ML17263A904

From kanterella
Jump to navigation Jump to search
Insp Rept 50-244/94-27 on 941122-1231.Violations Noted.Major Areas Inspected:Plant Operations,Maint,Engineering,Plant Support & Safety Assessment/Quality Verification
ML17263A904
Person / Time
Site: Ginna Constellation icon.png
Issue date: 01/10/1995
From: Lazarus W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML17263A902 List:
References
50-244-94-27, NUDOCS 9501180184
Download: ML17263A904 (16)


See also: IR 05000244/1994027

Text

U. S.

NUCLEAR REGULATORY CONISSION

REGION I

Inspection Report 50-244/94-27

License:

DPR-18

Facility:

Inspection:

Inspectors:

R.

E. Ginna Nuclear

Power Plant

Rochester

Gas

and Electric Corporation

(RGSE)

November

22 through

December

31,

1994

T. A. Noslak, Senior Resident

Inspector,

Ginna

E. C.,Knutson,

Resident

Inspector,

Ginna

Approved by:

W.

.

L

rus

Ch f

Rea

or Projec

ection

3B

INSPECTION SCOPE

r i~

Date

Plant operations,

maintenance,

engineering,

plant support,

and safety

assessment/quality

verification.

950ii80i84 950ii0

PDR

ADOCK 05000244

8

PDR

Operations

INSPECTION EXECUTIVE SUNNARY

The plant operated

at full power (approximately

98 percent)

throughout this

period.

Naintenance

The inspector

assessed

licensee

procedures

-and practices

regarding the removal

of safety-related

equipment

from service for on-line scheduled

maintenance

to

be effective.

The practice of limiting such maintenance

to a single component

at

a time is conservative

and reduces

the possibility of conflict with other

maintenance activities;

degraded

equipment,

or plant operations.

The inspector

reviewed the licensee's

program to protect safety-related

systems

against the effects of extreme cold weather

and concluded that the

program is satisfactorily implemented,

well documented,

and conscientiously

monitored by knowledgeable

personnel.

Corrective maintenance

has

been

appropriately prioritized and has

been timely for identified deficiencies.

Engineering

Following a recent service water system modification to upgrade the C-service

water

pump discharge

check valve,

an expansion joint between the

pump and the

check valve was stretched

beyond the manufacturer-specified

maximum allowable

length during reinstallation.

This condition led to partial material failure

that compromised the maximum pressure

retaining capability of the joint.

'lthough

the degraded

condition of the expansion joint was appropriately

evaluated

by the licensee,

the inspector

determined that the governing

procedure for installation of'he expansion joint lacked appropriate

acceptance

criteria to assure

proper installation.

This was

an apparent

violation of 10 CFR 50, Appendix B, Criterion V, "Instructions,

Procedures,

and Drawings."

Plant Support

Routine observations

in the areas of radiological controls, security,

and fire

protection indicated that these

programs

were effectively implemented.

Safety Assessment/guality

Verification

The Nuclear Safety

and Audit Review Board

(NSARB) was highly effective in

pursuing evaluation

and corrective action for recent

problems with pumps

and

pump motors in the safety injection, auxiliary feedwater,

and service water

systems

TABLE OF CONTENTS

.

TABLE OF CONTENTS

1.0

OPERATIONS (71707)

1. 1

Operational

Experiences

.

.

1.2

Control of Operations

.

.

.

.

.

.

.

.'.0

NAINTENANCE (62703,

61726)

2. 1

Preventive Naintenance

2. 1. 1 Routine Observations

~

~

~

~

~

~

~

~

~

~

~

~

~

~

~

~

~

~

~

~

~

2.2

2.3

2.4

Surveillance

Observations

.

.

.

.

.

.

.

.

.

.

.

.

.

.

2.2. 1 Routine Observations

Evaluation of On-Line Naintenance

(TI 2515/126)

Cold Weather Preparations

(71714)

.

~

~

~

~

~

~

~

~

3.0

ENGINEERING (71707,

37551)

3. 1

C-Service Mater

Pump Expansion Joint

~

~

~

~

4.0

PLANT SUPPORT

(71750)

4. 1

Emergency

Preparedness

- Licensee Action On Previous

Inspection Findings

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

4. 1. 1 (Closed) Violation (50-244/94-21-01)

Failure to

Perform quarterly Siren Growl Tests

.

