ML17300B144

From kanterella
Jump to navigation Jump to search
Insp Repts 50-528/87-38,50-529/87-37 & 50-530/87-39 on 871026-30.Violation Noted.Major Areas Inspected:Occupational Exposure During Extended Outages in Unit 1,Allegation RV-87-A-0066 & Followup of Nonroutine Events
ML17300B144
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 12/03/1987
From: Cicotte G, Russell J, Yuhas G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To:
Shared Package
ML17300B142 List:
References
50-528-87-38, 50-529-87-37, 50-530-87-39, NUDOCS 8712220030
Download: ML17300B144 (17)


See also: IR 05000528/1987038

Text

U.

S.

NUCLEAR REGULATORY COMMISSION

REGION V

Report Nos.

50-528/87-38,

50-529/87-37,

50-530/87-39

Docket Nos; 50-528,

50-529,

50-530

Licensee:

Arizona Public Service

Company

P.

0.

Box 52034

Phoenix,

Arizona

85072-2034

Facility Name:

Palo Verde Nuclear Generating Station

Inspection at: Mintersburg, Arizona

Inspection

Conducted:

October 26-30,

1987

J. +s'se11,

Health Physicist

G.

Ci ot e, Radiation

Sp

ialist

Inspectors:

Approved by:

P.

Yu

s, Chief, Facilities Radiological

Pro

ion Section

/z- f-P7

Date Signed

I

Q

IM

Da

e Signed

Da

e Signed

~Summer

Ins ection

on October 26-30

1987

(Re ort Nos.

50-528/87-38

50-529/87-37

and

50-530/87-39

inspectors

of occupational

exposure

during extended

outages (in Unit 1),

Allegation No.

RV-87-A-0066, followup of nonroutine events,

and

a tour of the

facility.

Inspection

Procedures

30703,

92701 and 83729 were addressed.

Results:

In the four areas

inspected,

one apparent violation was identified

involving Technical Specification 6.2.2.2.b

(see Section 2.B.).

87i 2220030 87i204

PDR

ADQCN 05000528

6

PDR

4

DETAILS

1.

Persons

Cont'acted

A.

Licensee

J. Allen, Unit 1 Plant Manager

"W. Ide, Unit 2 Plant Manager (Corporate.gA/gC

Manager)

"0. Zeringue,

Unit 3 Plant Manager

(Technical

Support Manager)

  • L. Brown, Radiation Protection

and Chemistry Manager.

P. Brandjes,

Outage

Manager

"T. Shriver,

Compliance

Manager

"G. Perkins,

Central

Radiation Protection

Manager (Radiological

Services

Manager)

  • L. Souza, guality Audits and Monitoring Manager
  • J. Mann, Corporate

Health Physics/Chemistry

Supervisor

K. Oberdorf, Unit 1 Radiation Protection

Manager

"T. Bradish,

Compliance Supervisor

K. Contois,

Dosimetry Supervisor

R.

Selman,

ALARA Supervisor

"D. Bland, Compliance

Engineer

B.

NRC

"J. Ball, Acting Senior Resident

Inspector

"Denotes present at exit interview.

( )Denotes

stated title if different from present

licensee

proposal.

The inspectors

also met with and held discussions

with other members of

the licensee

and contractor staff.

2.

Occu ational

Ex osure Durin

Extended

Outa

es

A.

~Plannin

(1)

ALARA

Pre-job reviews of outage

work were reviewed to determine the

level of review and adequacy of requirements

to ensure that

exposures

were kept As

Low As Reasonably

Achievable

(ALARA).

The licensee

performed estimations

of dose

as the work was

projected to progress.

Reviews

appeared

to be conducted

on a

case-by-case

basis,

rather than formatted for conformance with

each other.

No specific exposure

goal

had been set

by job

function.

The only exposure

goal set was

275 person-rem for

the outage.

The licensee staff stated that it was their

intention to set goals for following outages

based

on the

results of the current outage.

At the time of the inspection,

the licensee staff had calculated that cumulative exposure for

the outage

was approximately

70 person-rem.

This would, for

the point in the outage,

be just under

the cumulative

amount

expected,

consistent with a 275 person-rem

outage total.

No violations or deviations

were identified.

(2)

~Chan

ee

The licensee

was in the final stages

of an organizational

change.

The thrust of the change

was to place individual unit

Radiation Protection

Managers

(RPMs) under unit Plant Managers.

