ML17304B064

From kanterella
Jump to navigation Jump to search
Reactive Insp Repts 50-528/89-02,50-529/89-02 & 50-530/89-02.Violations Noted.Major Areas Inspected:Util Fire Protection Program,As Followup on Five Allegations Received by NRC
ML17304B064
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 02/24/1989
From: Andrea Johnson, Ramsey C, Richards S
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To:
Shared Package
ML17304B063 List:
References
50-528-89-02, 50-528-89-2, 50-529-89-02, 50-529-89-2, 50-530-89-02, 50-530-89-2, NUDOCS 8903150019
Download: ML17304B064 (30)


See also: IR 05000528/1989002

Text

-

U. S.

NUCLEAR REGULATORY COMMISSION

REGION V

Report

Nos.

50-528/89-02,

50-529/89-02,

50-530/89-02

Docket Nos.

50-528,

50-529,

50-530

License

Nos.

NPF-41,

NPF-51,

NPF-74

Licensee:

Arizona Nuclear

Power Project

P.O.

Box 52034

Phoenix,

Arizona 85072-2034

Facility Name:

Palo Verde Nuclear Generating Station Units 1, 2,

and

3

Inspection at:

Phoenix,

Arizona

Inspection

conducted:

January

9-13,

1989

Inspectors:

Joh'on,

Enforcement Officer

C.

amsey,

Reactor Inspector

Approved by:

S.

Richards,

Chief

Engineering Section

D te Si

ned

pe

Date Signed

29 89

Date Signed

~Summer:

Ins ection Durin

The Period Januar

9-13

1989

Re ort Nos.

50-528/89-02,

50-529/89-02

and 50-530/89-02

Areas Ins ected:

An unannounced

reactive inspection of the licensee's fire

protection program

by two regional

inspectors

to followup on allegations

received

by the

NRC.

Results:

General

Conclusions

and

S ecific Findin

s

1.

Two of the allegations

were substantiated.

One of the substantiated

allegations

regarding offsite fire department

assistance

resulted in a

violation of NRC requirements

and the other resulted in an open item that

will require

subsequent

NRC followup on corrective actions that have

been

initiated by the licensee.

2.

Two of the allegations

were partially substantiated.

However,

based

on

corrective actions

taken

by the licensee,

no further

NRC action is

required.

'-v~9~04.t ~ll.)()g '.)

O'W

e-))Ag(}i A..<()a.')q!

3.

One allegation

was not substantiated.

Therefore,

no further

NRC action

is required.

Si nificant Safet

Matters:

The violation concerning offsite fire department

assistance,

and the unresolved

item concerning qualifications of the fire

protection staff, are considered

to be significant safety matters.

During the

inspection,

the licensee

indicated that corrective action would be taken

expeditiously regarding the assistance

of offsite fire departments.

The.

licensee

had already initiated training to improve the qualifications of the

fire protection staff prior to the inspection.

According to the licensee,

training for the fire protection staff will be

a continuing process until

their qualifications meet or exceed

the criteria specified in ANSI 3. 1.

These

corrective actions will be verified by the

NRC during subsequent

inspections.

Summar

of Violations:

One violation was identified.

Summar

of Deviations:

None

Summar

of 0 en Items:

One

new unresolved

item and

one

new open item were

identified.

DETAILS

1.

Persons

Contacted

Arizona Nuclear'ower

Pro ect

"J.

Haynes,

Vice President,

Nuclear Production

T. Shriver,

Compliance

Manger

"K. Clark,

Lead Compliance

Engineer

"W. Marsh, Director, Nuclear Production

"0. Zeringue,

Manager,

Unit 3

"R. Adney, Assistant Plant Manager

"J. Allen, Manager,

Unit 2

"C'. Thurman,

Manager,

Unit 3

"R. Pontes,

Nuclear Engineering

"T. Thompson,

Nuclear Engineering

"J.

