ML17298B481

From kanterella
Jump to navigation Jump to search
Insp Rept 50-528/84-38 on 840827-0915.Violation noted:30 Out of 160 Bechtel Project Engineers Did Not Have Training Records to Substantiate Compliance w/10CFR50,App B, Criterion V
ML17298B481
Person / Time
Site: Palo Verde Arizona Public Service icon.png
Issue date: 10/16/1984
From: Ball J, Burdoin J, Clark C, Fiorelli G, Grayson M, Hernandez G, Ivey K, Johnston G, Kellund G, Kirsch D, Wagner W, Thomas Young, Zimmerman R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To:
Shared Package
ML17298B479 List:
References
50-528-84-38, NUDOCS 8411090146
Download: ML17298B481 (68)


See also: IR 05000528/1984038

Text

U. S.

NUCLEAR REGULATORY COMMISSION

REGION V

Report No.

50-528/84-38

Docket No.

50-528

License

No.

CPPR-141

Licensee:

Arizona Public Service

Company

P.

O. Box 21666

Phoenix, Arizona 85036

Facility Name:

Palo Verde Nuclear Generating Station - Unit

1

Inspection at;

Palo Verde Construction Site, Mintersburg, Arizona

inspection

conducted:

August

2

thru September

15,

1984

Inspectors:

R.

immerm

, Senior

(Team Le

ent

ngineer

/~-/~-8'P

Date Signed

d-/Z- F

, Reactor Inspector

K.- vey, Reactor

Insp

r

G. 'John ton,

si

t Insp ctor, Trojan

G. Fiore

,

Re

d t Insp ctor

.C

G.

. Kellund,

eactor Inspector

Date Signed

/0-lZ-fF

Date Signed

Date Signed

JO-rQ-8/

Date Signed

/c -/s-~)

Date Signed

/a-e-r'P

Date Signed

/u /p-R

. Clark

React

Ins

or

Date Signe

5 . Grayson

84ii090i4b05000528

g~iOi~

@gal

QQOCW

p9

8

adiat

n

eciali t

/o-/ -$"

Date Signed

t

l"

l

R

I

J

t'I

1

a

ll

I

4

i

J

-2-

G. Her

ndez, s't In

ector

Da

e

S gn d

W. J

agner,

eactor Inspector

)6 /

Da

S gned

Reviewed By:

. Young r., Chi

,

E

neering Section

Da

e

igned

Approved By:

D. P. Kir c

, Chief

Reactor Projects

Branch

D

e

igned

Summary:

Ins ection durin

the

eriod of Au ust

27 thru Se tember

15

1984

Re ort No. 50-528/84-38

Areas Ins ected:

A special,

unannounced

team inspection of design,

modifications, testing,

maintenance,

documents

and records,

and

QA/QC

activities for the startup of the auxiliary feedwater

system

(AFWS).

The team assessed

the licensees

effectiveness

in the areas of work

documentation,

and methodology of system organizational responsibility

turnover and testing.

The inspection involved 819 inspector hours by 13 NRC

inspectors.

Results:

Of the areas

examined,

one violation .was identified in the area of

project engineer training (paragraph

20.A).

i

II

I

DETAILS

1.

Persons

Contacted

A.

Arizona Public Service

Com an

(APS)

V.

J.

D.

"C.

J.

G.

F

D.

C.

R.

D.

IjT.

A.

D.

J.

IJ

J.

J.

T.

G.

L.

W.

M.

W.

S.

-<e.

,S.

R.

-j)W.

L.

A.

W.

R.

"<lQ.

~'R.

'W

R.

"R.

N"-D.

VJ

Rhodes,

Supervisor,

Drawing and Document Control

Flommerfelett, Nuclear Records Analyst

Rhodes, As-Built Records

Manager

Russo,

Quality Audits Monitoring Manager

Brantley, Supervisor, Discipline Test Schedule

Control Group

Smith, Startup-Information Center Supervisor

Hicks, Training Manager

Deruiter, Maintenance

Planner/Coordinator

Braun, Principle Startup Engineer,

AFWS

Becken,

Startup

Group Supervisor

Wittas, Quality Engineering Supervisor

(Mechanical)

Shriver, Quality Systems/Engineering

Manager

Ramey, Quality Systems

Supervisor

Webster,

Iead Auditor

Tills, Supervisor for Maintenance

Engineers

Minnicks, IRC Superintendent

Stout, Mechanical Superintendent

Terry, Electrical Work Group Supervisor

Robb, Acting Supervisor,

Maintenance

Support Section

(MCC)

Olson, Electrical Maintenance

Supervisor

Curr, Surveillance Control Group Supervisor

Simko, Engineering

Group Supervisor

Keubassion,

OPS Engineering Section XI Pump and Valve Operability

Program

Roman,

OPS Engineering Containment,

Mechanical Maintenance

Program

Callahan,

Operations Shift Supervisor

Nelson,

Maintenance

Manager

Penick, Supervisor,

QA Auditing Group

Badsgard,

Vice Chairman

TWG

~

Xde, Corporate Quality Assurance/Quality

Control Manager

Souza, Assistant, Corporate Quality Assurance/Quality

Control

Manager'ogers,Manager of Nuclear Operations

Quinn, Manager of Nuclear Licensing

Ecklund, Supervisor of Operations

Support

Sterling, Supervisor of Configuration Control

Bynum, Nuclear, Operations Director

Houchen, Transition Manager

Gross,

Compliance Supervisor

Craig, Startup Administrative Support Manager

Ferguson,

Startup Engineer

Baron,

QA Engineer

'eringue,

Technical Support Manager

Earner, Assistant Vice President,

Nuclear Production

Self, Nuclear Operation Transition Represent

Kirby, Startup

Manager

4

i"

r,

u

1

t

4

"-P. Coffin, QA Specialist

Various Other Personnel

B.

Bechtel Power Cor oration (Bechtel)

J. Black, Chief Resident Engineer

D. Cole, Quality Systems

Engineer

R. Randel,

Startup/Operations

Resident Engineer,

Supervisor

H. Foster, Project

QC Engineer

H. Mear, Assistant Project

QC Engineer

I,. Bowles,

Lead Welding

QC Engineer

J. Dallam, Administration Supervisor (Training)

Various Other Personnel

$/Denotes

those individuals attending the final exit interview on

September

15,

1984.

-Denotes

those individuals attending the preliminary exit interview on

August 31,

1984.

The team's

approach

was to direct 90 percent of its effort on work

controls, test results, test results evaluations

and quality assurance

applied to the auxiliary feedwater

system

(AFWS) while this system is/was

under the control of the Startup

Group.

This included the licensee's

control of technical work and an in-depth examination of a large number

of elements

related to this system,

including: application of QA/QC;

component testing;

maintenance;

resolution of NCR's and CAR's; evaluation

of test procedures;

evaluation of testing; evaluation of test results;

and other.

The other

10 percent of the team's effort was focused

on

inspection of other important areas,

including AFW support

systems

(electrical supplies),

and the

QA/QC program for operations.

The

AFWS was selected

because

of its high safety significance

and the

presumption that it would be representative

of the work controls,

testing,

documentation,

and methodology of system organizational

responsibility turnover and testing,

applied to all safety-related

work

performed while the systems

are under the",control of the Startup

Group.

The selection

and in-depth examination of such

a representative

sample

allowed

some extrapolation of the team's'indings

to the adequacy of all

safety-related

construction,

preoperational

and startup work controls

and

testing.

The examinations

discussed. above were conducted by:

II

J

(1)

physical inspection of systems

and components,

(2)

examination of testing

and maintenance

procedures

and documentation,

and

(3)

private interviews

and discussions

with over 50 craft and inspection

personnel.

A

k

3,

The inspection involved 819 hours0.00948 days <br />0.228 hours <br />0.00135 weeks <br />3.116295e-4 months <br /> by 13

NRC inspectors.

Results:

Of the areas

inspected,

one violation was identified in the area of

training for Bechtel project engineers.

2.

~Back round

During a previous

team inspection,

conducted in the fall of 1983,

Region V made

a finding that the basic construction at U-1 appeared

to be

generally satisfactory.

This conclusion

has been supplemented

by

on-going

NRC staff inspections

and special

reviews conducted

by the

licensee (in such areas

as personnel qualifications, control of vendors,

control of design activities, etc,).

The major findings of the last team

inspection were in the area of the Startup Test Group.

The Startup Test

Group is responsible for preoperational

testing after the systems

are

turned over from construction

and before the systems

are turned over to

the Operations

Department.

In November

1983, after the team inspection,

APS performed

an audit. to verify RV's findings and assess

the generic

implication of the findings.

At the conclusion of the audit,

APS stopped

all preoperational

testing in order to effect certain corrective actions.

Therefore,

the areas

selected for this inspection primarily focused

on

systems

under the control of the Startup Test Group.

3.

Desi n Control for and Im lementation of Modifications to the

AFWS

The objectives of this portion of the inspection

were to assess

the

effectiveness

of administrative controls regarding the verification of

design modifications

and changes

to the auxiliary feed water system

(AFWS).

These modifications

and changes

to the

AFWS have normally

resulted

from problems that were found during acceptance

walkdowns

and

testing of the

AFWS, performed by the startup test group.

