ML17262A737
| ML17262A737 | |
| Person / Time | |
|---|---|
| Site: | Ginna |
| Issue date: | 01/27/1992 |
| From: | Gramm R, Imbro E, Mark Miller Office of Nuclear Reactor Regulation |
| To: | |
| Shared Package | |
| ML17262A736 | List: |
| References | |
| 50-244-91-201, NUDOCS 9202050439 | |
| Download: ML17262A737 (89) | |
See also: IR 05000244/1991201
Text
i
U.S.
NUCLEAR RlM'UIATORY OCNNISSION
OFFICE OF NUCLEAR REACIOR REGULATION
Division of Reactor Inspection and Safeguards
NRC Inspection Report:
50-244/91-201
License No.:
DFR-18
Ekocket No.:
50-244
Licensee:
Rochester
Gas and Electric Corporation
Facility Name:
Ginna Nuclear Power Station
Inspection Conducted:
December
2 through 20,
1991
Prepared by:
Inspection Team:
Melanic A. Miller, Team leader,
Suresh K. Chaudhary,
Sr. Reactor Engineer,
RI
'Ihomas A. Moslak, Sr. Resident Inspector,
RI
Donna Skay, General Engineer,
James
E. Tatum, Sr. Reactor Engineer,
Jerzy Parkitny,
NRC Consultant,
AECL
44
g LLk
Melanic A. Miller, Team leader
Team Inspection Section
B
Special Inspection Branch
Division of Reactor Inspection
and Safeguards
0
ice of Nuclear Reactor Regulation
Reviewed by:
A.
Robert A. Gramm, Section Chief
Team Inspection Section
B
Special Inspection Branch
Division of Reactor Inspection
ard Safeguards
Office of Nuclear Reactor Regulation
~p
~by:
Eugene V. Imbro, Chief
Special Inspection Branch
Division of Reactor Inspection
and Safeguards
Office of Nuclear Reactor Regulation
te
Date
Date
9202050439
920130
ADDCK 05000244
I
ii
8
'Ihe Special Inspection Branch of the U.S. Nuclear ~atoxy Ocaanission
performed a pilat team inspectian,
the Service Rater System Op~tianal
Performance Inspection, at the Ginna Nuclear Poem Station, during the period
December
2 thrn)gh 20, 1991.
%he inspection included a me~nical design review of the sexvice water
system
(SNS); detailed system waMkams; review of system opexation,
maintenance,
and surveillance;
and assessment
of quality assurance
and
corrective actions related to the SNS.
Ihe team also assessed
the licensee's
implementation of actions required by Generic Letter 89-13, "Sexvice Rater
Sy.~n Problems Affecting Safety-Related
Equipnent," as well as system
unavailability to gain additianal insights for prababilistic risk assessment
application.
After inspectirg the
SNS in detail, the team identified several deficiencies
and we dresses.
%he current technical specification requiring that two of the
four sexvice water
(SW) puris be cperable is not sufficient to account for
single-failure assumptions
since two punps are required to cperate dump the
accident recirculation phase. ~ team also identified a failure to
adequately control engineering docunents
and a nunher of inaccuracies in the
Updated Final Safety Analysis Report.
'Ihe team found two exzcaples of
tive operational ~osophy:
(1) the practice of not entering a
limiting condition for operation when performing equi@nant testing and of
taking redundant equignent out of service simiLtaneously and (2) the practice
of performing long-term maintenance of SW panps durirg plant operation.
lhe
team identified a greater need of the licensee to understand
and adjust the
system hydraulic flow, in particular that flmr through the diese1 generator
coolers.
Further, the licensee
had not cansidered the single failure of a
pump discharge
and its implementation of Generic Letter 89-13
actions was not entirely adequate, ~xaially that of Action IV related to
verification of the SNS licensing basis.
1
review and corrective actions are necks;ey:
(1) mamlysis of the SNS
hydraulic model and applicatian of its reacts to the system,
(2) assessment
of the sirgle failure of a pump discharge ~~ valve,
(3) establishment of
the appmpriate
system lear-pressure
setpoint,
(4) assess'.nt
of any single
failures that would impair system operation due to the cross~nnected
configuration and relly.ation as necessary,
(5) evaluation of preoperational
test remits,
and
(6) inclusion of the ~rapriate
number of operable
pumps in
the Technical Specifications.
%he abave issues give rise to sane uncertainty
as to system operability.
