ML17321A770

From kanterella
Jump to navigation Jump to search
Insp Repts 50-315/85-21 & 50-316/85-21 on 850715-18. Violation Noted:Failure to Properly Implement Westinghouse Refueling Procedure FP-AEP-R8 by Not Signing Completed Procedures & Signing Procedures Not Yet Started
ML17321A770
Person / Time
Site: Cook  American Electric Power icon.png
Issue date: 08/08/1985
From: Eng P, Milbrot W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML17321A769 List:
References
50-315-85-21, 50-316-85-21, IEB-84-03, IEB-84-3, NUDOCS 8508130253
Download: ML17321A770 (16)


See also: IR 05000315/1985021

Text

U. S.

NUCLEAR REGULATORY COMMISSION

REGION III

Repor t No. 50-315/85021(DRS);

50-316/85021(DRS)

Docket No. 50-315;

50-316

License

No. DPR-58;

and

DPR-74

Licensee:

American Electric Power Service Corporation

Indiana

and Michigan Power

Company

1 Riverside

Plaza

Columbus,

Ohio 43216

Facility Name:

D.

C.

Cook Nuclear Plant, Units

1 and

2

Inspection at:

D. C.

Cook Site,

Bridgman, Michigan

Inspection Conducted:

July

15 through

18,

1985

Inspectors:

P. L. Eng

Date

M. E. Miibro~ g.

a

Approved By:

ll. G. Guldemond,

ief

Operational

Programs

Section

Da

e

ate

Ins ection

Summar

Ins ection

on Jul

15 throu

h Jul

18

1985

Re ort No. 50-315/85021

DRS;

RS

reas

ns ected:

outine,

announced

inspection of licensee

actions

on previous

inspection fin ings; inservice testing

program for valves; refueling activities;

and licensee

actions

regarding

IE Bulletin 84-03.

The inspection

involved a

total of 50 inspector -hours onsite

by two

NRC inspectors.

Results:

Of the four areas

inspected,

one violation was identified (failure

Co foCTow procedures

- Paragraph

4).

e

8508i30253 850808

'DR

ADDCK 05000315'

PDRQ

I

I

'I

(

DETAILS

1.

Persons

Contacted

  • W.
  • J
  • K.
  • N

T.

  • A.
  • J
  • C
  • L

M.

T.

  • M
  • T
  • R
  • T
  • J
  • M.
  • S

G. Smith, Jr., Plant Manager

D. Allard, Maintenance

Superintendent

R. Baker, Operations

Superintendent

Baker, guality Control Department Assistant

P. Beilman, Planning Supervisor

A. Blind, Assistant Plant Manager

R. Bobay, Project Superintendent

- Planning

A. Freer, guality Control/ Inservice Inspection

S. Gibson, Technical

Superintendent

L. Horvath, guality Assurance

Supervisor

Kriesel, Technical

Superintendent

- Physical

Sciences

A. Lester, Senior Performance

Engineer

K. Postlewait,

Performance

Supervisor

Simms, Station Superintendent

R. Stephens,

Performance

Engineer - Operations

F. Stietzel, guality Control Superintendent

S. Ackerman, Nuclear Safety

5 Licensing,

AEPSC

A.

Mc Aligott, guality Assurance Auditor, AEPSC

  • Denotes those attending

the exit interview held

on July 18,

1985.

Additional plant technical

and administrative

personnel

were contacted

during the course of the inspection.

2.

Action of Previous

Ins ection Findin

s

a

~

b.

C.

(Cl osed) Violation (315/84-13-Ol(DRS);

316/84-15-01(DRS) )

Turbine

Driven Auxiliary Feed

Pump

(TDAFP) discharge

pressure

allowed to

violate Technical Specification

(TS) limits.

The licensee

has

submitted

a proposed

TS change clarifying temperature

bases

for

TS

limits on the

TDAFP and deleted

the provision for temperature

compensation

from the

TDAFP test procedure.

(Open)

Unresolved

Item (315/84-13-03(DRS);

316/84-15-03(DRS) ):

Response

time testing of the turbine driven auxiliary feedwater

pump

per technical specification requirements.

