ML17285B128

From kanterella
Jump to navigation Jump to search
Insp Rept 50-397/90-01 on 900129-0202 & 12-16.Violation Noted.Major Areas Inspected:Occupational Exposure,Shipping & Transporation,Radwaste Sys & Radiological Environ Monitoring
ML17285B128
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 03/12/1990
From: Cicotte G, Coblentz L, Wenslawski F
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To:
Shared Package
ML17285B125 List:
References
50-397-90-01, 50-397-90-1, NUDOCS 9003290218
Download: ML17285B128 (22)


See also: IR 05000397/1990001

Text

U.S.

NUCLEAR REGULATORY COMMISSION

REGION V

Report No.

Docket No.

License

No.

Licensee:

50-397/90-01

50-397

NPF-21

Washington Public Power Supply System

P.

0.

Box 968

Richland,

Washington

99352

Facility Name:

Washington Nuclear Project

No.

2

Inspection at:

WNP-2 Site,

Benton County, Washington

Inspection

Conducted:

January

29-February

2 and February 12-16,

1990

Inspected

by:

Inspected

by:

lc

te,

a latlon

ecla lst

0

tz,

la

1

n

pecla ls

P~ l-Ro

ate

lgne

3-~~ -P~

a

e

lgne

Approved by:

ens

aws l,

le

Facilities Radiological Protection Section

a

e

lgne

~Summer:

Ins ection durin

the

eriod of Januar

29-Februar

2 and Februar

12-16

e ort

o.

Areas Ins ected:

Routine

unannounced

inspection

by two regionally based

lnspec ors

o

occupational

exposure,

shipping,

and transportation;

r'adioactive

waste

systems,

radiological environmental

monitoring;

and followup.

Inspection procedures

30703,

83750,

84750,

and 93702 were addressed.

Results:

No cited violations were identified in two of the three

areas

aaaressed.

In one area,

a non-cited violation was identified regarding

representative

environmental

sampling (Section 3.D).

In another area,

a

weakness

was identified in the area of radiological controls exercised

over

radioactive filter replacement,

resulting in a violation for inadequate

radiation surveys

(Section 4).

Overall, the licensee's

programs

appeared

capable of meeting their safety objectives.

$003290

m18

O00=-:12

PDR

ADCtCI', 05000397

C~

PFii

.

'

DETAILS

1.

Persons

Contacted

+G.

y*C

  • J
  • J
  • J

+J.

+C.

++R.

  • D

AD

+R.

q*D

++R.

AD

+K.

AR

S.

NRC

yAC

C.

C.

Sorensen,

Manager,

Regulatory

Programs

M.'owers, Plant Manager

A. Baker, Assistant Plant Manager

R. Allen, Health Physics

(HP) Craft Supervisor

D. Arbuckle, Compliance

Engineer

C. Bell, Manager,

Health

and Sciences

L. Bradford,

HP Supervisor

J.

Card, Senior Health Physicist (Radiological

Environmental

Monitoring Program

(REMP) Health Physicist)

G. Graybeal,

HP/Chemistry

(HP/C) Manager

A. Kerlee, Principal Quality Assurance

(QA) Engineer

R.

Kobus, Plant

QA Manager

L. Koenigs, Technical

Manager

E.

Larson,

Radiological

Programs

and Instrument Calibrations

(RPIC)

Manager

F. Patch,

ALARA Coordinator

J. Pisarcik,

HP Support Supervisor

A. Pritchard,

HP Craft Supervisor

A. Smith,

Radwaste

Program

Leader

L. Wardlow, Radiological

Services

Supervisor

L. Washington,

Plant Compliance Supervisor

J.

Bosted,

Senior Resident

Inspector

A. Sorensen,

Resident

Inspector

"Denotes

those present at the exit interview held

on February 2,

1990.

+Denotes

those present at the exit interview held on February

16,

1990.

In addition .to the individuals identified above,

the inspector

met and

held discussions

with other

members of the licensee's

staff.

2.

Occu

A.

ational

Ex osure

Shi

in

and Trans ortation (83750

Audits and

A

raisals

Several

Non-Conformance

Reports

(NCRs), Plant Deficiency Reports

(PDRs),

Problem Evaluation

Requests

(PERs),

and Technical

Evaluation

Requests

(TERs), for 1989 and 1990,

were reviewed.

The

NCR/PDR

system

had been replaced

by the

PER/TER form of problem

identification and resolution.

The licensee

had significantly

reduced

the number of outstanding deficiencies

from the older

system.

However,

some of the resolutions

approved for both the old

and

new systems

did not appear to address

the original concern

as

stated

in the tracking document.

See Section 3.D, below.

The licensee

s audit of,health physics activities,

by the Licensing

and Assurance

Group, will be examined in a subsequent

inspection,

as

it had not been completed at the time of the inspection.