.

.

.

.

.

4. 1.2 (Closed) Violation (50-244/94-21-02)

Failure to

NERP Changes to the

USNRC Region I Office

.

4.2

Radiological Controls

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

4.2. 1 Routine Observations

4.3

Security

\\

~

~

~

~

~

~

~

~

~

~

~

~

~

~

~

~

~

~

~

~

~

4.3. 1 Routine Observations

4.4

Fire Protection

.

4.4. 1 Routine Observations

~

~

Submit

~

~

~

~

~

~

~

~

~

~

~

~

~

~

5.0

SAFETY ASSESSMENT/OUALITY VERIFICATION (71707)

5.1

Review of Cor recti ve Action For Recent

Pump

5.2

gA/gC Subcommittee

Neeting

5.3

Periodic Reports

6. 0

ADMINISTRATIVE

6. 1

Senior

NRC management

Site Visits

.

.

.

6.2

Enforcement

Conference

6.3

Backshift and Deep Backshift Inspection

6.4

Exit Neetings

.

.

.

.

.

.

.

.

.

.

.

.

.

~

~

~

~

~

Failures

~

~

~

~

~

~

~

~

~

~

~

~

~

~

~

~

~

~

8

8

8

9

9

9

9

9

9

1. 0

OPERATIONS (71707)

1.1

Operational

Experiences

DETAILS

The plant operated

at full power (approximately

98 percent)

throughout the

inspection period.

There were no significant operational

events

or challenges

during the inspection period.

1.2

Control of Operations

Control

room staffing was

as required.

Operators

exercised

control over

access

to the control

room.

Shift supervisors

maintained authority over

activities

and provided detailed turnover briefings to relief crews.

Operators

adhered to approved

procedures

and were knowledgeable of off-normal

plant conditions.

The inspectors

reviewed control

room log books for

activities

and trends,

observed

recorder traces for abnormalities,

assessed

compliance with technical specifications,

and verified equipment availability

was consistent with the requirements

for existing plant conditions.

During

normal work hours

and on backshifts,

accessible

areas of the plant were

toured.

No operational

inadequacies

or concerns

were identified.

2. 0

NAINTENANCE (62703,

61726)

2. 1

Preventive Naintenance

2.1.1 Routine Observations

The inspector

observed

portions of maintenance activities to verify that

correct parts

and tools were utilized, applicable industry code

and technical

specification requirements

were satisfied,

adequate

measures

were in place to

ensure

personnel

safety

and prevent

damage to plant structures,

systems,

and

components,

and to ensure that equipment operability was verified upon

completion.

The following maintenance activities were observed:

~

Work Order 19402721,

"Service Mater

Pump "B" - Najor Pump Overhaul,"

performed in accordance

with Naintenance

Procedure

N-11.,10,

"Najor

Inspection of Service Mater Pump," revision 25, dated October

14,

1994.

The inspector

observed

the

pump removal

and noted

no obvious

material deficiencies.

The

pump was replaced with a rebuilt

spare;

the removed

pump will be rebuilt under

a separate

work

order

and maintained

as

a spare.

2.2

Surveillance Observations

2.2. 1 Routine Observations

Inspectors

observed

portions of surveillances

to verify proper calibration of

test instrumentation,

use of approved

procedures,

performance of work by

qualified personnel,

conformance to limiting conditions for operation

(LCOs),

and correct system restoration following testing.

The following surveillances

were observed:

Periodic Test (PT)-3g,

"Containment Spray

Pump quarterly Test," revision

17, effective date

December

15,

1994,

observed

December

19,

1994

PT-12. 1,

"Emergency Diesel

Generator A," revision 75, effective date

December

8,

1994, observed

December

20,

1994

PT-16M-T, "Auxiliary Feedwater

Turbine

Pump - Monthly," revision 8,

effective date

May 26,

1994,

observed

December

20,

1994

PT-12.2,

"Emergency Diesel

Generator 8," revision 80, effective date

December

8,

1994,

observed

December

21,

1994

The inspector

determined

through observing this testing that operations

and

test personnel

adhered to procedures,

corrective action was promptly initiated

if test results

and equipment operating

parameters

did not meet acceptance

criteria,

and redundant

equipment

was available for emergency operation.

