ML17278A333
| ML17278A333 | |
| Person / Time | |
|---|---|
| Site: | Columbia |
| Issue date: | 07/19/1985 |
| From: | Clark C, Compton R, Thomas Young NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V) |
| To: | |
| Shared Package | |
| ML17278A331 | List: |
| References | |
| 50-397-85-17, NUDOCS 8508090106 | |
| Download: ML17278A333 (12) | |
See also: IR 05000397/1985017
Text
U. S.
NUCIEAR RE'GULATORY COMMISSION
REGION V,,
Report No. 50-397/85-17
Docket No. 50-397
o.
21
License
N
NPF
r
Licensee:
Washington Public Power Supply System
P. 0.
Box 968
3000 George Washington. Way
Richland,
99352
Inspection at:
WNP-2 Site, Benton County, Washington
Inspection conducted:
May 6-10,
1985
C.
A
ark,
R actor Inspector
Inspector:
~
ompton,
C Co
ultant
Facility Name:
Washington Nuclear Project No.
2
(WNP-2)
H
7/1 ES
Date Signed
7-i7-8>
Date Signed
Approved by:
. Young, Chief
Engineering Sectio
Date Signed
~Summa r
Ins ection on Ma
6-10
1985
(Re ort No. 50-397/85-17)
technical review of the program plan, procedures
and records pertaining to the
WNP-2 inservice testing program for pumps
and valves.
The inspection involved
a total of 62 hours7.175926e-4 days <br />0.0172 hours <br />1.025132e-4 weeks <br />2.3591e-5 months <br /> onsite by one
NRC inspector
and one consultant.
Results:
In the areas
inspected,
one violation of NRC requirements
was
identified (failure to follow Code requirements
- paragraphs
3 and 4) and one
Unresolved Item was identified (adequacy of review of surveillance test
results
paragraph
4).
8508090106
850722
ADOCK 05000397
8
PDR'
r,
ii
v
1t
DETAILS
Persons
Contacted
'"C.
M. Powers,
Plant Manager
"D. S. Feldman, Plant
gA Manager
M. Bartlett,
QA Supervisor
D. R. Kidder, Plant Engineering Supervisor
A. Wood,
System Engineer
M. Reis,
Sr. Mechanical Engineer
jl
P
- "Denotes those attending
the exit meeting
on May 10,
1985.
J 1
tt
Xnservice Testin
(IST) 'Pro
ram Plan
f
/
Inservice testing is required to 'be performed in nuclear power plants in
accordance
with the
ASME Boiler and Pressure
Vessel
Code by 10 CFR 50.55a(g).
The
ASME Code,Section XI, Subsections
IWP and
IWV outlines
the rules for inservice testing of pumps, and valves.
Revision
2 to the
WNP-2 "Pump and Valve Inservice Test Program Plan,
issued
November 3,
1983," is the document currently "detailing the scope,
implementation
and
administration of the IST program.
Revision
3 i's being prepared
to
substantially revise
and update
the program
and to reflect the results of
a March 1985 meeting between the licensee
and the
NRC Office of Nuclear
Reactor Regulation
(NRR) staff.
Implementation of the IST program requirements
began in December
1983 and
the program
was required to be fully implemented at the
commencement.
of
"commercial operation" in December
1984.
The WNP-2 IST program is
committed to compliance with the
1980 Edition of the
ASME Code with
addenda
through Winter 1981.
This program applies to
18 pumps
and
approximately
475 valves.
The IST Program Plan, including draft changes
for Revision 3,
was
reviewed for compliance with the applicable edition of the
Code
and the
requests
for relief detailed in the plan.
The types
and frequencies
of
tests
appear
to be in compliance with Code requirements.
There were no violations of NRC requirements
identified.
IST Pro ram Procedures
The WNP-2 IST Program Plan is implemented
through various site
procedures.
The following procedures
were reviewed for compliance with
the
ASME code,
the IST Program Plan and
10 CFR 50 Appendix
B
requirements:
Nuclear Operations
Standard,
NOS-34, Rev. 2, "Inservice Testing of
Pumps
and Valves"
1k
k
I I
k
I
H
k
'I
I
I ki
~
'k
V
H
I'
kl
J
WNP-2 Operating
and Engineering
Test~ Procedure
8.3.1,
Rev. 2, "ISI
and Appendix J, Examination and Testing Program Administration and
Control"
WNP-2 Administrative Procedure
1.5.1,
Rev.
