ML17326B426
| ML17326B426 | |
| Person / Time | |
|---|---|
| Site: | Cook |
| Issue date: | 08/29/1988 |
| From: | Julian C, Lawyer L NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III) |
| To: | |
| Shared Package | |
| ML17326B425 | List: |
| References | |
| TASK-1.C.1, TASK-1.C.9, TASK-TM 50-315-88-15, 50-316-88-17, GL-82-33, NUDOCS 8809020223 | |
| Download: ML17326B426 (56) | |
See also: IR 05000315/1988015
Text
U. S.
NUCLEAR REGULATORY COMMISSION
REGION III
Reports
No. 50-315/88015(DRS);
50-316/88017(DRS)
Docket Nos. 50-315;
50-316
Licenses
No. DPR-58;
Licensee:
Company
1 Riverside Plaza
Columbus,
OH
43216
Facility Name:
D.C.
Cook Nuclear Plant, Units
1 and
2
Inspection At:
D.C.
Cook Site,
Bridgman, Michigan
Inspection Conducted:
July 5-15,
1988
1
I
Inspection
Team Ieader:
L. Lawyer
p zz/gp
Date
Inspection
Team Members:
G.
J.
M.
p.
B.
Bryan
DeBor
DeGraff
Kellogg
Jorgensen
Approved By:
C. A. Julian,
hief
Operations
Branch
Division of Reactor Safety,
Region II
ezra
8
Date
Ins ection
Summa
Ins ection on Jul
5-15
1988
(Re orts No. 50-315/88015(DRS).
50-316/88017(DRS))
Areas Ins ected:
Special,
announced
safety inspection to verify the adequacy
of the D. C.
Cook Emergency Operating Procedures
(EOPs).
This inspection
was
conducted in accordance
with Temporary Instruction (TI) 2515/92
(SIMS No.
HF 4.1).
Results:
Of the areas
inspected,
no violations or deviations
were identified.
Technical
and
human factor deficiencies
were identified during the inspection,
however,
none of these deficiencies
were identified as safety significant.
8809020223
880830
ADOCK 05000315
9
DETAILS
Persons
Contacted
Indiana Michi an Power
Com an
(IMPC)
8~M.
gE""K.
(P~A
g-M.
-P.
a"=D.
- L
8"-M.
Iar.
g%J,
d J
7jR.
8+w.
- J
/I*B.
8G.
Alexich, Vice President,
Nuclear Operations
Baker, Operations
Superintendent
Barker, Sr.
QA Auditor
Burgess,
Simulator Coordinator
Cooper, Requalification Program Administrator
Draper,
Procedure
Coordinator
Holmes,
QA Auditor
Horvath, Site
QA Superintendent
Runser,
Production Supervisor,
Operations
Rutkowski; Assistant Plant Manager
Sampson,
Safety and Assessment
Superintendent
Simms, Shift Technical Advisor, Supervisor
Smith, Plant Manager
Stubblefield,
Operations Training
Svensson,
Licensing Activities Coordinator
Tollas, Shift Supervisor
Other licensee
personnel
contacted
during the inspection included
engineers,
technicians,
operators
and office personnel.
U.S. Nuclear
Re ulato
Commission
N*J. Stang, Project Manager
jj+J. Zwolinski, Deputy Director, Division of Licensee
Performance
and Quality Evaluation
gB. Burgess,
Chief, Reactor Proje'cts
Section
2A
//Attended exit interview on July 14,
1988.
+Attended exit interview on July 15,
1988.
Exit Interview
The inspection
scope
and findings were summarized
on July 14 and 15,
1988, with those persons
indicated in Paragraph
1.
The
NRC described
the areas
inspected
and discussed
in detail the inspection findings
listed below.
The licensee
did not identify as proprietary any of
the materials provided to or reviewed by the inspectors
during this
inspection.
Note:
A list of abbreviations
and acronyms
used in this report is
~
contained in Appendix D.
.
Item Number
Status
Descri tion/Reference
Para
ra h
50-316/88017"01
(Open Item)
Open
Performance
of a labeling review
and correction of labeling
discrepancies
between
and panel indication as outlined
in Appendix
C (Paragraph
6)
50-316/88017-02
(Open Item)
Open
Correction of technical
and
human factors discrepancies
contained in the
as outlined
in Appendix
B (Paragraph
6)
50-316/88017-03
(Open Item)
Open
Upgrading two inadequate
procedures
(Paragraph
6)
50"316/88017-04
(Open Item)
Failure to maintain
a correct
procedure
and to take adequate
corrective action (Paragraph
6)
50-316/88017-05
(Open Item)
Open
Improve procedure
network control
(Paragraph
6)
50"316/88017-06
(Open Item)
Open
Review and resolve
accumulated
EOP comments
(Paragraph
8)
3.
Back round Information
Following the TMI acci dent,
the Office of Nuclear Reactor Regulation
developed
the "TMI Action Plan"
(NUREG-0660 and NUREG-0737) which
required licensees
of operating reactors
to reanalyze transients
and
accidents
and to upgrade
(Item I.C.l).
The plan also required
the
NRC staff to develop
a long-term plan that integrated
and expanded
efforts in the writing, reviewing,
and monitoring of plant procedures
(Item I.C.9).
NUREG-0899, "Guidelines for the Preparation of Emergency
Operating Procedures,"
represents
the
NRC staff's long-term program for
upgrading
EOPs,
and describes
the use of a "Procedures
Generation
Package"
to prepare
EOPs.
The licensees
formed four vendor type owner groups
corresponding
to the four major reactor types in the United States;
General Electric, Babcock 6 Wilcox, and Combustion
Engineering.
Working with the vendor and the
NRC, these
owner groups
developed
GTGs which set forth the desired accident mitigation strategy.
These
.GTGs were to be used by the licensee in developing their PGPs.
Submittal of the
PGP to the
NRC was
made
a requirement
by Confirmatory
Order dated
June
12,
1984.
Generic Ietter 82-33,
"Supplement
1 to
NUREG-0737 - Requirement for Emergency
Response
Capability" requires
each licensee
to submit to the
NRC a
PGP which includes:
a.
Plant-specific technical guidelines with justification for
differences
from the
GTG
b.
A writer's guide
c.
A description of the program to be used for the validation and
verification of EOPs.
d.
A description of the training program for the upgraded
EOPs.
From this
PGP, plant specific
were to have been developed that
would provide the operator with directions to mitigate the consequences
of a broad
range of accidents
and multiple equipment failures.
Due to various circumstances,
there
were long delays in achieving
NRC
approval of many of the
PGPs.
Nevertheless,
the licensees
have all
implemented their EOPs.
To determine
the success
of the implementation,
a series
of NRC inspections
were performed to examine the final
product of the program;
the EOPs.
The objective
was to perform table
top reviews, simulator exercises
where possible,
and inplant walkthroughs
of the
EOPs with licensed operators
to verify their adequacy.
The EOPs
were considered
to be adequate
for use if they could be understood
and
performed successfully
by the operators
and they incorporate
the accident
mitigation strategy
developed
by the appropriate
vendor specific owner
group.
This inspection report represents
findings, observations,
and conclusions
regarding the adequacy of the EOPs.
It did not,
as
a matter of intent,
review whether the
EOPs thus prepared
conformed to the
NRC staff's
long-term program for upgrading
and whether those
had been
properly prepared
using
a PGP.
The success
level of licensees
in following the
PGP submitted to NRC
is
a regulatory issue that will be dealt with on a case-by-case
basis.
Although some licensee's
EOPs strayed far from their PGP, that issue is
of secondary
importance to this inspection effort.
The purpose of this
inspection is to verify adequacy of the
EOPs for continued safe operation
of the facility.
EOP/GTG
Com arison
The
NRC compared
the D.C.
Cook EOPs to Revision
1 of the Westinghouse
Owners
Group ERGs.
The
ERGs were used
as the basis for the D.C. Cook
Plant Specific Technical Guidelines.
Deviations between the
NRC approved
and the D.C. Cook plant specific technical guidelines
were identified,
justified, and documented
by the licensee in the
SDD.
The D.C.
Cook ERG background
document
served
as the basis
from which
the D.C.
Cook EOPs
and their changes
were developed.
The D.C. Cook
EOPs closely parallel the generic
ERGs.
The licensee
uses plant specific
emergency
procedures
and abnormal operating procedures
to supplement
the
ERG based
EOPs.
The D.C.
Cook EOPs,
based
on the ERGs, together with
abnormal operating procedures
(4022 and 4023 series)
comprise the
licensee's
emergency operating procedures.
I
(C
The
NRC reviewed the emergencies
and other significant events
covered
by
the D.C.
Cook EOPs
and
as indicated by Appendix A.
Taken together,
the
NRC judged that the
and
AOPs cover the broad range of emergencies
and other significant events
necessary.
With respect to
QA involvement in the
EOP development,
a review of all
Revision
0 EOPs
was performed.
The scope of the
QA reviews consisted
of programmatic
assessments
such
as adherence
to D.C.
Cook procedure
for writing procedures
(PMI-2010, Plant Manager
and Department
Heads
Instruction, Procedures,
and Associated Index's, Revision 4),
and operator
training on the
new procedures.
In addition, although not procedurally
required,
the technical
adequacy of the Revision
0 EOPs
as assessed
in
a table top review.
The major deficiency in this
QA process
was that the
technical
adequacy
was not reviewed by a physical hands
on walkthrough,
resulting in numerous
discrepancies
not being identified such
as those
enumerated
in Appendix B.
There were
no violations or deviations
noted in this area.
Inde endent Technical
Ade uac
Review of the
The licensee
used Revision
1 of the
as the generic technical
guidelines for that portion of the
covered by the
ERG'evision
0 of the D.C.
Cook
was submitted
on April 15,
1983.
It included Revision
0 of the writers guide and
a sample of the
background
documentation
forms which collectively comprise the
SDD used
to document
EOP deviations
from the generic technical guidelines.
The
NRC issued
a draft SER on September
12,
1985, in response
to the licensee's
submittal of PGP Revision 0.