However,
we conclude that, with the interim actions
taken for items
(2) and (6), a presumptian of operability is warranted while
the issues
above are fully resolved.
%he licensee considered
item (2) to be autside its design basis.
In addition,
the licensee considered the need to maintain four SW purges operable outside
its design basis.
The NRC is continuing to evaluate bath of these issues with
respect to design basis considerations.
I
g
i ~
~
~
1
0
Strengths regarding the system were also identified.
Operators were
kncvledgeable of the system alignment, operation,
and cmponent location.
Operations pnxm3ures were detailed and agp~xpriate,
and operator training was
a strength.
In maintenarme,
procedures
were generally good, personnel
were
akilled and- kncvledgmble,
and the training program was very good.
9he
licensee's
develogtent
'of its Service Water Systxun Reliability Optimimtion
Program document represented
a positive ~roach to addressing
SNS issues.
k
~
~
g
~
~
TAKZ OF CNZ/%IS
EXECU'E SUMMARY
~
~
~
~
~
~
~
~
~
~
~
~
~
~
. ~
~
~
~
~
~
~
~
~
~
~
~
~
~
1. 0
INSPECTION SCOPE AND OBHCZZVES
2. 0
SYSTEM DIXCRIETION
3.0
DEZAIIZD INSPECTION FINDINGS
3. 1
Mechanical Design Review
3.1. 1
Document Control
3.l. 2
Syahnn %hernial-Hydraulic Design
3.1.2.1
3.1.2.2
3.1.2.3
3.1.2.4
3.1.2.5
Hydraulic Model
Opponent Cooling Water Heat E>ochangers
Spent Fue1 Pool Heat Exchanger.....
Diesel Generator Coolers........
5
6
6
8
9
3.1.3
3.1.4
3.1.5
3.1.6
3.1.7
3.1.8
Caamon-Mode
and Single-Failure Analysis
~tial for Service Water Pump Overheating
Heat Exchanger Heat Transfer Testing Program
Modification Review
UP.AR Discrepancies
Concluslons
~
o
~
~
~
~
~
~
~
~
~
~
~
~
~
~
10ll
11
12
12
13
3 ~ 2
Of%rat lons
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
14
3.2.1
Systxan Configuration WaDackams
3.2. 2 Ope~tions Procedures
3.2. 3
Operator WalMowns
3.2.4
Operations Training
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~ t
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
, ~
~
.
~ ,, ~
14
15
16
16
3.2.4.1
Training Programs
3.2.4.2
Training Materials
.
3.2.5
Conclusions
~
~
~
~
~
~
~
~
~
0
~
~
~
~
~
~
~
~
~
~
16
17
18
3. 3
Maintenance
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
18
3.3.1
3.3.2
3.3.3
3.3.4
3.3.5
3.3.6
Procedures
~
~
~
~
~
~
Activities Observed
Taxiing of Preventive
Tra 'n1ng
e
~
~
~
~
~
System Unavailability
Conclusions
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
and Corrective
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
18
19
19
20
21
21
g
A
s
g
J'1
3.4
Surveillance
anal Test~
22
3.4'.1
3.4.2
3.4.3
3.4.4
3.4.5
3.4.6
Preogeraticnal Test~
Surveillance Procedures
Inservice Testiag of Bmps and Valves
Piping arxl Oaqmnent Xnspectians
Biofouling Control and Surveillance During
Opera
'ion
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
Oonclusians
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
System
~
~
~
~
~
0
~
~
~
~
~
~
~
~
22
23
23
24
25
25
3. 5 Quality Assurance
and Oorrective Actions
~
~
~
1
~
1
~
>
~
~
~
26
3.5. 1
Root-Cause Evaluations
3.5.2
Occtparison of Firdi~
3.5.3
Oonclusians
~
~
~
~
~
~
~
~
~
~
~
~
~ t
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
0
~
~
~
~
~
~
~
~
~
~
~
~
~
~
26
26
27
4. 0
EXIT MEZFING
~
~
~
~
~
~
~
~
~
~
~
~
~
~
27
APPENDIX A
SUN%9K OF INSPECTION FINDINGS
APPENDIX B
EXZI'EETING ATZEKRNCE IZST - DECKER 20, 1991
APPENDIX C
ABHREV32KIONS
1 GINNA SERVICE WAR SYSTEM........ ~... ~ ~........... ~.....
~ .. ~..........