In order to

accomplish these objectives

the inspector evaluated:

the licensee's

design control procedures;

examined various design process

documents;

inspected,

in the field, certain modifications

and changes

to the AFWS;

conducted

a walkdown of the

AFW system;

reviewed

gC records for

modifications to the system;

and examined

(}C inspector qualification

records.

A.

Review of Desi n Control Procedures

The inspector

reviewed the following startup

and construction

group

procedures

to establish

how design control and verification is

accomplished:

(1)

Procedure

No.

90GA-OZZ19 Revision 8, "Startup Field Reports."

(2)

Procedure

No. IP-4.34, Revision 13, "Design Change

Package."

(3)

Procedure

No. IP-4.12, Revision 13, "Drawing Change Notice."

(4)

Work Plan Procedure

(WP/P) No. 3.0, Revision 18, "Field Control

of Design Documents."

, l

K

(5)

Work Plan Procedure

(WP/P) No. 20, Revision 20, 'Yield Change

Request."

(6)

Procedure

No.

90GA-OZZ08, Revision 13, "Pre-requisite/

Preoperational

Startup

Work Authorization."

These procedures

provide the administrative controls

and processes

for making technical inquires

and reporting problems identified

during startup activities, which require resident engineering

resolution to assure

proper disposition (redesign,

modification

etc.) to existing systems

as required,

and for the accurate

recording of all dispositions of such inquires

and problems.

The

following reports

and documents

are vehicles for accomplishing

design control and verifications:

Startup Field Report

(SFR)

Nonconformance

Report

(NCR)

k'ield Change

Request.

(FCR)

Drawing Change Notice

(DCN)

Design

Change

Package

(DCP)

Startup

Work Authorization

(SWA)

No violations of NRC requirements

were identified.

B.

Review of Desi n Control Re orts and Documents

The inspector

reviewed the following listed reports

and documents

to

assess

the implementation effectiveness

of the licensee's

design

control procedures.

(1)

Fifty-five SFRs, of a total of 402

SFRs closed-out to date, for

the

AFWS were examined to evaluate

the resident engineer's

resolutions of SFR's.

(2)

Twenty-three

NCRs, resulting from the 55

SFRs of item (1),

above,

were examined to evaluate

the dispositions of NCRs.

(3)

Twenty-one

DCPs, of a total of 52 completed to date,

applicable

to the

AFWS were examined to evaluate project engineering's

control of design

changes

to existing plant installations.

(4)

Eighteen

FCRs were reviewed to evaluate

the controls for

integrating field changes

into design documents,

such as

DCPs

and DCNs.

(5)

Forty-one

DCNs, which resulted

from DCPs

and FCRs,

were

reviewed in conjunction with seventeen

drawings, including the

piping and instrument diagram, piping isometric drawings of the

AFWS, piping hanger drawings

and vendor drawings.

This review

evaluated

the thoroughness

of the program for revising and

updating the

AFWS drawings.

A 'i

4

l'

'

)

,

l

II

(6)

Fourteen

SWAs were reviewed to evaluate

the controls for

coordinating these

documents with other design control reports

and documents,

such

as

NCRs FCRs,

DCNs etc.

(7)

The field revision log (FRL) and daily notification list (DNL)

were examined to evaluate their effectiveness

in controlling

the receipt

and distribution of design

documents in the field.

No violations of NRC requirements

were identified.

C.

Field Ins ection of Modifications and Walkdown of AFW S stem

The inspector visually examined, in the field, modifications

and

changes

made to the

AFW system under the following design

change

packages:

ISS-AF-019, Installation of Nine Pipe Supports

ISP-AF-027, Turbine Drain/Steam

Trap Piping

ISM-AF-062, Remove

AF Pump Full Flow Recirculation Valves

ISP-AF-065, Modify Pipe Hanger

13-AF-011-H-001

The inspector

examined the quality control records for modifications

and changes

made by the following design

change

packages:

ISP-AF-021,

ISP-AF-046,

ISM-AF-062)

ISP-AF-065,

Shorten Piping Vents

and Drain Lines

Changes

to Limit-Torque Valves (2)

Remove

AF Pump Full Flow Recirculation Valves

Modify Pipe Hanger

13-AF-011-H-011

The field inspection included

a walkdown of the auxiliary feedwater

system piping to check the configuration against that depicted by

the piping and instrumentation

diagram,

13-M-AFP-001, Revision 16.

The

AFW system

was walked-down from the condensate

storage

tank to

where it tapped into the main feedwater piping adjacent to the steam

generators.

The pull and termination cards for 13 cables

associated

with the

AFWS were examined in conjunction with the walkdown of this

system.

No violations of NRC requirements

were identified.

D.

C Ins ector

ualifications

The inspector

examined the qualifications of 15 mechanical

and

electrical,(}C inspectors.

Seven of these inspectors

had performed

(}C insp'ections

of the modifications for which the

gC records

were

examined by this inspector

and identified above in paragraph

C.

4

No violations of NRC requirements

were identified.

The inspector

concluded that the licensee's

system for control and

verification of design modifications

and changes

to the

AFW system, while

under the jurisdiction of startup test group,

does function properly to

accomplish the objectives.

It appears

that there is adequate

design

control and verification.

Licensin

Commitment Trackin

S stem

The inspector

met with key management staff to discuss

the licensee's

program for identifying and tracking licensing related items.

The

program is comprised of a main listing of commitments extracted

from such

documents

as the Safety Analysis Reports, Fire Protection Report, Safety

Evaluation Report,

the TMI Lessons

Learned Report and

APS correspondence

with the

NRC.

Other subprograms

exist which identify matters related to

NRC inspection report findings, Deficiency Evaluation Reports

and

Operating Experience Reports.

The main program is managed

and maintained

by APS licensing staff.

Based

on discussions

with staff members

and review of documents

dealing

with commitment tracking systems,

the inspector learned that the basic

commitment data

was extracted

from the referenced

documents

by a team of

people

who compiled the information into a master list.

Subsequent

to

the establishment

of the basic list,

a program was implemented to require

that every document,

issued to the

NRC by APS, be reviewed by a

responsible

APS engineer to identify licensing commitments.

The program also requires, in addition to the identification of the

commitment,

the review of the commitment by the organization responsible

for its disposition

and the entry of the item on the list by coordinators

dedicated

to the maintaining the list current.

These coordinators

are

assigned

to the various project organizational units.

Additionally,

individuals have been assigned

in the different organizations

to follow

the progress

of item disposition

and interface with the

APS licensing

organization.

The commitments

are tracked

on computer lists.

The information

associated

with each item includes

the source

document

and paragraph,

responsible

department,

item number,

due date,

completion date,

reference

documents,

disposition documents

and item description.

The listing is

maintained current by the completion of input forms which are processed

into the computer by the coordinators.

In order to assess

the quality of information. on the lists, the inspector

reviewed the program for commitments,

documented in the testing section

(Chapter

14) of the CMSAR, the TMI lessons

learned report,

and recent

violations identified in NRC inspection reports.

No discrepancies

were noted.

Mhile confirming the identification 'of the commitments,

the inspector

was

informed that the tracking system included only the "software" as program

type items.

Hardware or installation type items were encompassed

in the

plant design program.

The licensee is currently developing

documents

to describe

the program.

To date

a company policy has been written which addresses

the total

Action Tracking System

(ATS).

A procedure

describing the Licensing

Commitment Tracking System

(ICTS) is in draft and is expected to be

finalized in two weeks.

t'l'

I

~

I

P

The licensee

was informed that in addition to finalizing the

LCTS

procedure,

that subprogram

such

as the

NRC Inspection Finding Program

should be proceduralized in a timely manner.

The inspector also

discussed

the matter of including an "overdue" statistic in the monthly

report which documents

the number of open,

closed

and totals count of

commitments.

APS responded

that it would initiate actions to finalize

necessary

program procedures

by October 8,

1984,

and include the overdue

statistic in its reporting system.

Based

on discussions

with plant staff and

a review of program documents,

the inspector

concluded that

a program was being implemented to identify

and track licensing commitments,

although the program has not yet been

fully proceduralized.

No violations were identified.

5.

0 eratin

Iicense

0 en Item Trackin

S stem

The inspector met with key management

personnel

to discuss

the program

used by APS to identify and track the status of completion of Unit

1

items requiring resolution prior to the receipt of an operating license.

The program involves the identification of open items by all Unit 1

project organizations.

The coordination of the overall list is

accomplished

by the

APS licensing organization.

Overall cognizance of

status

and schedule,

as well as the coordination of APS management

efforts to support resolving the items, is carried out by the Transition

Manager.

Each of the project organizations

has

an assigned staff member

who serves

as

a central contact

and follows the activities associated

with the tracking and statusing of the items under their jurisdiction.

Knowledge of the progress

of schedules

is maintained through weekly

meetings

between the Transition Manager

and the various Project Managers.

The category of items which are

on the lists appeared

comprehensive

and

included such types as:

a

~

b.

c ~

d.

e.f.

g.

h.

1 ~

Licensing Commitments

NRC Inspection Findings

Deficiency Evaluation Reports

Bulletins and Notices

Allegations

Startup

Open Items

Operations

Open Items

Nonconformance

Reports

Test Exceptions

The listing of items requiring disposition prior to licensing is

undergoing final review.

