ML17311A813

From kanterella
Jump to navigation Jump to search
Forwards Insp Repts 50-528/95-03,50-529/95-03 & 50-530/95-03 on 950115-0225.No Violations Noted.One Unresolved Item Re Operability & Reportability of Ecws W/Nonseismically Qualified Instrument
ML17311A813
Person / Time
Site: Palo Verde  
Issue date: 04/19/1995
From: Beach A
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Stewart W
ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR
Shared Package
ML17311A814 List:
References
NUDOCS 9504250060
Download: ML17311A813 (10)


See also: IR 05000115/2002025

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION IV

611 RYAN PLAZADRIVE, SUITE 400

ARLINGTON,TEXAS 76011 8064

APR igm

Arizona Public Service

Company

ATTN:

William L. Stewart

Executive Vice President,

Nuclear

P.O.

Box 53999

Phoenix,

Arizona

85072-3999

SUBJECT:

NRC

INSPECTION

REPORT 50-528/95-03;

50-529/95-03;

50-530/95-03

This refers to the inspection

conducted

by K.

E. Johnston

and the inspectors

identified in the enclosed

report, of this office,

on January

15 through

February

25,

1995,

The inspection

included

a review of activities authorized

for your Palo Verde Nuclear Generating Station,

Units 1,

2,

and 3, facility.

At the conclusion of the inspection,

the findings were discussed

with those

members

oF your staff identified in the enclosed

report.

Areas

examined during the inspection

are identified in the report.

Within

these

areas,

the inspection consisted

of selective

examinations

of procedures

and representative

records,

interviews with personnel.

and observation of

activities in progress.

The results of this inspection

are documented

in the

enclosed

report.

The incorrect assessment

by plant operators of off-normal plant indications in

the safety injection systems of Units

1

and 3,

and the slow resolution

by

operations

management

indicates that your continued attention

appears

warranted

in the area of operator

performance.

We noted that,

in the presence

of nuclear

assurance

personnel

and

an

NRC inspector,

operations

personnel

deviated

from

a prerequisite

step without resolving the discrepancy.

In

addition,

inspection findings indicated continued

weaknesses

in the quality of

maintenance

work

instructions.

While we continue to find that maintenance

personnel

perform to high standards,

they appear to be unnecessarily

challenged with poorly prepared

work instructions.

We recognize that your

staff has initiated efforts to identify specific weaknesses

in the work

planning process

and its implementation.

We encourage

you to effect

improvements.

We noted that Nuclear Assurance activities in operations

and

maintenance

were aggressive

and questioning.

One unresolved

item was identified concerning

the operability and

reportability of the essential

cooling water system'ith

nonseismically

qualified instrumentation,

The issue

involved

a longstanding plant deficiency

which until recently

had received

weak technical

reviews

and low priority for

resolution.

This issue,

as well as several

similar ones

such

as condensate

in

the steam lines to the turbine-driven auxiliary feedwater

pump, indicates

a

continued

need for management

to give priority to unresolved plant

deficiencies.

9504250060 9504iq

PDR

ADOCK 05000528

8

PDR

)~

g q

0

Arizona Public Service

Company

In accordance

with 10 CFR 2.790 of the NRC's "Rules of Practice,"

a copy of

this letter

and its enclosures will be placed in the

NRC Public Document

Room.

Should you have

any questions

concerning this inspection,

we will be pleased

to discuss

them with you.

Sincerely,

. Bill Beach, Director

Division of Reactor Projects

Dockets:

50-528

50-529

50-530

Licenses:

NPF-41

NPF-51

NPF-74

Enclosure:

NRC Inspection

Report

50-528/95-03;

50-529/95-03;

50-530/95-03

cc w/enclosure:

Arizona Corporation

Commission

ATTN:

Nr. Steve

Olea

1200

W. Washington Street

Phoenix,

Arizona

85007

Southern California Edison

Company

ATTN:

T,

E. Oubre,

Esq.

P.O.

Box 800

Rosemead,

California

91770

Arizona Radiat'ion Regulatory Agency

ATTN:

Aubrey V. Godwin, Director

4814 South

40 Street

Phoenix,

Arizona

85040

Maricopa County Board of Supervisors

ATTN:

Chairman

111 South Third Avenue

Phoenix,

Arizona

85003

J

V

0

Arizona Public Service

Company

Palo Verde Services

ATTN:

Curtis Hoskins,

Executive

Vice President

and

Chief Operating Officer

2025

N. 3rd Street,

Suite

220

Phoenix,

Arizona

85004

Akin, Gump, Strauss,

Hauer

and Feld

El

Paso Electric Company

ATTN:

Roy P.

Lessey, Jr.,

Esq.

1333

New Hampshire

Avenue, Suite

400

Washington,

D.C.

20036

Arizona Public Service

Company

ATTN:

Angela K. Krainik, Manager

Nuclear Licensing

P,O.

Box 52034

Phoenix,

Arizona

85072-2034

1

e

E-Hail report to D. Sullivan

(DJS)

E-Hail report to

NRR Event Tracking System

( IPAS)

bcc to

DHB

( IE01)

bcc distrib.

by RIV:

APR

1 9 I995

L. J.

Callan

DRSS-FIPB

Branch Chief (DRP/F,

WCFO)

Senior Project Inspector

(DRP/F,

WCFO)

Leah Tremper

(OC/LFDCB,

HS:

TWFN 9E10)

Resident

Inspector

HIS System

RIV File

Branch Chief (DRP/TSS)

B. Henderson

(PAO,

WCFO)

DOCUMENT NAME: R:/ PV/PV503RP.KEJ

To receive copy cf document, indicate in box: "C" ~ Copy without encl

ur s " "

Copy with enclosures "N

~ No copy

RIV:SRI

KJohnston

04/7 /95

C:DRPF

HJWon

04/g/95

D:WCFO

KEPe kins

04

/9

R

C

D:

R

AB

a

04/ h

95

a

I

i',r

e

E-Mail report to D. Sullivan

(DJS)

E-Mail report to

NRR Event Tracking System

(IPAS)

bcc to

DMB (IE01)

bcc distrib.

by RIV:

APR

1 9 I995

L. J. Callan

DRSS-FIPB

Branch Chief (DRP/F,

WCFO)

Senior Project Inspector

(DRP/F,

WCFO)

Leah Tremper

(OC/LFDCB,

MS:

TWFN 9E10)

Resident

Inspector

MIS System

RIV File

Branch Chief (DRP/TSS)

B. Henderson

(PAO,

WCFO)

DOCUMENT NAME: R:/ PV/PV503RP.KEJ

To receive copy of document, Indicate in box: "C" ~ Copy without encl

ur s " "

Copywith enclosures "N" = No copy

RIV:SRI

KJohnston

04/7 /95

C:DRPF

HJWon

04/g/95

D:WCFO

KEPe kins

04

/9

D:

R

AB

a

04/ i

95

'

~