11, "Technical
Specification Surveillance Testing Program"
WNP-2 Administrative Procedure
1.3.7,
Rev.
7, "Maintenance
Work
Request,"
WNP-2 Maintenance
Procedure
10.2.8,
Rev. 4, "Testing and Repair of
Safety
and Relief Valves," J)eviations84-685,
84-1068,85-117,
and
85-377.
Various surveillance
procedures for pump and valve testing.
In general,
the above listed procedures
provided the information and
guidance
necessary
to adequately
manage
and control IST activities.
However, several discrepancies
and weaknesses
were noted.
(a)
(b)
Program Plan pump vibration monitoring details for acceptance
criteria for the type of measurement
(velocity or displacement)
and
location of vibration measurements
(pump or driver bearings)
have
not been properly translated
into the site surveillance
procedure
for the Diesel Oil Transfer
Pumps.
Test. data sheets
provide for
measuring
displacement
only on the pump outboard bearing.
Program
Plan relief request
RP-1 states
that vibration velocity (not
displacement) will be measured
and radial vibration readings will
also be taken at as close
as practical to the inboard
pump bearing.
There is no provision for the System Engineer to signoff for his
review of data sheets
and for documentation of the determination to
increase/decrease
test frequencies.
(c)
The safety
and relief valve test procedure
does not require that two
consecutive
acceptable lifttests
be achieved prior to acceptance
of
the valve.
This verification of repeatability is
a part of the
procedures
detailed in the
ASME Performance
Test
Code for safety and
relief valves.
(d)
(e)
The procedure for operability testing of the Diesel Oil Transfer
Pumps
does
not, provide for recording of storage
tank levels
and tank
correlating levels to pressure
as specified in Note A to the
"WNP-2
Pump Inservice Test Table" in the Program Plan.
Valve stroke timing/exercising'rocedures
did not have specific
precautions/requirements
to take data
on the first operation of the
valves.
Cycling of valves prior to the test of record could result
in stroke times not reflective of emergency condition operation.
Procedure
7.4.0.5.1 actually require,,cycling the
MSRV discharge
vacuum breakers
3 times prior to testing for operability.
This
approach is based
on general maintenance
information provided in a
vendor manual.
However, this does 'not provide all of the
operability assurance
intended, by ASME Section XI.
It yI
I
II
(
y,I
r
II
I
II
I
I~
I
y
I
IN
II
I
k
y
Ik
I
~
k
I
I
k
I I
~ J
y
'y
'
ll )
I
I
I, I,
yy kg
1
I
I
y
l
I'I
'I
k
JI
'k
I
(f)
The WNP-2 valve program does not provide for evaluation
and
corrective action of valve stroke times based
on the previous test
times
as required by ASME,Section 51, Subsection
IWV-3417.
t'
f
Failure to properly establish/implement
Code requirements, regarding the
proper evaluation of stroke times is an apparent violation of paragraph
4.0.5 of Technical Specifications
MPPSS Nuclear Project No.
2
(50-397/85-17-01).
t.
After a review of the findings noted above 'and in discussions
during the
inspection,
the licensee
stated to the senior resident inspector that the
Technical Department staff would review implementing procedures
against
Program Plan commitments
and requirements
and that the Program Plan
and/or procedures will be revised
as required.
This finding will be
carried, as
a Followup Item (50-397/85-17-02)
and will be 'examined
on
future inspections.
4.
IST Records
a
~
Selected
completed inservice test data sheets
were examined for the
following pumps for compliance with Section XI and site procedural
requirements:
RHR Pump
2A
Diesel Oil Transfer
Pump
1A
On RHR Pump 2A, two cases
were noted where tests
were accepted
as-is
when data
was outside of the acceptable
range.
Post-maintenance
testing
on 3/17/84 was accepted without any indication of increased
test frequency,
although
pump flow was in the alert range (high).
The surveillance test performed
on 11/6/84
was also accepted as-is,
but the data point, was in the action range of the attached
pump
curve.
In reviewing this discrepancy
the licensee
subsequently
determined that the curve in the procedure
on 11/6/84 was drawn
using tolerances
more restrictive than the
ASME Code allowed and
appears
also to have been
drawn erroneously.