Tench, Acting Director, Site Services

  • L. Souza,

Manager,

equality Audits and Monitoring

"C. Belford, Supervisor,

Fire Protection

"F. Garrett,

Fire Protection

Engineer,

Risk Management

"H. Bieling, Manager,

Emergency Planning/Fire Protection

"A. McCabe,

Manager,

Unit 1 Maintenance

"S. Karimi, Senior Compliance

Engineer

"Denotes

those attending the exit meeting held on January

13,

1989.

2.

Followu

on Alle ation File No.

RV-88-A-0057

On November 8, 1988,

Region

V received information alleging to possible

safety related

concerns

at the Palo Verde Nuclear Generating Station.

Followup activities relative to these

concerns

were performed

by the

inspectors

to address

each of the issues

discussed

in the allegation

and

their implied impact on safe operation of the plant.

Characterization

Alle ation File RV-88-A-0057a - An allegation

was received

by the

NRC indicating that the licensee's

staff did not understand

the

technical

design criteria relevant to required functional testing

o'

carbon dioxide fire suppression

systems.

It was alleged that due to

a lack of familiarity with the system design,

and fear of

inadvertent actuation of the systems

during required functional

testing,

the licensee's

staff falsified test results for the

systems.

It was further alleged that one individual's employment

was terminated

by the licensee for falsifying carbon dioxide system

functional test records,

but that the licensee's

investigative staff

believed that another individual, who is currently employed

by the

licensee,

was also involved in the falsification of the test

records.

i

Im lied Si nificance to Plant Desi

n

Construction

or 0 eration

The licensee's

operations staff may not be adequately

trained in the

design

and operation of carbon dioxide fire suppression

systems.

Therefore,

these

systems

are not properly being verified operable in

accordance

with Technical Specification requirements.

Assessment

of Safet

Si nificance

Carbon dioxide fire suppression

systems

are required to be verified

operable

through periodic functional testing to ensure their ability

to extinguish

a fire that threatens

redundant

safe

shutdown trains.

The operability of these

systems

is placed in question

by the

'lleged

falsified surveillance test results.

The inspectors

interviewed cognizant licensee

personnel

and examined

two reports of investigation relating to the termination of two

licensee

employees.

One of the investigations

was performed

by the

ANPP Affirmative Action Group,

dated

November 2, 1987,

and the other

investigation (involving falsification of surveillance test record

No.

14MT-9FP08

on August 1, 1987)

was performed

by the site security

group,

dated August 18,

1987.

The reports

were found to be detailed

and substantive,

and provided the basis for the licensee's

termination of the employees.

With respect to the allegation that another individual was involved

in the instance

of falsification of carbon dioxide fire suppression

system surveillance test records,

an individual who participated in

the site security group investigation dated August 18,

1987, stated

that

he did not believe

any other individuals employed

by the

licensee

were involved.

He documented

in the investigation report

that the working environment significantly contributed to the

confusion

and error that resulted in the termination of the

individual who performed the test.

The investigation reports

concerning the falsification of the test record did not support the

allegation that anyone other than the employee that was terminated

was involved.

The falsification of the test record

was immediately detected

by

licensee

personnel.

The falsification involved recording

a volt

meter identification number

on the test record other than the one

that was actually used in the test.

Although the wrong voltmeter

was

used in the test

by the individual who was terminated,

the

individual recorded unsatisfactory

conditions at steps

in the test

procedure

where the voltmeter was

used

and additionally noted that

there

was

no receipt of an alarm in the control

room when expected.

(i.e.

step

No. 8.2.3.3 of the August 1,

1987 test).

The falsified

test

was declared

void prior to acceptance

of the test results.

The

test

was re-run

on August 5,

1987 and satisfactory results

were

obtained.

However, this test identified the

same deficiencies at

the procedural

steps

requiring the

use of a calibrated voltmeter and

alarm receipt in the control

room.

i

Staff Position

Partially Substantiated

- Based

on the inspectors'ollowup

activities,

the inspectors

substantiated

that one licensee

employee

was terminated for falsifying carbon dioxide fire suppression

system

functional test records,

and the licensee's fire protection staff

was not adequately

trained to perform this testing.