This item remains

open

as

the licensee

has not identified the test method to be used.

The

licensee

indicated that testing would be performed in conjunction

with the

TDAFP test scheduled

during the startup of Unit 1 and the

next scheduled

quarterly

TDAFP test for Unit 2.

(Closed)

Unresolved

Item (315/84-12-03(DRS);

316/84-14-03(DRS));

96

hour operability determination.

The licensee

has incorporated

the

action limits for the inservice testing of pumps into the test

procedures

and inserted operability limits into the technical

data

book located in each unit's control

room, thereby providing the data

for operability determination

immediately following completion of

surveillance testing.

I

7

3

,II

~

I

I

1l

e

tI

1

d.

(Closed) Violation (315/84-13-06(DRS);

316/84-15-06(DRS)):

Failure

to implement

an inservice testing

program conducive to identifying

conditions adverse to quality.

The licensee

has taken the following

actions in response

to the violation:

(1)

Limiting stroke times for valves are being revised.

The

licensee

has identified alert and action times in accordance

with Code requirements for valves

based

on the first four

inservice test times

obtained following initial implementation

of the inservice testing program.

The licensee

stated that

these

times will be used for component operability determination

by December

31,

1985.

(2)

The licensee

has revised its valve stroke time records to

include all stroke time data including post modification and

maintenance

data.

In addition,

an increased

frequency log has

been established

to document those valves which are tested

on

increased

frequency.

A matrix of like valves to be used for

evaluation of generic

concerns

is being prepared

and will be in

use

by December

31,

1985.

Program level documentation for valve

problems is addressed

in licensee

procedure

12-gHP-5070ISI.014,

"ISI Valve Data Recording

and Corrective Action for Power

Operated

Valves," Revision 0, dated April 1, 1985.

The inspector

provided

an information copy of an Office of Nuclear Reactor

Regulation

(NRR) memo, attached,

clarifying the

NRC interpretation

of maximum stroke time requirements for inservice testing of

valves.

(3)

The licensee

stated that

a fixed set of maximum valve stroke

time alert and action ranges,

which are in accordance

with Code

acceptance criteria, will be used to determine

the status of the

valve in lieu of the percent

increases

of valve stroke times

as

defined in Section

XI of the American Society of Mechanical

Engineers

(ASME) Boiler and Pressure

Vessel

Code,

1974 Edition

including the appropriate

addenda.

Changes

to these

acceptance

criteria will be evaluated

in a manner similar to that described

in Section

XI for pump reference

value changes.

Licensee

procedure

12-(HP-5070ISI.014

requires that infrequently tested

valves exhibiting unacceptable

increases

in stroke times

be

evaluated

or repaired prior to mode change of the affected unit.

This is acceptable.

With regard to leak test trending, the licensee

stated that they

have requested relief from the trending requirements for

containment isolation valves (CIV); however, trending will be

performed for leak tested

valves which are not CIVs.

This

matter is discussed

further in Paragraph

3.

The licensee

has effectively addressed

the concerns identified by

the violation.

e.

(Open) Unresolved

Item (315/84-13-07(DRS);

316/84-15-07(DRS) ):

Remote position indication verification of all valves.

The licensee

responded

to this item by letter dated April 12,

1985, indicating

4

I

ll

I

I

II

I

I=

that remote position verification for Unit 1 valves will be completed

prior to the end of the current outage; Unit 2 valves will be

completed

by the end of the unit's next scheduled

outage.

The

inspector

expressed

concern that procedures for verifying remote

position indicators for accessible

valves

have not been written.

The licensee

maintains that remote position verification for Unit

1

valves will be completed prior to the end of the current outage;

Unit 2 valves will be completed

by the end of the unit's next

scheduled

outage.

This item remains

open pending completion of the

licensee's

commitment in their April letter.

(Open)

Open

Item (315/84-13-08(DRS);

316/84-15-08(DRS) ): Recording

first stroke for valve timing.

The licensee

has

issued

a

memo to

equipment operators

and operations staff requiring that the first

stroke time for a valve be used for operability determination.