~Chan

ea

No major changes

in equipment or procedures

had taken place since

the last inspection of this program area.

Some minor in-plant

organizational

changes

were briefly reviewed.

I

External

Ex osure Control

Representative

radiation

and contamination

survey records for

November

1989 through February

1990 were reviewed.

Radiation survey

techniques

were discussed

with several

health physics technicians

(HPTs).

With the exception of those

noted in Section

4 below,

no

concerns

were identified.

II

Use of personnel

dosimetry

was observed.

Representative

radiation

exposure

cards

(RECs), in use for individual radiation

dose

tracking,

were examined.

Thermoluminescent

dosimeter

(TLD) issuance

and

use

were reviewed.

No concerns

were identified.

Internal

Ex osure

Control

Representative

air sampling data log sheets

for 1990 were reviewed.

All of the

11 HPTs with whom air sampling techniques

were discussed

were in general

agreement

as to what constituted

an adequate

sample

of the breathing

zone for workers in areas

containing potentially

high airborne radioactivity.

However, three of the

HPTs with whom

air sampling

was discussed

stated that they believed that air

samples

conducted

during the breach of highly contaminated

system

boundaries

would be representative

of the airborne radioactivity

'concentrations

resulting from subsequent

disassembly

or

decontamination

of internal

components within those

system

boundaries.

The inspector

reminded the

HPTs that the differing

conditions described

above could, result in significantly different

concentrations

of airborne contaminants.

Representative

records of bioassay for 1990 were briefly reviewed.

No concerns

regarding

minimum detectable activity or the capability

to detect significant uptake of airborne radioactivity were

identified.

Control of Radioactive Materials

and Contamination

Surve

s

and

~oni or>n

Tours of the Radwaste

Building (RMB), Reactor Building (RB), and

Turbine Building (TB) were conducted.

Independent

radiation surveys

were performed with NRC ion chamber

survey instrument

model ¹R0-2,

serial

¹022906,

due for calibration

on April 16,

1990.

Radiological postings,

contamination control stepoff pads,

and other

access

controls that were observed

appeared

to have

improved over

-F.

previous inspections

and were consistent with the licensee's

procedures

and

TS requirements.

Housekeeping

appeared

adequate.

Only one area,

on the 522'levation of the

RB, was observed to have

significant accumulation of used contamination control materials

left on the floor.

However,

some contaminated

areas

appeared

to

have increased

in size..

The condition of the traversing in-core

probe (TIP) drive machine

area

appeared

to be much improved,

although the size of the contaminated

area

was unchanged.

For a

discussion of radiation surveys,

see Section 4, below.

For the

areas

toured,

no concerns

were identified.

Shi

in

of Low-Level Wastes for Dis osal

and Trans ortation

Radioactive solid waste

shipments for 1990 were reviewed.

The

records

indicated that all the shipments

had been

conducted in

accordance

with licensee

procedures

and quality assurance

requirements.

The licensee

stated that

no transportation

incidents

had occurred during 'the

18 mile trip to the commercial

disposal

facility.

No recent violations of transportation

or waste disposal

regulations

ha'd been identified by the State of Mashington.

The licensee's

program appeared fully capable of meeting its safety

objectives.

No violations or deviations

were identified.

3.

Radioactive

Maste

S stems

Radiolo ical Environmental Monitorin

(84750

A.

Audits and

A

raisals

B.

Corporate

Licensing and Assurance

Audit 89-490, "Radiological/

Nonradiological

Environmental

and Effluent Monitoring," was

reviewed.

The audit appeared

to be thorough

and of sufficient depth

to adequately

assess

the program.

Audit 89-500,

"Radwaste

Process

Control Program,"

was also reviewed.

The audit results

showed

marked

improvement over the previous audit of this program area.

The audit stated that the most significant findings were the high

volume of solid waste generated,

adherence

to health physics work

rules,

and

some program changes

which had not been

reviewed in

accordance

with procedure.

Most of the program change

reviews

had

been

completed

and procedural

changes

had been incorporated at the

time of the inspection.

Responses

to findi'ngs from the above audits

were timely.

No

significant concerns

were identified.

~Chan

es

No major changes

in procedures

had taken, place since the last

inspection of this program area.

However,

some organizational

changes

in radiological

support organizations

had occurred.

The

RPIC manager

was

no longer responsible

for environmental

monitoring.

Those duties

had

been

assumed

by the Manager,

Health and Sciences,

who reports directly to the Manager,

Support Services.

The main condenser

off-gas treatment

system

equipment

had been

upgraded

such that it could be operated

in sub-cooled

mode.

This

provides

more cleanup of gaseous

effluents,

by increasing

the

ability of the charcoal

adsorber

beds to adsorb radioactive

noble

gases

and iodines.

