Forwards Change to FSAR Re Initial Test Program,Revising Preoperational Test Method for Holdup Subsystem of Chemical & Vol Control Sys
ML17303A623
Person / Time
Site: Palo Verde  
Issue date: 10/08/1987
From: Haynes J
ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
161-00561-JGH-B, 161-561-JGH-B, TAC-67076, NUDOCS 8710150279
Download: ML17303A623 (6)


Text

I REGULA Y INFORMATION DISTRIBUTIO YSTEM (RIDS)

ACCESSION NBR: 8710150279 DOC. DATE: 87/10/08 NOTARIZED:

NO FACIL:STN-50-528 Palo Verde Nuclear Stations Unit ii *rizona Publi STN-50-529 Palo Verde Nuclear Stations Unit 2. Arizona Pub li STN-50-530 Palo Verde Nuclear Station.

Unit Si Arizona Pub li AUTH. NAME AUTHOR AFFILIATION HAYNESi J. G.

  • rizona Nuclear Poujer ProJect (formerly Arizona Public Serv RECIP. NAME RECIPIENT AFFILIATION Document Control Branch (Document Control Desk)

SUBJECT:

ForuJards change to FSAR re initial test programs revising preoperational test method for holdup subsystem of chemical 8c vol control sos.

DISTRIBUTION CODE:

AOOID COPIES RECEIVED: LTR 1

ENCL J SIZE:

TITLE:

OR Submittal:

General Distribution NOTES: Standardized plant.

Standardized plant.

Standardi zed p lant.

05000528 05000529 050005S0 RECIPIENT ID CODE/NAME PD5 LA LICITRAPE INTERNAL: ACRS NRR/DEST/ADS NRR/DEST/MTB NRR/DOE*/TSB OGC/HDS1 RES/DE/EIB EXTERNAL'G5G BRUSKEa S NRC PDR NOTES:

COPIES LTTR ENCL 1

0 1

1 6

6 1

1 1

1 1

0 1

1 1

1 1

1 1

1 REC IP IENT ID CODE/NAME PD5 PD DAVIS. M ARM/DAF/LFMB NRR/DEST/CEB NRR/DEST/RSB NR RB LPDR NSIC COPIES LTTR ENCL 5

5 1

1 1

0 1

1 1

1 1

1 1

1 1

1 1

TOTAL NUMBER OF COPIES REQUIRED:

LTTR 29 ENCL 26

II a

I I N

Arizona Nuclear Power Project P.o. BOX 52034

~

PHOENIX, ARIZONA85072-2034 Docket Nos.

STN 50-528/529/530 U.S. Nuclear Regulatory Commission Washington, D.C.

20555 October 8, 1987 161-00561-'JGH/BJA Attention:

Document Control Desk

Dear Sirs:

Subject:

Palo Verde Nuclear Generating Station (PVNGS)

Units 1,,

2 and 3

Change to the Initial Test Program File: 87-A-056-026; 87-A-005-419.05 In accordance with the provisions of the applicable license conditions of the Unit 1, 2

and 3 Operating

Licenses, ANPP is submitting the attached change to the initial test program which is described in the PVNGS FSAR and in CESSAR.

The change revises the preoperational test method for the holdup subsystem of the Chemical and Volume Control System (CVCS).

The change provides for greater flexibility in obtaining the necessary test data and will not result in the disposal of large amounts of treated water during performance of the test.

This change has been reviewed, in accordance with the provisions of 10 CFR 50.59 and ANPP has determined that this change does not involve an unreviewed safety question.

The holdup subsystem is a non-safety related portion of the CVCS that is not credited for any accident mitigation or prevention functions.

If you have any additional questions on this matter, please contact Mr.

W.

F.

Quinn of my staff.

Very truly yours, J.

G. Haynes Vice President Nuclear Production JGH/BJA/rw Attachment cc:

0.

M.

E. E.

J.

B.

J.

R.

G.

W.

A. C.

De Michele (all w/a)

Van Brunt, Jr.

Martin Ball Knighton Gehr 87ioi50279 87iooa r -- -~

~DocK osoooszg PDR

t

~

~

Pt."achment to 161-OQ561-JGH/BJA ATTACHMENT (FSAR CHANGE PAGE) 1.9.2.4 Holdu Subs stems Test CESSAR Section 14.2.12.1.15 CESSAR Section 14.2.12.1.15 specifies the following as a test method for the Holdup Subsystem preoperational test:

3.1 Fill the holdup tank and observe level indications and alarms.

3.2 Simulate holdup tank temperature and observe indications and alarms.

Using each holdup

pump, drain the holdup tank to the boric acid concentrator.

Observe holdup tank level indications, alarms and interlocks and holdup pump discharge pressure.

3.4 Refill and isolate the holdup tank.

Open the holdup tank recir-culation valves and start each holdup pump.

Observe tank level.

Lineup the holdup pumps to the reactor drain tank filter and observe holdup tank level.

This CESSAR specified test method precludes the capability to adjust for plant conditions at the time of testing and also does not address the site specific need to conserve treated water at PVNGS.

Therefore, the following modification to the CESSAR test description is utilized:

2.5 There is a sufficient inventory of water contained in the holdup tank to conduct testing in accordance with Section 3.0.

3.0 Test Method 3.1 Observe level indication,

alarms, and interlocks in response to actual or simulated holdup tank levels.

3.2 Simulate holdup tank temperature and observe indications and alarms.

3.3 Using each holdup

pump, transfer holdup tank contents to the boric acid concentrator.

Observe holdup tank level indication, alarms and interlocks and holdup pump discharge pressure.

3.4 Refill and isolate the holdup tank.

Open the holdup tank recir-culation valves and start each holdup pump.

Observe tank level.

Lineup the holdup pumps to the reactor drain tank filter and observe holdup tank level.

0 4