2.3

Evaluation of On-Line Maintenance

(TI 2515/126)

The inspector

conducted

a review of licensee

procedures

and practices

regarding the removal of equipment

from service for on-line scheduled

maintenance.

The purpose of this inspection

was to determine the extent to

which the cumulative impact of maintenance activities

on overall plant safety

is considered

=in the planning

and performance of preventive maintenance.

In January

1994,

RGSE initiated the practice of voluntary removal of safety-

related

equipment

from service for conducting preventive maintenance

during

power operations; this initial effort was discussed

in inspection report 50-

244/94-01.

To examine the effect that such maintenance

would have

on overall

plant operating safety, the licensee

had first conducted

an evaluation of

probabilistic risk analysis

(PRA) data for candidate

equipment.

In overview,

the evaluation consisted of a comparison of the effects that on-line

maintenance

would have

on the individual probabilities that relate to

equipment reliability (that is, the overall probability that the specific

equipment would perform its design function during an accident).

The two

reliability factors that were examined

were equipment unavailability and

equipment failure.

On-line maintenance

would increase

equipment

unavailability.

The change in this probability was estimated

by adding the

allowed outage time (AOT) to the amount of time that the specific equipment is

expected to be out of service during the operating cycle (for example,

due,to

corrective maintenance

or testing),

based

on the plant's operating history.

No attempt

was

made to quantify the change that on-line maintenance

would

produce in the equipment failure probability, since the magnitude of this

effect will only become evident from future trends.

However, it was

reasonably

assumed that increased

maintenance availability would decrease

the

equipment failure probability.

Furthermore,

comparison of these

two factors

revealed that the equipment failure probability was significantly greater than

(on the order of a factor of 10 times) the equipment unavailability

probability.

Therefore,

even

a small

decrease

in the equipment failure

probability would outweigh the projected

increase

in the equipment

unavailability probability.

From this, it was considered that on-line

maintenance

could reasonably

be expected to improve equipment reliability.

3

Beyond this initial PRA sensitivity analysis,

the licensee

has evaluated

some

specific equipment

as being unsuitable for on-line maintenance,

due to

significant risk contribution.

These

equipment include the emergency diesel

generators,

the turbine driven auxiliary feedwater

pump,

and

some valves in

the safety injection and residual

heat removal

systems.

Additionally, the

licensee is in the process of performing an in-depth

PRA-based analysis of on-

line maintenance.

The inspector

reviewed the licensee

process

and procedures for scheduling

on-

line maintenance.

The process for entering into a limiting condition for

operation

(LCO) for the purpose of performing maintenance

on safety-related

equipment is described

in administrative procedures

A-52.4, "Control of

Limiting Conditions for Operating Equipment,"

and A-1603.0,

"Overview of the

Ginna Station

Work Control System."

Requirements

for such maintenance

include:

~

The maintenance

is planned,

scheduled,

and coordinated to insure system

outage time is minimized;

~

Concurrent activities

do not increase

the likelihood of a plant

transient;

The scope of work should not result in an outage time that exceeds

50

percent of the AOT; and

~

Components that provide redundant,

compensating,

or equivalent safety

functions must

be operable.

On-line maintenance

scheduling originates in a comparison of equipment

maintenance

requirements

to the projected schedule for routine performance

testing.

Equipment maintenance

is scheduled

to coincide with performance

testing,

which then serves

as acceptance

testing for the completed

maintenance.

Only one safety-related

component is scheduled for maintenance

at any given time.

Preparations

are progressed

through daily shop foreman

meetings to ensure that all requirements

have

been satisfied prior to

commencing the maintenance,

as well as to avoid conflicts that could arise

due

to concurrent or emergent

maintenance.

When the scheduler is satisfied that

all preparations

have

been completed,

and that the maintenance will not

conflict with the existing plant equipment configuration

and operating

conditions,

the work order is released.

