ML17275A919
| ML17275A919 | |
| Person / Time | |
|---|---|
| Site: | Columbia |
| Issue date: | 02/20/1981 |
| From: | Spencer G NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V) |
| To: | Matlock R WASHINGTON PUBLIC POWER SUPPLY SYSTEM |
| Shared Package | |
| ML17275A920 | List: |
| References | |
| NUDOCS 8103250001 | |
| Download: ML17275A919 (4) | |
See also: IR 05000397/1981002
Text
~pQ RE0y
e
/p 0p*g0
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION V
1990 N. CAI.IFORNIABOULEVARD
SUITE 202, WALNUTCREEK PLAZA
WALNUTCREEK, CALIFORNIA94596
'EB 2 0 1981
Docket No. 50-397
Washington Public Power Supply System
P. 0.
Box 968
Richland, Washington
Attention:
R.
G. Matlock
Program Director,
WNP-2 Project
Gentlemen:
I
Subject:
NRC Inspection of Washington Nuclear Project
No.
2
U 3. IIUCLEAR RBRNATOgg
p
COAlhllS$ON
This refers to the inspection
conducted
by Messrs.
D.
P. Haist,
W.- J.
Wagner
and J.
F. Burdoin of this office on January
27-30,
1981 of activities
authorized
by NRC Construction Permit No. CPPR-93,
and to the discussion
of our findings with Mr. W.
G. Keltner and other members of your staff at the
conclusion of the inspection.
Areas
examined during this inspection are described in the enclosed
inspection report.
Within these
areas,
the inspection consisted of
selective
examinations of procedures
and representative
records, inter-
views with personnel,
and observations
by the inspector.
No items of noncompliance with NRC requirements
were identified within
the scope of this inspection.
In accordance
with Section 2.790 of the NRC's "Rules of Practice,"
Part 2, Title 10,
Code of Federal
Regulations,
a copy of this letter and
the enclosed
inspection report will be placed in the
NRC's Public
Document
Room. If this report contains
any information that you believe
to be proprietary, it is necessary
that you submit a written application
to this office, within 20 days of the date of this letter, requesting
that such information be withheld from public disclosure.
The applica-
4'
It
'"J,
'1
4
It
t "4
< ~ <<,
~ 't
e
Washington Public Power Supply System
-2-
tion must include
a full statement of the reasons
why it is claimed that
the information is proprietary.
The application should
be prepared
so
that any proprietary information identified is contained in an enclosure
to the application, since the application without the enclosure will
also
be placed in the Public Document
Room. If we do not hear from you
in this regard within the specified period, the report will be placed in
the Public Document
Room.
Should you have any questions
concerning this inspection,
we will be
glad to discuss
them with you.
Sincerely,
Enclosure:
IE Inspection Report
No. 50-397/81-02
Pp&
Reactor
Construction
and
Engineering
Support Branch
cc w/o enclosure:
M. E. Witherspoon, guality Assurance Director
W.
C. Bibb, Project Manager
WNP-2 Project