2
1.0 INS~GN SCOPE AND OB3ECTXVES
Fran December
2 through 20, 1991, the U.S. Nuclear Regulatory Occakssion
(NRC}
staff performed an announced pilot Service Water System Operational
Performance Inspection
(SNSOPI) at the Girna Nuclear Pc@mr Statian.
'Ihe
w
and surveillance of the service water systen
(SWS).
In additian, the team
evaluated quality assurance
and corrective action proc'ects
related to
the SWS.
lhe primary objectives of the SNSOPI were to:
(1)
Asm~ the operational perfornance of the
SNS thmugh an in-depth review
of mec~nical sy.~ns'unctianal
design and thermalWydraulic
f
i ~,,
1
p
their implementation;
and cinerator trainirg an the SNS;
(2)
Verify that the functional designs
and operational controls of the
P
" l
~ i
and that SNS cxapanents
are cyerated in a manner cansistent with their
design bases;
(3)
Assess the licensee's
planned or ccapleted actions in respanse to Generic
Ietter 89-13; and
t!W
surveillance,
and cxxnponent failures.
%he team has characterized its fincULngs within this report as deficiencies,
unresolved items, or observations.
Deficiencies are either
(1) the parent
H
failure of the licensee to satisfy a written cxmmitment or to conform to the
provisions of applicable codes,
standards,
guides, or other a~~ industry
practices
when the canmitment has not been made a legally bindirg requinanent.
Unresolved items involve a concern about which more information is requuxd to
~mctain whether it is acceptable or deficient.
Appropriate items willbe
reviewed by the NRC regional office for any enforcetmnt actions.
Observations
are items considered appropriate to call to licensee
management
attention, but
which have no ~rent dh~t regulatory basis.
2. 0
SYSTEM DESCRIPTION
'Ihe Ginna SWS, depicted in Figure 1, is an open-loop system that takes suction
from Lake Ontario via the screenhouse
ard ~lies cooling water to various
turbine plant loads as well as auxiliary reactor plant loads. ~ SWS
discharges
back into Lake Ontario via the plant discharge canal.
%he
consists of four SW pumps, two loop supply headers,
isolation valves,
a normal
discharge header,
ard an alternate discharge header.
Allportions of the
serving safety-related
equipnent are designed
as seismic Category I. All
other portions of the
SWS serving non-safety-related
loads are designated
as
nonseismic and are capable of being isolated fran the safety-related portion
of the system.
'Ihe SWS provides cooling water to the follcarirg equipnent:
two cmponent
cooling water heat exchangers
(Ot:RHXs), two diesel generator
(DG) lubricating
oil an2 jacket water cooler sets,
two spent fuel pool heat exchangers
SCACfCCWfLL
A'OOP CCfAOf4
'd'OOP CcfAOf4
'TI
CCDC
CD
Q
VI
CD
CD
Vl
C
CD
3
c)
O
'P
3P
(5
IN(o
gOy
DPz)
c
$
c
c
-
c
C
I
I
I tI" I
I PP
I
I peal
I
I
p (o
m
OO
$ C
~
(
~
li!
V
$~
t )~
b
JW.f
air coolers
(CACs), the safety-related
pump motor roan coolers (residual heat
~,
tllb
1
other non-safety-related
SW loads.
Manual valves are provided to isolate
varims canponents
when necessary.
%be SNS is also the alternate water source
for the auxiliary feahrater
pmIIps and the primary scmxe for the stardby
auxiliary feaster pcs.
I
'
, two~ge, cerrtrifugal pumps with a rated fleer of 5300 ~.
Plant load
requirements dictate two or three
SW puttps for normal full load and, for
accident conditions,
one
SW pump during the injectictn ~e ard two SW puaps
during the recirculation phase.
%he SNS cooley water supply consists of two trains
(A ard B) with two SW
pumps supplying each train.
Ihe SNS trains are cross-tied
and cooperate
as a
single system with main cross~nnect
valves at the DGs (4760 and 4669) ard
CACs (4756 and 4639) normally open.
She only train separation is normally
closed cross-cxxnect valves
(4610 and 4779) located in the main supply loop.
%he SNS can be isolated into two systems by manually closing the above-
mentioned cross~neet
valves with the exa~ion of the SI pumps which can
only be isolated so that one train would provide their total fleer.
%he SNS cooling loads sham di.~ibutian piping that can be fed fran either
one of the SNS headers
by the cpen cross~neet
valves (with the mxeption of
the CCNHXs and the standby auxiliary feechmter supply lines which are only
effectively cross-connected
through normally closed valves 4610 ard 4779) .