The

RPMs would also report to a Radiation Protection

and

Chemistry Manager.

Support functions,

such

as Dosimetry and

Respiratory Protection,

were to be under

a central

RPM.

Potential

impact of these

changes

is discussed

in paragraphs

2.B and 2.C,

below.

B.

Staffin

and Administration

Contractor

resumes,

work hour time records,

and training records

were reviewed.

Contract Radiation Protection

personnel

used

by the

licensee

to fill Technical Specification (TS) 6.3, "Unit Staff

Organization," positions

met or exceeded

the minimum qualifications

of ANSI 3. 1-1978,

as required in TS 6.3.

Work hour overtime

limitations are specified in TS 6.2.2.2 which states,

in part:

"6.2.2.2

The unit staff working hours shall

be as follows:

"a.

Administrative procedures

shall

be developed

and

implemented to limit the working hours of unit staff

who perform safety-related

functions; e.g.,

Senior

Reactor

Operators,

Reactor Operators,

radiation

protection technicians,

auxiliary operators,

and

key

maintenance

personnel..."

"...during extended

periods of shutdown for refueling, major

maintenance,

or major plant modifications,

on a temporary

basis,

the following guidelines shall

be followed..."

"...An individual should not be permitted to work more than

16

hours in any 24-hour period,

nor more than

24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> in any

48-hour period,

nor more than

72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> in any 7-day period, all

excluding shift turnover time..."

"Any deviation.from the above guidelines shall

be authorized

by

the

PVNGS Plant Manager or his designee

who is at supervisory

level or above,

or higher levels of management,

in accordance

with established

procedures

and with documentation

of the basis

for granting the deviation...."

A review of time records for contractor personnel

disclosed that two

individuals

had worked seven consecutive

days of 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />

each.

The

licensee

stated that the individuals,

who worked the

12 hour1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> days

respectively

on October

10 to 16,

1987, inclusive,

and October

13 to

19, 1987, inclusive,

had not received prior authorization,.since

they had days off work in the calendar

weeks preceding

and following

the period of work.

When presented

with the findings, the licensee

stated that procedure

10 AC-OZZ07, "Overtime Limitations," was

restricted to Arizona Nuclear

Power Project personnel,

and not to

contractors.

The technicians

noted above,

during the subject

periods,

were both assigned

to coverage of outage work, such

as

radiological

surveys

and monitoring of work activities.

Failure to limit the work hours of the technicians

represents

an

apparent violation of TS 6.2.2.2.a

(87-38-01).

C.

Trainin

and

ualifications of New Personnel

(1)

Training records

and

resumes

of several

contractor personnel

newly hired for the outage

were reviewed.

Observations

by the

inspectors

established

that personnel

assigned

to safety-

related positions

had the qualifications required

by ANSI

3. 1-1978.

Incoming radiation protection personnel

receive the

same training as other

new hires.

The licensee

used

a pre-test

to assess

the extent of training required.

Training for the

purpose of meeting

10 CFR 19. 12, "Instructions to Workers,"

was

either

a full training session

or an abbreviated

session,

governed

by the pre-test results.

The licensee

had assigned

escorts

and

a German/English interpreter to several

foreign

national contract technical

consultants

from the 'Reactor

Coolant

Pump

(RCP) manufacturer.

(2)

The licensee

had recently instituted procedure

75RP-9ZZ83,

"Hot

Particle Control," with an effective date of October 13,

1987.

Radiation Protection Technicians with whom this procedure

was

discussed

stated that training on the procedure

had consisted

of reading the procedure

once

and signing

a training doc'ument

indicating they had done

so.

Four technicians

responsible for

Hot Particle Control Areas

(HPCA) stated that they had

periodically reviewed the procedure

on their own, in addition

to the initial review.

The inspectors

discussed

hot particle control

and

75RP-9ZZ83

with the following personnel:

Radiation Protection

and Chemistry Manager

(RPCM)

Central

Radiation Protection

Manager

(CRPM)

Unit 1 Radiation Protection

Manager

(RPM)

Radiation Protection

Outage Coordinator

(RPOC)

Three (Lead) Radiation Protection Technicians

(LRPT)

One

ANPP

RPT

Seven Contractor

RPTs,

ANSI 3.1-1978 qualified, directly

assigned

to

HPCA work

Four Contractor

RPTs,

ANSI 3. 1-1978 qualified, not so

assigned

Three Contractor

RPTs,

not ANSI 3. 1-1978 Seniors

(Junior

RPTs)

During these

discussions,

the inspectors

made the following

observations:

Only three of the fifteen Senior

RPTs were able to

accurately

describe

the modified R02/R02A and discuss

survey techniques

appropriate- to the instrument.

