ML17311B104
| ML17311B104 | |
| Person / Time | |
|---|---|
| Site: | Limerick |
| Issue date: | 11/07/2017 |
| From: | V Sreenivas Plant Licensing Branch 1 |
| To: | Stewart G Exelon Nuclear |
| Sreenivas V, NRR/DORL/LPLI, 415-2597 | |
| References | |
| Download: ML17311B104 (1) | |
Text
From:
Sreenivas, V To:
Stewart, Glenn H:(GenCo-Nuc) (Glenn.Stewart@exeloncorp.com)
Subject:
Limerick Generating Station TSTF-542 RAIs : Response Requested by 12-08-2017 Date:
Tuesday, November 07, 2017 1:24:00 PM Attachments:
RAI_Limerick_TSTF_542_final.docx By application dated July 19, 2017 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML17200D096, Exelon Generation Company, LLC (Exelon), (the licensee), requested to adopt Technical Specifications Task Force (TSTF) Traveler TSTF-542, Reactor Pressure Vessel Water Inventory Control, Revision 2, which changes the Technical Specifications (TSs) for Limerick Generating Station, Units 1 and 2 (LGS).
Traveler TSTF-542, Revision 2, was approved by the U.S. Nuclear Regulatory Commission (NRC) on December 20, 2016 (ADAMS Accession No. ML16343B008).
The U.S. Nuclear Regulatory Commission staff has reviewed the Exelon submittal and determined that additional information is required in order to complete the review. The requested additional information is attached; please submit the response by Friday8th, December2017. Also, please note, as a result of anassociatedTSTF application currentlyunderNRC staffreview,ifsupplementalinformation is needed,anadditional generic RAImay be necessary.
Attachment V. Sreenivas Licensing Project Manager NRR/DORL/LPL2-1 (301)415-2597