In

addition, the licensee

is in the process

of incorporating the

requirement into all valve stroke time procedures.

This item

remains

open pending inspector review of the procedures

and test

data.

(Open)

Open

Item (315/84-13-09(DRS);

316/84-15-09(DRS)):

Valve

stroke time limits not provided to maintenance for post modification

testing.

The licensee

stated that the method of providing the

revised stroke times discussed

in Paragraph

2.d.(1) for post

modification/ maintenance

testing

has not yet been determined

but

will be accomplished

by December

31,

1985. Availability and review

of post maintenance/

modification test data will be reviewed in

subsequent

inspections.

(Closed)

Open Item (315/84-13-10(DRS);

316/84-15-10(DRS) ): Review of

valve leak test data for validity.

The licensee

has revised

procedure

12 THP 4030.STP.226,

"Surveillance Test Procedure

RHR and SI System

Check Valves," to include

a precaution

statement

addressing verifica-

tion of zero valve leak rates with regard to magnetically coupled

rotameters.

The licensee

has evaluated

previous valve leak test data

and found it acceptable.

(Closed)

Open

Item (315/84-13-12(DRS);

316/84-15-12(DRS)):

Correlation of January

bearing

temperatures

to summer conditions.

The licensee

has

rescheduled

inservice testing annual

bearing

temperature

measurements

to August.

(Closed)

Open item (315/84-13-13(DRS);

316/84-15-13(DRS)):

Use of

acceptance

ranges for both flow and pressure

during inservice

testing of pumps.

The licensee

stated that due to flow anomalies,

achieving the exact reference

value flow was extremely difficult,

and flow and the corresponding

observed

pressure

used to determine

pump operability were subject to the limitations and instrument

requirements

delineated

in the

ASME Code.

The inspector

reviewed the

licensee's

records

and correction factor

used for correcting test

pressures

based

on observed

flow and found them acceptable.

II

I

I

ti

II

t,

~

j,

II

'l F

Il

Inservice Testin

Pro

ram for Valves

During the review and discussions

with members of the licensee's

staff

regarding closure of the violation discussed

in Paragraph

2.d of this

report, the inspector noted that the licensee

had not addressed

trending

and evaluation

requirements for valve leak testing

as delineated

in Sub-

sections

IWV-3420f and

IWV-3420g of Section XI.

The inspector provided

a

copy of a

memo from NRR, attached,

regarding valve leak testing

and stated

that the requirements

of IWV-3420f and

IWV-3420g apply.

The licensee

repre-

sentatives

stated that they would evaluate

the position stated in the subject

memo and seek further clarification from NRR on this subject.

Implementation

of valve leak test trending by the licensee

per the

Code requirements

or the

granting of relief from said requirements

by the Commission will be tracked

as

an open item (315/85021-01(DRS);

316/85021-01(DRS)).

No violations or deviations

were identified.

Refuel in

Pre arations

The inspector

reviewed procedures,

tests

and surveillances

covering the

maintenance,

testing

and operational

check out of refueling tools,

equipment

and systems

required to support the fuel loading effort to

assure

that the applicable Technical Specifications

have

been included.

Equipment

and components

to be used during the performance of refueling

activities were checked for proper operation

and verified ready for use.

The inspector also reviewed completed surveillances

that had to be met

prior to entry into Mode 6.

The surveillances

were completed

as required.

Fuel handling personnel

training was completed

as required

and results

documented

on

a qualification letter and personal

work experience

records.

The inspector

reviewed several

completed refueling procedures for core

alteration preparations.

The review included recording of required data

and verification sign offs.

Two of the procedures

reviewed were

Westinghouse

Refueling Procedure

FP-AEP-R8, Revision 8, paragraph

9.2.6,

"Reactor Cavity Seal

Ring Installation

and Removal,"

and paragraph

9.2.8,

"Reactor Vessel

Head

Removal

and Installation."

Two record copies

are

maintained of the Westinghouse

refueling procedures.