Resolution of the items which obviously need

closure is ongoing.

APS has identified the criteria which it intends to

use in determining which open items must be resolved prior to licensing.

This criteria has just recently been formulated and it is APS's intent to

procedurally apply the criteria consistently throughout the project.

The consistent application of criteria, by all project organizations,

to

identify and prioritize open items

was stressed

with APS management.

In

lt

addition,

management

was informed that since several organizational units

were developing lists of open items, falling within their responsibility,

it was important that such lists have project cognizance

and

coordination.

The licensee

indicated agreement with this philosophy.

While the program to manage

the resolution of items requiring disposition

prior to licensing has essentially

been developed

and is being

implemented,

the description of program activities, responsibilities

and

interface controls

has not yet been written.

Management

was advised that

the completion of this document should be expedited.

This matter was

discussed

with APS management

who committed to the development of

necessary

program and procedures

documents

by September

24,

1984.

APS

also plans to apply the criteria consistently

and maintain project

cognizance of all Lists.

The open items list is to be finalized by

October

1, 1984.

A spot check of known problems with the Auxiliary Feedwater

System were

confirmed by the inspector to be on the'startup

open items list.

Based

on discussions

with plant staff and document reviews, it was

concluded that programmatic efforts to identify, resolve

and track the

status of items requiring resolution prior to licensing is in place

and

being implemented.

Verification that appropriate

items have been

identified, along with program description implementation, will be

addressed

during future inspection efforts.

No violations were identified.

Reactor Vessel Overfill

On August 27,

1984,

an unplanned overfill of the Unit 1 reactor vessel

occurred

because

of an incorrect valve lineup.

This event

was

one of a

series

which occurred

due to ineffective controls governing equipment

operations

carried out to support startup testing activities.

Details of

the event,

which is considered

a violation of regulatory requirements,

as

well as references

to previous operating errors are documented in NRC

Inspection Report 50-528/84-28.

Corrective actions

taken by the licensee

're documented in Inspection Report 50-528/84-33.

Because of NRC's

concerns for incidents of incorrect equipment alignment, 'this topic was

discussed

with APS management

during the exit meeting.

Measurin

and Test

E ui ment

(M&TE)

The quality assurance

program for Control of Measuring

and Test

Equipment

(M&TE) is described in Section 17.2.12 of the

PVNGS FSAR

and in Section

12 of the

PVNGS Operations

equality Assurance

Manual.

The inspector

reviewed the following procedures

contained in the

Station Manual in order to establish

whether the licensee

had

established

a program consistent with commitments.

(1)

Procedure

No.

34PR-OZZOl Rev.

3, "Measuring and Test Equipment

(M&TE) Control Program."

ig

p

0

(2)

Procedure

No.

34AC-OZZ03 Rev. 6, "Control of Nonconforming

Measuring

and Test Equipment

(M&TE) and Calibration Standards."

(3)

Procedure

No.

34AC-OZZ06 Rev. 4, "Calibration Requirements

for

Measuring

and Test Equipment

(M&TE) and Calibration Standards."

(4)

Procedure

No.

34AC-OZZ07, "Measuring and Test Equipment

(M&TE)

Users Administrative Requirements."

(5)

Procedure

No.

34AC-OZZ08 Rev.

0, "Measuring and Test Equipment

(M&TE) Work Control."

In addition to the above procedures

contained in the Station Manual,

the inspector also reviewed Metrology Laboratory Instruction No. 01,

"Control of M&TE Interval and Inaccuracy

Change,

"Rev. 0, which

provides

a method for evaluation

and control of calibration interval

and equipment accuracy revisions.

The inspector

concluded that the applicant's

QA Program for M&TE

established:

responsibility assignment

to assure calibration and control of

M&TE,

requirements for marking M&TE with calibration data,

due dates

and calibration status,

a system to assure

that

M&TE is recalled

and calibrated before

the calibration period has expired,

controls to preclude inadvertent

use of M&TE for which the

calibration period has expired,

out-of-calibration controls assuring evaluation of cause of

out-of-calibration status

and the acceptability of items

previously tested

or measured

using this equipment,

criteria and responsibility for assignment

of calibration

frequency,

and

requirements

that calibrations

be performed in accordance

with

procedures,

manufacturer's

specification or written

instructions.

The inspector

found that Procedure

No. 34AC-OZZ08, "Measuring and

Test Equipment

(M&TE) Work Control" was approved by the Plant Review

Board on July 9,

1984, then lost for about

a month.

The procedure

was being used during this period of time even though it had not yet

officially been approved by plant management.

The procedure

was

made effective August 28,'984.

This apparent

lapse in

administrative controls implementation

was found to be of minor

safety significance since only minor differences

between the old and

new work control procedure for M&TE were found to exist.

L ~

t

4

t

s'

A

10

The inspector

reviewed work order records for calibrations of M&TE

accomplished

from August

1 to August 28,

1984.

Of the 584

calibrations performed,

535

(92 percent)

were performed in

accordance

with approved station procedures,

28 (five percent)

were

performed using the manufacturers'pecification

or a vendor's

manual, eight (one percent)

were performed using other written

instructions,

and

13 (two percent)

were performed by an outside

source.

The inspector

choose at random

a work order in which the calibration

of a Hewlett Packard

Model 334A Distortion Analyzer (Equipment

No. SL2017)

was to have been performed in accordance

with

manufacturer specification,

Tech Manual No. EIM290.

Completed data

sheets

were reviewed against the requirements

in the Tech Manual.

Not all data specified in the manual had been taken.

The licensee

provided the inspector with technical justification for not

performing certain steps in the vendor manual.

The observation that

on the work order did not identify those specific steps in the

vendor's

manual which were to be performed,

or were exempted,

indicates

an apparent

weakness

in administrative control of

calibrations of MME performed in accordance

with a manufacturer's

specification or vendor's

manual.

The licensee

committed to

corrective action in this area.

(84-38-06)

The inspector's

review of 15 out of tolerance notices

(OTN's) issued

for MME resulted in the following findings.

OTN 84-460,

issued against

megger

EM 1065,

was found to be

dispositioned

by verifying only the last use of the megger.

This instrument.

was used for preventive maintenance

on a number

of motor operated

valves in the safety injection and auxiliary

feedwater

systems.

Procedure

No.

34AC OZZ03 "Control of

Nonconforming Measuring

and Test Equipment

(MME) and

Calibration Standards"

specifies that one method of determining

the acceptability of tests

when

a piece of MME used is found

out of tolerance,

is by verifying only the last test performed

with that instrument.

It is conceivable that

a satisfactory

verification of the last performed test

may not be sufficient

reason for acceptance

of other tests.

The licensee

stated their practice is to evaluate all tests to

determine

the necessity of additional verifications.

The

licensee

committed to revising the administrative controls to

bring these into line with actual practice.

Both OTN 84-675,

issued against pressure

gage, GU-0008,

and

OTN 84-692,

issued against micrometer

MM 1021, indicated that

these pieces of MME had not been used in the interval for

which the OTN's had been written.

Review of the usage

logs for

the micrometer

and pressure

gages

indicated the devices

had

been used.

Review of the work orders listing usage of these

two pieces of MME did, however, establish that the micrometer

S

"a

n

'tl

C

had not been used in making any critical measurements

and that

the pressure

gage

had been

used in a non-safety related

application.

In reviewing

OTN '84-690

and

OTN 84-691,

no usage

cards

were

found to exist for the pieces of MME affected,

crimp tool

EM 4170 and digital ammeter

EM 1313, respectively.

Although

usage

cards

were not created in these

two cases,

the licensee

stated it is their practice to create

a usage

card

when

a piece

of MME is received at its place of issuance.

Although none of the above findings represent violations of NRC

requirements,

the problems identified in the small sample of OTN's

reviewed indicate possible

weaknesses

in the evaluation of out of

tolerance notices.

The licensee

committed to perform additional

in-depth reviews in this area.

This area will be evaluated

during

a

subsequent

inspection

(84-38-06).

8.

Surveillance Testin

and Calibration Control

The inspector

examined the following procedures

to assure

that

a

program had been developed

to accomplish the surveillance testing,

calibrations

and inspections

required by the proposed

Palo Verde

Unit 1 Technical Specifications

and the

ASME BSPV Code Section XI

with regard to pump and valve testing:

(1)

Procedure

No.

73AC-OZZ10 Rev.

0,

"ASME Section XI Inservice

Inspection"

(2)

Procedure

No.

73AC-9ZZ04 Rev.0, "Surveillance Testing"

Based

upon the above review and discussions

with licensee personnel,

the inspector

concluded that the licensee had'established

or was in

the process

of establishing:

a comprehensive listing of required surveillances

including,

Tech Spec paragraph

surveillance

frequency,

and

modes in which

surveillance is required,

assignment

of responsibility for the accomplishment of each

surveillance

requirement to a particular licensee

organization,

procedures

for the performance of each surveillance test,

assignment

of responsibility for review of surveillance

data to

assure

Tech Spec compliance,

a system to ensure that each required surveillance is scheduled

and tracked,

and

a system to assure

compliance with the pump and valve section

(IWP and DN) of the

ASME BRPV Code Section XI.

12

The inspector determined that the licensee is tracking open items in

this area.