In
the event of a malfunction in either subsystem, it is possible to manually
isolate the portion of the subsystan affected ard maintain service to all
other portions of the plant.
%he engineered safety features equiprent can be
split between the two subsystems with the exception of the SI punps.
Double valves in series
(one papered
by train A, the other bjy train B) are
safety injection signal
(SIS) coincident with an urdervoltage or lossmf-
offsite-pc~ cordition.
On an SIS only, non-safety-related
loads are not
isolated.
~ OCNHXs, SFRiX A, SI pump thnxst bearings,
standby auxiliary feedwater
pump
man coolers,
and the safety-related
pump man coolers located in the
auxiliary building have redurdant
SNS discharge lines that empty ttuaugh a
seismic Category I discharge stature to Deer Cretic and then to lake Ontario.
discharge is only used if the normal discharge
becanes
the
SW puatps are connected to the 480 V train A and train B buses
(buses
17
ard 18, mspx<ively) that can be ~lied by the DGs in the event of a loss
of offsite power.
One
SW pump per bus is autanatically started on bus
urdervoltage or SIS.
For an urdexvoltage ~tion with SIS, the SNS is
configured to ~ly cooling water only to the required emergency
systems.
1
~
I
~
3.0
KSHPQIED INSPECTICN FINDINGS
3.1
Mechanical Design Review
She mechanical design review of the Ginna SNS included detara6aaticn of
whether the system's design basis,
design assuaptices,
calaQaticns,
analyses,
boundary corditions,
and medels met licensing ccamitments
and regulatory
requirements
and were capable of meetirg the thermal ard hp3raulic performance
specificatices
during accident ar ather abnormal cxzxKtians.
9he team also
reviewed the system design vulnerabilities and a sample of implemented
edification packages.
During the ~~ion, the licensee provided the team with limited design
dcx~tatian supporting the design basis of the SNS.
She licensee did not
have available a list of design calculations or any formal listing of SNS
design documents.
%he lack of a donunented design basis could be a
shortcmung
when modifying the plant Mxlware, software, or pracxdures ard
represented
a weakness.
3.1.1
Document Control
During the review of design calculations, modification packages,
and answers
provided in response to questions,
the team noted that the licensee
was not
properly controlling, verifying, and a~inp design reports, calculations,
or analyses.
For example,
(1)
%he NUS Corporation calculation, 'Ryiraulic Analysis of the Service Water
System,>> dated February 1988, supporting Engineering Work Request
(ENR)
1594 was submitted to the licensee marked <<preliminary, for review ard
comment
in March 198 8 ~
As of DBcGlk)ez
1991 g the analysis
had nat beell
reviewed and accept
by the licensee,
but was being used for hydraulic
analysis
and balancing of the
SNS following installation of SFFSX B.
(2)
Bechtel-KHU Report,
"Heat Zoad Capacity/Design Margin Analysis for RED,
CCNHX, SF&K, Non-Regenerative
HX,>> Job No. 20031,
Rev. 1, dated
January
22,
1989, did nat have any indicatian that it. had been reviewed
and accepted
as mguired by Section 3, >>Configuration Control," of the
licensee's
Quality Assurance Manual, Rev. 13, dated Noveakar 1, 1986.
(3)
Rochester
Gas ~ Electric Corporation
(RG&E) design analysis document
entitled>>Insitu Motor Zaad Detenninatians>> for ENR 4232,
<<SNS
Pump Rotor
Studies," dated July 15, 1986, included inca~ assunptians
based
on a
law slip motor ar6 inappropriate equatians.
Consequently,
the results
were also incorrect.
Ihe licensee
had known this for mere than a year;
however, action to revise the calculation and conclusions
was not
initiated.
'Ihe incorrect assumptions
had not been identified by the
design verification process.
'Ihe licensee
s actions are discussed in
Section 3.1.4.
(4)
Two copies of the RG&E design analysis ~rting ERR 3689
<<Containment
Fan Cooler Air Flow,>> Rev. 0, dated June 4, 1984, were given to the team.
One contained handwritten notes and corrections,
the otter did not.
We
licensee stated that.the correct design analysis was the ane with
~
~
~
handwritten additians even though they had not been incozporated into a
new revisions
(5)
Rg&E design analysis su~rting XHR 4658~W09,
Minimun Diesel
!!
dated July 25, 1991, was poured to justify DG operas.ity with high
differential pressure
(dp) across the coolers due to zebra mussel tube
plugging.