The licensee
submitted
PGP Revision
1 on
May 16,
1986.
Updated
sample
documentation
forms and Revision
1 of the
writer's guide were included.
No SER has been issued
on the D.C.
Cook
PGP.
This inspection
was based
upon the effective Unit 2 EOPs listed in
Appendix A, Revision
0 of the Writer's Guide and Revision
1 of the
The
NRC determined that
ERG Revision
1 generic technical guideline step
sequence
and placekeeping
requirements
were met and that entry and exit
points were correct except
as noted in the enclosed
Appendix B.
Revision
1 of the Writer's Guide has not been applied to the EOPs,
but is scheduled for September
1988 when an EOP upgrade will incorporate
Revision lA of the
Transfers within the
EOPs were well defined
and appropriate
except
as noted in Appendix B.
The general priority of treatment
and order
of steps
was maintained.
I
Because of the self contained nature of the
EOPs it was not generally
necessary
for the operators
to remove pages.
For this reason,
placekeeping
was not a significant problem.
I
The
NRC verified that procedure entry and exit points were generally
correct, properly and clearly identified,
and could be easily followed
by the operators.
The licensee's
use of notes,
cautions,
and transfer instructions
was
clear
and consistent with the
ERGs except
as noted in Appendix B.
The
NRC verified that the priority of accident mitigation was maintained
in the
EOPs except
as noted in Appendix B.
Major identified deviations
between
the plant specific
and the
generic technical guidelines
appeared
to be based
upon adequate
technical
justification.
Safety significant deviations
had been reported to the
NRC.
As noted in Appendix B, the
NRC identified some deviations
which
were not included in the
SDD; none were considered
safety significant.
Plant unique operator action setpoints
were contained in the setpoint
document.
Many parameters
were selected
from the
and traced to the
SPD with generally satisfactory results
except in the case of adverse
containment.
There were several
instances'where
the
ERG contemplated
adverse
values
and the setpoint
document either carried normal and
adverse
values
as identical or omitted adverse
values entirely.
These deficiencies
are documented in the attached
appendices.
Control room drawings
were inspected
to verify that management
controls
were effective and that plant changes
were reflected in interim and final
drawings in a timely manner.
Twelve drawings were inspected; all were
up-to-date.
The licensee
has
an onsite drawing production capability
and does not use interim drawings.
Final installation drawings are
issued
when the change
package installation is complete.
There were no violations or deviations
noted in this area.
Review of the
b
In lant and Control Room Walkthrou hs
Inplant and control room walkthroughs of the emergency
and abnormal
procedures
listed in Appendix A were conducted.
When strictly compared,
the instrumentation
and control labeling on the control board
and the
nomenclature
used in the procedures
was inconsistent.
However, the
majority of the discrepancies
observed
were minor in nature
and only
those discrepancies
which the
NRC felt were significant have been
identified in Appendix C.
The licensee
should review and resolve
not only "those discrepancies
identified in Appendix C, but also perform
a procedure/control
board labeling review and evaluate all discrepancies.
Resolution of this issue will be identified as
an Open Item (316/88017-01).
Indicators,
and controls referenced in the
EOPs were found
to be available to the operators.
There
was one set of ERG based
maintained in the control room at all times.
These procedures
were
verified to be of the latest revision and free of any handwritten changes.
While the result of these walkthroughs
was generally positive,
discrepancies
in the areas of technical
adequacy,
writer's guide
adherence
and
human factors were noted.
These discrepancies
are
identified in Appendix B.
The licensee
committed to review and resolve
the discrepancies
identified in the aforementioned
appendix.
Appendix
B
discrepancies will be identified as
an Open Item (316/88017-02).
As a result of inplant and control room walkthroughs,
two procedures
reviewed by the
NRC were determined
to be inadequate.
The procedures
were 2-0HP-4023.001.011,
Reactor
Shutdown from Hot Standby Panel
due
to Control Room Inaccessibility,
Revision
2 and 2-0HP-4023.001.006,
Loss
of Control Air, Revision 1.
The licensee
committed to review and resolve
the inadequacies
in these
procedures
as described
below.
Resolution of
this issue will be identified as
an Open Item (316/88017"03).
The first of these
inadequate
procedures;
reactor
shutdown from
the hot standby panel procedure
contained insufficient direction in
that the majority of the procedure
appeared
to be an inventory of the
instrumentation
and controls available to the operator at the hot standby
panel.
Little guidance
on the control of the unit following a reactor
trip when evacuation of the control room is required
was provided.
Discussion with the licensee
indicated that'his
procedure
was to be
implemented in conjunction with existing plant procedures.
However,
no reference
was
made to existing normal,
abnormal or emergency procedures
within the hot standby panel procedure.
In response
to this concern,
the
licensee
informed the operators
that until the procedure is revised,
the
guidance for control from the hot standby panel is dictated by the
procedure that applies at that time, e.g.,
E-O, Reactor Trip or Safety
Injection, etc.
The second
inadequate
procedure;
loss of control air did not identify the
instrumentation that would be inoperative following a loss of control air.
The licensee
should revise the procedure
to include
a listing of those
instruments
which would be inoperative following a loss of control air.
As a result of recent revisions to E-O, Reactor Trip or Safety Injection,
Attachments
A and
B were also revised to correct several errors in the
listings of. valves.
Attachments
A and
B are used in E-O to verify that
the'applicable
valves close
on either
a Phase
A or Phase
B containment
isolation signal.
The
same attachments
are also used in ECA-O.O, Loss
of All AC Power and FR-Z.l, Response
to High High Containment Pressure.
At the time that E-0 was revised,
the other two procedures
containing
these
attachments
were not revised.
The licensee
could not provide the
NRC with a reasonable justification as to why the two remaining procedures
were not revised.
The fact that ECA-O.O and FR-Z.1 were not revised
resulted in both missing
and erroneous
information in Attachments
A and
B.
The valves missing from Attachment
A were erroneously listed under
Attachment
B as
Phase
B isolation valves.
They were 2-NCR-252, Primary
Water to Containment,
2-GCR-301, Nitrogen to PZR Relief Tank,,2-QCR-919,
Demineralized water to Containment,
and 2-QCR-920, Demineralized
Water
to Containment.
Valves missing from Attachment
B were 2-CCM-459,
l
II'
to RCP Coolers;
2-CCM-452,
2-CCM-454,
CCW from
RCP thermal barriers;
2-ECR-33,
Lower Containment Air Sample to RMS/PASS;
and 2-ECR-32,
Lower Containment Air Sample to ERS-1300.
Furthermore, after
the licensee
had been informed of and had corrected
these discrepancies,
a
control room walkthrough of 2-OHP 4022.034.003,
Recovery from Containment
Phase
A, Revision 3,
was performed.
From this walkthrough it was
determined that Phase
A isolation Valve 2-GCR-314
was not labeled
on the
safety injection/accumulator
panel
as
a Phase
A isolation valve nor was
it included
on Attachment A, Revision
0 or 1.
2-GCR-314 is identified
as
a Phase
A isolation valve in Unit 2 TS 3.6.3.1,
Table 3.6-1,
Item 50,
and on print OP-1-98283-6
Emergency
Core Cooling (Safety Injection)
~
Sheet
3.
Consequently,
the control room operators
have not had
a complete
list of containment isolation valves for at least
two years.
This issue
is identified as
an Open Item (316/88-17-04).
The
NRC is concerned with the present controls for the review and revision
process for the EOPs.
A QA review,
one of the current management
controls
in the review process,
requires
only a programmatic
review and does not
include
a technical review.
Prior to final approval
and implementation
of the EOPs neither
QA nor the other management
control groups performed
an adequate
detailed technical
review.
The
NRC recognizes
that,
when
developed,
the procedures
received
a table top review and
some procedures
received
a task analysis
review and walkthrough during the
DCRDR.
Nevertheless,
many technical problems
were discovered
during this
inspection.
Timely and thorough review and revision of EOPs is
discussed
further in Paragraph
8.
Discussion with the licensee indicated that they intend for their QA
reviews to become
more performance
based
by examining the
EOPs during
simulator exercises.
While this will improve the technical content of
the EOPs,
the
NRC cautions that the errors identified above, specifically
with 2-GCR-314 would not have been found during simulator exercises
in
that there
was
no indication to lead operators
to believe that the valve
belonged
on the attachment.
It is recommended
that the licensee:
a.
Conduct walkthroughs of the procedures
in the control room
and in the plant.
b.
c ~
Conduct
a verification of technical specification requirements.
Conduct
a evaluation of the review and revision process
as it
applies to EOPs.
'
Resolution of this issue will be identified as
an Open Item (316/88017-05).
7.
Simulator Observations
The
NRC observed
an operating
crew performing the following eight
scenarios
on the
D AC. Cook simulator:
l
a
b.
C ~
d.
e.f.
g"
h.
Loss of Offsite Power with One
EDG Inoperative
RCS Leak Causing
ECCS Actuation
Loss of All Feedwater
Steam Line Break Outside Containment/Inside
the MSIV
SG Tube Rupture
Station Blackout
Anticipated Transient Without Scram
RCP Trip/Verification of Natural Circulation
The procedures
provided operators, with sufficient guidance to
fulfilltheir responsibilities
and required actions during the
emergencies,
both individually and as
a team.
The procedures
did not cause
the operators
to physically interfere
with each other while performing the
and AOPs.
The procedures
did not duplicate operator actions unless
required
(e.g., for independent verification).
When
a transition from an
EOP to an
AOP or other procedure
was required,
precautions
were taken to ensure that all necessary
steps,
prerequisites,
and initial conditions
were met.
Operators
were found to be generally
knowledgeable
about where to enter
and exit the procedures.
Activities that should occur outside the control room were initiated
by the operators
and proper confirmation of their completion was given.
These actions
were inspected
during inplant walkthroughs of the procedures.
The
EOP lesson plans
cover both the technical basis
behind the procedures
and their structure
and format.
The training scenarios
provide sufficient
coverage of the EOPs (with the exceptions
noted below), including multiple
malfunctions.
