Ack Receipt of Providing Addl Info to Suppl 911024 Response to 910920 Notice of Violation Re Acceptance Criteria for MOV Dynamic Testing.Nrc Understands That Util Intends to Review Proposed Time Frame for Data Evaluation
ML17306A948
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 08/27/1992
From: Miller L
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To: Conway W
ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR
References
NUDOCS 9209090038
Download: ML17306A948 (4)


Text

~h hEoy~

~4 O

~e

~ifl c

4'p~

n +a*t+

UNITED STATES NUCLEAR REGULATORYCOMMISSION REGION V 1450 MARIALANE WALNUTCREEK, CALIFORNIA94596-5368 QUQ 2V 1992 Docket Nos. 50-528 50-529 50-530 Arizona Public Service Company P. 0. Box 53999, Station 9082 Phoenix, Arizona 85072-3999 Attention:

Hr. Milliam F.

Conway

, Executive Vice President, Nuclear

References:

I.

2.

3.

Gentlemen:

Letter from 0. Kirsch, Chief, Reactor Safety Branch, NRC, to M. F. Conway, Executive Vice President,

Nuclear, APS, dated September 20, 1991.

Letter from M. F. Conway, Executive Vice President,

Nuclear, APS to U.S. Nuclear Regulatory Commission, dated October 24, 199).

Letter from 0. Kirsch, Chief, Reactor Safety Branch, NRC, to M. F. Conway, Executive Vice President,

Nuclear, APS, dated February 28, 1992.

Thank you for your letter of July 10, 1992.

The letter provided additional information to supplement your original reply (Reference

2) to Notice of Violation A (Reference
1) concerning acceptance criteria for motor-operated valve (HOV) dynamic testing.

Your letter addressed the additional acceptance criteria discussed in Reference 3 that you expect to include for verification of NOV 'operability.

Me are concerned about the timeliness of your evaluation of test data, specifically, that you intend to return HOVs to service before verifying compliance with your test acceptance criteria.

These concerns were discussed with members of your staff on August 21 and 24, 1992.

Me understand that you intend to review your proposed time frame for data evaluation and provide additional information to the NRC addressing the issue of timeliness by September 21, 1992.

m090900s8 saosa7 ~

PDR ADDCK 05000528 8

PDR

~/

gr~l

Your corrective actions will be v'erified in a future inspection.

Your cooperation with us is appreciated.

Sincerely,

~

~

L. F. Hiller, Jr., Chief Reactor Safety Branch cc'r.:0. Hark DeNichele, APS Hr. James M. Levine, APS Hr. R. Stevens, APS Hr. S. Guthrie, APS Hr. Thomas R. Bradish, APS Hr. Robert M. Page, APS

's.

Nancy C. Loftin, Esq.,

APS Hr. Al Gutterman, Newman

& Holtzinger Hr. James A. Boeletto, Esq., Assistant Counsel, SCE Company Hr. Charles B. Brinkman, Combustion Engineering, Inc.

Hr. Milliam A. Mright, Acting Director, Arizona Radiation Regulatory Agency

=

Chairman,'aricopa County Board of Supervisors Hr. Steve H. Olea, Chief Engineer, Arizona. Corporation Commission Hr. Curtis Hoskins, El Paso Electric Company Roy P. Lessey, Jr., Esq., Akin, Gump, Strauss, Bauer and Feld Bradley M. Jones, Esq., Akin, Gump, Strauss, Hauer and Feld Hr. Jack R.

Newman, Esq.

(Newman

& Holtzinger)

DCorporandy s/z.v/ q m ES NO HRoyack FQp/ez-YES NO N

TO PDR ES NO S

TO DCS E

NO

bcc w/copy of letter dated July 10, 1992:

Docket File Resident Inspector Project Inspector G.

Cook R.

Huey B. Faulkenberry J. Hartin bcc w/o copy of letter dated July 10, 1992:

H. Smith J. Zollicoffer Region V/ann