One Senior

RPT was observed

using the modified R02/R02A

for surveys of personnel

in an

HPCA.

The

RPT used the

instrument at an angle that could have precluded incident

betas

from reaching the open window, and did not survey

all high contact areas

as called for in 75RP-9ZZ83.

One Senior

RPT assigned

to

HPCA work stated

he did not

trust and would not use the modified R02/R02A for

personnel

surveys.

One Senior

RPT in the Reactor Building (RB) described

the

modified R02/R02A as having

a "round hole" for a beta

window.

The instrument

had

a slotted window and the

RPT

had

an instrument in his possession,

i.e.,

on his desk.

Two Senior

RPTs in the

RB stated that 20,000

dpm per probe

.

area

on the modified R02/R02A would indicate the presence

of a hot particle.

The instrument

has

a scale calibrated

in mr/hr,

and

no external

probe.

The

RPTs

had

an

instrument

on their desk.

Ten of the Senior

RPTs were unfamiliar with the action

levels associated

with stop-work orders

based

on radiation

exposure

estimates

specified in 75RP-9ZZ83.

Most of the

errors

were conservative.

The inspectors

concluded that

hot particles, if discovered

during surveys of personnel,

would be unlikely to result in unconservative

actions.

One technician stated that

he thought dose estimations for

hot particle exposures

were averaged

over the whole-body

skin area.

An assembly

from RCP-1B was

removed

from a hot particle

control area without being surveyed to preclude

the

presence

of hot particles

and placed in a tent not marked

as

an

HPCA.

The inspectors

called this to the licensee's

attention approximately eight hours after the

move

I

occurred.

The tent area

was posted

HPCA approximately

five hours later.

The Unit 1

RPM stated that

he had been

informed that

RCP

shaft/impeller assemblies

being decontaminated

were

"coming up particle-free."

RPTs assigned

to

RCP work in

the decontamination

area stated that they did not perform

surveys for particles

on material inside posted

HPCAs due

to excessive

dose rates.

The

RPOC stated that she

had not received

any formal

training on 75RP-9ZZ83,

but was sure that the contractor

RPTs

had received

such training during initial General

Employee Training (GET).

The Unit 1

RPM stated that, although

he was not familiar

with operation of the modified R02/R02A,

he was sure the

RPTs were.

The

CRPM expressed

familiarity with 75RP-9ZZ83,

but was

unable to recall

dose estimation/stop

work action levels

called for therein.

The

RPCM stated at the exit interview that

he

had been

under the impression that the Nuclear Training Department

had presented

a formal lecture

on hot particle control for

new hire RPTs.

The inspector verified that

a formal

lecture

on hot particle control

had not been presented.

The inspectors

discussed

these

observations

with the licensee

during a meeting held on October 18, 1987,

and at the exit

interview.

The licensee

acknowledged

the observations

and

stated that

a video presentation

on hot particle control

had

been prepared for review prior to viewing by RPTs

on shift.

The licensee

showed the inspectors

two recent

memoranda

addressed

to all personnel,

emphasizing

proper radiological

controls in areas

where hot particles

were suspected.

No violations or deviations

were identified.

D.

External

Ex osure Control

~oosimetr

Personnel

dosimetry

was observed

in use

and representative

licensee

records

were reviewed.

The licensee

uses

pocket dosimeter

readings

for daily accumulated

exposure.

TLD readings

are

compared to pocket

dosimeter

readings

when the

TLD is read

and the record is updated to

reflect the

TLD reading.

Anomalous

comparisons

and lost/offscale

dosimeter

readings

are investigated.

The licensee's

dosimetry program is National Voluntary Laboratory

Accreditation Program (NVLAP)-certified.

guality control

and

abnormal

TLD readings

were reviewed.

Anomalous readings

are

0

investigated

by the licensee

through visual examination of TL

phosphors

and analysis

of causes

for abnormal

readings.

Dose

estimations

were performed for those

cases

in which defective

TLDs

were determined to be the cause.

Representative

examinations

of

abnormal

readings

were reviewed

and observed to be adequate.

