Proposed Tech Specs Re Min Condensate Storage Tank Indicated Level
ML17310B166
Person / Time
Site: Palo Verde  
Issue date: 03/28/1994
From:
ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML17310B165 List:
References
NUDOCS 9404060111
Download: ML17310B166 (6)


Text

- PLANT SYSTEMS Q)R INFGRMAYIGNGNL+

CONDENSATE STORAGE TANK LIHITING CONDITION FOR OPERATION T

3.7. 1.3 The condensate storage tank (CST) shall be OPERABLE with an indicated level of at least

25. feet (300,000 gallons).

APPLICABILITY:

H S 1, 2, 38, and 4"0.

ACTION:

.With the condensate. storage tank inoperable, within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> either:

a.

. Restore the CST to OPERABLE status or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in HOT SHUTDOWN within the following 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />, or b.

Demonstrate the OPERABILITY of the reactor ma'keup water tank as a

backup supply to the essential auxiliary feedwater pumps and restore the condensate storage tank to OPERABLE status within 7 days or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in HOT SHUTDOWN with a OPERABLE shutdown cooling loop in operation within the following 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />.

SURVEILLANCE RE UIREHENTS 4.7.1.3.1 The condensate storage tank shall be demonstrated OPERABLE at least once per 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> by verifying the level (contained water volume) is within its limits when the tank is the supply sdurce for the auxiliary feedwater pumps.

4.7.1.3.2 The reactor makeup water tank shall be demonstrated OPERABLE at least once per 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> whenever the reactor makeup water tank is the supply source for the essential auxiliary feedwater pumps by verifying:

a.

That the reactor makeup water tank supply line to the auxiliary feed-water system isolation valve is open, and b.

That the reactor makeup water tank contains a water level of at least 26 feet (300,000 gallons).

"Until the steam generators are no longer required for heat removed.

Not applicable when cooldown is in progress.

PALO VERDE - UNIT 1 94040S0XZS 940me PDR ADQCfC 050005Z8 P

PDR 3/4 7-6 AHENDHENT NO.

27

~

}

~ ~

~

'=QR /NFQRMATIQN QN~g PLANT SYSTEMS CONDENSATE STORAGE TANK LIMITING CONDITION FOR OPERATION 3.7. 1.3 The condensate storage tank (CST) shall be OPERABLE with an indicated level of at least~

eet (300,000 gallons).

9 S APPLICABILITY:,MODS 1, 2, 3,II and 4."A'CT1DH:

With the condensate storage tank inoperable, within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> either:

Restore the CST to OPERABLE status or be in at least.HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in HOT SHUTDOWN yithin the following 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />, or b.

Demonstrate the OPERABILITY of the reactor makeup water tank.as a

backup supply to the auxiliary feedwater pumps and restore the condensate storage tank to OPERABLE status within 7 days or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />. and in HOT SHUTDOWN with a OPERABLE shutdown cooling loop in operation within the following 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />.

SURVEILLANCE RE UIREMENTS 4.7.1.3. 1 The condensate storage tank shall be demonstrated OPERABLE at least once per 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> by verifying the level (contained water volume) is within its limits when the tank is the supply source for the auxiliary feedwater pumps.

4.7, 1.3.2 The reactor makeup water tank shall be demonstrated OPERABLE at least once per 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> whenever the reactor makeup water tank is the supply source for the auxiliary feedwater pumps by verifying:

a.

That the reactor makeup water tank supply line to the auxiliary feed system isolation valve is open,, and b.

That the reactor makeup water tank contains a water level of at least 26 feet (300,000 gallons).

"Until the steam generators are no longer required for heat removed.

Not applicable when cooldown is in progress.

PALO VERDE - UNIT 2 3t4 7-6 AMEHDMEHT HO.

11

4r4

r

~

e ~

J g~QR INFGHMATIGN OÃy'LANT SYSTEMS CONDENSATE STORAGE TANK LIMITING CONDITION FOR OPERATION h~

ivoicarsD 3.7. 1.3 The condensate storage tank (CST) shall be OPERABLE withe level of at least feet (300,000 gallons).

9.

APPLICABILIT:

MODES 1, 2, 3,¹ and 4"¹.

ACTION:

Mith the condensate storage tank inoperable, within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> either:

as b.

Restore the CST to OPERABLE status or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in HOT SHUTDOWN within the following 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />, or Demonstrate the OPERABILITY of the reactor makeup water tank as a

backup supply to the essential auxiliary feedwater pumps and restore the condensate storage tank to OPERABLE status within 7 days or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in HOT SHUTDOWN with a OPERABLE shutdown cooling loop in operation within the follow-ing 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />.

SURVEILLANCE RE UIREMENTS 4.7 '.3.1 The condensate storage tank shall be demonstrated OPERABLE at least once per 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> by verifying the level (contained water volume) is within its limits when the tank is the supply source for the auxiliary feedwater pumps.

4.7. 1.3.2 The reactor makeup water tank shall be demonstrated OPERABLE at least once per 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> whenever the reactor makeup water tank is the supply source for the essential auxiliary feedwater pumps by verifying:

a ~

b.

That the reactor makeup water tank supply line to the auxiliary feedwater system isolation valve is open, and That the reactor makeup water tank contains a water level of at least 26 feet (300,000 gallons).

"Until the steam generators are no longer required for heat removed.

¹ s

Not applicable when cooldown is in progress.

PALO VERDE - UNIT 3 3/4 7-6