The shift supervisor

has the final

responsibility for verifying that plant conditions will support the equipment

outage, prior to declaring the equipment inoperable

and authorizing work to

commence.

The inspector

examined the processes

that were in place to integrate

scheduled

maintenance activities with existing degraded/inoperable

equipment.

Along

with the processes

.discussed

above,

the licensee lists upcoming scheduled

maintenance

on safety-related

equipment

on the status

sheet

used at the daily

Morning Priorities Action Required

(NOPAR) meeting.

Discussions

at

NOPAR

meetings

have led to recognition of incompatibility between

scheduled

maintenance

and emergent

degraded

equipment.

The inspector

noted that review by the Plant Operations

Review Committee

(PORC)

was not required prior to safety-related

equipment being placed out of

service for planned maintenance.

Technical specification (TS) 6.5. 1.6.f

states that one of the responsibilities of the

PORC is to review facility

operations

to detect potential safety hazards.

With respect to inoperable

safety-related

equipment, this requirement is satisfied

by review of

documentation

prepared in accordance

with A-52.4, Attachment I; however, this

review does not occur until after the equipment

has

been returned to service.

While review of completed on-line maintenance

appears

to be in compliance with

TS,

PORC review prior to performing such maintenance

would provide additional

assurance

that proposed

maintenance

would not conflict with emergent plant

equipment conditions or plant operations.

The inspector

noted that

PORC has

historically been consulted prior to the conduct of significant on-line

maintenance.

In summary,.-the

inspector

assessed

licensee

procedures

and practices

regarding

the removal of safety-related

equipment

from service for on-line scheduled

maintenance

to be effective.

The practice of limiting such maintenance

to a

single component at

a time is conservative

and reduces

the possibility of

conflict with other maintenance activities,

degraded

equipment,

or plant

operations.

2.4

Cold Weather Preparations

(71714)

The inspector

reviewed the licensee's

program to protect safety-related

systems

against the effects of extreme cold weather.

In preparation for the onset of freezing conditions, the licensee

completed

Naintenance

(N) procedure

N-1306. 1, "Ginna Station,

Naintenance

Oepartment,

Winterizing Inspection

Program," dated October 27,

1994.

Procedural

requirements

included:

~

Inspection of heat trace circuits and piping insulation in identified

plant areas

susceptible

to freezing;

~

Verification of anti-freeze protection for the Technical

Support Center

diesel,

the security diesel,

and the diesel fire pump;

and

~

Inspection of windows, ventilation supply/exhaust

vents,

and unit fan

heaters

in various plant and outbuilding areas.

In carrying out this procedure,

Preventive

Maintenance .(PN) Analysts

coordinated

the inspections,

documented

completion of the maintenance

work

orders resulting from the inspections,

and informed operations

supervision of

the findings and status of any outstanding

maintenance

items.

Fifteen work

orders

were generated,

prioritized,

and assigned to the appropriate

maintenance

shops for action.

Through in-plant tours, the inspector

concluded

that the outstanding

maintenance

items identified in H-1306. 1 are being

appropriately addressed.

In accordance

with administrative

(A) procedure A-54.4. 1, "Cold Weather

Walkdown Procedure,"

an inspection is routinely performed weekly by an

Auxiliary Operator

from November

1 through April 1.

This frequency

may be

increased

at the discretion of the Shift Supervisor

depending

on weather

conditions.

A-54.4. 1 identifies the plant areas

and specific equipment that

the operator verifies operable

(by step sign-off) to assure that area

temperatures

remain greater than 45 degrees

F.

In addition to performing

weekly dedicated

cold weather walkdowns, the operator records

temperatures

of

designated

thermometers

in potential cold areas

during routine tours once

each

shift.

Should temperatures fall below 45 degrees

F in these

areas,

the

operator is directed to notify plant management

for initiating corrective

action.

The inspector

independently

determined that the attributes of A-54.4. 1 were

satisfactorily addressed

and identified deficiencies,

such

as

an inoperable

space heater,

were appropriately reported to the Maintenance

Department for

action.

