Confirmatory Action Ltr,Confirming NRC Understanding of Actions Util Intends to Take Re Evaluation & Analysis of Circumstances Surrounding Introduction of Nonconservative Info Into Channel B Core Protection Calculator
ML17304A222
Person / Time
Site: Palo Verde Arizona Public Service icon.png
Issue date: 06/23/1988
From: Martin J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To: Van Brunt E
ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR
References
CAL, NUDOCS 8806280191
Download: ML17304A222 (4)


Text

ACCELERATED DTRIBUTI ON DEMONSTTION SYSTEM REGULATORY INFORMATION DISTRIBUTION SYSTEM (RIDS)

ACCESSION NBR:8806280191 DOC.DATE: 88/06/23 NOTARIZED: NO ~'OCKET g

FACIL:STN-50-529 Palo Verde Nuclear Station, Unit 2, Arizona Publi 05000529 AUTH.NAME AUTHOR AFFILIATION MARTIN,J.B.

Region 5, Ofc of the Director RECIP.NAME RECIPIENT AFFILIATION VAN BRUNT,E.E.

Arizona Nuclear Power Project (formerly Arizona Public Serv

SUBJECT:

Confirmatory Action Ltr re analysis of nonconservative info introduction into Channel B core protection calculator.

DISTRIBUTION CODE'E35D COPIES RECEIVED'LTR L

ENCL LS.IZE' TITLE: Emergency Preparedness-Appraisal/Confirmatory Action Ltr/Exercise Rep D

NOTES:Standardized plant.

05000529 S

RECXPXENT ID CODE/NAME PD5 PD DAVIS,M INTERNAL: ARM/DAF/LFMB N

S ILRB12 RE FILE 02 RGN2/DR

/EPRPB EXTERNAL: LPDR NSIC NOTES:

COPIES LTTR ENCL 1

1 1

1 1

0 1

1 1

1 1

1 1

1 1

1 1

1 RECXPXENT ID CODE/NAME LICITRA,E NRR/DREP/EPB 10 NUDOCS-ABSTRACT RGN5 FILE 01 "NRC PDR COPIES LTTR ENCL 1

1 1

1 1

1 1

1 1

1 A

j A

TOTAL NUMBER OF COPIES REQUIRED:

LTTR 14 ENCL 13

JUN 23

)98B CONFIRMATORY ACTION LETTER Docket No. 50-529 License No.

NPF-51 Arizona Nuclear Power Project P. 0.

Box 52034 Phoenix, Arizona 85072-2034 Attention:

E.

E.

Van Brunt, Jr.

Executive Vice President Gentlemen:

The purpose of this letter is to confirm our understanding of the actions you intend to take regarding the continued operation of Palo Verde Unit 2 and your evaluation and analysis of the circumstances surrounding the introduction of nonconservative information into the Channel B Core Protection Calculator.

Based on the 'discussions between Messers.

Dennis Kirsch of my staff, Gary Holahan, of NRR, and J.

G. Haynes, of your staff, it is our understanding that your actions will include, but not be limited to, the following:

1.

Complete your evaluation and analysis of the circumstances surrounding the introduction of nonconservative information into Unit 2 Channel B

Core Protection Calculator (CPC).

2.

Verify that the inputs to and operation of all Unit 2 CPCs are correct at 70% power. If any are found to be incorrect, power will not be increased above 70% until NRC and ANPP have agreed that the power can be safely increased.

3.

Verify the operation of Unit 1 CPC channels are acceptable.

4.

Within 30 days, submit a report to Region V, with a copy to NRR, which includes the results of your evaluation and analysis, root cause identified, and specifying the actions taken or to be taken which will preclude recurrence of the conditions or actions that resulted in the errors in the CPC software We understand that a problem with CPC Channel B was identified prior to going critical and Channel B has been in bypass, or tripped, during the investigation of the problem and, therefore, was not relied upon for safe operation of Unit 2.

8806280191 880623 PDR ADOCK 05000529 P

DCD

E.

E.

Van Brunt, Jr.

JUN 2~

1935 If our understanding concerning your proposed actions, as summarized

above, is not correct, you should promptly notify this office in writing.

Sincerely, J.

B. Martin Regional Administrator cc:

J.

G. Haynes, Vice President, Nuclear Production W. F. Quinn, Director, Nuclear Safety 5 Licensing R. Papworth, Director, Quality Assurance L. Souza, Manager, Quality Audits 5 Monitoring T.

D. Shriver, Manager, Compliance C.

N. Russo,

Manager, QA Audits/Monitoring Ms. Jill Morrison, PVIF Lynne Bernabei, GAP of the Institute for Policy Studies Timothy Hogan, Chief Counsel A. C. Gehr, Esq., Snell 8 Wilmer bcc:

G. Holahan, NRR G. Knighton, NRR T. Polich, Palo Verde Site, SRI RSB/Document Control Desk (RIDS)

Project Inspector Resident Inspector G.

Cook B. Faulkenberry J. Martin RV P

DKirsch 06+P/88 Holohan,NRR BFaulkenberry J

tin 06/g$/88 06/p>/88

/gjP88 REQU ST C

PY R

VEST C

PY R

UEST C

PY REQUEST PY REQUEST C

PY YES /

NO ES /

NO ES /

NO YES /

NO YES /

NO ND TO PDR E

/

NO