When the refueling

work area is within a contaminated

area,

a working copy of the procedure

is provided at the job site

and the two record copies

are maintained

in

a contamination free location.

Both record copies

are considered official

copies.

One is retained

by the licensee

and the other by Westinghouse

upon completion of the refueling.

The licensee

has

no administrative

procedures

governing verification sign offs.

When special

sign off

conditions are involved, the licensee will provide additional instructions

in the particular procedure.

No special

instructions covering sign offs

were contained in the refueling procedures

reviewed by the inspector.

Review of the subject refueling procedures

revealed

the following verifi-

cation sign off discrepancies

and inconsistencies:

a.

Procedure

9.2.6, "Cavity Seal Installation", steps

1 through

12.

I

I

I

lj

'\\

E

/H

'4

IV

H

'

lt

Status:

Work complete

Sign offs made in both record copies;

no sign offs made

in working copy.

b.

Procedure

9.2.6,

"Reactor Cavity Seal

Removal", steps

1 through

4

Status:

Work not started

Sign offs made in one record copy;

no sign offs made in

the second

record

copy or working copy.

c.

,Procedure

9.2.8,

"Reactor

Head Removal", item c.

Status:

Work complete

Sign off not made in either record copy; sign off made

in working copy

d.

Procedure

9.2.8,

"Reactor

Head Installation", steps

A through

E.

(Reactor

Head reinstalled temporarily to support

instrumentation

maintenance

work prior to core alterations.)

Status:

Work complete

No sign offs made in either record copy; sign offs made

in working copy.

'tems

a, c, and

d indicate

a lack of control regarding required verifi-

cation signatures'that

identify satisfactory

work completion.

Item b is

a condition where sign offs were

made for a work operation that had not

commenced.

Failure of the licensee to follow refueling procedures

as

required

by Technical Specification 6.8. 1 is

a violation

(315/85021-02(DRS) ) .

No other violations or deviations

were identified.

5.

Followu

of IE Bulletin 84-03, Refuelin

Cavit

Water Seal

On August 24,

1984, the

NRC issued

IE Bulletin

( IEB) 84-03 to all power

reactor facilities.

The IEB, which described

the events

surrounding

a

refueling cavity water seal failure at the

Haddam

Neck facility, required

licensees

to evaluate

the potential for and consequences

of a seal

failure and to submit

a suranary report supporting their conclusions.

On November 27,

1984, the licensee

submitted the required report.

In

that report the licensee identified design differences

between

the seal

used at D. C.

Cook and the seal

used at Haddam Neck, seal installation

techniques

to be followed, the D. C.

Cook postulated

seal failure accident

based

upon the failure of the inflated portion of the seal,

the capacity

of available cavity water makeup

systems,

an assessment

of no fuel becoming

uncovered,

and emergency

procedures

in place to mitigate the consequences

of such

an event.

During the inspection,

the inspector

reviewed the licensee's

response

and

supporting information which included the potential for loss of refueling

cavity and/or spent fuel pit (SFP) water inventory by means other than

N

,I

I

S

II

I"

1

t

cavity seal failure with the following results:

a.

The annulus

between

the reactor vessel

and the refueling floor was

measured

to determine

gap dimensions

and inspected for cleanliness

and uniformity.

The nominal

two inch gap

had

a maximum deviation of

0. 109 inch which is in agreement

with original construction

drawings.

b.

c ~

d.

e.

Prior to seal installation,

a 20 psig bubble test

was performed

on

the entire seal ring.

No leaks were detected.

The annulus

was

inspected for sharp

edges,

burrs, etc., that could damage

the seal.

Discontinuities were removed

as required.

Following installation, seal integrity was confirmed by pressurizing

the seal to 45 psig and verifying a pressure

decrease

of less

than

one

psi for one hour.

Seal

pressure

was then

reduced to the operating

range

(15-35 psig)

and the nitrogen supply line relief valve set at

40 psig.

In addition,

RTV was applied to the vessel-seal

and

refueling floor-seal interfaces.

The licensee

is evaluating cavity seal

receipt inspection require-

ments.