These

open items include: completion and incorporation

into the station manual of the cross-reference

relating technical

specification requirements

to surveillance procedures

or other

implementing instructions;

assignment

of responsibility for

performance of Tech Spec surveillance

requirement 4.3.3.9,

Table 4.3-8 Gaseous

Radwaste

System Explosive

Gas Monitoring System

channel

checks,

and Tech Spec surveillance

requirement 4.11.2.6,

quantification of radioactive material contained in Gaseous

Radwaste

System storage

tanks;

and completion of a comprehensive list of

hydraulic and mechanical

snubbers

subject to surveillance

requirements

of Tech Spec 4.7.9.

The inspector also determined that the licensee

was planning to use

printouts from the non-safety related plant computer

system

as

a

means of accomplishing certain required safety-related

channel

checks in lieu of using qualified instrumentation.

The inspector

discussed

the philosophy and intent of a channel

check,

described in

section

1.5 of the Tech Specs (i.e.,

a channel

check is intended to

be

a qualitative assessment

of channel behavior during operation by

observation).

The licensee

committed to perform channel

checks

using the plant computer

system only when direct indication from

qualified safety-related

instrumentation is not otherwise available.

In addition,

the inspector discussed

with the licensee

the

requirement of Section 4.7.9i of the Tech Specs

regarding the need

to ensure that the service life of both hydraulic and mechanical

snubbers

is not exceeded

between surveillance inspections.

The

inspector noted that no preventive maintenance

program for

mechanical

snubbers

had been defined nor did the licensee provide

sufficient justification for the absence

of such

a program.

This

will be carried

as

an open item and examined during

a future

inspection

(Open Item 50-528/84-38-01).

Im lementation

The licensee

has identified 261 surveillance test implementing

procedures

to be required for performance of all surveillance

requirements.

The licensee indicated that

96 of these

were required

for entry into Mode 6.

Of the total required for all modes,

the

licensee

stated

that.

69 percent

were ready for use.

Of the

96

required for Mode 6,

81 percent

were said to be complete.

Implementing procedure

review will be the subject of future

inspection effort.

The inspector did discuss with the licensee

the need to perform

surveillances,

using the proposed

surveillance test implementing

procedures,

prior to their actually being required in order to

verify procedure

adequacy.

The licensee

indicated they were doing

this to some extent

and would consider increasing their efforts in

this area.

No violations or deviations

were identified.

h

h

13

9.

Haintenance

Performed

on the

AFWS

The inspector

examined selected preventative

and corrective maintenance

actions performed

on the

AFWS while the system is under control of the

Startup

Group.

The sample consisted of 22 completed

SWA/NCR packages,

23

work orders

and two Startup Turnback Work Orders.

The packages

were

reviewed for technical

adequacy,

proper review and approval,

proper

equipment classification

and proper initiation, disposition

and

documentation.

The packages

examined

appeared

adequate

in the above

areas.

No violations of NRC requirements

were identified.

10.

Thermal Ex ansion Testin

of AFWS

The inspector

reviewed test procedure

91HF-1ZZ08

(BOP Piping Thermal

Expansion Test)

and test guideline PETG-6-XX-1 (Piping Vibration, Thermal

Expansion,

and Dynamic Effect Verification) as they apply to thermal

expansion testing of the

AFWS.

The inspector discussed

the testing

program with licensee

representatives

and reviewed the test results

on

all pipe hangers

tested

on the

AFWS.

All hangers

were tested

successfully

and no discrepancies

were identified.

No violations of NRC requirements

were identified.

ll.

Desi n Chan

e and Hodifications durin

Plant 0 erations

The quality assurance

program for design control is described in

Section 17.2.3 of the

PVNGS FSAR.

The requirements

for plant and

corporate safety committee (Plant Review Board) review of design

changes

and modifications are defined in Section 6.5 of the

PVNGS

Unit 1 draft Technical Specifications.

The inspector

reviewed the

following procedures

contained in the Station Hanual in order to

determine whether the licensee

has established

a design control

program consistent with his commitments

as described in these

documents.

(1)

Procedure

No.

73AC-OZZ12, "Plant Change Request

(PCR),"

Revision 2, of May 25,

1984.

This procedure

establishes

the

method for controlling and processing all design

change

requests,

including modifications, associated

with the

PVNGS.

(2)

Procedure

No.

73AC-OZZ15, "Plant Change

Package

(PCP),"

Revision 1, of June

25,

1984.

This procedure provides the

method to develop,

review, implement and closeout plant change

packages

(PCPs).

The

PCP package

contains

the

PCR and the

Design

Change

Package

(DCP).

(3)

Procedure

No. 79AC-9ZZ07, "Nuclear Safety Review and

Evaluation," Revision 0, of February

14,

1984.

This procedure

describes

now safety evaluations

are performed to evaluate

J

't

'I II

1

proposed

design,

procedural

and operational

changes

according

to the criteria set forth in 10 CFR 50 '9.

(4)

Procedure

No.

73AC-OZZ17, "Detailed Design Development,"

Revision 0, of June

29,

1983.

This procedure

establishes

and

describes

the methods

used for the development of a detailed

design, in accordance

with ANSI N45.2.11, for plant

modification.

(5)

Procedure

73AC-OZZ27,

"Change Control Process,"

Revision 0, of

July 5,

1984.

This procedure

establishes

administrative

controls for the request,

processing,

review and approval of

design

changes,

including closeout

and tracking of all plant

changes'6)

Procedure

No.

73AC-OZZ24, "Field Change Requests,"

Revision 0,

of April 5,

1984.

The purpose of this procedure is to control

the use of Field Change Requests.

(7)

Procedure

No.

73AC-OZZ26, "Impact Review and Transmittal of

Design Change

Documents (Prior to Acceptance),"

Revision 0, of

June

19,

1984.

This procedure

establishes

a method, including

documentation,

for review of design

changes for impact on

licensing, documents,

procedures,

programs

and activities.

B.

Procedure

Review

The above procedures

were reviewed to establish

whether the quality

program for design

and modification change

contained

the following

attributes:

procedures

establishing

controls for design

and modification

change

request,

including:

(a)

method for initiating a design or modification change.

(b)

design

change

request. control form, or equivalent, with

provisions for documenting

completion of required reviews,

evaluations,

and approvals prior to implementing the

change.

(c)

method for assuring that proposed

change

does not involve

an unreviewed safety question,

as described in

10 CFR 50.59, or a change in the technical specification.

l

(d)

method for assuring that applicable guidelines for fire

protection are included in design documents.

(2)

procedures

and responsibilities for design control have been

established

including:

(a)

identification of organizations

responsible for performing

design work'.

1

I 1

1'

15

(b)

responsibilities

and methods for conducting safety

evaluations.

(c)

procedures

and responsibilities for identifying,

reviewing,

and approving design input requirements.

(d)

methods,

procedures,

and responsibilities for performing

independent

design verifications.

(e)

responsibilities for final approval of design

documents.

(f)

procedures

and responsibilities .for assuring proper

inclusion of fire protection/prevention

requirements.

(3)

Administrative controls for design

document, control have been

established for the following:

(a)

controlling changes

to approved design

change

documents.

(b)

release

and distribution of approved design

change

documents.

(4)

administrative controls require that design documentation

and

records,

which provide evidence that the design

and review

process

was performed,

be collected

and transmitted to records

storage.

(5)

controls require that implementation of approved

design

changes

be in accordance

with approved procedures.

(6)

responsibility and method for reporting design changes/modifi-

cation to the

NRC in accordance

with 10 CFR 50.59.

(7)

program provided for periodic management

reviews

and audits of

the activities in this area in order to appraise

the

effectiveness

of the program.

C.

Audit Review

The procedures satisfactorily addressed all of these

program

controls.

In order to assess

the management

appraisal of the design

program,

the inspector

reviewed audits performed by the (}uality

Audits and Monitoring Group.

The following evaluations

and audits

were reviewed.

(1)

Evaluation of Operations

Readiness

(performed April 25 - May 6,

1983).

This activity was conducted to evaluate

the operations

readiness

of departments

within APS to support operation of

PVNGS.

The design control portion of the evaluation

was to

assure

the overall effectiveness

and ability of APS to control

design

and design configuration. It should be noted that this

activity was performed in the early stages

of operations.

Therefore, draft procedures

were audited

and all findings were

then presented

to Corporate

gA as program recommendations.

The

16

audit report identified nine major .recommendations

which were

responded

to by APS management.

(2)

Operations

Readiness

Audit (performed February

14 - April 18,

1984) of Design Control.

No major problems identified.

(3)

Operations

Readiness

Audit (performed July 5-25,

1984).

Resolution of problems identified are in process.

This portion of the inspection

was intended to verify that the

licensee's

program for control of design

changes

and modifications

was adequately

implemented.

However, at this earlier stage of

operations,

no safety-related

design

change or modification record

packages

have been turned-over to the licensee.

Therefore,

inspection of program implementation will:be performed during a

future inspection.

No violations or deviations

were identified.

Startu

Work Control

To determine

the scope

and depth of work controls associated

with the

Startup

Program of Palo Verde for Un'it 1, the inspectors

examined

documentation

associated

with test'ctivity.