Accurate drafting,
using
code allowed tolerances,
in a 12/4/84 revision to the
procedure
would place the test data in the acceptable
range.
For the 3/27/84 test
on the Diesel Oil (DO) Transfer
Pump
1A, an NCR
documenting
a discharge
pressure
in the action range
was
dispositioned
as "acceptable,"
because
the amount of specification
was within the accuracy of the pressure
used; 2.8/.
However,
ASME Section XI, Subsection
IVP-4110 requires pressure
instruments
to have at least
an accuracy +/- 2/ of full scale.
Also during this
test,
no vibration readings
were taken for the east-west
and
vertical directions.
For the 7/30/84,
10/17/84
and 1/14/85 tests of
DO Pump
1A there were no signatures
on the data sheet indicating the
review by the Shift Manager or the ISI Engineer.
On the 10/17/84
test of DO Pump
1A no vibration readings
were taken in the east-west
and north-south directions
and the attached strip chart indicated
\\
)
k
H
l
I
I
/
vibration velocity was measured,
'but the data sheet reflected
displacement.
The licensee
stated that the equality Assurance
organization would
perform specific reviews of IST program implementation including
proper evaluation of test results
and corrective actions.
The
question of the adequacy of test result reviews will be considered
an Unresolved Item (50-397/85-17-03)
and will be evaluated
during
a
future inspection.
Valves
A small sample of completed valve test data
sheets
were examined for
compliance with Code
and procedural
requirements.
Valves for which
tests
were reviewed included hydraulic
(HY) valves,
relief valve
(MSRV) discharge
vacuum breakers,
residual heat
removal
(MS) valves
(Procedure
7.4.5.1.8)
and reactor core isolation
cooling (RCIC) valves
(Procedure
7.4.7.3.3).
Other than the
deficiencies
already noted in paragraph
3 of this report only one
discrepancy
was noted.
For the
HY valves stroke tested per
procedure
7.4.0.5.12
no actual stroke times are recorded,
only an
indication that times were less
than
15 seconds.
This practice
prevents
trending of times
and thus possible early identification of
problems
and is another
example of failure to properly
establish/implement
code requirements
and is an apparent violation
of paragraph 4.0.5.a of technical specifications
WPPSS Nuclear
Project No. 2, which was discussed
in paragraph
3 (50-397-17-04).
General
ASME Section XI, Subsections
IWP-6210,
IWP-6250 and IWV-6210 require
summary listing of pumps
and valves to document the current status
of testing
and the corrective actions
taken with regard to pumps.
The licensee
could not provide any summary listings as required by
Code.
Consolidation
and tabulation of test data is necessary
to
provide, in a practical usable format, the information needed
by
system engineers
to evaluate
component performance.
This is
especially beneficial in meeting
commitments
and requirements for
pump operability, valve stroke timing and relief valve testing.
Due
in part to this lack of required
summaries,
the inspectors
had
difficulty in tracing records
and determining the source
and
accuracy of reference
values.
This failure to implement
Code
requirements
into site procedures
is another
example of an apparent
violation of paragraph
4.0.5.a of Technical Specifications
Nuclear Project No. 2,
as discussed in paragraph
3 (50-397-17-05).
The licensee is developing
a computerized
performance
monitoring
program that will potentially provide very useful trending
information to the engineers
responsible for the pump and valve IST
program.
Based
on a review of preliminary outputs the
NRC
inspectors
consider this program will be an excellent
engineering/management
tool when established.
The inspectors
discussed
the role of the licensee's
(}A organization
in the
XST program with site
gA management.
Only surveillances
(not
audits)
are performed by site
gA personnel.
Surveillances in
January
and July 1984 addressed
the IST program.
A thorough
surveillance of program implementation is listed on the Annual
Surveillance Plan, but had been postponed
pending issuance
of
Revision
3 to the program plan.
No corporate audits of the IST
program had yet been performed.
Other than already indicated,
there
were no violations of NRC
requirements identified.
The inspectors
met with licensee
management
personnel
denoted in
paragraph
1 at the conclusion of the inspection
on Hay 10,
1985.
The
scope,
observations
and findings of the inspection were discussed.
J'
C
P
0
IK
4
4
Id
W 't '
i
0
0