Cold weather

preparations

observed to be in place

by the inspector

included installation of temporary. plywood closures

over intermediate building

vent louvers located

on the east wall of the building, securing various

exhaust

fans with louvers closed,

and staging portable heaters

for expeditious

use.

Based

on this review, the inspector

concluded that the freeze protection

program is satisfactorily implemented,

well documented,

and conscientiously

monitored by knowledgeable

personnel.

Corrective maintenance

has

been

appropriately prioritized and has

been timely for identified deficiencies.

3.0

ENGINEERING (71707,

37551)

3. 1

C-Service Mater

Pump Expansion Joint

On September

20,

1994, the C-service water

(SW)

pump was declared

inoperable

due to excessive

noise

and vibration.

Investigation revealed that the

pump

had undergone

a major mechanical failure.

Root cause evaluation

determined

that reverse rotation of the idle pump had contributed to the failure,

and

that the probable

cause of the reverse rotation was intermittent failure of

the discharge

check valve (4603) to fully close.

As a result, valve 4603 was

replaced with a new style check valve.

The

C-SW pump was returned to service

on October ll, 1994; further details are presented

in inspection reports

50-

244/94-22

and -25.

An elastomeric

expansion joint is installed in the 14-inch discharge line

between

each service water

pump and its associated

discharge

check valve.

After completion of the

C-SW pump discharge

check valve replacement,

the

licensee

had noted that the expansion joint had developed external radial

splits in several

locations.

This condition was subs'equently

evaluated

by the

vendor (Garlock),

who determined

1) that the splits had tom through

some of

the fabric bias plies,

and therefore

compromised the maximum pressure

retaining capability of the expansion joint, and 2) that,

as installed,

the

expansion joint was stretched to twice its maximum allowable elongation.

In

an October 26,

1994 correspondence

to the licensee,

the vendor noted that

immediate failure did not appear to be a factor unless the expansion joint was

subject to excess

movement,

and recommended that the expansion joint be

inspected periodically and replaced

during the next scheduled

outage.

The

licensee

generated

a nonconformance

report

(NCR 94-128) to document the

deficiency and performed

a safety evaluation of the condition pursuant to 10 CFR 50.59.

From this evaluation,

the licensee

concluded that, subject to

frequent inspection

by auxiliary operators

and security force personnel,

the

C-SW pump expansion joint was acceptable for interim use until the

1995

refueling outage.

During a routine in-plant inspection

on December

13,

1994, the inspector first

became

aware of the degraded

condition of the

C-SM pump expansion joint.

The

inspector

was concerned that the adjustment of the four control units (metal

rods that connect the=flanged

ends of the expansion joint and serve to limit

its maximum elongation) might not be appropriate.

Specifically, following

installation of. the

new style discharge

check valves

on the A- and

B-SW pumps

during the

1994 refueling outage,

the associated

expansion joints were found

to be at their maximum elongation;

per the vendor's

recommendation,

the

lengths of the control units

had

been adjusted

(shortened to where the

retaining nuts were tight against the flanged ends) to prevent

any additional

elongation.

Following completion of the

same modification for the

C-SM pump,

however, the lengths of the control units were apparently set per the vendor's

standard

procedure;

that is, their lengths

were set to be slightly longer than

the expansion joint, such that they would allow the joint to stretch to its

designed

maximum length before the retaining nuts would be tight against the

flanges.

When questioned

by the inspector regarding this inconsistency,

the

licensee

responded

that the vendor

had not included adjusting the

C-SM pump

expansion joint control units in their recommendations

for interim use.

When

subsequently

contacted

by the licensee

regarding this issue,

the vendor

recommended that the control units

be adjusted to prevent additional

elongation.

In reviewing

NCR 94-128, the inspector

became

aware of the overextended

condition of the

C-SW pump expansion joint.

The inspector

was concerned that

the pressure

retaining capability of the expansion joint was degraded,

in that

service water is a safety-related

system.

The inspector

reviewed the

licensee

s interim use justification and

10 CFR 50.59 evaluation.

The

inspector noted that, although the

SW system is a seismic category

1 system,

the effect of the degraded

expansion joint on the existing structural

analysis

had not been considered

in the safety evaluation.