According to licensee

records,

no personnel

received

whole body

exposures

in excess

of the limits of 10 CFR 20.101(a) for the

current

and second quarters of 1987.

All personnel

records

reviewed,

except for those of the foreign nationals previously

mentioned,

contained

form NRC-4 equivalents

completed in accordance

with 10 CFR 20. 102, prior to approaching

the limits of 10 CFR 20.101(a).

The licensee distributes

an occupational

dose status

report twice

daily on weekdays

during the outage,

organized

by department

and by

record

number.

Department

managers

can then review their

department,

and individuals can locate their most recent

update

by a

unique

number assigned

to them, or alphabetically

by their

departmental

report.

No violations or deviations

were identified.

Internal

Ex osure Control

Licensee

records of MPC-hour calculations,

bioassay,

whole body

counting

and internal

exposure

estimations

were reviewed.

No

personnel

had exceeded

40 MPC-hrs for the outage.

Adequate air

sampling appeared

to be in use for airborne radioactivity areas.

Bioassay calculations

and air sampling results

appeared

to be

consistent.

Records for two personnel,

determined to have ingested

small quantities of Sb-124,

were examined.

No violations or deviations

were identified.

Control of Radioactive Mat'erial

and Contamination

Surve

s

and

~Monitorin

Use of field radiation instruments,

portal monitors, friskers,

and

monitoring practices

were observed

by the inspectors.

One

RM-20

frisker

No.

993 being

used

by personnel

for frisking in a clean area

was located just inside

an area posted

"contaminated

area."

One

RM-20, Serial

No. 725,

was available in the

same clean area,

but

with battery power too low to allow operation.

The instrument

was

not connected to a power line.

One

RM-20, Serial

No. 649, dated

calibration due October 26, 1987,

was observed to be in use at the

exit to the radiation control area

on October

27, 1987.

The

instrument

was immediately removed from use by an

RPT accompanying

the inspectors.

On October 29, 1987, the

same

RM-20, Serial

No.

649, dated calibration due October 26,

1987,

was observed

in use for

personnel

frisking in the Unit 1 Turbine Building.

The instrument

was immediately

removed

from use

by an

RPT accompanying

the

inspectors.

e

Waste

volume reduction efforts appeared

adequate.

Personnel

bringing material into the

RCA were observed to be removing

packaging materials prior to entry,

and the licensee

used

segregation

of waste to prevent mixing of uncontaminated

and

contaminated

waste.

The licensee utilized a group of contractor personnel

to perform

area decontamination,

in order to reduce the total area within

contaminated

areas,

and to reduce

contamination levels to minimize

the spread of contamination.

The process

appeared

to be effective

in that contaminated

areas

in the auxiliary and radwaste buildings

were smaller than during the last inspection.

Housekeeping

was

generally

improved.

No violations or deviations

were identified.

3.

Alle ation RV-87-A-0066

This refers to an anonymous allegation received

by telephone

concerning

radiation protection personnel.

The allegations

were

as =follows:

A.

Radiation Protection

(RP)

ersonnel

erformed

smear

surve

s without

loves or other anti-contamination clothin

Several

RPTs were observed

in the performance of smear

surveys.

No RPTs

among the several

observed

were noted to be performing

surveys without adequate

protective clothing.

The licensee's

procedures

and training describe

the protective clothing

appropriate

for performing surveys.

No other

examples

of this

allegation were observed.

B.

An RPT was re orted to have said.to the alle er that

he did not know

what the alle er should

do with some

e ui ment which caused

the

RPT's frisker to read off-scale hi h.

The inspector discussed

surveys

and disposition of contaminated

material with several

RPTs,

both

ANSI. 3. 1-1978 Senior Technicians

and three Junior

RPTs.

Procedure

75 RP-SZZ61,

"Radioactive

Material Storage

and Control," describes

actions to be taken to

control contaminated material.

No material

was observed to

leave contaminated

areas without an adequate

survey,

and all

personnel

engaged

in discussions

appeared

to understand

what actions

should

be taken.

This allegation

was not substantiated.

This matter is closed.

(RV-87-A-0066)

4.

~Fol 1 owo

At approximately 8:00 p.m.

on October 25, 1987, the licensee's

Fuel

Building (FB) was contaminated

extensively

by deposition of airborne

radioactivity when

an apparently vigorous chemical reaction took place

during decontamination

of Reactor Coolant

Pump

(RCP) components.

The

inspectors

discussed

the incident with licensee staff and toured the

area.