The calculatians
were prepared based
an data fran the Gild~
and Associates Billof Material No. 216048 which did not use the
~licable design conditians, e.g., cooling water inlet tarperatuze
ard
heat load.
'Ihe incorrect design values resulted in incozzect assurptions
and results.
'Ihis calculation is further discussed in Section 3.1.2.4.
'Ihe licensee stated that all dcxxment deficiencies identified by the team
would be properly addressed
and corrected.
%he team identwfied items
(3) and
(5)
(above)
as instances in which the lack of ~~riate donunent control and
verification resulted in technically inadequate
analyses.
Ghe failure to
prcperly review and control engineering
documents is identified as Deficiency
No. 91-201-01 in 2gperxtu( A.
'Ihe absence of effective document control and verification for the above cases
indicated a lack of a~ion to detail in canplyirg with documentation
!!
!
situation,
based
on the licensee's
zeanalysis,
where these weaknesses
had
impaired the capability of the SHS to perform its safety function.
3.1.2
System 'Ihezmal-Hydraulic Design
3.1.2. 1 Hy:haulic Model
'Ihe licensee
had a fairly detailed hydraulic model of the SNS that was
developed by NUS Corporation to ~rt installation of a new SFERX
(EHR 1594).
Ihe team reviewed the hydraulic model and concluded that it was
relatively accurate for most of the process equi~t and piping.
9he major
limitation associated with the model was the limited anaunt of actual plant
data used to verify the fleer resistance.
For emcnple, the dp was!
re+At of a single resistance mxltiplication factor having been used for all
equipnent arxi piping which was too high a value for these coolers and other
heat exchangers
(see Section 3.1.2.4 for naze details) .
In response to these
findings, the licensee
informed the team that it was planning to upgrade the
hydraulic resistances
in the model associated with the major flee paths in the
safety-related portion of the SHS.
As a minizxnn, the licensee will detezmine
the actual f1m'nd pressure
drop for the flow paths thigh the Cps,
CCHHXs,
and
DG coolers,
and apply an appropriate resistance multiplication factor in
the model.
Me pressure
drop and flow data would then be used to adjust
actual system flaws by setting throttling system valves as a~ropriate. It is
the team's understanding that the licensee will submit a letter to NRC
outlining its plans and schedule for inpmvtng its flow model and ~lying
those zesults to actual system flow balancing.
this model and flow balancing
is Unresolved Item No. 91-201W2 in Agpendhc A.
lhe team reviewed the SNS flows with re@met to design-basis-accident
conditions.
The injection phase requires
one
SW pump and the recizculation
5
1
~
<
~
~
~
y
phase requiem two pumps.
Any sir@le
SW pump falling an SIS ccahined with
an undervoltage event is capable
(using anergency power) of supplying the
required cooling capacity to the CACs,
DG coolers,
and auxiliary f~ter
pumps during the injectian phase.
Two SW pzqps are required during the
recinulatian ~e because of the additional load of the (XRKs.
Par the two
phases,
the flaw di.~ibutian to the critical safety canpaoents
appeared to be
ackquate.
3.1.2.2
Ccapanent
Cooling Water Heat Zhzhangers
'Ihe team reviewed available design calculations,
a general assembly drawing of
the OCRHXs, and the proauenant
and verdor specificatians
and their
specification sheets.
'Xhe team noh'hat the proaument specification
(Westirghause Specification No. 676228) required the CORK to be designed
and
KY
Boiler and Pressure
Vessel
Oode Section III. Instead, the heat
exchanger
was designed
and marmfactured to the ASME Code Sectian VIII
requiranents
(vendor specification ~mt 54-Z-70135).
93m licen ae possessed
no documentation to support this code change, but stated that based
on the
original design phil~y, ASME Code Sectian VIIIwas appropriate for the
design of the OZRXs.
The code difference had been previously reviewed and
accepted by the NRC staff within the framework of its review of Systematic
Evaluation Prcxpam
(SEP) Topic III-1, "Classification of Stxuctures,
~nents,
and System."
'Ihe team performed independent sizing calculations of the CCNECs and concluded
that they were adequately sized.
Hal~er, at the normal flaw rates, there was
a potential for flaw-irduced vibratian.
Qhe team requited the maxim flaw
rates for the shell side of the
OCRHX to make an assessment
of the potential
for vibration-related tube damage.