The licensee

subsequently

reviewed the seismic'analysis

of the affected portion of the service water

system

and verified that the pipe stresses

would remain acceptable

with the

control units adjusted to prevent further elongation of the joint.

Additionally, the vendor stated that movement of the expansion joint with the

control units

as originally adjusted

would not be anticipated to result in

immediate catastrophic failure.

Given this additional information, the

inspector considered

the licensee's

interim use justification to have

been

adequate.

The inspector

reviewed station modification procedure

SN-5284B.2,

"C-Service

Water

Pump Check Valve 4603 Nodification."

The inspectot

noted that this

procedure

contained

no requirement to measure

distance

between flange faces

on

the

SM pump discharge

and the check valve prior to installation of the

expansion joint.

Expansion joint installation was directed to be accomplished

per maintenance

procedure

N-37. 130,

"Disassembly

and Reassembly of Pipe Flange

Connections,"

which does not address limits on elongation.

Failure to address

requirements

for acceptable

installation of the expansion joint is an apparent

violation of 10 CFR 50, Appendix B, Criterion V, "Instructions,

Procedures,

and Drawings," which states,

in part:

"Instructions,

procedures,

or drawings

shall include appropriate quantitative or qualitative acceptance criteria for

determining that important activities have

been satisfactorily accomplished."

(50-244/94-27-01)

On December

28,

1994,

a new, correctly sized expansion joint was installed in

the

C-SM pump discharge

piping.

As a result of issues identified during

review of the degraded

condition of the

C-SW pump discharge

expansion joint,

the licensee

commenced

a review of the existing application of the remaining

three

SM pump discharge

expansion joints. 'his investigation

was in progress

at the close of the inspection period.

4.0

PUST

SUPPORT (71750)

4. 1

Emergency

Preparedness

Licensee Action On Previous Inspection Findings

4. 1. 1 (Closed) Violation (50-244/94-21-01)

Failure to Perform quarterly Siren

Growl Tests

The inspector

reviewed the adequacy of the licensee's

response

following

identification that siren growl tests

were not performed during the period

Narch 2,

1994 through-October

5,

1994

as required

by the Nuclear

Emergency

Response

Plan

(NERP).

The subject tests

were successfully

performed

on all

96

sirens

on October 7,

1994.

To better establish clear accountability to verify

that time-related

program requirements

are being met, the licensee

designated

the Corporate

Nuclear Emergency Planner to schedule

and verify completion of

all required tests

and inspections.

In carrying out this responsibility, the

Planner will submit

an emergency

preparedness

planning schedule

and tracking

list to the corporate

"Emergency Planning Milestone Committee" monthly,

verifying that all key scheduled tests

and inspections

have

been completed

as

required.

Through this review, the inspector

concluded that the licensee's

actions

were comprehensive

to adequately

address this finding.

This item is

closed.

4.1.2 (Closed) Violation (50-244/94-21-02)

Failure to Submit NERP Changes to

the

USNRC Region I Office

The inspector

reviewed licensee

actions regarding

a failure to submit

NERP

changes to NRC Region I office as required.

Copies of the current revision

(Revision

14) were submitted to regional office on October 6,

1994.

RGSE

placed the

NERP on

a controlled user distribution and the

RGSE Document

Control Department

has assigned

user

numbers to the Region I Office to assure

that future revisions

are properly distributed to all concerned

organizations.

Through this review, the inspector

concluded that the licensee's

actions

were

prompt and adequate

in addressing this matter.

This item is closed.

4.2

Radiological Controls

4.2.1 Routine Observations

The inspectors periodically confirmed that radiation work permits were

effectively implemented,

dosimetry was correctly., worn in controlled areas

and

dosimeter

readings

were accurately recorded,

access

to high radiation areas

was adequately controlled,

survey information was kept current,

and postings

and labeling were in compliance with regulatory requirements.

Through

observations

of ongoing activities

and discussions

with plant personnel,

the

inspectors

concluded that the licensee's

radiological controls were effective.