In addition, operators
were trained on significant revisions
of the
EOPs prior to their implementation.
The training simulations
should duplicate actual plant operations
whenever
possible.
The extent of simulation should be such that the operator is
required to take the
same action on the simulator to conduct
an evolution
as
on the reference plant'sing the
same procedure.
It was noted during
the simulator exercises
and procedure
walkthroughs that in one case,
pertaining to BIT isolation and the restoration of seal injection flow,
the operators
were being trained'to perform the steps
out of sequence
with the procedure.
Discussion with the licensee
indicated that they
intend to revise the procedure
to reflect this improved method of system
operation.
The
NRC encourages
improvements in plant operation wherever
identified and expects that the improvements to be incorporated,
through
temporary revision and procedure revision; however, until such actions
are taken adherence
to existing procedures
is expected.
No violations or deviations
were noted in this area.
I t
On oin
Evaluation of the
Procedures
and records
were reviewed
and licensee
personnel
were
interviewed to determine
whether the licensee
has
an acceptable
program
for long-term continuing evaluation of the EOPs.
The
NRC found that
Plant Manager's Instruction,
PMI-4020 Operating Procedures,
Revision 6,
established
administrative controls for preparation,
review and approval
of revisions to the
EOPs.
"Guidelines for Preparing
Emergency Procedures
for Nuclear Power Plants,"
NUREG-0899, "Guidelines
for the Preparation
of Emergency Operating Procedures,"
and the
licensee's letter
(AEP:NRC:00773Q)
"Response for Draft Safety Evaluation
on D.C.
Cook Procedures
Generation
Package,"
were all specifically
referenced in PMI-4020.
The procedure
required that "significant"
revisions to the
EOPs must comply with the guidelines'stablished
by
the
PGP - which was the process
used to develop'lant specific procedures
from the
Proposed
revisions to EOPs could be initiated from many sources,
but
operations
and training department
proposals
were predominant.
"Comments"
had arisen
from simulator exercises,
plant and control room walkthroughs,
individual studies
or observations,
biennial reviews,
a
QA surveillance,
and the
DCRDR effort.
In addition, industry experience is evaluated
through Operations
Department
review of semiannual
WOG updates,
and
by Safety and Assessment
Department
by review of NRC correspondence
(Bulletins, Notices
and Generic Letters)
and
SENs,
and other information from the SEE-IN program).
The licensee
stated that all but "minor" EOP revisions will be subjected
to V and
V on the plant simulator.
This intent is not formalized, nor
were the criteria for segregating
and/or prioritizing proposed
revisions.
At the time of the inspection,
there
was
no formal mechanism
describing
and controlling the process for handling
EOP "comments."
An
Operations
Department procedure
was being developed
which the licensee
indicated would address prioritization, feedback,
and means for
inter-department
communications - e.g.,
from training to operations.
The existing informal process
was found to be fairly uniformly used
and
understood.
Proposed
EOP changes
had been submitted to a procedure
group
within the Operations
Department.
This group had only a single individual
working part time on EOPs.
A large number of comments
(well over
a hundred
items of various kinds) had been accumulated for which final action had not
been taken.
The
NRC viewed the failure to make timely and thorough
revisions to EOPs concerning certain
known deficiencies,
to be
a significant
weakness.
The licensee
should review and resolve these procedural
comments
in a timely fashion.
This issue will be identified as
an Open Item
(316/88017-06).
The
QA organization
was found to be involved in both the original and
the ongoing
EOP development process.
Three
QA staff members,
who had
been licensed at the
SRO level, reviewed all the current-generation
for various attributes'arious
communications illustrated that
QA and
10
the operations
procedure
group had continued working together
on an
upcoming major EOP revision to owner's
group
ERG Revision
1A.
The
group had
a representative
on the plant subcommittee
on procedures,
as
mandated
by PMI-1040, "Plant Nuclear Safety Review Committee."
All
procedure
revisions require
QA review and concurrence.
The
QA group
also performed audits (routine)
and
a surveillance
(nonroutine) in the
EOP area.
NRC Information Notice No. 86"64, "Deficiencies in Upgrade
Programs for Plant Emergency Operating Procedures"
(and its Supplement
1)
had resulted in the licensee
obtaining and reviewing documents
describing
industry deficiencies,
and
QA Surveillance
12-88-23
was specifically
focused
on checking
a sample of the D.C.
Cook EOPs for similar
deficiencies.
QA did not subject the entire body of EOPs to
a
line-by-line comparison to ERG requirements.
While the procedure
comment/suggestion
process
needed formalization,
and
the number of accumulated
comments
was rather large,
as described
above,
the
NRC determined that the licensee
had an acceptable
program
for continuing evaluation of the EOPs.
No violations or deviations
were noted in this area.
9.
EOP User Interviews
Ten interviews were conducted
by the
NRC and it was determined that
the current
EOPs satisfy the needs of the operational personnel.
The
operators felt the
EOPs were adequate
and compatible with the level of
knowledge of the typical operator
and the operations staff was confident
that the
EOPs would function effectively during an actual event.
The
operators
expressed
concern over the double negative
aspects
of some of
the steps in the EOPs.
These
steps
require
a negative finding to remain
in the
AER column and not "kick out" to the
RNO column.
This is contrary
to normal convention which would "kick out" to the
RNO column on a negative
response.
This was also noted to be an item which caused
confusion in
the simulator exercises.
The licensee
has previously identified this
item to the
WOG.
However, the
WOG has taken no action to correct this
deficiency.
The licensee
should consider revising their procedures
to
remove the double negatives
found in the
During interviews, operators
expressed
a concern over the lack of
timely incorporation of comments or proposed
changes
into the procedures.
It should be noted that
a number of items identified by the
NRC had
previously been identified by licensee
personnel.
This lack of
timeliness in incorporating procedure
changes
has
caused
the operators
to be less than enthusiastic
about making comments
on procedures.
Examples of procedure
changes
submitted,
but not yet acted
on include:
ECA-O.O:
On Page 5, the last entry in the
RNO column references
the
wrong procedure
and unit (should be 1, not 2).
Comment sheet
submitted
6-17-87 .,
ECA-O.O:
Step 9.a refers to closing
a non-existent valve (2-C-141).
Comment sheets
submitted 9-9-86 and 11-1-86.
ECA-0.1:
Step 3.d, to start
NESW, should be performed before Step 3.a,
to start
an air compressor,
because
either the compressor
would not
start
(NESW pressure
interlock) or it could be damaged.
Comment
sheets
submitted
10-31-86,
12-1-86,
and 12-26-86.
ECA-O.O:
Step 2.a instructs that Procedure
2 OHP 4022.001.003
be
used.
This is not an appropriate
procedure for emergency
use.
A
deficiency was recognized in the Revision
1 to E-0 and
was corrected
in E-0.
ECA-O.O remains uncorrected.
There were no violations or deviations
noted in this
arear'0.
~ee Items
Open items are matters
which have been discussed
with the licensee
which
will be reviewed further by the inspectors,
and which involves
some action
on the part of the
NRC or licensee,
or both.
Open items disclosed during
this inspection are discussed
in Paragraphs
6 and
8 of this report.
12
APPENDIX A
PROCEDURES
REVIEWED
NUMBER
TITLE
REV-DATED
E-0
ES-O.O
ECA"0 ~ 0
ECA-0.1
'CA-0.2
E-1
ES-1. 1
ES"1.3
ECA-1.1
ECA"1.2
E-2
ECA-2.1
E-3
ECA-3.1
ECA-3.2
ECA"3.3
Reactor Trip or Safety Injection
Rediagnosis
Reactor Trip Response
Natural Circulation Cooldown
Natural Circulation Cooldown with
Steam Void in Vessel (with RVLIS)
Natural Circulation Cooldown with
Steam Void in Vessel (without
Ioss of All AC Power
Ioss of All AC Power without SI
Required
Required
Loss of Reactor or Secondary
Coolant
SI Termination
Post
LOCA Cooldown and
Depressurization
Transfer to Cold Leg
Recirculation
Transfer to Hot Leg Recirculation
Loss of Emergency Coolant
Recirculation
LOCA Outside Containment
Faulted
Uncontrolled Depressurization
of all Steam Generators
Tube Rupture
Post-SGTR
Cooldown Using Backfill
Post-SGTR
Cooldown Using Blowdown
Post-SGTR
Cooldown Using Steamdump
SGTR with Loss of Reactor Coolant-
Subcooled
Recovery Desired
SGTR with Loss of Reactor Coolant-
Saturated
Recovery Desired
SGTR without Pressurizer
Pressure
Control
1-07/01/88
0-05/25/86
0-06/06/86
0-05/30/86
0-05/30/86
0-06/06/86
0-06/11/86
0-05/30/86
0-05/28/86
1-06/23/88
0-05/28/86
1-04/07/88
0-05/30/86
0-05/25/86
0-05/28/86
0-05/25/86
0-05/30/86
0-05/25/86
0-06/06/86
0-05/30/86
0-05/28/86
0-05/30/86
0-05/30/86
0-06/06/86
0-06/11/86
F-0.1
F-0.5
F.0.6
Subcriticality
Core Cooling
Heat, Sink
Integrity
Containment
Inventory
0-05/30/86
0-05/30/86
0-05/30/86
0-05/30/86
0-05/30/86
0-05/30/86
FR-S.1
FR-S. 2
FR-C. 1
FR-C.2
FR"C.3
FR-H.1
FR-H. 2
FR"H. 3
FR-H. 4
FR-P. 1
FR-P. 2
FR"Z. 1
FR-Z.2
FR-2 '
Response
to Nuclear Power Generation/
Response
to Loss of Core Shutdown
Response
to Inadequate
Core
Cooling
Response
to Degraded
Core
Cooling
Response
to Saturated
Core
Cooling
Response
to Loss of Secondary
Heat Sink
Response
Overpressurization
Response
High I,evel
Response
to Ioss of Normal Steam
Release
Capabilities
Response
Low Level
Response
to Imminent Pressurized
Thermal Shock Conditions
Response
to Anticipated Pressurized
Thermal Shock Conditions
Response
to High-High Containment
Pressure
Response
to Containment Flooding
Response
to Containment Radiation
Level
0-04/21/88
0-05/25/86
0-05/25/86
0-05/25/86
0-05/25/86
1-06/23/88
0-05/25/86
0-05/25/86
0-05/25/86
0"05/25/86
0-05/30/86
0-05/25/86
0-05/30/86
0"05/25/86
0-05/25/86
FR-I.1
FR-I.2
FR-I.3
Response
to High Pressurizer
Level
Response
to Low Pressurizer
Level
Response
to Voids in Reactor
Vessel
0-05/25/86
0-05/25/86
0-06/06/86
2-OHP 4022.001.003
2-OHP 4022.005.002
UNIT SHUTDOWN WITH A FAILED
TURBINE VALVE
EMERGENCY BORATION
2-0HP-4023.019.001
2-OHP 4023.020.001
2-OHP 4023.001.001
LOSS
OF ESSENTIAL SERVICE WATER
LOSS
OF NON-ESSENTIAL SERVICE
WATER
'REMOTE SHUTDOWN PROCEDURE-
ATTACHMENT LS-4
APPENDIX B
TECHNICAL AND WRITER'S GUIDE COMMENTS
This appendix contains technical
and writer's guide
comments,
observations
and
suggestions
for EOP improvements
made by the
NRC.