Included in this

examination were 304 Startup

Work Authorizations

(SWAs),

221 Startup

Field Reports

(SFRs),

and

71 Nonconformance

Reports

(NCRs) for the

testing

done under the portions of 91PE-1SI08

(Safety Injection System

Full Flow Verification Test) associated

with the low Pressure

Safety

Injection System.

For procedures

91PE-lAF01 (Auxiliary Feedwater

System)

and 91HF-lAFOl (Precore

Emergency

and Auxiliary Feedwater

System Test)

the inspectors

examined

407 SFRs,

430

SWAs,

and

140 NCRs.

An area of concern regarding the depth of NCR resolution review during

examination of NCR's

SM-3567 (initiated January

17, 1984),

and

SM-4201

(initiated April 18, 1984).

NCR SM-3567 identified a rumbling sound

phenomena

in the suction piping associated

with l,ow Pressure

Safety

Injection Pump B.

The disposition of the

NCR was to keep the flow below

2200 gallons per minute,

as the phenomena

was observed in the range of

3000 gallons per minute.

The cause

was thought to be due to the system

lineup in use,

which was recirculation through the Refueling Water Tank

via a recirculation line rather than the normal injection path.

NCR

SM-4201 identified the

same

phenomena,

and

was initiated to facilitate an

investigation into the phenomena.

The startup organization

was fully

aware of, and had extensive

discussions

about, the situation following

the closure of NCR SM-3567.

This indicates that there

was considerable

concern about the potential effects of the phenomena.

Therefore,

the

closure disposition of NCR SM-3567 would appear to have been premature.

It also appears

that thoroughness

in the review of the

NCR was lacking in

that no consideration

was given to follow-up during later testing.

Other than the above item, the inspectors

found that startup work

controls were in place.

And were sufficient to assure

that no work

J

I

II

t

~h

17

activity would take place without sufficient managerial

review and

involvement.

SWAs and work orders, in general,

controlled work activity

sufficiently to a level that would prevent unauthorized

work being done.

No violations or deviations

were identified.

13.

Test Results

To examine the processes

that, Test Results

Reports

undergo during review

and approval the inspectors

reviewed the following procedures:

90AC-OZZ02, Startup Test Conduct

90AC-OZZ09, Startup Test Working Group

90AC-OZZ14, Startup Procedures

Preparation,

Review and Approval

90AC-OZZ18, Startup Test Results

Review

90AC-OZZ19, Startup Field Reports

The inspectors

then examined three Test Results Reports for the following

preoperational

tests:

91PE-1AFOl, Auxiliary Feedwater

System Test.

91HE-1AF01, Precore

Emergency

and Auxiliary Feedwater

System Test

91PE-1SI08,

SI Full Flow Verification Test

The Test Results

Reports

were examined to determine

the depth

and

thoroughness

of the reviews

conducted

by the Test Working Group

(TWG).

The three reports

chosen

were in different phases

of the review cycle

and, therefore,

presented

a good overview of the processes

that reports

undergo during

a review by TWG.

Report 91PE-lAFOl had undergone

a full

review and had included all comments

by TWG that had concurrence

by the

Principal Startup Engineer

and the Group Supervisor.

All Test Exceptions

were concurred with and all SFRs resolved

as to final disposition.

Report 91HE-lAFOl had just undergone

TWG review and was in the

comment

review phase

where the

comments

made by TWG were in the process

of

concurrence prior to approval by the

TWG Chairman.

Again, except for TWG

comments

the Test Exceptions

and the

SFRs were resolved.

For 91PE-1SI08,

the Test Results Report was in the process

of being prepared.

The

inspector discussed

the process with the Principal Startup Engineer

a

Group Supervisor.

All test exceptions

were reviewed

and fully resolved

prior to submittal to TWG, as were outstanding

SFRs or NCRs that would

have

a bearing

on the acceptability of the Test Results Report.

In no

case

would TWG accept

a package without a fully successful test,

or a

satisfactory resolution of acceptance

criteria.

In the case of the testing conducted

under 91PE-1SI08 for the low

pressure

safety injection pumps,

two SFRs that were associated

with the

failure to achieve

a flow of 9600 gallons per minute in the combined

suction header

were prepared.

The flowrate was necessary

to measure

net positive suction head

when both

the containment

spray,and

low pressure

safety injection pumps are running

with a

common suction per

CESSAR 14.2.12.1.23-3.4,

The 9600 gallons per

minute is minimum projected flow for both pumps,

however, it could not be

achieved in the configuration used for testing,

which was through the,

k

H

iV

18

normal injection path for low pressure

safety injection.

The flow rates

that were achieved

were 8900 gallons per minute for LPSI "B" and

containment

spray "B" and

8600 gallons per minute for IPSI "A" and

containment

spray "A".

The higher head of the containment

spray pumps

held back the flow that could be achieved

from the LPSI pumps.

Therefore,

the desired point at which to measure

net positive suction

head could not be reached.

The resolution for the

SFRs

was to

extrapolate

to 9600 gallons per minute and calculate

the

NPSH at that

point.

The acceptance

criteria for NPSH at the suction of the LPSI pumps

is 22 feet.

The

NPSH at 8900 gallons per minute for LPSI "B" pump was

73.7 feet,

and for LPSI "A" pump at 8600 gallons per minute the

NPSH was

72.2 feet.

Calculations

by Combustion Engineering

showed that the head

would only be reduced

about

10 feet, in both cases,

when extrapolated

to

9600 gallons per minute.

Two items of interest occurred during testing of the Auxiliary Feedwater

System.

The first was

a problem the turbine driven pump experienced in

achieving multiple cold starts.

The resolution

was to change the

configuration of the steam supply to the turbine driver, which had

apparently affected the delivered pressure

to the driver.

The cold line

apparently prevented

the driver from achieving sufficient speed before

an

overspeed protection circuit tripped the turbine stop and throttle valve.

The second

problem had to do with excessive piping vibration on the

discharge line of the

same

pump.

The configuration of the valves in the

line led to a condition where the pump was pushing

on a column of water

in a fashion where the beat frequency of the pump and column were close.

To resolve the problem the flow through the recirculation line was

increased with a larger orifice.

Combustion Engineering

has

done an

analysis that

shows the reduced flow to the steam generators will be

sufficient to meet design requirements.

No violations or deviations

were identified.

Test Workin

Grou

The inspectors

held discussions

with four members of the Test Working

Group

(TWG), two who are permanent

members,

and two who are alternates.

The discussions

included Test Results

Reviews, test procedure

reviews,

disposition of TWG comments,

and conduct of TWG activities.

One of the

permanent

members

interviewed

was the

TWG Chairman.

At present

the process for review of test procedures

is such that the

proposed

procedure is routed to

a

sub-TWG review group.

Sub-TWG is a

group of level III startup

engineers

reporting to the

TWG Chairman (there

are

29 members in various discipl'ines).

The procedure is. review by this

group,

any comments

generated

are sent back for incorporation into the

body of the procedure.

After all comments

are resolved the procedure is

routed to the

TWG for review.

This provides

a two tier review, of

substantial

depth

and scope, for a test results report.

The results

are

summarized in a report attached

to the procedure

and data.

This receives

a review by each

member of TWG prior to the report being scheduled for a

meeting of the

TWG.

Each

member is responsible for assuring

the

discipline area

he represents

thoroughly reviews the report. It then

I

It

It

J"

~ ttI'f

19

I

goes to a meeting

and any comments

are. gathered,

a comment sheet is

filled out,

and the package

routed back to the Principal Startup

Engineer.

" After resolution of the

comments

the report can be approved.

This conforms to the procedures

governing the review process.

No violations or deviations'ere j.dentified.

15.

Records

and Document'Control durin

Plant

0 erations

A.

General

The licensee's

program for documents

and records control was

evaluated

against

commitments

contained in Sections

17.2.6

and 1.8

of the licensee's

Final Safety Analysis Report, Regulatory

Guide 1.88 (Collection, Storage,

and Maintenance of Nuclear Power

Plant (}uality Assurance

Records),

and licensee

implementing

procedures'nspection

emphasis

was directed to the licensee's

operational

phase

records

and document control programs.

B.

Document Control

(1)

Procedural

and Administrative Controls

The inspector

reviewed the following licensee

operational

phase

document control procedures.

78PR-OZZ01 Rev.

1,

PVNGS Document/Record

Control

78AC-OZZOl Rev.

1, Nuclear Operations

Document 6 Manual Control

78AC-OZZOl Rev.

1,

PVNGS Document/Record

Control

78AC-OZZ04 Rev.

1, Control and Issuance

of Design Document,

78AC-OZZ06 Rev.

1, Document/Record

Turnover Control

78AC-OZZ07 Rev.

1, Document/Record

78AC-.OZZ11 Rev. 0, Control and Issuance

of Field Change Request

78AC-OZZ12 Rev.

0, Control and Issuance

of Plant

Change

Package

78AC-OZZ13 Rev.

0, Control and Issuance

of As-built Drawings

and Drawing Amendments

Bechtel Internal Procedure

4.12, Drawing Change Notice

(a)

Administrative Controls

Review of these procedures

indicated that the licensee

had

established

administrative controls which:

assure As-built design

documents

are provided to the

plant in a timely manner,

(Bechtel IP 4.12,

78AC-OZZ04).

provide for control of obsolete

drawings

(78AC-OZZ04).

establish

master indices of controlled documents,

including dates

and revision.