4.3

Security

4.3.1 Routine Observations

During this inspection period, the inspectors verified that x-ray machines

and

metal

and explosive detectors

were operable,

protected

area

and vital area

barriers

were well maintained,

personnel

were properly badged for unescorted

or escorted

access,

and compensatory

measures

were implemented

when necessary.

No unacceptable

conditions were identified.

4.4

Fire Protection

4.4. 1 Routine Observations

The inspectors

periodically verified the adequacy of combustible material

controls

and storage

in safety-related

areas of the plant, monitored transient

fire loads, verified the operability of fire detection

and suppression

systems,

assessed

the condition of fire barriers,

and verified the adequacy of

required compensatory

measures.

No discrepancies

were noted.

5.0

SAFETY ASSESSNENT/EQUALITY VERIFICATION (71707)

5. 1

Review of Corrective Action For Recent

Pump Failures

In August 1994, the Nuclear Safety

and Audit Review Board

(NSARB) tasked site

management

with reviewing recent

problems with pumps

and

pump motors in the

safety injection, auxiliary feedwater,

and service water systems,

and

developing

an action plan to address

the resultant operational,

maintenance,

and design issues.

On November 29,

1994, site management

presented

results of

this review in a teleconference

meeting with the

NSARB.

Through attendance

of

this meeting,

the inspector determined that site management's

investigation

had been extensive

and thorough.

Responses

from the

NSARB were incisive and

critical, and led to development of several

more action items for site

management.

The inspector

concluded that the

NSARB was highly effective in

fulfillingits independent

oversight function in this matter.

5.2

QA/QC Subcomaittee

Meeting

On December

19,

1994, the inspector

attended

a meeting of the Quality

Assurance/Quality

Control

(QA/QC) Subcommittee of the

NSARB.

The meeting,

chaired

by senior licensee

management,

addressed

the status,'indings,

and

trends identified in various audits, surveillance

programs,

arid corrective

action systems.

A summary of the Corrective Action Performance

Indicators

presented

to the subcommittee

showed

improvements. in overall site performance.

No new areas of concern were evident that required further detailed analysis

or warranted

increased

management

attention.

The status of various

open items

was discussed

in detail.

Through this attendance,

the inspector

concluded that senior licensee

management

was properly informed of factors affecting the quality of overall

plant performance

and material condition.

Issues

are thoroughly and candidly

discussed

with action items assigned to assure

a timely resolution of

unresolved

concerns.

Management

expectations

in addressing

issues

were

clearly stated.

5.3

Periodic Reports

Periodic reports

submitted

by the licensee

pursuant to Technical Specification 6.9. 1 were reviewed.

Inspectors verified that the reports contained

information required

by the

NRC, that test results

and/or supporting

information were consistent with design predictions

and performance

specifications,

and that reported information was accurate.

The following

reports were reviewed:

~

Monthly Operating Report for November

1994

No unacceptable

conditions were identified.

6.0

ADMINISTRATIVE

6.1

Senior

NRC Management Site Visits

During this inspection period,

one senior

NRC manager visited Ginna Station.

On December

19-20,

1994,

Mr .

James

C. Linville, Chief of Reactor Projects

Branch 3, toured the. site

and met with senior licensee

management.

6.2

Enforcement Conference

On December

20,

1994,

an enforcement

conference

was held at the

USNRC Region I

office, to discuss

weaknesses

in the licensee

s fitness for duty testing

program.

Details are presented

in inspection report 50-244/94-28.

-6.3

Backshift and Deep Backshift Inspection

During this inspection period,

deep backshift inspections

were conducted

on

November

27 and December

18,

1994.

10

'.4

- Exit Meetings

At periodic intervals

and at the conclusion of the inspection,

meetings

were

held with senior station

management

to discuss

the scope

and findings of

inspections.

The exit meeting for inspection report 50-244/94-26

(Problem

resolution,

conducted

November

21 December

2,

1994)

was held by Mr. James

Stewart

on December

2,

1994.

The exit meeting for inspection report 50-

244/94-28 (Health'hysics,

conducted

December

19-22,

1994)

was held by Mr.

James

Noggle on December

22,

1994.

The exit meeting for the current resident

inspection report 50-244/94-27

was held on January

5,

1995.