Unless specifically stated,
these
comments
are not regulatory requirements'owever,
the licensee
agreed
in each
case to evaluate
the
comment
and take appropriate action.
These
items
will be reviewed during a future
NRC inspection
as noted in Paragraph
6.
General
Generally,
there
was apparent
lack of adverse
containment values applied
to RCS subcooling within the majority of the procedures.
This is not
consistent with the
WOG guidelines
and there
appears
to be very little
documentation within the licensee's
SDD to support this deviation.
The licensee
should evaluate this deviation and resolve appropriately.
2 ~
E-0 Reactor Tri
or Safet
In ection
a
~
~S
atoms:
The listing of conditions which require
a reactor trip is
incomplete.
Although RPS initiated trips are listed, manual trips
required by other procedures
are not (e.g.,
2-OHP 4022.002.001,
Pump Malfunction, requirement to manually trip the
reactor
and then trip the affected
RCS pump).
The licensee
should
revise E-0 symptoms to include "manual reactor trip" and "manual
safety injection" as conditions.
b.
~Sn~toms:
There are two subparagraphs
numbered
2.
Recommend
deleting the "2)" on Page
1; no other change is required.
C.
Ste
3a
AER and
RNO:
The intent of this step is to verify power
available to at least
one train of equipment.
This requires
power
to either Buses
T21A and
B or T21C and
D or to both bus pairs.
Existing
EOP terminology is confusing
due to the use of "at least
one energized"
and "one
AC emergency
bus" when referring to four
buses;
two bus pairs.
The licensee
should revise the wording to
eliminate this confusion.
d.
Ste
s
14 and 15:
The licensee
should revise the procedure
to eliminate Step
15.
Since these valves are included in
Attachment A, they are properly positioned in Step
14.
e.
Ste
18a
AER and
RNO:
The licensee
inserted the word "remained"
which did not appear in the
ERG.
Use of the word "remained" implies
that containment
spray should be reinitiated if pressure
has ever
been
above 2.9 PSIG,
even if it is currently below 2.9 as it might
be following ice condenser
suppression
of a pressure
spike from a
leak which has
been isolated.
There is no technical justification
I
for reinitiation under these
circumstances.
The licensee
should
review and resolve this condition.
~gte
30:
The note before
Step
24 applies
to Step
30 also.
The licensee
should revise the procedure
to include the note
before Step 30.
Attachment
A
Pa
e 19:
The 2-CRV-445 valve is
CCW from south spent
fuel pit HX, not from the "North."
The licensee
should correct the
noun name of this valve.
h.
Attachment
A
Pa
e 19:
The 2-CRV-485 valve noun name omits the word
South in this attachment.
In order to be consistent with the valve
label, the noun name in this attachment
should read
"CCW to South
Boric Acid Evap."
The licensee
should correct the noun
name of this
valve in Attachment A.
1 ~
Attachment
A
Pa
e 21:
The Containment Auxiliary Subpanel
(CAS)
which is physically located in the auxiliary building, Elevation 633,
does not have the Phase
A labels adjacent
to the indicator lights.
In order to be consistent with the control room labeling,
the
licensee
should
add the Phase
A tags to the
CAS panel switches.
Attachment
A
Pa
e 21:
The
"VC panel" is actually the
"VS Panel."
The licensee
should correct this error.
k.
Attachment
A
Pa
e 21:
The eight
VS panel
HV switches
are designated
with only the switch numbers not the noun names.
In order to be
consistent with the rest of Attachment A, the licensee
should
add
the noun names for the
HV switches.
Attachment
A
Pa
e 22:
The licensee
should revise the procedure
to insert the "Attachment A" heading
as found on Pages
18-21.
3.
ES-O.O Redia nosis
~gte
3:
The licensee
should evaluate
the need to revise the procedure
to more clearly define "High radiation."
4.
ES-O.l Re'actor Tri
Res
onse
a
~
Ste
1
RNOs
a and c:
The licensee
should revise the procedure
to be consistent with the terminology used by the operators, i.e.,
and control board usage of "SG steam
reliefs."
b.
operation of Valve 2-QRV-301.
Ca
~gte
da:
This step is identical with that of the
WOG guidelines,
"check
SG levels:
a. Narrow range level greater
than x g."
Neither
the
WOG guidelines nor the
EOP indicate whether it refers to one or
more or all steam generators.
The background
document indicates it
applies to one or more.
The licensee
should revise this step to
"a. Narrow range level in at least
one
SG greater
than 6g."
d.
The procedural
process
of electrical power restoration varies
from excellent (e.g.,
Step
7 and
7
RNO with Attachment A)
to inadequate
(e.g.,
E-0 Step
19
RNO, "Try to restore offsite
power," unamplified).
The problem is complicated
by the existence
of 2-OHP 4023.001.021,
Restoration of Power From Blackout,
and the
belief of at least three licensed operators
that loss of offsite
power with successful
sequencing
of the diesel generators
onto
.
their busses
is an entry condition to ECA 0.0 (because
of the
transient loss of all AC while the
DGs are sequencing).
It is
recommended
that:
(1)
be reviewed to assure
that power restoration
requirements
are adequately specified.
(2)
The need for and application of 2-OHP 4023.001.021
be
reviewed.
(3)
Operator training provide increased
emphasis
on,
(1) the difference between blackout and total loss
of AC power and (2) the entry conditions of ECA 0.0.
5.
ES-0.2 Natural Circulation Cooldown
a
~
~gte
1:
This step contains
a check for plant status
"Containment-
Accessible."
If the containment
were not accessible
the operator
may resort to the
RNO which would direct him to the next step
and
preclude starting
a RCP.
The licensee
should revise this step to
clarify the desired action.
b.
~gte
6:
The note preceding this step
has
been
added by the licensee
and is not contained in the
WOG guidelines,
but no deviation document
was generated.
The licensee
should generate
a step deviation
document for this note.
Ca
~Ste
15:
The caution preceding this step
has been
added by
the licensee
and is not contained in the
WOG guidelines;
however,
no. deviation document
was generated
by the licensee.
The licensee
should generate
a step deviation document for the caution.
6.
ES-0.3 Natural Circulation Cooldown With Steam Void in Vessel (with RVLIS)
a
~
~Ste
2:
Same
comment
as noted in ES-0.2,
Step
1 above.
b.,
~Ste
7:
Same
comment
as noted in ES-0.2,
Step
15 above.
Cs
~gte
13:
This step under the
EEO contains
an incorrect refereace
to Step 8.
The licensee
should revise this step to reference
the
correct step.
a
~
~gte
2:
Same
comment
as noted in ES-0.2,
Step
1 above.
7.
ES-0.4 Natural Circulation Cooldown With Steam Void in Vessel (without
b.
~gte
2.
This step requires
the operators
to hand rotate the
to be started.
Other procedures
and ES-0.3)
make this step
conditional with the words "ifpractical."
The licensee
should
revise this step to be uniform with the other procedures.
c.
~Ste
11:
Same
comment
as noted in ES-0.2,
Step
15 above.
d.
~gte
23:
This step
under the
RNO contains
an incorrect reference
to Step
23'he
licensee
should revise this step to reference
the
correct step.
e.
Foldout:
The foldout page
does not contain the adverse
containment
values for RCS pressure
under the
RCP trip criteria or RCS subcooling
under the SI actuation criteria.
The licensee
should revise the
foldout page to include these values or provide documentation in
the
SDD.
8.
ECA-O.O I,oss of All AC Power
a
~
The last entry in the
RNO column on Page
5 should be "Unit One
D/Gs per
1-OHP 4023.001.020."
The licensee
should evaluate
this discrepancy
and revise
as appropriate.
b.
~gte
S.a:
This instruction cannot
be accomplished
as stated
because
the referenced
valve (2-C-141)
no longer exists.
An alternate valve
for accomplishing
the intended objective should be identified.
The
licensee
should evaluate this discrepancy
and revise
as appropriate.
c ~
~gte
14:
Design changes
to both the
CRID and the
TDAPP latching
solenoid
may make this step unnecessary.
If it remains desirable,
I and
C (not
C and I as stated)
should disconnect
the
TDAFP electrical
overspeed trip without waiting for an attempted
emergency
fan hookup.
The licensee
should evaluate this discrepancy
and revise
as
appropriate.
d.
~gte
16:
The
RNO column should read If Un"it one's
The licensee
should evaluate this discrepancy
and revise
as
appropriate.
e.
~gte
21: It appears
inappropriate
to give instructions to
stop fans
as necessary"
in the Response
Not Obtained
column,
when the procedure is at a point where no fans
have
power.
The licensee
should evaluate this discrepancy
and
revise
as appropriate.