The inspectors

found no evidence that other individuals currently employed by the

licensee

were involved in falsification of the test records.

This

portion of the allegation was not substantiated.

Action Re uired

The licensee

has initiated a training program to upgrade

the

qualifications

and training of the fire protection staff.

This is

further discussed

in paragraph

2.D of this report.

B.

Characterization

Alle ation File RV-88-A-0057b - An allegation

was received

by the

NRC indicating that the licensee's

quality assurance

staff did not

followup on other

safety related work that was performed

by an

individual that the'icensee

terminated for falsifying test records.

Im lied Si nificance to Plant Desi

n

Construction

or 0 eration

The licensee's

guality .Assurance

Department

may not be properly

addressing

quality verification and root cause analysis

in the area

of work performed

by individuals.

Therefore,

the ability of

important to safety equipment to perform its intended safety

function may not be systematically verified by the licensee's

quality assurance

program.

Assessment

of Safet

Si nificance

The inspectors

intervewed cognizant licensee

personnel

and examined

the licensee's

guality'Assurance

Investigation Report

No.87-072.

The licensee

performed this investigation in response

to a "Hot

Line" concern that was phoned in by the employee

who was terminated

by the licensee

for 'falsifying the carbon dioxide fire suppression

system functional test discussed

in item 2.A above.

The quality assurance

investigation report was substantive

and

contained detailed information about the work performed

by the

individual who was terminated.

In an interview with the inspectors,

the quality assurance

investigator,

who was the author *of the

report, stated that the terminated individual had not performed

any

other safety related work.

He stated that the individual's work had

been limited to firefighting duties

and visual surveillance

of

firefighting equipment.

The quality assurance

investigator

also

stated,

and his report documents,

his conclusion that the terminated

individual had never performed

a carbon dioxide functional test

before.

The report further concludes that training on the test

procedure

and the

use of calibrated test equipment,

was requested

prior the individual's falsification of the test record,

but in

violation of ANSI 3.1, this training was denied

by the incumbent

fire protection supervisor.

Staff Position

Unsubstantiated

- Based

on the inspectors'nterviews

with cognizant

licensee

personnel

and examination of the licensee's

guality

Investigation

Report

No.87-072, substantial

evidence

was produced

which established

that the licensee

performed

a detailed

investigation of work that was performed

by the individual who was

terminated.

Furthermore, this evidence

showed that the licensee

performed

a comprehensive

root-cause

analysis of the circumstances

which contributed to falsification of the test record by the

terminated

employee.

On this basis,

the inspectors

could not

substantiate

the allegation.

Action Re uired

None

Characterization

Alle ation File RV-88-A-0057c - An allegation

was received

by the

NRC indicating that false information was provided to the

NRC in

Licensee

Event Report

(LER) No.84-001,

and in the Unit 1, July 6,

1988,

Transformer

Fire Post Trip Report.

Specifically, the licensee

stated

in

LER No.84-001, that the cause

of inoperable fire rated assemblies

(a violation of plant Technical

Specifications)

during the period December

1984 to June

1988,

was

cognitive personnel

error.

The alleger stated that the cause of

these conditions

was

a conscious

decision

by plant management

to

omit the subject fire rated assemblies

from Technical Specification

requirements.

Additionally, the licensee

stated in the Unit 1 transformer fire

post trip report dated July 6, 1988, that there

was

no backup power

supply to the transformer

deluge automatic sprinkler valves,

and

that the oil retention pits for the transformers

did not adequately

contain the oil and water during the fire.

Therefore,

the burning

oil flowed down the storm drain into the drainage ditch which

resulted in spreading

the fire outside of the controlled area.

The

alleger maintained that there is

a backup

power supply to the

transformer

deluge automatic sprinkler systems,

and the transformer

oi 1 retention pits have

enough capacity to hold the entire

transformer

lube oil inventory plus ten minutes of simultaneous

automatic sprinkler water flow from all sprinkler

systems.

The

alleger alleged that the reason

the burning oil flowed outside the

controlled area

and spread

the fire, 'is that the oil retention pits

were improperly maintained

and they were"filled with water at the

time of the fire.