The licensee

stated that the

RCP shaft

and impeller assemblies

were being

decontaminated

by a chemical

process

developed

by Kraftwerk Union

(KWU)

and used extensively in nuclear power plants in Europe.

If the

RCP

components

remain in the decontamination

solution for long periods,

as

occurred with RCP-lB,

due to other equipment problems,

the contractor

procedure called for addition of a quantity of oxidizing agent,

calculated

by the "Decon Supervisor."

In this case,

the Decon Supervisor

was

a Federal

Republic of Germany

(FRG) national working under

a

Bechtel-KWU contract.

-The oxidizing agent

was to be added to break

down

a passivated

corrosion layer created

by the long-term immersion.

The

addition was required after 100 hours0.00116 days <br />0.0278 hours <br />1.653439e-4 weeks <br />3.805e-5 months <br /> of immersion.

The licensee

stated

additionally that about

24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />

had transpired with RCP-1B in'he

solution.

RCP-1B was resting

on the lip edge of the tank so as to form a

seal

between

the assembly

and the tank.

The mixture was being maintained

at 205~F.

Pressure

generated

from the exothermic reaction

between

the

decon solution and the oxidizing agent

was to relieve via the "kittybone"

labyrinth and out a seal water flange connected

to a 20-foot rubber hose.

The licensee staff stated that when they began to inject the agent at the

minimum speed of the-air-operated

diaphragm

pump, they heard

a rapidly

increasing

noise of escaping

pressure

and began to evacuate

the area

as

liquid and vapor from the tank began to spray out.

The licensee

estimated

approximately

20 gallons of mixture spewed out as water and

steam,

contaminating

the

FB.

No personnel

injuries occurred.

An air sample

taken at the time of the incident indicated approximately

0.5

MPC for the total nuclide mix observed.

Personnel

in the

FB at the

time of the incident were surveyed for contamination

and sent for

whole'ody

gamma

scans.

The results of whole body counting

(WBC) indicated

no

significant uptake of airborne radioactivity.

A licensee

review of the incident was in progress

at the time of the

inspection.

No procedural

changes

were required

by the licensee prior to

resumption of the process,

and decontamination

of the

RCP assemblies

resumed.

The licensee

representative

informed the inspector that the

Decon Supervisor

had been instructed to avoid the addition of chemicals

which could produce similar reactions.

No violations or deviations

were identified.

Facilit

Tour

A tour of the facility, during which independent

radiation measurements

were

made using

an

NRC ion chamber

survey instrument,

Eberline

R02A,

Serial

No. 897, calibrated

on September

28, 1987,

and due for calibration

on December

28,

1987,

was conducted.

The licensee's

postings

appeared

to comply with 10 CFR 19. 11, "Posting of

Notices to Workers,

and

10 CFR 20, "Standards

for Protection Against

Radiation.'"

However,

numerous

instances

of practices

inconsistent with

the licensee's

procedures

as stated in 75RP-OZZOl, "Radiological

Posting,", were observed:

A radiation area posting in the concentrated

radwaste

evaporator

room- had partially fallen such that it was not easily

readable.

A contaminated

area posting in a decontamination

area

on the

120'adwaste

Building was partially obscured.

A high contamination

area

(HCA) posting near door F101 for an area

which was

no longer an

HCA had fallen such that it appeared

that an

area outside the Fuel Building (FB) was

an

HCA.

The contaminated

area posting

on the laundry monitor in the Unit 1

Radwaste

Building was not visible from the side of the monitor from

which surveyed

laundry was

removed.

The barrier

and posting for a decontamination

cubicle

on the

120'levation

of the Unit 1 Radwaste

Building containing

an

RCP shaft,

posted

as

an High Radiation Area, Respiratory Protection

Required,

HPCA,

HCA, and Airborne Radioactivity Area had fallen to the floor,

but was still visible.

A tent containing scaffold material,

located outside the

FB near

door F101,

was posted inconsistently:

One side (the entrance)

was

posted with only the radiation caution symbol.

One side

was not

posted,

one side

was posted

as

a "Radioactive Material Storage

Area,"

as

was the roof which had fallen in, and the fourth side

was

posted

as "Radioactive Material."

A box used

by the Operations

Department for storage of radioactive

material

had its sign flipped over so it could not be read.

An area

contaminated

during the incident involving airborne

radioactivity in the

FB, was behind

a boundary rope,

posted only

with the radiation caution symbol.