~gte
29a:
There is no
SUPPLEMENT FOR ADVERSE CONTAINMENT attached
to this procedure
as indicated.
The Unit
1 procedure
(Unit 1 was
in operation during the inspection) did contain the Supplement.
The licensee
should evaluate this discrepancy
and revise
as
appropriate.
go
~Ste
10.c:
Some brief instructions for locating Valve 2-MS-141
should be provided at this step.
It is both rarely operated
and
not easy to locate.
The licensee
should evaluate this discrepancy
and revise
as appropriate.
~gte
17:
A cross-reference
should be
made at this step to existing,
.
approved
methods to "locally dump steam using
SG steam relief
e.g.,
Attachment IS-4, Section IS-4-3 to Procedure
2-OHP 4023.001.001,
"Remote
Shutdown Procedure."
The licensee
should evaluate this
discrepancy
and revise
as appropriate.
the
WOG guidelines,
should be clarified or deleted.
It may be
either ill-advised or impossible to "bleed and feed with demineralized
water" through the BIT and the
BAST in the condition in which no
busses
are energized.
The licensee
should evaluate this discrepancy
and revise
as appropriate.
9.
ECA"0.1 Loss of AC Without SI Re uired
a
~gte
3:
The specificity of this step should be improved to:
~
identify the instrument
number
and pressure
for instrument
air AVAILABLE (Step 3.a)
~
identify valves to be checked
by valve number
(Step 3.b)
~
provide the flow/ratio to achieve the desired
VCT makeup
concentration
(Step 3.c)
The licensee
should evaluate
these
discrepancies
and revise
as
appropriate.
b.
~gte
3.d:
Since this step (restoring
NESW) is
a precondition to
Step 3.a (restoring
a control air compressor)
the sequence
needs
to be revised.
The licensee
should evaluate this discrepancy
and
revise
as appropriate.
c ~
~Ste
11:
The current laaguage
of this step
caused
confusion regarding
whether all three
RCP seal injection valves are supposed
to be
opened - an unusual condition.
The licensee
should evaluate this
discrepancy
and revise
as appropriate.
10.
ECA-0.2 Loss of AC With SI Re uired
~Ste
10:
Same
comment
aa noted
above in ECA-0.1, Item c; Step
11.
11.
E-1 Loss of Reactor or Secondar
Coolant
Pa
e
1
S
toms or Entr
Conditions:
Entry condition number five,
refers to Step
28 of Procedure
SI Termination, but, it should
refer to ES-l,l Step
31.
The licensee
should correct the entry
conditions in E-l.
b.
Pa
e
1
S
toms or Ent
Conditions:
Entry condition number
seven,
refers to Step
10 of Procedure
ECA-0.2, Loss of All AC
Power - Recovery Without SI Required, but, it should refer to
ECA-0.2, Step ll.
The licensee
should correct the entry condition
in E-l.
Pa
e
3
Ste
3.a:
This procedure lists auxiliary feedwater
flow units in "1b/hr" but the meter face units are "PPH."
The
abbreviation
PPH is not in the approved writer's guide list of
abbreviations.
The licensee
should establish
parameter unit
consistency
between procedures
and panels.
d.
Pa
e
8
Ste
14.a:
This step
uses
The licensee
should correct this abbreviation.
e".
Su
lement
Pa
e 1:
The scale graduations
on Graph A
(300-700-1100-1500-1900-2300)
PSIG are inconsistent with
scale
graduations
on the wide range
RCS pressure
chart
recorder
(0-500-1000-1500-2000-2500-3000)
PSIG.
The inconsistent
scales
and graduations
on Graph A, make it difficult for the
operator to use.
- The licensee
should revise
Graph A to be
consistent with the chart recorder scale.
Su
lement
Caution
rior to Ste
9:
This caution states
the
pumps must be manually restarted if RCS pressure
decreases
to
less
than 300 psig.
However, the caution does not include the
RCS pressure
of 590 psig for an adverse
containment condition.
The licensee
should include the
RCS pressure
reading for adverse
containment or provide documentation in the
SDD.
12.
a
~
Pa
e
1
S
toms or Ent
Conditions:
The entry conditions,
Item 1,
states
that the procedure is entered
from E-O, Reactor Trip or Safety
Injection, Step 26.
However, this procedure is actually entered
from
E-O, Step 29.
The licensee
should correct the Item
1 entry conditions
in ES-1.1.
b.
Pa
e
1
S
toms or Ent
Conditions:
The entry conditions,
Item 2,
states
that this procedure is entered
from FR-H.l, Response
to Loss
of Secondary
Heat Sink, Step 29.
However, this procedure is actually
entered
from FR"H.l, Step 30.
The licensee
should correct the Item 2
entry conditions in ES-l.l.
c
~
and outlet BIT isolation valves.
However, the operator is not given
the valve numbers.
In order to be consistent with the previous steps
and the writer's guide,
the licensee
should revise this step to
include:
2-IMO-255
2"IMO-256
2-ICM-250
2"ICM"251
d.
Pa
e
12
Ste
25:
This step instructs
the operator to transfer
NR-45 to the source
range scale.
However, the NR-45 chart recorder
has been replaced
by the 2-SG-12 chart recorder.
The licensee
should
change all steps
referencing
NR-45 to 2-SG-12.
e.
Pa
e 21
Attachment
B Action Statements:
"Control removed" at the
end of this statement
should read "control power removed" to make
it consistent with the panel label.
13.
ES>>1.2 Post
IOCA Cooldown and
De ressurization
Pa
e 4
Caution
rior to Ste
7:
This caution instructs
the operator
to evaluate
steam flow rates in "LB/HR."
The vertical steam flow meters
indicate
steam flow in "PPH."
The safety parameter
display system
indicates
steam flow in "KBH." Furthermore,
the D.C.
Cook list of
abbreviations
does not include
"PPH" or "KBH." This
same
comment applies
to feedwater
and other meters
on the steam generator
and feed
pump panels.
The licensee
should apply parameter units consistently
and in agreement
with the writer's guide.
See
DCRDR Human Engineering Discrepancy, Vl-5.-
14.
ES-1.3 Transfer to Cold Ie
Recirculation
~Ste
3:
The
RNO coatains
a reference
to ECS-1.1.
The correct
reference is ECA-1.1.
The licensee
should revise this step to
correct the reference.
15.
ECA 1.1 Loss of Emer enc
Coolant Recirculation
a
~
h
should evaluate
whether
some qualification should be placed
on
water transfer from the spent fuel pool to RWST.
b.
S~te
dc:
The licensee
should revise the procedure
to emphasize
the fact that this is not a transfer to ES-1.3.
c
~
S~te
21a:
No adverse
containment value is provided for RCS pressure
This is not consistent with the
WOG guidelines
which indicate that an
I a
adverse
containment value is applicable.
The licensee
should revise
the procedure
to include the adverse
containment value if applicable
or provide the necessary
documentation in the
SDD.
16.
ECA-1.2 LOCA Outside Containment
Pa
e
1
S
toms or Ent
Conditions:
The entry conditions state that
this procedure is entered
from E-O, Reactor Trip or Safety Injection,
Step 30.
However, this procedure is actually entered
from E-O, Step 31.
The licensee
should correct the entry conditions in ECA-1.2.
17.
E-2 Faulted
Steam Generator Isolation
a
~
~Ste
B.1:
This step contains
an incorrect reference
to Step
22 of
an E-0 entry condition.
The licensee
should revise the procedure
to correct, this reference.
b.
~gte
5:
This step under the
RNO contains
a reference
to the
crosstie
Valve 2-CRV-51.
The correct valve number is 12-CRV-51.
The licensee
should revise this step to reference
the correct
valve designation.
18.
ECA"2.1 Uncontrolled
De ressurization of All Steam Generators
a
~
~gte
S.a:
This step
does not contain the adverse
containment
value for RCS pressure
as contained in the
WOG guidelines.
The
licensee
should revise this step to include this value or provide
documentation in the
SDD.
b.
~gte
4:
This step
under the
RNO contains
a reference
to the
crosstie
Valve 1-CRV-51.
The correct valve number is 12-CRV-51.
The licensee
should revise this step to reference
the correct
valve designation.
C ~
~Ste
6:
The caution
does not contain the
contained in the
step to include this
preceding this step concerning the
RHR pumps
adverse
containment value for RCS pressure
as
guidelines.
The licensee
should revise this
value.
d.
Ste
s 38
39
and 40:
These
steps
do not contain the adverse
containment values for RCS hot leg temperatures
and pressures
as contained in the
WOG guidelines.
The licensee
should revise
these
steps
to include these values.
e.
~gte
9:
The note preceding this step
concerning
the start of
an RCP with a noncondensible
bubble is not contained in the
guidelines
and
a step deviation document
does not exist.
The
licensee
should generate
a step deviation document for this note.
S~te
17:
This step
energizes
the hydrogen igniters.
It is not
contained in the
WOG guidelines nor has
a deviation document
been
generated.
The licensee
should generate
a deviation document for
this step.
Ia
19.
E-3 Steam Generator
Tube
Ru ture
a
~
The entry. conditions
from E-O, listed on Page
1, from Step
23 and
Step
30 appear
to be out of sequence.
The licensee
should revise
the procedure to include the correct step
numbers.
b.
and containment isolation Phase
A and B.
In the
WOG guidelines
these
steps
do not occur until Steps
8 and 9.
The licensee
has
not provided documentation of this difference in their SDD.
~Ste
12:
The caution prior to this step
does not include the
adverse
containment value for RCS pressure.
The licensee
should
revise the procedure
to include this value or provide the necessary
documentation in the
SDD.
d.
~Ste
27:
The value for adverse
containment
conditions
on
pressurizer
level in the
AER column is 47 percent while the value
in the
RNO column is 50 percent.
The licensee
should review and
resolve this apparent
discrepancy.
e.
~Ste
35:
Same
comment
as noted in ES-3.2,
Step
12.
20.