C.

Im lementation of Radioactive

Waste

Pro

rams

2)

3)

Solids

The licensee's

program for determining the quantity and

composition of solid wastes

was reviewed.

The licensee

conducts

dewatering operations

through

use of a contractor.

However, the licensee

recently incorporated contractor

procedures

into plant procedures,

for review and control.

This

was

done to address

audit findings with respect to the level of

review provided for contractor procedures.

Dewatering

activities were observed.

No concerns

were identified.

Li uid and Gaseous

Effluents

The most recent

Semiannual

Radiological Effluent Release

Report, for the period of January-June,

1989,

was reviewed in

Inspection

Report 50-397/89-29.

Approximately 30

representative

radioactive liquid and gaseous

release

reports

for 1989

and 1990 were reviewed.

All the reports indicated

that effluents were

ALARA in acc'ordance

with 10 CFR 50

Appendix I and

TS limits, and were

much less

than

10 CFR 20

Appendix

B limits.

The licensee's

Offsite Dose Calculation Manual

(ODCM),

delineates

how doses

are calculated,

and describes

the various

methods

for obtaining environmental

and effluent information.

See Section

D, below, for further discussion.

No unmonitored release

paths

were identified as

a result of

this inspection.

The magnitude of gaseous

effluents

had been

reduced

as

a result of the change to the treatment

system

noted

in Section

B, above.

Instrumentation

Representative

recent radioactive effluent monitor channel

checks,

channel

functional checks,

routine tests,

and

some

corrective maintenance,

were reviewed for the main steam line

radiation monitors, radioactive liquid effluent monitors,

and

the air ejector off-gas post-treatment

radiation monitors.

Effluent sample

data indicated adequate

agreement with effluent

monitor readings.

Instrument readouts

had improved in

readability.

Operabi 1ity of monitors

was adequate,

with few

periods of unavailability for the effluent radioactivity

monitors.

No significant maintenance

problems

were identified.

4)

Air Cleanin

S stems

4

The inspectors

reviewed the two most recent test records for

charcoal

adsorber

and

HEPA filtration units, including the

standby

gas treatment

system.

Also, tests of both the radwaste

building and reactor building exhaust ventilation systems

were

reviewed.

No concerns

were identified.

On February 12,

1990,

the inspector

observed that the control

room intake ventilation

units exhibited several

small leaks or degraded

access

doors.

Mhen this was brought to the attention of the licensee,

an

operator

was dispatched

to examine the units and several

deficiency tracking numbers

were assigned

to identify the

problems.

Lab test results for charcoal

adsorber

media were briefly

reviewed.

The licensee

had identified a situation in which the

test requested

had been inadvertently assigned

commercial

~rade

versus quality grade test criteria.

However, the licensee

s

followup indicated that the

same criteria had been

used for

both quality and commercial

grade,

and that only the reporting

and warranty of results varied with the commercial/quality

grade

assessment.

D.

Radiolo ical Environmental Honitorin

Pro

ram

The inspector

observed

the performance of Environmental

Program

Instruction (EPI) 12.4.8,

"Drinking and River Mater

Sample

Collection," by the Radiological

Environmental Monitoring Program

(REMP) technician.

Samples

were taken at the following locations:

Station 26, surface water upstream (circulating water system

intake);

27, surface water downstream (circulating water system

blowdown (CMBD)); 28, drinking water near site (Hanford site "300"

area);

and 29, drinking water location (Richland Mater Treatment

Plant).

Although the composited

samples

which were observed

were collected

in accordance

with the EPI,

a review of licensee

records

and

discussion with RENP personnel

revealed that there

had been

disagreement

within the:licensee's

organization

as to whether

the

RENP was being conducted

in accordance

with the TS.

TS 3. 12, "Radiological Environmental Monitoring," states

in part

that the radiological environmental

monitoring program shall

be

conducted

in accordance

with TS Table 3. 12-1.

TS Table 3. 12-1

states

in part that the surface water samples

shall

be collected

as

composites,

such that the quantity (aliquot) of liquid 'sampled is

proportional to the quantity of flowing liquid and in which the

method of sampling

employed results in a specimen that is

representative

of the liquid flow.

Sample aliquots are to be

collected at time intervals that are very short (e.g.,

hourly)

relative to the compositing period (e.g., monthly).

According to

footnote (a) of the table, deviations

are permitted from the

required sampling schedule if specimens

are unobtainable

due to

malfunction of automatic

sampling equipment.

However, if specimens

are unobtainable

due to sampling equipment malfunction, effort shall

be

made to complete corrective action prior to the end of the next

sampling period.

The inspectors

noted that Stations

26, 28,

and 29 sample

from lines

in which'he flowrate is relatively constant,

and for which a

timed-interval compositor is used.

