Rev 6 to EOP AP-TURB.3, Turbine Vibration
ML17263A193
Person / Time
Site: Ginna Constellation icon.png
Issue date: 03/24/1993
From: Marlow T
ROCHESTER GAS & ELECTRIC CORP.
To:
Shared Package
ML17263A191 List:
References
AP-TURB.3, NUDOCS 9304080156
Download: ML17263A193 (9)


Text

EOP:

P-TURB.3 TITLE TURBINE VIBRATION REV:

6 PAGE 1 of 6 ROCHESTER GAS AND ELECTRIC CORPORATION GINNA STATION CONTROLLED COPY NUMBER TECHNICAL REVIEW PORC REVIEW DATE

~~ <.N PLANT SUPERINTENDENT EFFECTIVE DATE CATEGORY 1.0 REVIEWED BY:

,(

9304080'g 930330'Do~K0SO00aqq.

PDR

EOP:

P-TURB. 3 TURBINE VIBRATION REV:

6 PAGE 2 of 6 A.

PURPOSE This procedure provides the necessary actions

.to be taken in the event of increasing turbine vibrations.

B.

ENTRY CONDITIONS/SYMPTOMS 1.

SYMPTOMS The symptoms of TURBINE VIBRATION are; a.

Annunciator I-27, Rotor Eccentricity or Vibration alarm is lit.

b.

Increasing or High Turbine'ibration detected.

v,I.

EOP:

P-TURB.3 TURBINE VIBRATION REV:

6 PAGE 3 of 6 STEP ACTION/EXPECTED RESPONSE

RESPONSE

NOT OBTAINED NOTE:

The exciter bearing No.

9 is not as limiting as the turbine bearings Nos.l through 8.

1 Check Turbine Vibration:

o Bearings No.

1 through No. 8-LESS THAN 14 MILS o

Bearing No.

9 - INDICATION ON SCALE Perform the following:

a. Trip the turbine.

b.

Go to AP-TURB.1, TURBINE TRIP WITHOUT RX TRIP REQUIRED OR E-Oi REACTOR TRIP or SAFETY INJECTION, as required.

2 Check No.

9 Bearing Vibration LESS THAN 14 MILS Initiate load reduction to decrease vibrations.

IF vibrations can NOT be reduced, THEN shutdown the plant, (Refer to 0-2.1, NORMAL SHUTDOWN TO HOT SHUTDOWN).

fVL h

EOP $

P-TURB.3 T1TLF.$

TURBINE VIBRATION REV:

6 PAGE 4 of 6 STEP ACTION/EXPECTED RESPONSE

RESPONSE

NOT OBTAINED CAUTION IF AT ANY TIME VIBRATIONS EXCEED 14 MILS, THEN RETURN TO STEP 1.

3 Check Turbine Vibration:

a. Bearings No.

1 through No.

8 LESS THAN 7 MILS

a. Attempt to stabilize vibration as follows:

o IF increasing turbine speed, THEN stop speed increase and evaluate.

o IF generator on line, THEN begin reducing load to stabilize vibrations.

b. Bearing No.

9 - LESS THAN 7 MILS

b. Attempt to stabilze vibrations as follows:

o Adjust generator hydrogen temperature,

-OR-o Adjust turbine lube oil temperature,

-OR-o Adjust exciter cooling.

EOP:

P-TURB.3 TURBINE VIBRATION REV 6

PAGE 5 of 6 STEP ACTION/EXPECTED RESPONSE

RESPONSE

NOT OBTAINED 4 Evaluate Plant Conditions:

a.

Check turbine vibrations STABLE OR DECREASING

a. Continue load reduction until turbine vibrations stabilize.

IF vibrations can NOT be stabilized with the plant at

power, THEN take unit off line (refer to 0-2.1, NORMAL SHUTDOWN TO HOT SHUTDOWN).
b. Stop load reduction 5 Establish Stable Plant Conditions:

a.

Tavg - TRENDING TO TREF

a. Insert control rods or, if necessary decrease turbine load to match Tavg to Tref.

b.

PRZR pressure

- TRENDING TO 2235 PSIG

b. Verify proper operation of PRZR heaters and spray or take manual control of PRZR pressure controller 431K.

c.

PRZR level - TRENDING TO PROGRAM

c. Verify proper operation of charging pump speed controllers

~ OR take manual control of speed controllers to control PRZR level.

d. Rod insertion limit alarms-EXTINGUISHED
d. Borate as necessary and withdraw control rods to clear insertion limit alarms (refer to affected rod bank alarm response procedures if necessary).

\\,

h

EOP:

P-TURB 3

TURBINE VIBRATION REV:

6 PAGE 6 of 6 STEP ACTION/EXPECTED RESPONSE

RESPONSE

NOT OBTAINED 6 Evaluate Turbine Operation:

a. Verify no unusual noises exist locally at turbine generator
a. IF unusual noises
detected, THEN notify the Maintenance Manager.
b. Monitor turbine supervisory instrumentation to ensure conditions stable 7 Notify Higher Supervision

- END-