ES-3.1 Post
SGTR Cooldown Usia
Backfill
a
~
~Ste
4:
The caution prior to Step
4 informs the operator that
it will be necessary
to line up alternate
water sources if the
CST level decreases
to less
than
13 percent.
The licensee
should
consider revising the procedure to include the applicable procedure
through which this task would be accomplished.
b.
~Ste
5:
The direction provided for the operator in this step to
dump steam to the condenser
from the intact steam generator is not
consistent with other steps
completing the
same action.
The
licensee
should revise the step.
c ~
~Ste
8:
This step directs
the operator to establish auxiliary
spray if letdown is in service.
However, this step
does not
direct the operator
on the specific valves to be used.
This
is not consistent with other steps
completing the
same action.
The licensee
should revise the step.
d.
General
Comment:
Same
comment
as noted in ES-3.2,
Step
12, below.
21.
ES-3.2 Post
SGTR Cooldown Usin
Blowdown
a ~
~Ste
4:
The caution prior to Step
4 informs the operator that
it will be necessary
to line up alternate
water sources if the
CST level decreases
to less
than
13 percent.
The licensee
should
consider revising the procedure
to include the applicable procedure
through which this task would be accomplished.
b.
~Ste
5:
The direction provided for the operator in this step to
dump steam to the condenser
from the intact steam generator is not
consistent with other steps
completing the
same action.
The
licensee
should revise the step.
c
~
spray if letdown is in service.
However this step
does not direct
the operator
on the specific valves to be used.
This is not
consistent with other steps
completing the
same action.
The
licensee
should revise the step.
d.
~Ste
9:
The note prior to this step is not in the
and
is not documented in the licensee's
SDD.
The licensee
should
review and resolve this discrepancy.
e.
~Ste
9:
Same
comment
as noted in ES-3.2,
Step 4.
ga
~Ste
12:
This step directs
the operator to check if RCPs
must
be stopped.
The criteria used for stopping the
RCPs is less
than
210 psid on the number
one seal or number
one seal leakoff flow
less
than 0.4 gpm.
This criteria is not consistent with the starting
values of greater
than 200 psid or 0.2
gpm leakoff flow.
Discussion
with the licensee
indicated that they intend to revise the steps
to
include the latter set of values to avoid operator confusion.
22.
ES-3.3 Post
SGTR Cooldown Usin
Steam
D
~
~
~
b.
~Ste
12:
Same
comment
as noted in ES-3.2,
Step
12.
c ~
~Ste
'14:
Same
comment
as noted in ES-3.2,
Step 5.
23.
ECA-3.1
SGTR With loss of Reactor Coolant-Subcooled
Recove
Desired
a.
'S~te
9:
The caution prior to this step is not in the
and
is not documented in the licensee's
SDD.
The licensee
should
review and resolve this discrepancy.
b.
S~te
15b:
The adverse
containment values in the expected
response
and
RNO columns differ.
The licensee
should review and resolve this
discrepancy.
c
Ste
s
16
23 and 35:
Same
comment
as noted in ES-3.2,
Step
12.
d.
Ste
s
17
18 and 19:
The note concerning the use of the supplement
for determining subcooling criteria during adverse
containment
conditions
does not appear in the
and the licensee
has not
provided documentation in their SDD.
The licensee
should review
and resolve this discrepancy.
10
e.
~Ste
29b:
This step directs the operator to transfer auxiliary steam
loads to Unit 2.
The reference
to Unit 2 is incorrect.
The licensee
should revise the procedure
to include the correct reference.
step is incorrect.
This equipment
has
been
removed
and is no longer
in service.
The licensee
should revise the procedure
to remove the
incorrect reference.
ga
~Ste
29:
This step directs
the operator to minimize secondary
system contamination.
This step is not consistent with other steps
completing the
same action in that it fails to direct the operator
to separate
miscellaneous
drain tanks if necessary
and close the
turbine
room sump
pump discharge
valve as necessary.
If applicable,
the licensee
should revise the procedure
to include these actions
such that steps
completing the
same action are consistent with each
other.
24.
ECA-3.2
SGTR With Loss of Reactor Coolant-Saturated
Recover
Desired
a
~
should evaluate
whether
some qualification should be placed
on water
transfer
from the spent fuel pool to the
RWST.
b.
~Ste
4:
The caution prior to Step
4 informs the operator that
it will be necessary
to line up alternate
water sources if the
CST level decreases
to less
than
13 percent.
The licensee
should
consider revising the procedure
to include the applicable procedure
through which this task would be accomplished.
Ca
~Ste
10:
Same
comment
as noted in ES-3.2,
Step
12.
d.
Ste
s ll
12 and 13:
The note concerning
the use of the supplement
to determine
subcooling criteria during adverse
containment conditions
is not included in the
and the licensee
has not provided the
necessary
documentation in their SDD.
The licensee
should review
and resolve this discrepancy.
e.
loads to the backup plant heating boiler if the plant heating boiler
is not available.
The backup heating boiler has
been
removed.
The
licensee
should revise the procedure
to correct this outdated
reference.
~Ste
23e:
This step directs the operator to close turbine
r'oom
sump pumps discharge
Valve 2-DRV-710 as necessary.
Discussion with
the licensee
indicated that this valve is
common to both Unit 1 and
Unit 2.
The licensee
should revise the procedure to change
the
reference
to 12-DRV-710.
25.
ECA-3.3'GTR Without Pressurizer
Control
a
~
~gte
4:
Beginning with step four, the procedure
establishes
a
series of RNO actions which, if followed through by the operator,
would result in an incorrect operator action or expected
response.
The licensee
should review and resolve the step
sequence
problem
in this procedure.
b.
~gte
6:
Beginning with Step
6, the procedure
establishes
a series
of RNO actions which if followed through by the operator would result
in an incorrect operator action or expected
response.
The licensee
should review and resolve the step
sequence
problem in this
procedure.
c.
~gte
30:
This step directs
the operator to depressurize
the
RCS and
ruptured
SG to less
than 425 psig.
There are
no adverse
containment
values applied to this pressure.
This is inconsistent with the
guidelines.
The licensee
should review and resolve this discrepancy.
d.
~gte
31:
The note
and caution before this step
are in conflict
with the
WOG guidelines.
In the
WOG guidelines
they appear before
Step
30.
The licensee
should review and resolve this discrepancy.
26.
F-0.2 Core Coolin
Status
Tree
The operators
are appropriately trained to use five core exit thermocouples
when evaluating
temperature,
but the instructions in
this safety function tree
do not specify the number of thermocouples
that
should be used.
The licensee
should specify in this safety function tree
the number of thermocouples
to be used
when assessing
core exit temperature.
27.
F-0.3 Heat Sink Status
Tree
The brace following the safety function tree (Total AFW flow to
SGs greater
than 200X10 LB/HR and
NR level in at least
one
SG greater
than 22/) is
confusing.
The proposed Revision
1 bracket to replace
the brace
does
not eliminate the logic flaw.
The licensee
should correct the tree
logic.
28e
F-0.4 Inte rit
Status
Tree
a
The logic in the bottom half of this status tree is incorrect.
The operator is instructed to go to Procedures
FR-P.l or FR-P.2
based
on RCS cold leg temperatures
of 242oF.
The operator could
only be in this branch if any
RCS cold leg temperature
was less
than
152 F.
The licensee
should correct this logic.
b.
This Integrity status tree is not colored in Unit 2 and should be.
The licensee
should correct this.
12
c ~
Fi ure F-0.4.1
Inte rit
0 erational Limits:
This figure lists the
colors red, orange,
yellow and green,
but is presented
in black and
white.
In order to be consistent with Unit
1 and the
WOG guideline
and to enhance
the usability of Figure F-0.4.1, it should be colored.
The licensee
should correct this.
29.
F-0.5 Containment Status
Tree
One path indicates that the containment critical safety function is
satisfied
when containment radiation is less
than 200 R/HR.
The basis
for this setpoint is not clear.
The concern is that 200 R/HR represents
neither habitability limits or equipment limits'he licensee
should
reassess
the objectives of the containment critical safety function,
and modify this setpoint
and the setpoint
document
as needed.
30.
F-Oe6 Inventor
Status
Tree
The statement
"RVLIS Indicates
Upper Plenum not Full 100/'s
confusingly
stated.
It could be clarified by stating "Upper Plenum RVLIS indicates
less
than
100$ ."
The licensee
should modify all four statements
referring
to Upper Plenum RVLIS.
While this step is in agreement with the ERG, the
statement is confusing.
31.
FR-S.1
Res
onse to Nuclear Power Generation/ATWS
s a
~
Ste
2
RNO a.2:
This step
uses
the term "trip" as applied to the
SG stop valves.
It does not meet the action verb definition in the
writer's guide.
The operators
indicated that it meant to close the
stop valve using the fast trip circuitry.
The licensee
should revise the
writer's guide to include this definition.
b.
path alignment
and that shown in Procedure
2-OHP 4022.005 '02
Emergency Boration.
Step 4.2.3 closure of the recirc. valve
is not included in the
EOP version.
The licensee
should review
this discrepancy
and revise procedures
as appropriate.
c ~
to verify the
PORV closed after pressure
has
decreased
and to
shut the block if the
PORV is not closed.
The licensee
should
add the guidance
from the
ERG or document the discrepancy in
the
SDD.
d.
~Ete
12:
The
ERG AER does not verify mein feed pumps tripped nor
does the
RNO manually trip these
pumps.
The licensee
should verify
applicability of this step and/or provide documentation in the
SDD.
32.
FR-S.2
Res
onse to Loss of Core Shutdown
a.
Ste
s la
RNO and
2
RNO:
The licensee
should revise these
steps
to specify whether normal or emergency boration is to be used.
13
's
b.
~gte
3:
The
WOG guidelines
caution concerning the need to continue
boration until shutdown margin is achieved
has
been omitted.
The
licensee
should revise the procedure
to include the caution before
Step 3, if applicable,
or provide the necessary
documentation in the
SDD.
C..
Ste
12
last bullet on Pa
e 7:
Although this step is technically
accurate
as written it could result in closure of both TDAFP valves
in error.