%he licensee
was unable to pravide this
information.
'Ihis is Observation
No. 91-20103 in Appendix A.
~ team also observed that Bechtel-MJ Report No. 20031 arrived at a similar
conclusion regarding potential for flaw-irx2uced tube vibration and resulting
potential for tube deterioration due to fretting.
Ghe team concluded that the
licensee
had not given this report adequate attention
(see Section 3.1.1) .
Instead,
the licensee relied an a later ABB-Impell report
(No. 095~66~01),
which used simplified manual calculation methods ard did not identify the
potential for flaw-irxhmd tube vibration.
'Ihe team also reviewed the COAX eddy-c~nt inspectian procedure,
tube
plugging criteria, and tube pluggixg procedures
and found them acceI~le
except for nat irdicatmp an eddy~rrent testing frequency.
'Xhe licensee
stated that the CGA will be eddy-current-tested
every 10 years. ~ team
indicated that a 10-year eddy-cd~ testing frequency with no ather
inspections or observations in the interim may not be sufficient to pravide
adequate
warning of tube thinning or fretting caused by flaw-induced
vibration.
3.1.2.3
Spent Fuel Pool Heat Exchanger
'Ihe team reviewed available design calculations for the newly installed
SFRiX B, a general
assenibly drawing of the SFHKs A and B, and the procurement
4
I
5
I
IL
'
j4
~
~
I
~
and vendor specificatices
and associated specification sheets for both heat
exchange.
'Ihe team noted the follmring:
(1)
the procurement specificatian for SFFRX B (like that for SFHiX A)
II ~
fg
fabrication of the tube side.
Ihe verxhr's data sheet far SFFHX B
(Joseph Oat Oorporatian Job No. 2427) indicated that the heat e)zharx3er
I
. g
licensee pmvided additional design doaments to support that bath the
shell and the tube sides of the SF'
were designed
and manufactured to
be corrected accordingly.
9he team reviewed the additional evidence
and
found it acceptable.
I ~ I
provisions to permit easy disassembly of the tube hurdle for inspection
and cleaniLng of the shell side
(SNS side) of the tubes. ~ SFFHX B
I~I
gW
hurdle rival.
'Ihe licensee ~xmded that althm~ the SFRiX B had
provisions to allow shell and tube burxQe disassembly,
the original
design
(welded nozzle cannectians,
adjacent equignent) did not
specifically consider disassembly for cleaning. ~ licensee also stated
that if disassanbly for cleaning were required it could be performed,
albeit at a greater cost and effort to grind and ~d pipe cannections
atxi move adjacent equi~ent.
'Ihis was a~~le to the team.
'Ihe team performed independent sizing calculatians of the SFHK B arxl
concluded that it was adequately sized.
Hn~er, at the design flow rates
there was a potential for flew-induced vibration. ~ team also observed that
Bechtel-KHU Report No. 20031 arrived at a similar conclusian regarding
potential for flow-induced tube vibratian ard resulting potential for tube
deterioration due to fretting.
%he team concluded that the licensee had not
given this report adequate attention
(see ~on 3.1.1) .
Instead, the
licensee relied on a later ABB-spell report
(No. 095~66~01),
which used
simplified manual calculation methods and did not identify the potential for
flaw-induced tube vibration.
'Ihe team also reviewed the SF'ddy-current
inspection procedure,
tube
plugging criteria, arxl tube plugging procedures
and found them acceptable
except for not indicatirg an eddy-current testirg frequency. ~ licensee
stated that the SFERX will be eddy-current-tested
every 10 years. ~ team
indicated that a 10-year eddy-current testirg frequency with no ather
oections or cbservations in the interim may not be sufficient to provide
adequate
warning of tube thinning or fretting caused by flaw-induced
vibration.
'Ihe team noted that SF'
was no longer classified as safety related
follcaring the installation of SFERX B.
However,
SFFHX A remained a part of
the Section IIIpressure
boundary and served as a backup heat exchanger to
SFPHX B.
As such, it appears that SFFHX A should retain its safety-related
classification and be subject to the applicable code ard inspection
I
I
in Appendix A.
'L
~
1
~
~
~
BI
0
l~
If
~
~
~
3.1.2.4
Diesel Generator Coolers
~
~
~
~
~
~
~
~
~
~
~
'Ihe team reviewed available design calculaticas,
a geneva
assenhly drawing of
the
DG lubricating oil and jacket water coolers,
and the vendor specification
ard its specificatian st~.