(78AC-OZZ04,

78AC-OZZOl, 78AC-OZZ04,

78AC-OZZ13)

e

I

20

provide for issuance,

distribution and control of

Design Documents,

Technical Specifications,

and Final

Safety Analysis Report.

These include marking design

documents

as Controlled, Uncontrolled or Controlled

by User.

(78AC-OZZOl, 78AC-OZZ04,

78AC-OZZ06,

78AC OZZ07 )

78AC OZZ 1 1 ~

78AC OZZ1 2 ~

78AC OZZ 1 3 >

78PR-OZZ01).

provide for receipt Controls by DDC-PV (78AC-OZZ06,

78AC-OZZ07).

(b)

Procedural

Controls

The inspector verified compliance with selected

procedural

controls, including but not limited to:

(1)

Procedure

78AC-OZZ04, Control and Issuance

of Design

Documents

paragraphs

3.1.1.1 through 3.1.1.4

(Stamping of

drawings).

paragraph 5.2.1

(Use of drawing/transmittal

document)

paragraphs

5.2.2 and 5.2.3

(Use of Design

Document Distribution Matrix and System

38 to

track document transmittals

and status).

paragraphs

5.2.6

and 5.8 '

(Verification of

controlled document updates within 2 days)

paragraph 5.7.1

(Use of Controlled Drawing

Transmittal Acknowledgement Form and Tickler

File)

paragraph 5.8.1 (Stick files were identified by

a unique number to the Design Document

Distribution Matrix).

paragraph 5.8.2 (Stick files cover sheets

show

station

and drawings contained)

paragraph 5.8.6 (Physical removal of superseded

design

documents

by DDC-PV) (Refer to report

Section B,a,A for additional discussion).

(2)

Procedure

78AC-OZZ01, Nuclear Operations

Document

and

Manual Control

paragraph

3.1.5

(Use of "Information Only"

copies of procedures)

1

21

'

paragraphs

3.1.6

and 3.1.7

(Use of the

Procedure Distribution Matrix and Procedure

Index).

paragraph

3.1.7.1 (Distribution and use of Daily

Change List)

paragraph

3.1.8

(Use of Procedure

Change

Notices,

PCNs)

paragraph 5.1.3

(Use of DDC-PV Receipt Log)

(3) Procedure

78PR-OZZOl,

PVNGS Document/Record

Control

paragraph 3.1.f.2

(Use of Field Revision Log)

paragraph 3.1.f.3

(Use of Daily Notification

Log)

paragraph 3.1.f.5

(Use of System

38 to reflect

as-built conditions at PVNGS)

The inspector

found that the definition of responsibilities for

distribution of controlled documents,

contained in procedure

78AC-OZZOl (Nuclear Operations

Document

and Manual Control),

needs revision to reflect the actual practice of As-built

Records

Management

Group performing the actual distribution and

update of procedures.

Discussions

with licensee

representatives

indicated that this change in responsibilities

had taken place

on August 13,

1984,

and that the licensee

was

already evaluating

how these procedures

should be revised.

No violations of NRC requirements

were identified.

(c)

Document Control Verification

The inspector verified that the licensee

had established

master

indices to control document distributions

and

an index to

reflect current revisions.

To evaluate

program effectiveness,

current revisions of procedures,

technical specifications

and

design drawings

were evaluated

at. multiple locations onsite.

Controls over the Final Safety Analysis Report were also

reviewed at several locations although this is presently

controlled by Bechtel from Norwalk, California.

(1)

Desi n Drawin Verification

Design drawings were evaluated at eight locations onsite

(NSSS-Trailer

10, Unit 1 Operators-Trailer

8, Unit 2

Startup Manager-Trailer 29, equality Control

Manager-Trailer 30, Unit 1 Technical Support-Trailer 2,

Unit 1 Control Room, Administrative Library, and the

Unit 2 Control Room).

At each location four

safety-related

Piping and Instrumentation

Diagrams

and

4

22

associated

Design Change Notices were evaluated

against

the current revision maintained by As-built Records

Management.

Drawings utilized to verify licensee

document

control effectiveness

included:

12-M-CHP-003 Rev. 9,

Chemical

and Volume Control System

PAID with 19 Design

Change Notices

(DCNs); 13-M-IAP-003 Rev. 6, Instrument

and

Service Air System

PAID with 18 DCNs;

13-M-SGP-001

Rev.

13, Main Steam

System

PAID with 6 DCNs;

and

13-M-SGP-002 Rev.

10, Main Steam

System

PAID with 4 DCNs.

Thus, total of 32 controlled drawings

and

376 DCNs were

inspected.

Based

on this review the following

observations

were noted:

Drawing 13-M-IAP-003 Rev.

6, Instrument

and Service

Air PAID, at the Quality Control Managers Trailer 30,

was missing

DCN No. 128.

Drawing 13-M-IAP-003 Rev. 6, Instrument

and Service

Air PAID, at the Administrative library, was missing

DCN No.

128.

Drawing 13-M-SGP-002 Rev.

10, Main Steam

System PAID,

at the Administrative Library was missing

DCN No. 51.

Thus,

two out of eight locations with controlled drawings

were found to not have

a fully up-to-date

DCN status.

Of

the 376 DCN's reviewed

as part of this inspection,

only

three problems

were observed.

This represents

a problem

rate of less

than one percent.

Drawing 13-M-SGP-001

Rev.

13, Main Steam

System

PAID,

at the Quality Control Manager, Trailer 30 location

still had superseded

DCNs Nos.

64, 65,

66>

67

68'9,

70,

71,

75 present in the Nuclear Projects

Records

Managements

(NPRM) DCN's folder.

The Unit 2

Control Room also had superseded

DCN No.

75 present

in the

NPRM DCN folder. It was, also,

noted that the

drawing revision which incorporated

these

DCNs

correctly reflected their incorporation.

Drawing 13-M-SGP-002 Rev.

10, Main Steam

System PAID,

at the Quality Control Manager Trailer-30 had

superseded

DCNs 41,

50 and 52 through 57 present in

the

DCN folder.

It,was, also,

noted that the drawing

revision which incorporated

these

DCNs correctly

reflected their incorporation.

Since

a revised drawing was present at these locations,

the presence

of the superseded

DCNs was not considered

to

be

a significant safety concern.

The licensee

corrected

this problem during the inspection.

The inspector identified discrepancies

in the

DCN status

of two "Controlled by User" drawings at the Unit 1

'I

a

4.

23

Technical Su'pport-Traile'r No.

2 location.

These included:

6 missing

DCNs to piping and instrumentation

drawing

13-M-SGP-,002

Rev.

9; and

2 missing

DCNs to piping and

instrumentation

drawing 13-M-IAP-003 Rev.

6.

Previous

licensee internal reviews ohe controlled drawings in

the Unit

1 Technical Support Trailer had identified

'imilar problems including 'missing DCN's and wrong

revisions of drawings.

Since the licensee

had already

identified simila'r, problems with the drawings at this

location, the need to provide improved controls over user

updated

drawings

was noted at the exit interview.

Two drawings

(13-M-CHP-003,

Rev. 9, Chemical

and Volume

Control System,

and 13-M-IAP-003, Rev.

6, Instrument

and

Service Air System)

were identified to have

19 and

18 DCNs

issued to these

drawings, respectively.

The lack of a

specific limit in Bechtel Internal Procedure

4.12 (Design

Change Notice) to control the number of DCNs outstanding

against

a drawing, prior to revision of the drawing,

during the construction/startup

phase

was discussed

with

licensee

representatives.

Licensee

representatives

stated

that controls

had been established

over the number of

outstanding

DCNs allowed during operations.

Based

on the above observations,

although isolated in

nature

and of minor safety significance,

the inspection

team leader

requested

that the licensee

commit to an audit

of their document control program to determine whether

additional controlled drawings

have not been maintained.

The licensee

agreed

to perform this audit at the exit

interview.

Pending evaluation of the licensee's

audit

findings, this is considered

to be an unresolved

item

(84-38-02).

(2)

Control of Station Procedures

Control over Station Manual procedures

was evaluated

by

comparing the latest revision of procedures,

identified by

DDC-PV from the Station Manual Procedure

Index and Daily

Change List (DCL), with the revision status four

procedures

at five locations.

No discrepancies

were

identified.

(3)

Controls over Technical

S ecifications

and the Final

Safet

Anal sis

Re ort

As an additional check on document controls,

the inspector

randomly selected

several locations where distribution of

Technical Specifications

was controlled by As-built

Records

Management.

All locations were found to have the

latest draft revision of June

21,

1984.

Although

distribution of the Final Safety Analysis Report is

presently controlled by Bechtel,

the inspector verified

that current copies

(Amendment

13) were present at four

J

I

24

locations.

No problems

were noted with the control of

either of these

documents.

No violations of NRC requirements

were identified.

C.

Records

Stora

e and Control

General

(2)

The licensee

was in the process

of transferring records

from

multiple onsite groups to Nuclear Projects

Records

Management

(NPRM).

Licensee

implementing procedure

78AC-OZZ07 Rev.