The alleger cited these conditions

as

examples of

licensee

management's

inattention to detai

1 in the fire protection

area.

Im lied Si nificance to Plant Desi

n

Construction

or 0 eration

The allegation implies that the licensee

may not have

implemented

and properly maintained

a plant design that is required

by the

facility operating licenses.

Licensee

management

attention to

detail in. the area of fire protection

may not be adequate

to achieve

the relevant expectations

of the

NRC approved fire protection

program requirements

for Palo Verde Units 1, 2,

and 3.

Assessment

of Safet

Si nificance

Regarding

LER No.84-001,

the licensee

provided the inspectors with

a copy of licensee

Technical Specification Interpretation

No.

143

for Section 3/4.7.12 of plant Technical Specifications

dated

September

16,

1985.

The request for this interpretation

was

initiated as characterized

in the allegation.

The management

resolution to the requested

interpretation

reads,

"The phrase,

separating

safety-related fire areas

or separating

portions of

redundant

systems

important to safe

shutdown within a fire area,

applies to the sealing devices that are part of those fire-rated

assemblies

providing safety-related fire area separation,

or

separating

portions of redundant

systems

important to safe

shutdown.

It's these that are required for OPERABILITY to exist".

To acquire

a clear understanding

of the meaning of the management

intent represented

by the interpretation,

the inspectors

interviewed

a licensee

individual who was

an originator of the management

resolution.

This individual stated that the resolution intended

that sealing devices that are part of safety-related fire area

boundaries

and fire area

boundaries

protecting redundant

safe

shutdown

systems

be verified operable

pursuant to plant Technical

Specifications.

According to this individual,

no sealing

devices in

safety-related

fire-area

boundaries

or boundaries

separating

portions of redundant

systems

important to safe

shutdown were

identified as exceptions

to this resolution.

The bases

of Technical Specification

No. 3/4.7. 12 reads,

"The

OPERABILITY of the fire barriers

and barrier penetration

seals

ensure that fire damage will be limited.

These

design features

minimize the possibility of a single fire involving more than

one

fire area prior to detection

and extinguishment."

The licensee's

interpretation of the Technical Specification requirements

appeared

to be consistent with the Technical Specification

bases.

Therefore,

the inspectors

could not establish that the cause of the inoperable

fire barrier penetration

seals

was attributed to a conscious

licensee

management

decision to omit the seals

from the Technical

Specification requirements,

as alleged.

Regarding the licensee's

July 6,

1988 Transformer Fire Post Trip

Report,

the licensee

explained that the concerns

raised

by the

licensee's

staff as

a result of the fire and which were

documented

in the report, did not represent

factual

statements

about the

facility design.

The licensee

acknowledged that the statement

in

the report concerning

a backup

power supply to the transformer

deluge

sprinkler systems

was incorrect.

In response

to this concern,

as

stated in the post trip report,

the licensee

issued

Engineering

Evaluation Report

(EER) No. 88-FP-155,

dated July 12,

1988.

The

EER

dispositioned

the concern

by verifying that backup

power supplies to

the transformer

deluge automatic sprinkler systems

already existed

from two sources

(Uninteruptable

Power Supply E-gDN-N02 and diesel

generators).

Therefore,

manual initiation of the deluge sprinkler

systems for all the transformers

was not necessary

as described

in

the post trip report.

Regarding the capacity of the transformer oil retention pits, the

licensee is basically required to meet the requirements

of NFPA 15

and

NFPA 92M.

The licensee

provided the inspectors with Bechtel

Corporation Calculation

No. 13-CC-2V-110,

Job

No. 10C07-002,

sheets

171,

172 and

173 of 228, which demonstrates

that the oil retention

pits are capable. of containing the oil from the largest transformer,

together with the water from the deluge water

spray sprinkler

systems

operating simultaneously for ten minutes.

Deluge sprinkler

flow is calculated at 1,730 gallons per minute for two systems

operating simultaneously for ten minutes,

or 17,300 gallons.