Flow in the

CWBD, however,

regularly changes

by a factor of about

800 (typically 50 to 4000

gpm); Station

27 uses

a compositor which varies the time interval in

proportion to the

CWBD flowrate.

Sampling records

indicated that

the

CWBD compositor

had been subject to chronic failures,

due to

repeated

pump failures, flow indicator malfunctions,

and other

similar causes.

For example,

the compositor could not collect

representative

samples

during more than

one third of 1989:

Dates

Compositor Not Sampling

Total

Days

Month

b

Flow-Pro ortional Method

Out of Service

January

May

June

July

August

.

September

October

November

13th to 30th

10th to 30th

1st to 4th; 6th to 21st

12th to 31st

1st; 16th to 31st

entire month

1st to 5th; 28th to 31st

1st to 7th

17

20

19

19

16

30

8

7

Difficulty in obtaining

a representative

surface water downstream

sample

had

been

documented

in two PERs,

three

TERs,

NCR 288-0365,

and the licensee's

internal monthly

REMP Status

Reports for May to

September

1989.

During each of the above periods,

REMP personnel

obtained

grab samples

at the compositor

sample point.

The issue of

whether

manual

grab sampling provided

an acceptable

alternative

during times

when the compositor

was out of service

had been

a topic

of frequent disagreement

within the licensee's

organization.

NCR

288-0365,

originated

by the

REMP Health Physicist in August 1988,

included

one of several

clear statements

by

REMP personnel

that grab

sampling did not comply with TS 3. 12. 1.

The "immediate disposition"

block for this

NCR was not approved until March 1989.

Technical

review and final disposition approval

were not completed until

February

1990.

The plant compliance supervisor

(PCS)

acknowledged that the

TS

requires

the sampling technique to be flow-proportional.

An

Inter-Office Memorandum

(IOM) from the

PCS to the plant manager,

dated

December

13,

1989, stated that grab sampling did not meet this

requirement.

The

PCS stated to the inspectors that,,at the request

of plant management,

his department

had agreed to revise the

IOM to

state that grab sampling satisfies

the TS; however,

he also stated

'hat

the revised

IOM, when issued,

would clearly state that

TS Table

3. 12-1 could only be satisfied if the grab sampling is frequent

'

relative to the compositing period,

as required

by footnote (f) of

TS Table 3. 12-1.

In addition, the

PCS stated that the grab samples

obtained

had never

been performed for compositing,

nor had they been

obtained for the purpose of meeting the flow proportionality

requirement.

At the exit interview, the

HP/C manager

and the plant manager stated

that manual

grab sampling is an acceptable

alternative

method for

obtaininq

a representative

sample

when the compositor is

malfunctioning.

The plant manager

acknowledged that the

CWBD

compositor problems

needed to be addressed,

and committed to a

"speedy resolution" of chronic compositor failures, including

consideration of the feasibility of obtaining

a compositor of more

reliable design.

The inspectors

noted that deviations

from the required sampling

schedule

are permitted by Footnote (a) of TS Table 3. 12-1 only if

the samples

are unobtainable.

The failure to obtain composited

samples

from aliquots proportional to the flow rate of the

CWBD line

appears

to be

a violation of Technical Specification

4. 12. 1 and

Table 3. 12-1.

However, the violation is not cited because

the

criteria of Subpart V.A'of the Enforcement Policy were met

((NCV)50-397/90-01-01)

.

The

AEOR for 1988 was reviewed.

Except for a certain lack of

discussion

of licensee

plans for preventing recurrence

of the

compositor failures,

no concerns

were identified.

See Section

5

below.

E.

Meteorolo ical Monitorin

Pro

ram

Meteorological monitoring equipment maintenance

records

were briefly

reviewed.

Operation of the equipment

was observed.

No concerns

were identified.

The licensee's

program appeared fully capable of meeting its safety

objectives.

No cited violations or deviations

were identified.

4.

Onsite Followu

of Events at 0 eratin

Power'eactors

(93702)

Introduction

On January

10,

1990, while replacing radioactive resin filter

elements for the equipment drain--radioactive

(EDR) system,

the

licensee

discovered

an in-plant spread of contamination,

which

resulted in contaminated

footwear and the

need to decontaminate

a

large portion of the floor on the 507'levation of the Radwaste

Building (RWB).

The licensee

determined that-the contamination

spread

was the result of poor contamination control during the

filter element

(septum)

replacement

work.

After the

NRC resident

inspector

asked the licensee

what the airborne radioactivity

exposure

was,

the licensee

conducted further evaluation.

On January

12,

1990,

the licensee

conducted

whole body counts

on the workers to

confirm whether there

had

been

exposure

to high airborne

I

radioactivity.