%he team made the follawing absezvatians:
(1)
'Ihe calculation,
Minimm> Diesel Generator Jacket Cooler & Zube Oil
y
~ztirg ERR 4658~-009
was perfozmed to assess
the impact of changes
in SHS flow due to zebra nussel clogging an jacket water cooler
performance.
these calculations were based
on input data fnxn the
original Gilbert and Associates Bill of Material for the
DG coolers,
which g as already mentioned in Section
3 ~ 1 . 1, did not reflect the design
corxlitions.
For instance,
the SWS inlet tenperature to the oil cooler
should have been 80'F, not 75'F as used in the calculation.
Also, the
licensee
assumed that zebra mussel blockage decreased
SNS flaw to all
tubes uniformly without plugging any tubes in the first tube pass of
these two tube pass ooolers.
By assuming sane ccaplete tube blockage,
as
appeared
reasonable
on the basis of pictures of the actual zebra mussel
blockage,
heat transfer capability would have been rerhxxd.
(2)
The team noticed that the
DG coolers did nat have tube thinrung criteria
to irxhcate when tubes shauld be played.
'Ihe licensee develcped the
tube thinning criteria and gave the team an acceptable
preliminazy
analysis.
%he licensee
intended to formalize the analysis in the near
future.
'Ihe licensee also stated that both
DG coolers would be eddy-
currmt inspected
on an annual basis.
Gxtpletion of this analysis is
part of Observation No. 91-201M5 in Appendix A.
Me team performed independent sizing calculatians of the lubricating oil arxl
jacket water coolers ard concluded that both coolers ~~ed to be sized
adequately for the original design carditians.
Hater, at these conditions,
the jacket water cooler did nat appear to have any design mazgin. ~~fore,
any tube plugging at the design canditians would not be peanitted because the
heat transfer capability would not be sufficient.
However, at aperating
conditions, the heat duty recp.'unnnents
are less.
For example, at the worst-
case opemting conditions, the jacket water cooler's heat duty requirenents
would be reduced
(per the vendor's heat balance)
fran the design value of
3.924 MHIU/hr to only about 3.0 MHIU/hr rejected to the jacket water cooler.
'Ihis would allow the jacket water coolers to cperate with a limited number of
tubes plugged, either mechanically or by zebra mussels.
'Ihe licensee repeated
the jacket water coolers'perability calculations using the co~ data ard
assuming that zebra rmssels would block apprcochnately
66% to 764 (first tube
pass only) of the tubes in the jacket water cooler.
%he team reviewed the
prelimlunary calculations
and concluded that they were based
an oozzect design
parameters
arxl an adequate level of conservatism for design assumptions (i.e.,
numb'f tubes plugged) .
'Ihe licensee will formalize this calculation ard
amerd
(by adding an explanatozy note) or invalidate the original calculation.
Completion of this analysis is part of Gbsezvation
No. 91-20105 in
Appendix A.
In addition to zeviewing the design donunents,
the team reviewed the
~
~
~
~
administrative requirements for the pressure
drop (i.e., differential
pressure)
across the
DG coolers.
The licensee established
an adm:inistrative
8
L
~
I
~
~
~
1'.
~
~
>
~
~
~
limitof 25 psid across the coolers,
above which action would be taken to
reduce dp.
During the discussian of the pressure drop criteria, the team
noticed that the dp during ncemal cyeraticn was a~mimately 15 psid and was
thus excessive
when cxmpared with the original dp of 5.5 psid that was
required during the precperatianal test.
'Ihe licensee's first xespanse,
that
the increase in dp was largely due to the equipment deterioratica and the
resulting increase in resistance,
was qu~ianed further.
She licensee then
flaw to the
DG coolers were performed; the results
starved a flee of 526 to 556
d.>>.p>>
drop at 320 gran SHS fleer would have been approximately 5.5 psid.
'Ihe test
results indicated that the actual
SNS flaw to the
DG coolers during normal
plant operation was mxh higher than expected ard that this excessive flaw
acoomted for the unusually high dp.
She excessive
fleer to the DG coolers may
prevent scae other equipnent fran getting adequate flmr.
The licensee will
evaluate flmr to the
DG coolers and ather equi~nent as part of the plant data
gathering to cptimize the existing SNS hydraulic model and will adjust
throttle valves as necessary
(see Section 3.1.2).
Due is part of Unresolved
Item No. 91-20102 in Appendix A.