1,

(Document/Record Vault Storage

and Maintenance)

Section 5.1.1,

states

that "Records

generated prior to issuance

of an

operating license are to be turned over to Nuclear Projects

Records

Management

Drawing and Document Control, Palo Verde

location

(NPRM-DDC-PV) upon completion, within 24 months".

Review of licensee

Nuclear Projects

Records

Management monthly

status

report of document

and record turnover,

dated August 1,

1984, indicated the majority of licensee

records

are yet to be

transferred

to DDC-PV for archival storage.

Licensee

implementing procedure

78AC-OZZ06 Rev.

1 (Document/Record

Turnover Control) describes

the licensee's

program for

individual and bulk transfers of quality related records.

Inspection

emphasis

was directed

toward licensee procedural

controls which would be utilized during operations.

The scope

of records

maintained by Bechtel during construction

and by the

startup

group was not emphasized

during this inspection since

this had been evaluated

during previous inspections.

The

inspector 'reviewed the licensee's

DDC-PV vault design

documents

to verify that the permanent

records

storage facility was

designed

to meet the National Fire Protection Association

(NFPA) two hour rating.

Administrative and Procedural

Controls

The following licensee

procedures,

evaluated

by the inspector,

were the principle procedures utilized to evaluate

records

storage

and handling controls which would be in place during

operations:

78PR-OZZ01 Rev.

1,

PVNGS Document/Record

Control

78AC-OZZ06 Rev.

1, Document/Record

Turnover Control

78AC-OZZ07 Rev.

1, Document/Record

Vault Storage

and

Maintenance

Plant Policy 20

PVNGS Generated

Documents/Records

(a)

Administrative Controls

The inspector verified that administrative controls

had

been established

which:

II

25

define responsibilities for records

storage

and

transfer including designation of records

custodians

(78PR-OZZ01,

78AC-OZZ06) 78AC-OZZ07).

provide verification that records

received

are in

agreement

with transmittal

documents.

(78AC-OZZ06,

78AC-OZZQ7)

control access

to and distribution of records.

(78AC-OZZ07,

78PR-OZZOl)

assure

that the records

storage facility/storage

conditions meet regulatory requirements.

(Plant

Policy 20,

78PR-OZZOl,

78AC-OZZ06,

78AC-OZZ07)

controlled transfer of records to archival storage.

(78PR-OZZOl,

78AC-OZZ06,

78AC-OZZ07)

records retention provided in accordance

with

regulatory commitments.

(78AC-OZZ06)

perscribe

actions necessary

when lost or damaged

or

illegible documents

are identified.

(78PR-OZZOl,

78AC-OZZ06,

78AC-OZZ07)

(b)

Procedural

Controls/Im lementation

The inspector also reviewed licensee

compliance with the

following procedural

requirements

and controls.

The licensee

was stamping

documents

as required by

Section 3.1.1.3

and 3.1.1.4 of 78AC-OZZ04 as

"CONTROLLED BY USER",

and

"CONTROLLED".

The licensee

was observed

to be stamping reproduced

documents

as

"Information Only", as required by Section 5.5 of

78AC-OZZ07.

The inspector

randomly selected

several

documents

from the licensee's

Receipt

Log to evaluate

document

retrievability.

All documents

were provided in a

timely manner.

Procedure

78AC-OZZ07, Document/Record

Vault Storage

and Maintenance

paragraph 5.2.3

The licensee is maintaining

a

document receipt log as required

by procedure.

paragraph 5.3.1.1

Documents

were observed to be

kept in folders or envelopes

and

not stored loosely.

26

paragraph

5.4

Access lists were observed to be

posted at the DDC-PV vault, which

were signed by Nuclear Projects

Records

Manager.

paragraph 5.7.1

Temperature

and humidity controls

were observed to be monitored in

the

DDC-PV vault,

a maximum

humidity reading of 74'/, was

noted.

The licensee

has

initiated a plant change request,

dated August 22,

1984, to improve

humidity/temperature

controls in

the

DDC-PV vault.

Procedure

78AC-OZZ06, Document/Record

Turnover

Control Document.

Transfers of individual and groups

of records

are performed in accordance

with

78AC-OZZ06 and

78AC-OZZ07.

The inspector

discussed

the requirements

contained in Sections

3.2 '

and

5.3(2) of ANSI N45.2.9 with licensee

representatives

during the inspection.

Licensee

representatives

agreed to review the clarity of how these

requirements

are proceduralized.

No violations of NRC requirements

were identified.

16.

Ins ection of Technical Activities Related to Startu

Field Re orts and

Nonconformance

Re orts

Unit 1

A.

O~b'eccive

The inspector

examined the site administrative programs

and

documentation

related to startup field reports

(SFRs), startup

nonconformance

reports

(SFR/NCRs)

and Arizona Public Service

Company

(APS) nonconformance

reports

(NCRs) issued against the auxiliary

feedwater

system

(AFWS) installation in Unit 1, to assess

the

effectiveness

of the startup test group in maintaining the quality

of the

AFWS while under their control.

B.

Technical

A

roach to Ins ection

(1)

Review and obtain applicable

copies of SFR,

SFR/NCR and

NCR

administrative procedures

used onsite.

(2)

Review available

SFRs,

SFR/NCRs

and

NCRs issued against the

AFWS installation in Unit 1, to assess

such things

as technical

adequacy,

documentation

and disposition.

C,

Ins ection Activities and Findin s

t

(1)

The

AFWS was turned over to the startup

group approximately

March 9,

1983 and as of August 29,'984,

approximately

400

SFRs

I

I

1

27

had been issued against

the

AFWS by the startup test group,

along with various

NCRs, per the startup test group'ecords.

(2)

The inspector obtained

copies 'of the following site documents

listed below to identify 'the

SFRs,

SFR/NCRs

and

NCRs issued

against the

AFWS.

<<C

(a)

Report'umber:10;

Definition Number:01 Report title:

,Unit 1, all items for AF-S/S sort.

[from the master

tracking system

(MTS), as of August 31,

1984].

/

(b)

Report Number:05; Definition Number:NC, Report Title: All

open and closed

APS NCRs,

NCR No. Sort-Unit

1 [from the

MTS, as of August 30, 1984].

(c)

Report Number:04; Definition Number:CR, Report Title:,all

open and closed

BPC NCRs,

NCR Sort-Unit

1 [from MTS, as of

August 30, 1984].

(d)

Special

Run:

File: Activity tracking master, Unit 1 all NCRs for system

AF [from MTS, as of August 28, 1984].

(3)

Using the documents identified above

and available site

records,

the inspector

examined essentially all identified

SFRs,

SFR/NCRs

and

NCRs issued

and/or dispositioned

against

the

AFWS by the startup test group

as of August 30,

1984.

The

number of applicable

documents

examined

by the inspector are

listed below.

400

SFRs

102

SFR/NCRs

[SFRs assigned

NCR numbers]

46

NCRs

12

APS NCRs

(4)

Examination of SFRs,

SFR/NCRs

and

NCRs identified that

additional clarifications would have been desirable for some

documents in the initial write up of the reported condition,

information, deficient condition, etc., to aide

evaluation/disposition

of the applicable

documents in an

effective manner.

Also,

some dispositions of SFRs,

SFR/NCRs

and

NCRs could have

used additional information to

clarify/document the justification for the final disposition.

For example,

NCR No. SE-1830

(issued April 4,

1983)

and

NCR

No. SJ-1842

(issued April 8,'983)

were dispositioned

and

stamped

'1NVALIDATE'nApril 13,

1983, without detailed clear

documentation of the justification for the final disposition.

The two NCRs noted in the example

above were identified

August 30,

1984, to the

APS group representative

assisting

the

inspector in his document examination.

The APS representative

notified the inspector

on August 31,

1984 that information

would be added to the above

two NCRs to provide additional

clarification of the final disposition.

This was typical of

the types of problems identified by APS during the

gA audit

k

V

h

l.

V

28

after the

CAT inspection in November 1983, which required

APS

to stop all preoperational testing.

No documentation

problems

of this nature

were identified after testing

was resumed.

D.

Conclusions

(1)

The examination of available

SFRs,

SFR/NCRs

and

NCRs issued

and/or dispositioned

by the startup test group for the

AFWS

installation in Unit 1,

as of August 30,

1984, did not identify

any violation of NRC requirements.

However,

weakness in

initial documentation of descriptions of reportable

conditions

and dispositions

were noted.

(2)

Examination of the startup test group administrative

programs

for SFRs,

SFR/NCRs

and NCRs, did not identify any problems in

maintaining the quality of the

AFWS installation in Unit 1

while under the startup test group control,

as of August 30,

1984.

17.

QA/

C Administrative Controls

and Audits

The inspector

reviewed the following Operations

QA Criteria and Corporate

QA Department

Procedures

(QADP):

Operations

QA Criterion 2, "Quality Assurance

Program"

Operations

QA Criterion 6,

"Document Control"

,Operations

QA Criterion 18, "Audits"

QADP 1.0, "Organization and Responsibilities"

QADP 6.0, "Control of Corporate Quality Assurance

Department

Procedures"

QADP 6.1, "Control of Operations

QA Criteria Manual"

QADP 18.0, "Quality Auditing"

The reviews were conducted to evaluate

the licensee's

administrative

controls

and audit program in general,

and to:

(1) verify implementation

of FSAR and proposed Technical Specification

commitments for

administrative controls and'udits;

(2) verify that administrative

controls

and responsibilities exist for review of the effectiveness

of

the

QA program;

(3) verify that administrative controls exist to modify

the program

and its procedures

and that responsibilities exist for review

and approval of such modifications;

and (4) verify that the master audit

schedule

meets

the requirements

of Regulatory

Guide 1.33, "Quality

Assurance

Program Requirements,"

and associated

commitments.