The

volume of oil from the main transformer is calculated to be 12,000

gallons.

The total storage

capacity of the oil retention pits is

calculated to be 29,300 gallons with the four bays of the pits

connected

by underground piping.

There are six deluge sprinkler

systems protecting six transformers.

Therefore, if the oil from all

six of the transformers,

and sprinkler water from all of the deluge

water spray sprinkler systems

discharged

simultaneously,

the pits

would not have the capacity to contain this volume.

However the

overflow from the retention pits would be to a safe location,

such

that

no safety related

equipment would be

damaged.

This design

satisfies

the intent of NFPA 15-1977 sprinkler water

drainage

requirements

as specified in NFPA 92M and the

NRC approved fire

protection program.

The licensee

was not certain of the condition of the retention pits

at the time of the July 6,

1988 transformer fire.

However, the

licensee

stated that the pits have

been

observed to contain water,

and they may have contained water at the time of the fire.

There

was

no maintenance

program established

for the pits at the time of

the fire.

The licensee

indicated that consider ation was being given

to increasing

the capacity of the pits and establishing

a

maintenance

and surveillance

program to ensure availability of the

retention capacity.

Staff Position

Partially Substantiated

- Based

on the inspectors'followup

activities, the inspectors

did not substantiate

that the. cause of

the inoperable fire barrier penetration

seals

discussed

in

LER No.84-001

was

a conscious

decision

by licensee

management

to omit the

seals

from Technical Specification

requirements.

The inspectors

did

not substantiate

that the transformer oil retention pits had the

capacity to hold the entire inventory of oil from all of the

transformers

and water flow from the deluge water spray sprinkler

systems

simultaneously,

however the inspectors

concluded that the

design of the retention pits meet the applicable

NRC requirements.-

The inspectors

did substantiate

that the licensee

did not have

a

maintenance/surveillance

program established

for the transformer oil

retention pits.

Because all the deluge

systems

were activated

manually during the July 6 event

and the duratibn of the water flow

was not recorded,

the inspectors

could not establish that the lack

of a maintenance/surveillance

program

was the cause of the burning

oil flowing down the storm drains

and spreading

the transformer fire

outside of the controlled area.

The inspectors

substantiated

that

the lack of an established

maintenance/surveillance

program for the

transformer oil retention pits at the time of the transformer fire

was

an example of the licensee's

inattention to detail in the fire

protection area.

Action Re uired

The licensee

indicated that

a maintenance/survei-llance

program would

be established

for the transformer oil retentiOn pits.

The

potential for the oil and fire suppression

water inventory to

overflow from the pits and expose

other. safety related

equipment

has

generic implications

and will receive further

NRC followup.

This is

considered

an open item (528/89-02-01)

pending further licensee

and

NRC action.

Charaterization

Alle ation File RV-88-A-0057d - An allegation

was received

by the

NRC indicating that the licensee's

operations fire protection staff

was not qualifi'ed through training and experience

to implement the

program requirements.

The alleger cited one example that is

contained in the licensee's

LER No.88-005.

This

LER reported to

the

NRC that the root cause of an event that led to. isolation of the

Unit 1 fire protection water supply loop, which rendered

required

fire suppression

systems

inoperable,

was personnel

error,

and

an

inadequate

procedure.

The alleger stated that the reason

the

licensee's fire protection staff isolated the Unit 1 fire protection

water supply was that they did not have the required expertise to

read the appropriate

P&ID's for the system.

The allegation further states

that the current Operations

Fire

Protection Supervisor did not have the required

knowledge

and

expertise

to implement the fire protection program requirements,

and

that the licensee

did not have

a technical

basis for using Bisco and

ICNS penetration

seal materials to seal fire barrier penetration

openings

in Unit 1.

The alleger also stated that these materials

may not be compatible,

and

as

a mixture, the fire rating of the

materials

has not been established.

The licensee

is required to use

materials

whose qualifications

have

been established

by test for

fire barrier protection of redundant

safe

shutdown trains.