A chronology of events,

based

on review of records

and interviews with personnel,

follows:

January

9,

1990

(times are approximate)

0900 All work was conducted

on Radiation Work Permit

(RWP) 2-90-00043.

Shielding plugs

on the 507'WB were removed, after which the

EDR

filter/demineralizer (F/D) vessel

head

was

removed

and the support

plate with 50 long narrow cylindrical filter septums

suspended

from

it was lifted up to the 507'WB.

The

HPT took one contact

gamma

reading,

recorded

on the survey

map as "20 mr" [20 mi lliroentgens

per hour (mr/h)] with a geiger-mueller

(GM) survey instrument [later

found to be 225 mr/h], and recorded

a large area

smear with

removable contamination of 500,000 disintegrations

per minute (dpm).

The inspector later noted that this was the upper limit of the

highest meter range for the counting instrument

used

by the

HPT.

1300 After observing the septum/support

plate lift, a safety department

representative

informed the workers that work could not proceed

until improvements

in scaffolding/handrails

were made.

The

HPT who

was monitoring the job had the mechanical

maintenance

(MM) workers

place the filter assembly

back in the vessel.

Work on the filters

was delayed until the requisite handrail

work was complete.

January

10,

1990

0800

The filter assembly

was again

removed

from the vessel

and brought to

the 507'levation,

where half of the 50 individual elements

were

removed

by hand from the support plate.

The elements

were placed in

a wooden

box located just inside the posted

contaminated

area.

After decontamination

and monitoring, the box was transported

to the

decontamination facility.

The

HPT obtained

gamma radiation exposure

rate measurements

of 225 mr/h on contact,

and

25 mr/h at

3 ft

relative to the box.

Further disassembly

awaited the construction

of another,

larger box.

1230

The other

25 septums

were

removed

and placed in a box located just

outside the posted

contaminated

area.

The

HPT obtained

gamma

measurements

with an ion chamber

survey instrument of 50 mr/h on

contact

and

15 mr/h at 3 ft.

According to the survey by the

HPT,

large area

smears

on the septums

in the box measured

60 to

200 mrad/h.

1400 The two

MM personnel,

who had been providing support outside the

posted

contaminated

area,

caused portal contamination monitors to

alarm.

Surveys of the individuals revealed

low level (less than the

limit of 100 counts

per minute) contamination

on their shoes.

No

individuals were found to have skin contamination.

1500 The

HPT who had. controlled the job conducted

a paper

smear

survey

and found

a maximum contamination

level outside the posted

contaminated

area of 5000 dpm/100

sq

cm, in the vicinity of the

boundary.

The

HPT posted

a larger area,

reported the results of the

survey to the lead

HPT,

and ended the shift.

Two other

HPTs were

sent

by the lead

HPT to perform followup surveys,

and found small

particles of contamination of up to 30,000

dpm/100

sq

cm in several

locations

on the floor leading from the posted

area to the elevator,

an area of about

2800 sq ft.

The area

from the elevator to the F/D

removal area,

and the area itself, were barricaded

and posted

as

contaminated until decontamination

was conducted later in the shift.

Decontamination

and reinstallation of cleaned filter elements

was

conducted later using respiratory protection

and contamination

control techniques

consistent with licensee

procedure

and the

potential

hazards.

The

HPTs who performed that decontamination

effort informed the inspector that pre-decon

readings

had

shown

up

to 400 mrad/h per large area

smear

on the floor next to the-

assemblies.

Li'censee

Evaluation

The inspector

asked 'the licensee if their evaluation of the matter

was complete.

The

HP supervisor stated that

a Report of

Radiological

Occurrence

(RRO) had been completed,

that several

performance

issues for the

HPT had

been identified,

and that

some

planning issues

had also contributed to the incident.

The

licensee's

RRO, dated January

12,

1990,

and

a "Category 3" root

cause

evaluation,

made the following observations:

1)

The

HPT did not follow good

HP job coverage practices.

2)

Contamination control work practices

were not followed.

3)

Pre-job planning did not happen.

The job was

'made up's it

went along (licensee

emphasis).

4)

HP supervision

was told by the

HPT that the job was not well

coordinated,

but did not feel it was out of control.

5)

Specific job planning problems which resulted in the area

becoming highly contaminated

were listed as:

the manner of

handling and packaging

septums,

delays

due to waiting for

replacement

septums,

and allowing the old septums

to dry out.

6)

The

HPT did not keep

up with increasing

contamination levels,

due to lack of surveys

inside and outside the area,

resulting

in loss of contamination control.

The

RRO stated that the corrective actions

taken to prevent

a

similar occurrence

were to provide better Health Physics pre-job

planning

and to counsel

the

HPT.

