operators can use the different indicators at different times.

The following areas showed weaknesses on the written examination and are included to be factored.into the facility's SAT requalification program:

Reactor operators on the effects of a load shed on bus T21D.

Trips available for emergency diesel generator.

When the Nuclear Emergency Alarm must be sounded.

Senior reactor operators on the Emergency Plan classification of Technical Specification required shutdown.

Actions required to restart Turbine Driven Auxiliary Feedwater pump.

ATHS Hitigation System Actuation Circuitry (At1SAC) actuation signal.

Reactor operators on automatic makeup flow rate.

Number of steam dump valves that would actuate during an event.

Automatic rod stop bistable effects.

6.

Pro ram Evaluation The NRC administered requalification examination results meet the criteria of NUREG-1021, ES-601 for a satisfactory program; therefore, the licensee's requalification program is evaluated as satisfactory.

7.

Examiner Concern One individual failed a second retake examination.

This individual had been remediated in accordance with the facility

's requalification

'program.

The facility must ensure that individuals who are remediated are objectively evaluated to determined their ability to resume licensed duties.

8.

~E An exit meeting was held on February 8, 1991, between the NRC and facility management to discuss the requalification program and operator deficiencies and strengths, as well as the NRC concerns.

NRC re resentatives in attendance were:

J.

Isom, Senior Resident Inspector D. Passehl; Resident Inspector D. Shepard, Examiner Indiana flichi an Power Com an re resentatives in attendance were:

A. Blind, Plant Hanager R. Anderson, Requalification Program Administrator K,. Baker, Assistant Plant Manager, Production W. Burgess, Simulator Supervisor V. Kincheloe, Training Superintendent N. Nichols, Operations Training Supervisor J.

Sampson, Operations Superintendent E. Tatrault, Senior Training Instructor T. Werk, Operations Training (Contractor, NEC)

SIMULATION FACILITY REPORT Facility Licensee:

D.

C.

Cook Facility License Docket Wos. 50-315; 50-316 Operating Tests Administered On: January 30 through February 7, 1991 During the conduct of the simulator portion of the operating tests, the following items were observed:

ITEtl Containment Recirculation Fan not starting Synchronized light of DG breaker not lit Simulator froze DESCRIPTION Fan 2HV-DE(-2 did not star t on a

containment spray/phase B signal-corrected by facility.

During attempts to parallel

EDG, the Synchronized light on EDG DC output breaker did not remain lit if operator held the breaker switch - DR written.

During SGTR scenario, the simulator stopped tracking-Facility believes it is related to rad 'monitor print out.

REQUALFICATION PROGRAt"i EVALUATION REPORT Faci 1 ity:

D.C.

Cook Examiners.

D. Shepard, N. Haguire-Hoffitt Date(s) of Evaluation:

'January 30, 1991 through February 7, 1991 Areas Evaluated:

X Written X Oral X Simulator Examination Results:

RO SRO Pass/Fail Pass/Fail Total Pass/Fail Evaluation (S or U)

Written Examination 10/0 9/1 Operating Examination Oral 9/1 9/1 19/1 18/2 Simulator 10/0 9/1 19/1 Evaluat'ion of facility written examination grading S

Crew Examination Results:

Crew 1

Pass/Fail Crew 2 Pass/Fail Crew 3

Pass/Fail Operating Examination Pass Pass Pass Crew 4 Pass/Fail Pass Overall Pro ram Evaluation Satisfactory.

Crew 5

Pass/Fail Pass Evaluation (S or U)

Sub@i,ttedg ShepaA.d/cg Examiner 03/

/91 For rded>,

i Bur ick Section Chief 03/ g/91 oved:

P ips Branch Chief 03/ ~91