Im lied Si nificance to Plant Desi

n

Construction

or

0 eration

The licensee's

operations fire protection staff may not be qualified

to implement the program requirements.

Unqualified materials

may be

used in Unit 1 as fire barrier protection for safe

shutdown trains.

Assessment

of Safet

Si nificance

Regarding

LER No.88-005, the licensee

acknowledged that the fire

protection staff had difficulty reading the PAID's for the fire

protection water supply system.

However,

the licensee

stated that-

the staff's difficulty in determining the correct method of

isolation of the system did not contribute to the system being

inoperable for more than

24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

According to the licensee,

the

system

was isolated in a manner to declare it inoperable

because

of

leaking Post Indicator Valves (isolation valves).

As corrective

action for LER No.88-005,

the licensee

developed

an enlarged

composite,

one line diagram of the fire water isolation system,

implemented

new procedure

No.

140P-OFP05

and conducted training

sessions

to provide direction to the fire protection staff on the

proper methods of .isolating the system.

Regarding the qualifications of the licensee's fire protection

staff, the Licensee's guality Assurance

Investigation

Report

No.87-072 identified that the staff was not properly trained

on

seventy-three

percent of 82 procedures

that they were required to

perform.

The qualifications of the staff are governed

by the

FSAR and

ANSI

3.1-1978Property "ANSI code" (as page type) with input value "ANSI</br></br>3.1-1978" contains invalid characters or is incomplete and therefore can cause unexpected results during a query or annotation process..

A suitable training program is required to be established

for managers,

supervisors,

professional

operators,

technicians

and

maintenance

personnel

to properly prepare

them for their

assignments.

Technicians

and maintenance

personnel

are required to

be trained on-the-job

by participation in initial calibration,

testing

and equipment

acceptance

programs.

Technicians

are required

to have three years of working experience

in their speciality of

which one year is required to be related to technical training.

In response

to Corrective Action Report

(CAR) No.

Cg87-0099 for the

training deficiencies,

the licensee initiated a training program for

the fire protection staff.

According to the licensee,

the training

program

had not completely- addressed

all of the deficiencies

identified in the guality Assurance

Investigation Report.

When this

training is completed,

the licensee

indicated that

a retraining

program would be established

and documented

to ensure that the

qualifications of the staff would be maintained.

Interviews with

fire protection staff individuals by the inspectors

disclosed that

the training has

been ongoing since January

1988,

and

has

significantly improved the staff's confidence in their ability to

perform assigned fire protection duties.

To further verify the qualifications of the licensee's

fire

protection staff, the inspectors

reviewed the licensee's

job

position descriptions

and personnel

resumes

for the positions of

Fire Protection Supervisor,

Fire Captain

and Fire System Technician.

The licensee's

job position description for the position of Fire

Protection Supervisor

requires that this individual possess

an

intimate knowledge of fire protection

systems

and firefighting

techniques;

thorough

knowledge of nuclear

power plant systems;

NRC

fire protection regulations;

National Fire Protection Association

(NFPA) codes

and standards;

and,

have

a sound understanding

of

engineering

and design principles associated

with fire protection

systems.

The Fire Protection Supervisor's

qualifications described

in the

resume of the individual filling this position does not appear

to

meet the criteria for the licensee's

job position description

and

ANSI 3. 1.

The individual's resume

indicates considerable

experience

in firefighting and emergency

medical

techniques,

but the resume

does

not indicate that this individual possesses

an intimate

knowledge of fire protection systems;

thorough

knowledge of nuclear

power plant systems;

NRC fire protection regulations;

NFPA codes

and

standards;

and

a sound understanding

of engineering

and design

principles associated

with fire protection

systems.

The licensee's

job position description for the position of Fire

Captain requires that these individuals have

a detailed

knowledge of

fire protection

systems,

and

have

a good understanding

of

firefighting and emergency

medical

techniques.

The position

description also requires that these individuals

be skilled in the

operation of firefighting and emergency

medical

equipment.