Currently, cavity seal

receipt inspection consists of

inspecting for apparent

shipping

damage

and that the item appears

to

be the item ordered.

The licensee is considering

a revision to the

inspection

acceptance

criteria which will require the vendor to

furnish

a "certificate of conformance" to the licensee

assuring that

the Presray seal,

PRS 585, meets material,

dimension,

and hardness

requirements.

The inspector considers

that the upgraded

seal

receipt inspection

criteria are necessary

to assure

seal acceptability.

Revision of

the licensee's

cavity seal

receipt inspection

requirements will be

tracked

as

an open item (50-315/85021-03(DRS)).

A new seal

or a seal

retained

from a previous refueling may be

installed in the refueling cavity.

The seals

have

been

added to the

plant shelf life program to protect from using

a deteriorated

seal.

Present

shelf life has

been established

at 60 months.

The licensee

has

conducted

an evaluation of fuel height drop.

Based

on an evaluation of Westinghouse

and plant drawings,

the maximum

fuel height drop would be

14 inches.

Testing conducted

by TVA and

Duke have demonstrated

seal

adequacy

based

on

a two foot drop onto

the Presray

585 seal installed in a two inch annulus.

Consequently,

the licensee

does not intend to conduct additional tests.

g.

Procedures

are in effect directing that fuel suspended

from either

the Manipulator Crane or Spent

Fuel Pit (SFP)

crane

be placed in a

safe location to prevent

becoming

uncovered

during

a loss of water

accident.

The procedures

also provide instructions for closing the

Transfer Tube Valve and the Weir Gate

on the SFP.

1

~ H

0,)i

I

,r

I

W

~

II

'I

'

W

lt

II

h.

The licensee

stated that the

SFP could not drain to within two feet

of the stored fuel.

This was

based

on engineering

judgement

following administrative action of aforementioned

procedures

to

recover from a small leak.

It was estimated that should the seal

fail and the

SFP drain to the lowest possible reactor level, seven

inches of water will always cover the fuel.

This is sufficient to

ensure

adequate

cooling.

Fuel in the core will be covered

by

greater levels of water.

i.

The licensee

concludes,

based

on engineering

judgement, that if the

active portion of the seal

(the inflated lower portion)

was to

fail, the passive portion, (the solid wedge

shaped

upper portion) of

the seal

would limit leakage to less

than the makeup capacity of

4500 gallons per hour.

This would provide additional

time for

mitigation.

It is concluded

tha

the licensee

has adequately

resolved the issues

identified in IEB 8 -03 and the

IEB is closed.

During the inspection,

a review was conducted to determine if other

potential

mechanisms for loss of water from the refueling system existed.

These potential

leakage

paths

include NI detector well covers,

sand plug

covers, refueling canal drain covers, refueling cavity floor drain valve,

transfer tube to unit not being refueled,

Residual

Heat

Removal

System,

steam generator

nozzle

dams

and reactor vessel

head 0-ring seal leakoff

line.

Procedures

are in place to verify that all covers

are properly

sealed

and bolted and that valve line ups are correct prior to flooding.

It was determined that none of these potential

leak paths

would lead to

catastrophic failure resulting in water uncovering stored fuel.

It is concluded that the issue of loss of refueling system water

inventory is adequately

resolved.

No violations or deviations

were identified.

6.

~0

Open items are matters

which have

been discussed

with the licensee,

which

will be reviewed further by the inspector,

and which involve some action

on the part of the

NRC or licensee or both.

Open

items disclosed

during

the inspection

are discussed

in Paragraphs

3 and 5.d.

7.

Exit Interview

The inspectors

met with licensee

representatives

(denoted

in Paragraph

1)

on

July 18,

1985, to discuss

the scope

and findings of the inspection.

The licensee

acknowledged

the statements

made

by the inspectors

with

respect

to items discussed

in the report.

The inspectors

also discussed

the likely informational content of the inspection report with regard to

documents

or processes

reviewed

by the inspectors

during the inspection.

The licensee

did not identify any such documents/processes

as proprietary.

j'

~

II

I N

N

r

N

H

li

tl

I