The inspector discussed

the evaluation with the

HP supervisor,

who

had concurred in the

RRO corrective action.

The

HP supervisor

stated that the issues

regarding job planning included the delay due

to safety, that the wait for replacement

septums

had not been

necessary,

but had occurred

due to miscommunication,

and that as

a

result of the incident each involved department

had participated in

10

a post-job review, with specific action

needed

by departmental

management.

The

HP supervisor

and the

HP/C manager

both stated that

the method of counseling the

HPT was still under review, but that

the incident had clearly occurred

due to failure of the

HPT to

conduct necessary

contamination

surveys.

C.

NRC Review of Licensee

Evaluation

The following licensee

records

and documents

were related to the

licensee's

evaluation:

RRO 2-90-001;

RWPs 2-90-0043

(EDR system

filter element replacement),

2-89-00432 (reactor water cleanup

system

(RWCU) filter element replacement),

and 2-89-00419 (floor

drain--radioactive

(FDR) system filter element replacement);

Health

Physics

Log, January 4-30,

1990.

Other

RWPs and associated

ALARA

program review records

(APRR), were briefly reviewed,

as

appropriate.

The inspector

made the following observations

with respect

to issues

addressed

by the licensee's

evaluation:

1)

The lack of survey referred to by the licensee

was, according

to the licensee,

the exercise of bad judgment by the

HPT

regarding

when and

how extensively to take surveys,

particularly for contamination control purposes.

Licensee

procedure

(PPM) 11.2. 13. 1 requires

the surveyor to exercise

good judgment--strict verbatim compliance is not required.

The licensee

stated that they rely on the good judgment of

their

HP personnel,

due to the difficulty of foreseeing

every

contingency regarding inaccessibility of areas

to be surveyed,

applicability of a particularly survey technique,

and other

similar aspects.

The inspector

reminded the licensee that

reliance. on the good judgment of personnel

is fully effective

only when personnel

perform above the level required

by their

procedures.

The licensee

stated that the performance of the

individual

HPT was considered

to be anomalous

and thus

an

individual performance

issue.

2)

Although not iterated in the

RRO or root cause analysis,

the

HP

supervisor

informed the inspector that

a post-job review had

been

conducted specifically to address

job planning issues,

and

that actions

by

MM department

personnel

had been specified,

so

as to prevent recurrence.

The inspector discussed

the matter

with MM supervisory

personnel

who had been at the post-job

review.

The inspector

asked

them what method of tracking was

being

used to assure

that the problems did not recur.

They

stated that their method of ensuring that similar jobs would

have better engineering controls

and

be better planned

was that

everyone there

knew about it and wouldn't forget.

P.

I~lk 11

Licensee

procedure

(PPM) 1. 11. 8, "Radiati on Work Permi t, "

Revision 2, dated

March 20, 1989, states,

in part:

Pre-job briefings are required for all activities involving

work within High Radiation Areas.

The Job Supervisor...initiates

an

RMP as follows... Enter job

description...Be specific... to give a clear understanding

of

work to be performed...Obtain

an

ALARA Scope

Sheet

and complete

all but the shaded portion...Submit the

RMP and

ALARA Scope

Sheet to Health Physics...for

processing.

LHP/C] Representative

shall:...For jobs with work area

exposure

rates greater

than or equal to 100 mR/hr, but less than

300

mR/hr,...Greater

than 0.3 man-rem,

but less

than 5.0 man-rem

total... the

ALARA Coordinator ...will complete the evaluation,

and document the

ALARA requirements

on an

ALARA Program

Review

Record.

[HP/C] Representative

shall:...Determine

radiological

conditions

and enter onto the

RWP.

Be specific to provide

adequate

information.... (i.e, radiation levels, contamination

levels,

hot spot locations

and airborne activity, etc).

Provide

comments to warn or guide workers of radiological

conditions.....Enter

any special

instructions or precautions

as

appropriate,

including ALARA recommendations.

Be specific,

provide all Health Physics

information required to control

and

guide the workers...

The [HP] Supervisor or Designated Alternate shall:...Review the

RWP and resolve

any questions with the appropriate

personnel...Sign

and date the

RWP indicating acceptance

of the

RWP requirements.

The inspector

noted the following regarding the

ALARA Scope

Sheet,

the

ALARA Program

Review Record,

and the

RWP:

j.)

The

ALARA Scope

Sheet contains

an unshaded

block titled:

"Are there

any other aspects

of the work that are

important for ALARA planning?

Describe..."

The block had

been filled in with the word "none."

2)

The

ALARA Program

Review Record contains

a checklist of

items to be considered.