The Fire Captain's qualifications described

in the resumes

of the

individuals filling these positions indicate that the individuals

have considerable

training and experience

in firefighting, emergency

medical

techniques,

and the operation of firefighting equipment.

Their qualifications

appear to meet

or

exceed

the licensee's

job

position description for Fire Captains,

but these qualifications

do

not appear

to meet the criteria for maintenance

technicians

as

specified

by ANSI 3: l.

The licensee's

job position description for the position of Fire

Technician requires that these individuals have

a good understanding

of fire protection

systems,

and

be knowl edgeabl e concerning plant

safety related

systems

and the effects of fire on these

systems.

The position description requires that these individuals

be

knowledgeable

of plant fire protection maintenance

procedures

and

the system's

operations

procedures,

in additon to posessing

basic

firefighting and emergency

medical technician skills.

These

individuals are required to perform maintenance,

engineering,

and

testing

and update

required engineering

drawings to reflect the

actual condition of fire protection

systems.

,1

10

The Fire Technician's qualifications described

in the

resumes

of the

individuals filling these positions indicate the the individuals

have considerable firefighting and emergency

medical technician

training and experience.

None of the

resumes

reviewed by the

inspectors

indicated that these individuals were qualified by

training or. experience

to perform maintenance,

engineering,

or

testing of fire protection

systems

as specified

by the criteria of

ANSI 3.1.

Regarding the incompatibility of penetration

seal materials

used in

Unit 1, the licensee

provided the inspectors with a licensee

vendor

evaluation (Impell Corporation

No. 1658-045-005,

dated August 4,

1987) of Bisco and

ICMS penetration

seal materials.

The evaluation

co'ncludes that both materials

are formulated from Dow Corning

Sylgard 170,

and can

be mixed together to provide equivalent fire

resistance.

Staff Position

Substantiated

Based

on the inspectors'ollowup activities,

the

inspectors

substantiated

that the licensee's

fire protectioh staff

is not qualified by training and experience

to implement all the

program requirements,

particularly regarding maintenance activities.

The licensee's

guality Assurance

Investigation Report

No.87-072

documented training deficiencies that were in violation of the

FSAR

.and

ANSI 3. 1.

The inspectors

determined that the staff's

qualifications apparently

do not meet the criteria of the licensee's

job position description for the position of Fire Protection

'upervisor

and the maintenance

engineering

work experience

and

training criteria of ANSI 3. 1 for Technicians

and maintenance

personnel.

The licensee initiated corrective action for this concern

in response

to Corrective Action Report

(CAR) No.

Cg87-0099 prior to

the inspector's

followup

activities'he

inspectors

further substantiated

that the licensee

used Bisco

and

ICMS penetration

seal materials to seal penetration

openings

in

fire barriers in Unit 1 without having

a technical

basis for the

compatibility of the materials

and their fire endurance

as

a

mixture.

However, the licensee's

vendor evaluation (Impell

Corporation

No. 1658-045-005)

subsequently

determined that the

materials

are compatible

and as

a mixture, they provide appropriate

fire endurance.

Action Re uired

This is considered

an unresolved

item (528/89"02-02)

pending

completion of the licensee's

corrective actions for the training and

qualifications deficiencies

and verification by Region V.

11

Characterization

Allegation File RV-88-A-0057e - An allegation

was received

by the

NRC indicating that the licensee's

training, coordination

and

offsite fire department

assistance

from the Phoenix Fire Department

is not adequate.

The alleger stated that such training and

coordination is rarely, if ever performed.

Im lied Si nificance to Plant Desi

n

Construction

or

0 eration

Training, coordination

and drills by the licensee with offsite fire

department

assistance

is essential

to the site's

emergency

readiness

capability to combat major fire occurrences.

The allegation implies

that this aspect of the licensee's fire protection program

may not

meet the program requirements

as specified in Sections

B.5(b) and

8.5(c) of Table 9B.3-1 of the

FSAR.

Assessment

of Safet

Si nificance

Offsite fire department

assistance

is required to be provided by the

NRC approved fire protection program

as

implemented

by license

condition, to supplement

the fire brigade in the suppression

of a

fire so that safe

shutdown

can

be achieved

and maintained in the

event of a major fire occurrence.