The licensee
should revise this step to emphasize
that
only the steam supply valve from the faulted generator
should be
closed.
33.
FR-C.1 Inade uate
Core Coolin
a
~
Ste
s
17 and 24:
The licensee
should revise the procedure
to repeat
the second
"CAUTION" (Page
2 of 13) at these
steps
as
a reminder.
b.
~gte
5.a:
The reading
sequence
of this step for three instrument
flow checks is not the
same
sequence
as the left-to-right arrangement
of the instruments.
The licensee
should review and revise the step
as appropriate.
c ~
~gte
13:
The degree of detail in this step for establishing
and
operating
the steam
dump in the pressure
control mode should be
revised to be consistent with other steps
completing the
same
action.
34.
FR-C.2
De raded
Core Coolin
~
~
~
~
~
a.
~gte
S.b.3:
The reading
sequence
of this step for three flow
b.
checks differs from the panel arrangement (left-to-right) of the
instruments.
The licensee
should evaluate this discrepancy
and
revise
as appropriate.
Ste
s 6.b.2
6.b.4 and 6.b.5:
The
RCP operating support status
checks
include three items which are not used to accomplish the
same objective in Procedure
FR-C.l.
The licensee
should evaluate
this discrepancy
and revise
as appropriate.
35.
FR-C.3 Saturated
Core Coolin
~gte
2:
This procedure verifies
ECCS flow - an objective also accomplished
at Step
3 of FR-C.l and at Steps
3 and
17 of FR-C.2.
Each of the four has
minor differences in language/structure
detail from all the others.
The
licensee
should evaluate this discrepancy
and revise
as appropriate.
36.
FR"H.l Res
onse to Loss of Seconda
Heat Sink
a
~
~gte
5:
The first caution prior to this step is not in the
and has not been
documented
by the licensee in their SDD.
The
licensee
should review and resolve this discrepancy.
14
b.
~gte
7:
The second
and third cautions
as well as
the note are
not in the
and have not been
documented
by the licensee in
their SDD.
The licensee
should review and resolve this
discrepancy.
c ~
~gte
20:
This step
does not appear in the
and the licensee
has
not provided documentation in their SDD.
The licensee
should review
'nd
resolve this discrepancy.
d.
~gte
20:
The action verb "perform" used in the
RNO column of this
step
does not appear in the writer's guide.
The licensee
should
review and resolve this discrepancy.
e.
~Ste
22:
The third note in the
sequence
does not appear in the
and the licensee
has not provided documentation of the difference in
the
SDD.
The licensee
should review and'resolve
this discrepancy.
~gte
23:
Same
comment
as noted in Step
22 above.
37.
FR-H.2 Steam Generator
Ove
ressure
a
~
Ste
s
2
4
6
and 8:
This procedure
should specify valve
identifications by number in these
steps
to minimize the
potential for misidentifying or omitting an action.
b.
~gte
8:
Instructions for unisolating blowdowa address
only one of
the conditions which may be the cause of the isolation.
The other
causes
and
how to deal with them should be included
as appropriate.
38.
FR-P.1
Res
onse to Imminent. Pressurized
Thermal Shock Condition
a
~
No position indication is installed on any of the steam generator
reliefs (neither the one
PORV relief nor the five code safety relief
valves installed
on each of the four steam generators)
nor are there
any acoustic or thermal sensors.
During walkthroughs
and simulator
drills, every operator took this step to refer only to the
From the context,
the
NRC believes it requires verification that all
six valves
on each generator
are closed.
It is recommended
that the
intent be evaluated
and procedure
or training changes
be made
as
appropriate.
b.
Ste
s 5
12
15b
and 22:
These
statements
are of the form "See
supplement plus x degrees
F for adverse
containment."
The wording
is unclear.
The licensee
should revise this to read
"See supplement.
Add (or subtract)
x degrees
F for adverse
containment."
c ~
by opening:
(repeat
the four valve IDs from the
AER side)."
d.
~Ste
14a:
This step is performed outside the control room.
The licensee
should revise to read:
"a. Iocally restore
power
II
to
"if" statements
by a blank line for clarity.
~gte
19:
The licensee
should add the following:
~
2-QMO-451 and
2-QMO-452 open
~
2-IMO-910 and 2-IMO-911 closed
g ~
the
WOG ERG curve is defined to zero psig.
The licensee
should
evaluate
the need to extend the curve to lower pressures.
h.
Step
1
RNO rather than to Step l.
34.
FR-P.2
Res
onse to Antici ated Pressurized
Thermal Shock Condition
a
~
the
WOG ERG curve is defined to zero psig.
The licensee
should
evaluate
the need to extend the curve to lower pressures.
b.
is limited by the yellow path conditions of the
CSF shown in
F-0.4,
Psat for 272 degrees
or 28 psig.
Allowing for a condenser
vacuum which could be held by auxiliary steam
from the opposite
unit, the pressure differential from the
SG to the condenser is
a maximum of 43 psig.
It is doubtful that this pressure
could
lead to an uncontrolled depressurization.
It is recommended
that this be evaluated, particularly the F-0.4 plant unique
parameters.
40.
FR-Z.l Res
onse to Hi h-Hi h Containment Pressure
a
~
containment isolation Phase
A valves closed,
using Attachment A.
The existing Revision
0 version of Attachment
A has
numerous errors
and omissions.
The licensee
has corrected
many of the Revision
0
discrepancies
in the Revision
1 version of this attachment that has
been published in the new Revision
1 E-0 procedure.
All Revision
0
attachments
should be replaced
by the Revision
1 Attachment A.
containment ventilation isolation, but this has already been
accomplished in Step 2; while verifying Phase
A isolation.
The licensee
should review the applicability of Step
3 and
revise
as appropriate.
16
C ~
Pa
e 4
Ste
4.c:
This step instructs
the operator to verify
spray additive tank low-level alarm, but, this step should refer
to the "low-low" level alarm which indicates that the tank is
nearing
empty.
The licensee
should
change "low-level" to "low-low"
level.
d.
Pa
e
8
Ste
9.d:
This step instructs
the operator to verify
RHR to containment
spray flow on Meters
2-IFI-330 and 2-IFI-331.
These'meters
display invalid flows of 1000
GPM and 500
GPM
respectively during normal operation.
The licensee
should
correct the meters
(Units
1 and 2) to read
0 when there is
no RHR flow and actual flow when it exists.
e.
Pa
e
9
Ste
10:
This step instructs
the operator to check if
hydrogen igniters should be turned on.
In order to accomplish
this step,
the operator
needs
to check hydrogen monitors in service,
which he is not instructed to do until Step lla.
The licensee
should
move Step
11.1 for checking the hydrogen monitors in service,
to 10a.
This will assure
that the operator
has the indication he
needs
to make the required decisions in Step
10.
f.
Pa
e
9
Ste
11.c:
This step instructs
the operator to turn on the
hydrogen recombiner
system.
Since this is
a seldom-used
procedure,
it should be referred to in the step
as
2 OHP.4022.034.004.
41.
FR-Z.3 Res
onse to Hi h Containment Radiation Level
~dte
2a:
The licensee
should revise the procedure
to more clearly define
the "high radiation activity levels" which make it necessary
to place the
filter cleanup
system in service.
During walkthroughs,
the operators
were
uncertain what radiation level the phrase
referred to but offered several
possible values, e.g.,
the monitor alert point or the high alarm point,
and the 200 R/hr value
shown in the yellow path of F-0.5 as possible
values.
42.
FR-I.2 Res
onse to Low Pressurizer
Level
Pa
e
2
Ste
2:
This step instructs
the operator to close "2-QRV-171."
This is incorrect.
The correct valve that should be closed is 2-QRV-170,
EXS I LETDN HX OUT PRESS rather than 2-QRV-171,
EXS LETDOWN HS OUTLET
SELECT.
The licensee
should revise this step.
43.
Attachment
A (Containment Isolation Phase
A)
a
~
Pa
e ll
IV Panel:
The list of Phase
A valves is incomplete.
The missing valves are:
2-NCR-252
Primary Water to Containment
2-GCR-301
Nitrogen to PZR Relief Tk
2-QCR-919
Demin Water to Containment
2-QCR-920
Demin Water to Containment
17
Note:
These four valves are
on the Attachment
B, Phase
B
list of valves.
b.
Pa
e ll
IV Panel:
2-VCR-21 and 2-VCR-11 are reversed
on the
list of valves.
These valves
need to be switched in order to
systematically evaluate
the vertical rows of switches.
c.
Pa
e
11
IV Panel:
The noun names "in the procedure
are not
similar to the panel labels.
Procedure
Panel Label
Compartment
Fan Cooler
Ice Cond
CNTMT
Air HDLG
Note:
There are significant differences in nomenclature
on both Attachments
A and B.
d.
Pa
e
12
IV Panel:
Valve 2-CCR-441.
CCW Pm Pen Cool, is not
a Phase
A valve.
e.
Pa
e
12
IV Panel:
Valve 2-QCR-300 is not functionally grouped
with other Phase
A isolation valves.
Pa
e
12
IV Panel Status Li hts:
Valves 2-GCR-22 and 2-ECR-21
are in reverse
order on the verification list.
g ~
Pa
e
12
IV Panel Status Li hts:
Seven valves in this list have
numbers but "no description."
All of these status lights have
descriptions
on the status lights.
h.
Pa
e
14
CAS Panel:
These
switches which are located in the
auxiliary building, do not have
Phase
A labels like the control
room.
They should be labeled the
same
as the control room.
44.
Attachment
B (Containment Isolation Phase
B)'
~
Pa
e
15
IV Panel:
Five valves are missing from the Phase
B list:
2-CCM-459
-2-CCM"452
2-CCM-454
2"ECR-33
2-ECR-32
Iower CNTMT Air Smpl to RMS/PASS
Lower CNTMT Air Smpl to ERS-2300
b.
Pa
e
15
IV Panel:
The Phase
B list contains four Phase
A
valves:
2-NCR"252
2"GCR"301
2-QCR-919
2-QCR"920
18
45.