RP personnel

stated that the

floor had been

decontaminated

and therefore

no protective clothing

was required,

but that other horizontal

surfaces within the area

(but not posted

"contaminated area"),

had yet to be released

as

uncontaminated.

The concerns identified above were brought to the attention of the

licensee

during the tour,

and were corrected

at that time by an

RPT

accompanying

the inspectors.

No areas

requiring posting were found to be

completely unposted.

The inspectors

noted that housekeeping

in the Auxiliary Building had

improved.

Little extraneous

material

was observed

in the

RB considering

the outage status,

'and

no unlabeled radioactive material

was observed in

uncontrolled areas.

In one instance,

yellow polyethylene

bags,

normally

reserved

by 75 RP-9ZZ61, "Radioactive Material Storage

and Control," for

radioactive material,

were being used in an uncontaminated

area 'walkway,

under

some

heavy objects.

The inspectors

were informed the material

was

not contaminated,

and that the plastic

was to prevent scuffing the floor,.

A tour of the radiologically controlled area outside of the

Radwaste

Building indicated that the

same level of attention

was not being given

10

to these

areas.

The outside yard area contained

numerous cigarette butts

and even

an empty soft drink can.

The area

was posted

"no eating,

drinking, or smoking."

Many of the caution signs,

though still visible,

were difficult to read

due to deterioration.

In the Radwaste Building,

most areas

posted

as either "Radiation Area" or "Contaminated-Area"

contained debris.

In one case,

a ladder within the

Radwaste

Evaporator

rooms

was blocked completely by protective clothing,

a fire extinguisher,

and other equipment.

In the

FB, the licensee

was in the process

of recovering

from a

contamination incident on October

25,

1987 (see

paragraph

4).

Much'f

the building, particularly within the hot particle control areas,

was

cluttered.

The licensee staff stated that they had experienced

difficultywith leakage

from various connections

on the decontamination

system,

and contamination levels were, according to

RP staff in the area,

extreme.

By the conclusion of the inspection,

however,

the areas

outside

contaminated

area boundaries

were

much improved.

The inspectors

noted that adhesive step-off pads

were

used extensively at

contaminated

area exits, but that many were not being kept sticky by

removal of expended

adhesive

pads.

During the tour, it was noted that three radiation monitors were alarming

and unacknowledged.

RU-2 and 3, for Essential

Cooling Water "B" and "A,"

respectively,

on the 70'levation of the Auxiliary Building, were

alarming.

RU-2 was alarming

on low flow.

The licensee staff

subsequently

stated that both were being acknowledged,

and that the

RU-3

alarm was determined to be spurious.

Waste

Gas

Decay Tank Monitor RU-12

was also alarming unacknowledged.

The licensee

RP staff provided the

inspectors with an "Alarm Response

Worksheet,"

showing the response

to

the alarm subsequent

to the tour of the facility.

The RU-12 alarm was

also determined

by the licensee

to be spurious, with a reading of 6.01

E-4 pc/cc

and

an alarm setpoint of 2.00 E-3 pc/cc.

During the course of the inspection,

a severe

thunderstorm

struck the

site

on October 29,

1987, resulting in a partial

power

outage.

The

inspectors

noted that postings

and barriers

located outside

had been

restored,

with the exception of a "potentially radioactive material

storage

area,"

where the barrier was visible.

The Central

RPM,

upon

discovering that power would not quickly be restored to respiratory

protection,

whole body counting,

and dosimetry areas,

promptly suspended

all work involving a high potential for uptake of radioactivity or high

external

dose, until such power could be restored.

No violations or deviations

were identified..

Exit Interview

The findings of the inspection

were brought to the attention of the

licensee

on October 30,

1987.

The licensee

was informed that failure to

limit overtime hours worked for Radiation Protection Technicians

was

an

apparent violation of TS 6.2.2.2.

The licensee

stated that

TS 6.2.2.2

did not apply to contractor personnel,

and that this position

had been

agreed to by

NRC Region

V management.

The subject agreement

was related

to a resident

inspector identified overtime limitation being exceeded

by

a contractor

wor king on safety-related

equipment

(see

Inspection

Report

50-528/85-26).

The inspectors

determined that

RPTs are identified

specifically in Technical Specification 6.2.2.2

(see paragraph

2.B) and

the overtime limitations apply to contract

as we] 1

as

house technicians.

e