Staff Position

Substantiated

The inspectors'ollowup activities

and interview with the Phoenix

Fire Department

on January

9,

1989 disclosed

the. following:

Agi cement with the licensee

to provide offsite fire department

assistance

was

made

between the licensee

and the City of

Phoenix Fire Department

on July 19,

1984, prior to the Unit 1

initial startup.

The Phoenix Fire Deparment's

understanding

of

this agreement

is that they are to provide firefighting and

hazardous

material

assistance

for major fire events

involving

non-nuclear

materials,

but they are not required to provide

firefighting assistance

in safety related

areas

in support of

safe

shutdown.

The licensee

has

no other offsite fire

department

assistance

agreement.

(2)

At the time the agreement

was

made

on July 19, 1984,

the

Phoen'ix Fire 'Department's

Hazardous

Material

Team

(3-.5 man

shifts) were given

a familiarization tour of Unit l. It took 2

or 3 days for the three shifts of Hazardous

Material

Team

members to complete the familiarization tour.

Other

than the

familiarization tour, the Phoenix Fire Department

has not

received additional training at the Palo Verde site.

(3)

The Phoenix Fire Department

does not participate in annual

drills at the site and has

neve'r received

any type of

radiological training from the site.

12,

(4)

The licensee

did notify the Phoenix Fire Department to be on

the alert during the July 6, 1988 transformer fire, however,

this was

an unusual

request.

The licensee

does not normally

notify the department of fire occurrences.

(5)

The licensee's

only method of requesting

assistance

from the

Phoenix Fire Department is via commercial

telephone.

(6)

The Phoenix Fire Department's

response

time to the site by

ground transportation

or by helicopter is l-hour.

(7)

The Phoenix Fire Department

does not have

a helicopter

designated

for emergency

response

to the site.

The

department's,helicopter

is shared with another state

department

and

may not be available for this purpose.

According to the

department's

spokesman,

by agreement,

the licensee is required

to provide helicopter transportation for the department if

assistance

is needed.

The licensee

indicated that their

corporate helicopter

may not be available for this purpose

during day shift hours

due to other corporate

needs.

The

helicopter pilot is only available during normal

day shift

hours.

Therefore,

the helicopter is not available during

backshift hours.

(8)

Other than

by agreement with the licensee,

the Phoenix Fire

Department

has

no jurisdiction at the site because

the site is

located in an unincorporated

area.

Therefore,

the department

is not required to respond to fire occurrences

at the site.

(9) If required through agreement,

the Phoenix Fire Department

could dispatch

the following equipment

and manpower to the

site:

60 firefighters

10 fire engines

3 ladder trucks

1500 to 2000 gallons of chemical

foam

1-2000 gallon tanker

2-1000 gallon tanker s

(10) The Phoenix Fire Department

has

no record of training or drills

with the site because

these activities

have not been performed.

(11) The Phoenix Fire Department

has

no preplanned

emergency

strategies

for the site because

such planning with the licensee

has not been performed.

13

'0

Action Re uired

This is considered

a violation of License Condition Nos. 2.c(7),

2.c(6)

and 2.f of Facility Operating

License

Nos.

NPF-41,

NPF-51 and

NPF-74, respectively,

which indicates that Palo Verde has entered

into an agreement with the local offsite fire department for mutual

support,

and will provide appropriate training (528/89-02-03).

The licensee

has since indicated that action

has

been initiated to

correct the above deficiencies.

3.

~Oen Items

Open items are matters that have

been discussed

with the licensee,

that

will be reviewed further by the inspector,

and that involve some action

on the part of the

NRC, the licensee,

or both.

Open items disclosed

during the inspection

are discussed

in paragraph

2.D of the report.

4.

Exit Meetin

30703

An exit meeting

was held with the licensee's

staff on January

13,

1989.

The items of concern in this report were discussed

at that time.

The

licensee

acknowledged

the scope

and content of the inspection findings.

'