2-OHP 4022.001.003
Shutdown With a Failed Turbine Valve
This procedure,
"entered"
from ECA-O.O Step 2.a, is inappropriate for
emergency
use.
This had been previously recognized
and entry from E.O
(REACTOR TRIP) was
removed with Revision l.
ECA-O.O should be similarly
revised.
46.
2-OHP 4022.002.001
Malfunction of a Reactor Coolant
Pum
licensee
should revise this step to reference
the correct procedure.
b.
~gte
5.2:
Same
comment
as a.
47.
2-0HP-4023.001.006
Loss of Control Air
a
~
Pa
e
3
Ste
6.1:
The pressurizer
spray valve does not have valve
position indication, therefore,
the operator will not be able to
make
a position verification of valve position on loss of control
air.
The licensee
has
a design
change
request in progress
that
will correct this concern.
b.
Pa
e
8
Ste
6.7.1-1:
This step identifies more than
40 valves
that are
now presented
in a disorganized list.
The list should
be revised
so that the user
reads
the list from top to bottom,
left to right.
48.
2-OHP 4023.001.011
Reactor
Shutdown From Hot Standb
Panel
Due to Control
~
~
~
Room Inaccessibilit
a
~
The licensee
should revise the procedure
to remove the reference
to the "folding doors" from the procedure.
The hot standby panel
enclosure is now closed off by a roll up steel door which was
installed during a modification.
b.
The licensee
should revise the procedure
to place the note which
currently follows Step 4.4.2 prior to Step 4.4.
c.
~Ste
5.5:
There is
a typographical error.
The licensee
should
revise the procedure
to change "If" to "It."
49.
2-OHP 4023.001.014
Ener izin
the Pressurizer
Heaters
From the Emer enc
Diesel Generators
a
~
by closing breaker
21PHA3 (Groups
2 and 3).
The breaker for Group
2
is 21PHA3 and the breaker for Group
3 is 21PHA5.
The licensee
should
revise this step to correct this error.
b.
Ste
5.2.6:
I
Same
comment
as Step 5.1.6 above.
19
50.
2-OHP 4023.017.001
Loss of RHR (Shutdown Coolin )
a
~
~Ste
5.5:
The last sentence
directs that the use of automatic
steam
dumps
be governed
by. secondary activity level.
The licensee
should
revise the pr'ocedure to include an operator action setpoint
above
which steam
dump use is prohibited.
The licensee
should review the
applicability of an operator action setpoint for steam
dump use
and
provide as appropriate.
b.
~Ste
5.9:
The licensee
should revise the procedure
to add steps
providing makeup
feed to the steam generator.
51.
2-OHP 4023.019.001
Ioss of ESW
"SYMPTOMS" 3.3 and Steps 4.2.1
and 4.2.3.2 appear to be out-of-date
with respect
to design
changes
which deleted certain annunciator
drops
and
removed certain "opposite Unit" indication and control (for fire
protection. separation criteria reasons)
from each Control Room.
These
should be revised.
52.
2-OHP 4023.020.001
Loss of NESW
a.
SYMPTOMS 3.2 and 3.3:
Same
comment
as above.
c ~
The sequence
at Step 5.1.3 should specify closing the
NESW crosstie
valves before tripping all NESW pumps for the Unit.
The licensee
should evaluate this step
and revise
as appropriate.
Step 4.2.2 is actually a "Note," not an Immediate Manual
Action.
This should be revised.
20
APPENDIX C
NOMENCLATURE DISCREPANCIES IDENTIFIED
BY
NRC EOP
INSPECTION TEAM
PROCEDURE
ECA 0.0
~STEP
PG
PROCEDURE
NONENCLRTURE
LABEL ON E UIPMENT
8/7
RCP seal return isolation
RCP SEAL WATER RETURN
valve
ECA 0.0
16/13
2-CRV-51
12-CRV-51 (Note: the
valve controller is
in U-1 control rm,
not U-2)
ECA 0.1
4.a/5
4.f/6
Charging line flow control
CCP DISCH FIOW CONTROL
ECA 0.1
4.b/5
Charging line header valve
HEADER PRESSURE
CONTROL VALVE
ECA 0.1
ECA 0.1
ECA 0.1
12.a/ll
letdown HX outlet valve
Pg ll,
Right
(2)
RCP seal water filter
inlet; (5) excess
letdown
HX flow ctrl
LETDOWN HX TEMP CTRL
SEAL WATER RETURN
EXS LTDN HX OUT PRESS
10.c/9
RCP seal water filter inlet
SEAL WATER RETURN
ECA 0.1
ECA 0.2
ATT.A
Pg
15
thru 23
6/5
(various breakers
are
functional described
by phrases)
AFW flow control valves
(brief names:
e.g."MAIN"
CONTROL
I
RSRV )
FEED FROM EAST MDAFP
(WEST)
ECA 0.2
7/6
(rt column)
skimmer valves
CCW TO CEQ FAN
1
MAC
tt (FROM) tt
II (2)
ECA 0.2
7/7
(rt column)
Air recirculation/hydrogen
skimmer fans
suction isolation
valves
CNTMT RECIRC FAN
1
II
II
tl
(2)
CNTMT RECIRC FAN 1 SUCTION
II
II
II (2)
II
ECA 0.2
9.c/8
RCP seal water filter inlet
SEAL WATER RETURN
ECA 0.2
FR-C.1
10.b/9
1"QRV-200
4.c/13
Air recirculation/hydrogen
skimmer fans
suction isolation
valves
2"QRV-200
CNTMT RECIRC FAN
1
II
II
II (2)
CNTMT RECIRC FAN
1 SUCTION
II
II
tl (2)
II
FR-C.2
FR-H.2
4/4
2/2
2/2
4/2
6/3
6/3
(same
as
two above)
Flow control valves
FRV isolation valves
steam supply valves to
TDAFP supply valves
(same
as
two above)
LEVEL CONTROL VALVES
SG(g)
FEEDWATER ISOLATION
FP TURBINE
FEED FROM EAST MDAFP
tl
tl
(WEST)
Il
8/4
steam supply valves to
1.1/3
RHR pump
HX bypass valve
2-OHP 4023
Symptom
2 Reactor Breaker Undervoltage
E-0
Trip A
(B)
FP TURBINE
PUMP DISCH XTIE
Rx Trip Bkr Train
A
(B)
2c
Alt exciter field ACB
2-OHP 4023.
017.001
2c
alt exciter field ACB
3.2
E and
W low flow
Supplement
Cabinet
2a
RNO
Panel
12/drop
Rack
Panel 212/drop
Exciter field CB 41F
loop flow low
3.3
3.6
3.13
sump alarms
RHR pump trip alarm
Hx inlet and outlet
sump high
1
W and
E
(should be plural; two
alarms per pump)
pump disch and loop
return
2-OHP 4023
2a2
RNO
SG stop valves
FR-S.1
Dump Valve 2-MRV-2xl
(2x2)
2-OHP 4023
FR-S.2
8c
1c
to normal position
NR-45
to bypass position
Neutron Flux 2SG12
2-OHP 4023
5alc
FR-P.l
RCP oil cooler
RCP bearings
14b
17
accumulator isolation
VCT makeup control
18RN02
RCP seal water inlet
10b/10g
charging line header
Up BRG CLR
CCW RETURN
CCW RETURN
charging
HDR PRESS
CNTRL
ACCUM OUTLET
BA Blender Feed Flows
RCP seal water return
18RN03
Splmnt
2-OHP 4023
15d
ECA-1.1
VCT
Cabinet
8 (ll)
~
0 normal
0
~
Rack
8 (ll)
BA Blender
2-OHP 4023
4c
RNO 3
excess
letdown diversion
Pg.
5
EXS Letdown HX Outlet
Select
Same
normal
ECA-2.1
7RNO c
10c
lc/3
5/3
1b/2
1b/2
1b/2
2c/3
2b/3
29/12
31/14
recover
NR-45
Oil Lift Pump
BEARINGS
THERM BAR
SAME AS 1b/2
ABOVE
SAME AS 1b/2
ABOVE
SAME AS 1b/2 ABOVE
SAME AS lb/2 ABOVE
recovery (typo)
SG-12
Bearing Lift Pump
CTRL Rod Drive Mech Fan
IWR BRG CLR
CCW RETURN
THERMAL BARRIER CCW RET
4/4
5b/4
7/5
24/9
32c/15
7/3
7/3
7/3
CST CROSSTIE
VALVE
BIOCK VAIVES
CTNMT SPRAY
TO VCT
NR-45
SG STEAMLINE RADIATION
BLOWDOWN RADIATION
SAMPLE LINE, RADIATION
UI CST TO U2 XTIE
RELIEF LINE BLOCK
NORMAL
2-SG-12
MONITOR
BLOWDOWN TREATMENT
BLOWDOWN SAMPLING
APPENDIX D
LIST OF ABBREVIATIONS
AER
ASW
BAST
BIT
DCRDR
GTG
NR
NRC
PZR
RNO
SDD
VRV
Action/Expected
Response
Abnormal Procedure
Auxiliary Service Water
Boric Acid Storage
Tank
Boron Injection Tank
Containment Auxiliary Subpanel
Component Cooling Water
Condensate
Storage
Tank
Detailed Control Room Design Review
Emergency
Core Cooling System
Emergency Operating Procedure
Emergency
Response
Guidelines
Essential
Generic Technical Guidelines
Institute of Nuclear Power Operations
Loss of Coolant Accident
Main Steams Isolation Valve
Non-essential
Narrow Range
Nuclear Regulatory
Commission
Procedure
Generation
Package
Power Operated Relief Valve
Pressurizer
Quality Assurance
Pump
Response
Not, Obtained
Reactor Protection
System
Reactor Vessel Level Instrumentation
System
Refueling Water Storage
Tank
Step Deviation Document
Safety Evaluation Report
Safety Injection
Setpoint Document
Senior Reactor Operator
Turbine Driven Auxiliary Feed
Pump
Three Mile Island
Volume Control Tank
Validation and Verification
Owners
Group
~
J