The inspector concluded that

several

of those

items, if given more consideration

than

was apparent

from discussion with personnel

involved in

12

the work, could have prevented

the problems

encountered

or

otherwise mitigated the situation:

Item

Checklist

1.8

"Lessons-Learned"

reviewed

2.7

Radiological Controls:

Radiological Conditions

Known and

RMP Issued

Ventilation

Flushing/Filling

Decontamination

2.8

Protective

Equipment:

. Respiratory Protection

Face/Eye

Protection

yes

es

not applicable]

[not applicable]

[not applicable]

yes [as required

by HP]

[not applicable]

3)

The three records

noted above did not contain discussion

'of decontamination efforts to be conducted

on the filter

housing,

support plate,

and other internals.

The pre-job

briefing documentation,

required

by the "yes" check

on the

review record,

did not contain

any reference

to

decontamination

in the list of topics discussed.

4)

RMP 2-90-00043,

under

"Special Instructions," stated in

part:

Respirators

required in areas

[greater than or equal

to] 25K HPC or for job evolutions which could create

airborne radioactivity as determined

by H. P.

5)

The

HPT who had covered the job had also approved

the

RWP

as

HP supervisory

designee.

The

HP supervisor

stated that

most of the senior

HPTs are

on the list of authorized

individuals to sign

RWPs.

He further stated that

HPTs

will routinely come to him for guidance

on specific

matters pertaining to

RWPs under pre-job review, but that

they will still approve the

RWPs themselves

when those

- questions

are resolved.

The

HP supervisor did not recall

having been consulted

regarding

RWP 2-90-00043.

-The lead

HPT who had been in charge during the work, and whose

responsibilities

included oversight of HPTs assigned

to tasks,

stated that

he had not visited the job site prior to the

contamination

instances.

The lead

HPT further stated that this was

because

the

HPT had relayed the problems

encountered,

but had stated

that he did not believe

he

had lost control of the work.

E.

Health

Ph sics Procedures

The inspector interviewed the personnel

who had conducted

the work,

including supervisory

and planning personnel.

The inspector

noted

that several

licensee

procedures

governing the work had

recommendations

or guidelines

which were not followed.

However,

the

13

procedures

did not require compliance,

as they stipulated that

individual steps

were to be followed when appropriate

in the

judgment of, or at the discretion of, the procedure

user.

The

procedures

contained wording such

as "guideline," "typically,"

'should," "appropriate," "normally," and "usually," as noted below.

PPM 1. 11. 11, "Entry Into, Conduct In, and Exit From Radiologically

Controlled Areas," Revision 0, dated

May 15, 1989, states

in part

that individuals exiting the radio1ogically controlled area should,

if applicable,

complete self frisking or proceed

through the whole

body frisking booths.

One of the two individuals whose

shoes

caused

the frisking booths to alarm stated

he had not performed

a

subsequent

whole body frisk.

The inspector

noted that this was

contrary to an

HP night order regarding

response

to frisking booth

alarms.

PPM 11.2.4. 1,

"MPC-Hour Assessment

and Documentation,"

Revision 4,

dated April 26,

1989, states

in part that the required

RWP for areas

entered shall provide adequate

documentation for entries into and

exits from such areas for the purpose of determining

exposure

times.

- Discussion with the workers

on

RWP 2-90-00043

revealed that only two

of the workers were regularly in an area with a significant

potential for high airborne radioactivity,

and that they were in the

area

much less time than

was indicated

on the

RWP entry record or

their radiation exposure

record cards.

PPM 11.2. 12.2, "Selection of Protective Clothing,"'evision 5, dated

September

7, 1988, states

in part that the radiological work

conditions should

be

known prior to selection of protective

clothing.

Respiratory protection equipment is included in the

listing of protective clothing.

Table

1 to the procedure

indicates

that for smearable

contamination levels of 10-30 mrad/h per 100 sq

cm,

a negative pressure air purifying respirator

should

be selected.

PPM 11.2. 13. 1, "Area Radiation

and Contamination Surveys,"

Revision

4, dated

November 14,

1988, states

in part that the surveyor

should

ensure that the survey accurately

and clearly portrays the

radiological conditions present.

The

HPT who performed the pre-job

survey

and wrote the

RWP indicated

on the

RWP that airborne

radioactivity concentrations

were:

"assumed to be [less than]

7.5 x 10E-10 [microcuries per milliliter (uc/ml)] based

on low

contamination levels; airborne radioactivity will be determined

during various job evolutions."

The contamination

survey did not

include the internals of the F/D, as the system

had not been

breached

at that time.

PPM 11.2.9.8,

"Eberline Teletector

Model 6112," Revision 3, dated

April 10,

1989, states

in part in the limitations section that the

instrument is not normally used to set work area

dose rates,

that

applications

are for hard to reach areas,

and that it is to be

used

as

an

"ALARA tool" to check dose rates

once they have

been

established

with an ionization chamber

instrument.