The inspector

concluded that the administrative controls were in

accordance

with commitments

and the audit program was well established.

The inspector

reviewed

a sample of the audits

(scheduled

and unscheduled)

completed by the Quality Audits/Monitoring Section to verify

implementation of the audit program.

The inspector also reviewed the

training and qualification records of the auditors to verify their

qualifications to perform quality audits.

The licensee

appears

to be

correctly implementing the audit program with qualified personnel.

N

lg

r.

l0 "'

29

No violations or deviations

were identified.

18.

Review of Maintenance

Pro

ram

The inspector

reviewed numerous Station Manual Procedures

including the

following primary documents:

30AC-9ZZOl, Rev.

1,

"Work Control"

30AC-9ZZ02, Rev.

1, "Preventive Maintenance"

30PR

9ZZ01

p Rev.

1, "Maintenance

Program"

Procedure

reviews

and discussions

with maintenance

personnel

were

conducted to verify that

a maintenance

program had been developed in

conformance with proposed

Technical Specifications,

regulatory

requirements,

and commitments to industry standards.

The inspector

concluded that the maintenance

program was in accordance

with requirements

and documented appropriately.

Implementation of the maintenance

program

was not inspected

due to the

recent turnover of responsibilities for review of work packages.

This

will be examined during future inspections,

No violations or deviations

were identified.

19.

Maintenance Trainin

The inspector

reviewed the following Station Manual Procedures

to

evaluate

the maintenance

training and qualifications program in effect at

the site:

80PR-OZZ01,

Rev. 3, "Training Program"

83TR-OZZ04, Rev.

0, "General Employee Training Pathway"

83TR-9ZZOl, Rev.

0, "Maintenance Specialty Training"

Based

upon discussions

with maintenance

superintendents

for the

mechanical, electrical,

and

ISC disciplines

and

a review of procedures,

the inspector noted that the process

to establish

the qualifications for

maintenance

personnel

was incorporated into written procedures.

Station

Manual Procedure

No. 83TR-9ZZOl, Rev.

0,

(Maintenance Specialty

Training), defines

the pathway for training of maintenance

personnel

and

their trainees.

However, the licensee is presently hiring only

journeyman level personnel

to perform maintenance

functions

and this

procedure is not being used.

The program for establishing

the

qualifications consists of numerous

telephone

and personal interviews,

a

written exam,

and

a "hands-on" practical test.

This program is not

included in procedures

and the test records

are not a part of the

individual training files.

In addition, the inspector

found that the

licensee

had not established criteria by which an individual maybe

deemed

fully qualified to perform his job function and duties.

The inspector

found the program currently in use for establishing

the

qualifications of maintenance

personnel

needs

to be revised to reflect

actual practice,

including definition of records

storage

requirements.

'VJ

0

, g'll

30

Upon notification of this finding at the exit meeting,

the licensee

committed to draft a procedure outlining the basis for the qualification

of maintenance

personnel.

Maintenance training remains

an open item to be followed up during a

future inspection.

(84-38-03)

20.

Trainin

Records for Resident

En ineers

A.

Bechtel

En ineers

The inspector

examined the training records for Bechtel project

engineers

assigned

to the Palo Verde site for conformance

to Bechtel

Engineering Department

Procedure

No. 5.34, "Engineering

Indoctrination and Training."

The inspector

found that contrary to

the procedure,

the records indicated that about

30 engineers

had not

received the required training.

Additionally, an Interoffice

Memorandum,

dated October

18,

1983, indicated that management

had

become

aware that many engineers

were not returning their training

sheets

and, therefore,

were not in compliance with the procedure

requirements.

Apparently, sufficiently high levels of licensee

and

Bechtel management

were not advised of the discrepancy with the

result that the identified discrepancy

was still not corrected

almost eleven months later.

The failure to comply with training requirements

as specified by

procedure is considered

an apparent

item of noncompliance.

(50-528/84-38/04)

B.

The inspector

examined the training records for APS resident

engineers

assigned

to the corporate office in Phoenix, Arizona, for

conformance

to APS Nuclear Projects

Procedure

No. NS-5,

"Indoctrination and Training."

The inspector

found that

APS Audit

No. S-84-002 had determined that

a considerable

disparity existed

among the training records of the three engineering discipline

groups.

As a corrective action,'

responsible

group was created to

establish

parameters

for consistency in procedures,

syllabi,

and

required training documents.

At present,

the licensee

has revised

their training procedure to comply with this commitment.

Nevertheless,

the inspector reviewed the training records of the

engineers

to assure

conformance to the previous revision of NS-5, to

establish that all engineers

received training in a timely manner

after being assigned

to the project and that all training

requirements

had been complied with as specified by the previous

revisions of the procedure.

The inspector

found that the records

examined

complied with the previous revision of the training

procedure.

No,violations or deviations

were identified.

I

r

~

21.

Audits

S-83-029

August 4,

1983

Design Control

Design Control

S-84-002

April 26,

1984

i

F1

The audits

were reviewed to assure'hat

the audits were comprehensive,

that items were closed out in a timely manner; that sufficient

documentation

was,reviewed

to. assure that an item had been properly

addressed

and resolved before closure, that items were followed up as

necessary,

and that audit checklists

were retained

as part of the

permanent

record.

I

The inspector

reviewed

two licensee audits of Bechtel design activities

conducted in 1983 and

1984.

The following two audits

were reviewed.

Audit No.

Audit Date

T~01 c

The audits

reviewed were found to be comprehensive

and of sufficient

depth to identify and correct problems

found in the area audited.

However,

one

NRC concern

was identified and this item is further

described in paragraph

22, below.

22.

Radwaste

S stem

During the review of APS Audit No. S-84-002,

dated April 26,

1984, the

inspector noted that

a Corrective Action Report

(CAR) No. CA-84-0138,

had

been written indicating that the Bechtel Design Criteria was out of date

relative to the requirements

of Regulatory Guide 1.143.

The licensee

stated in Amendment No.

4 to the FSAR, dated

May 1981, that they complied

with Regulatory

Guide 1.143,

"Design Guidance for Radioactive

Waste

Management

Systems,

Structures,

and Components Installed in Light Water

Cooled Nuclear Power Plants," Revision 0, dated July 1978.

The

CAR is

still open and is currently being processed

by the licensee's

system for

resolving these

issues.

However,

due to the late stage of construction

and the proximity of the licensee's

targeted fuel load date,

the

NRC is

concerned

whether the Radwaste

and Steam Generator

Blowdown Systems

are

constructed

and designed in accordance

with the Regulatory Guide's

requirements,

including the equality Assurance

requirements

stated

therein.

Discussion with the licensee

indicated that the systems

are constructed

and designed in accordance

with the project's

Class

"R" requirements.

The licensee further states

that Class

R components

are under

a equality

Assurance

Program consistent with the requirements

of Regulatory

Guide 1.143.

This issue

was referred to NRR for evaluation

and resolution.

23.

Interview with Workers

In order to assess

the receptiveness

of supervision to worker's safety

concerns,

50 interviews of both APS and Bechtel craftsman

and first line

supervision

were conducted.

Additionally, 43 of those interviewed were

I

ha

4

,;4 <,~

5

i.i

"I

specifically asked if they felt intimidated or harassed.

The

interviewees indicated that they have not felt intimidated, harassed

or

restricted in the performance of their jobs.

Two individuals, however,

acknowledged that there

was

a high degree of schedular

pressure

and

mandatory overtime requirements. 'ven so,

these persons

could not point

out instances

where these pressures

had caused

improper quality

situations.

These issues

were already

known to the

NRC and will be

followed up during subsequent

inspection activities.

All but three

workers interviewed said they felt their supervision is receptive to

their work related

concerns.

An area of potential concern,

which was noted during the interviews

and

subsequently

discussed

with licensee

management,

involved a need for APS

to review and reassess

the use of required overtime and the impact of

scheduler

pressures

to assure

they do not impact on safety.

APS

management

acknowledged

the

comment.

A second

area of potential concern

dealt with the thoroughness

of training (general administrative

and

maintenance

related).

This area will be evaluated

during

a subsequent

inspection

(84-38-05).

Workers Interviewed

D~isci line

No. Interviewed

Arizona Public Service

gA/QC Inspectors

and Engineers

ISC Technicians

Electricians

Mechanics

Resid'ent Design Engineers

11

6

4

4

7

Bechtel

QC Welding Inspectors

Electricians

Pipe Fitters/Welders

Resident Design Engineers

3

2

l5

8

24.

On August 31 and September

15,

1984,

an exit meeting

was conducted with

the licensee

representatives

identified in paragraph

1.

The inspectors

summarized

the scope of the inspection

and findings as described in this

report.

The licensee

acknowledged

the violation identified in the area

of project engineer training record completion.

Jeaay

f