The survey

instrument

Model 6112 is

a

GM survey meter.

PPM 11.2.13.1 further states

in part:

"Do not use

a

GH survey

instrument without an energy

compensated

probe to set

dose rates

except where high dose rates

or location make it necessary

to use

a

teletector."

The procedure

also states

that direct beta

and

gamma

exposure

rate measurements,

and

maximum and typical dose rates that

would be received

by specified work crew activities,

should

be

included.

The procedure further states:

"usually smears will be

taken of the areas

where contamination is most likely to be found or

spread."

The inspector

noted that the surveys which were conducted

on January

9 and 10, 1990, during the filter element work, did not

include beta readings,

that only a teletector

was

used until the

filter element

removal

was more than half done, that

no smearable

contamination levels in the work area

were indicated

on the surveys,

and that the survey performed

on January

9, 1990,

appeared

to have

been in error by a factor of approximately

10 lower than the actual

gamma radiation

dose rate

on contact with the assembly.

11.2. 13.8, "Airborne Radioactivity Surveys,"

Revision 1, dated

May 23, 1989, states

in part: "Ideally, air samples

taken primarily

for personnel

protection should

be representative

of the air

actually breathed

(breathing

zone samples).

If breathing

zone

samples

are not practical,

samples

that provide conservative

results...may

be used."

From discussion with the

HPT who conducted

the surveys

during the work, the inspector

determined that the

sampler location was

such that it would not have

been representative

of the breathing

zone during filter element disassembly,

and would

have provided non-conservative

results.

However,

subsequent

bioassay

determined that

no significant uptake occurred.

F.

Conclusions

Based

on a sequence

of events

as correlated

between

interviewed

personnel,

comparison with conduct of similar tasks,

and review of

practice

versus

recommendations

of licensee

procedures,

the

following concerns

are

summarized

below:

All the job-specific

RMPs in use at the time of the inspection

had

been

approved

by HPTs,

as

HP supervisory

designees.

The

NN engineer

who had initiated

RMP 2-90-00043 stated that

the

ALARA supervisor did not contact

him to discuss

the job

during planning.

The

HPT who had conducted

the pre-job surveys

also wrote the

RMP, including statements

that indicated

a low hazard potential

for contaminations

or airborne radioactivity.

The

HPT who

approved

the

RMP was not even the lead

HPT.

The lead

HPT did

not visit the job site, although significant problems

were

brought to his attention

by the

HPT who was providing job

coverage.

The

ALARA scope

sheet,

APRR,

and

RMP were vague or misleading

in content.

Although these

forms contain provisions for

consideration of radiological

hazards

other than whole body

penetrating radiation,

those provisions

were not used.

The licensee's

HP procedures

contained

many generalizations,

such

as deferring to 'good judgment.'he

procedures

essentially

did not require compliance.

One

HPT with whom survey techniques

were discussed

was not

aware of the special

hazards

associated

with beta radiation.

The licensee

had

done studies for beta penetration of the lens

of the eye, but the studies

did not include analysis of the

specific close disassembly

inherent in F/D filter replacement.

Two other

HPTs stated that although they would have required

respiratory protective devices for workers

on F/0 septum

replacement,

they would only require respirators

during breach

. of the F/0 housing,

and would use air sample results

from the

activity to determine

whether later work could be done without

'espirators.

.Nost of the other

HPTs stated that they would

have required several

contamination control techniques,

any of

which would have contributed significantly to the safety of the

task.

The failure to conduct surveys for beta radiation of the F/D filter

septum

assembly,

adequate

to -fully assess

the radiological

hazards

~rior to or during work, 'appears

to be

a violation of 10 CFR 20.201,

'Surveys."

(50-397/90-01-02)

The level of contamination

recorded

. on a subsequent

survey of the filter septums

was

200 mrad/h of beta

radiation per smear.

A reading of 400 mrad/h of beta radiation

had

been obtained

from the floor, subsequent

to the work.

No other

violations or deviations

were identified.

5 ~

Exit Interview

The inspector

met with those individuals denoted in Section

1, above, at

the conclusion of the inspection

on February

16,

1990.

The scope

and

findings of the inspection

were summarized.

The inspectors

reminded the

licensee

at the exit interview that the 1989 Annual Environmental

Operating

Report would be expected

to contain the licensee's

specific

plans to prevent recurrence

of failure to obtain

a representative

downstream

surface water sample.

The licensee

acknowledged

the

inspectors'bservations.

The licensee

was informed at the exit interview on February 2, 1990, that

several

licensee

procedures

appeared

to have not been followed with

respect to the contamination incident described

in Section 4, above.

The

licensee

acknowledged

the inspector's

observations,

although the licensee

did not agree with all the inspector's

conclusions

as described

at the

end of Section

4.