As a result of its design review of the
DG coolers, the team questioned
whether the coolers shmQd be included in the plant's thermal perfonnance
testing prcxp~.
We licensee stated that it would test thermal performance
an both sets of DG oil and jacket water coolers.
3.1.2.5
Contairnnent Air Coolers
'Ihe team reviewed the design analysis ard heat renaval capability of the
'
single
CAC heat renaval capabilities between
50 MBIU/hr (to canply with the
main steamline break analysis)
and 75 MBIU/hr (to canply with the loss-of-
n ~y
47 MBIU/hr, the value currently contained in the UFSAR.
About 1984, the
licensee determined that the CACs were not supplied with the full design
SNS
fleer since part of that fleer was used to cool the CAC fan motors (this fleer
had been previmaly negl~) .
this corditian was not fullycorrec~ in the
Updated Final Safety Analysis Report
(UFSAR) and was identified again in 1991
an9 docune~ted in Potential Oondition Adverse to Quality (PCAQ) Report No.91-048.
In response,
the licensee performed a reanalysis to determine that
the containment pressure integrity would nat be impaired by this diverted
f1m'.
'The reanalysis indicated that, the contairnnent pressure limit of 60 psig
would still be met in all cases,
but identified a number of cases
where heat
removal capability of a CAC would be less than 47 MBIU/hr. ~ reanalysis,
hemmer,
indicated that the contairnent would be subjected to a slightly
longer ard higher tenperature transient than originally determined.
Because
the contairnnent teaqxzature profile changed in oanparison with the original
profile, the team advised the licensee to include consideration of this charge
as part of an updated containment analysis to NRC.
'%he licensee will do so as
part of a licensing autxnittal to support a propo.-.ed barm concentration
mdification due in apprc0tunately
6 months.
%his is Observation No. 91-201-06
in 2gpendix A.
During the CAC design review, the team determined that the licensee had not
calculated condensate
drainage capability.
'Ihe licensee prepared preliminary
9
~
~
~
~
~
4
~
calculatians to subst mtiate that the drainage capability of the ChQs was
satisfactory. ~ team reviewed the calculations and cancluded that the
drainage capability of the coolers was adaymte.
%he team urderstood that the
licensee would formalize these preliminary calculations.
Oaapletion of this
calculatian is part of Obsexvatian No. 91-201W5 in ~ndhc A.
3.1.3
and Single-Failure Analysis
'Ihe team reviewed the system design as patented in the licensee's
UFSAR and
CF W~
conditions.
%he team identified the follawing vulnerabilities:
(1)
Currently, the
SWS has been operated in a czoss~nected
configuration
since 1988.
Ihis aligrunent could render the entire
SWS incperable during
an SI actuation if the discharge cia~ valve for cne of the
SW parries
failed to close upon system realignment so that, if the associated
pump
was not operating, water could be pumped in the ogxxsite dation
throogh the eke~ valve into the
SW intake bay. Its scenario was
identified, but not appropriately analyzed, in a single-failure report
(Altran report).
'Ihe licensee cxxrnitted to more ccNnpletely evaluate this
item, provide campensatozy
me;mures in the interim, and to review the
entire Altran report to ensure similar oversights did not occur.
'Ihis is
Unresolved Item No. 91-201W7 in ~rdix A.
Also, the safety evaluation
supporting the configuration change did nat cansider this failure.
(2)
'Ihe Ginna Technical Specifications
(TS) recp.dred two SW pe~ to be
opezable
(one fran each power train) .
However, the UESAR stated that two
SW punps are required for the recirculation phase following SI and, as
such, the TS were not consistent with the licensing basis when
considering potential single failures.
In its safety evaluation report
(SER) related to SEP Tcpic ZX-3, "Station Service and Cooling Water
Systems," dated Novenkxa 3, 1981, the NRC staff specifically requested
that the licensee address this vulnmahility.
'Ihe licensee had not
licensing basis is identified as Deficiency No. 91-201-08 in A~ndix A.
By metmzandum to the opemtians staff dated December 5, 1991, the
licensee
implemented adminiLstzative controls requizirg at least three
pumps to be curable while the cordition is being evaluated.
Although
this did not eliminate the sir@le-failure vulnerability, it provided an
increased level of confidence that the system would function during an
event.
Also, as a result of the team's concern, the licensee increased
its sensitivity to nuncving the fourth SW pump fran sexvice for extended
periods of time.
To resolve this issue, the licensee
was pursuing
denenstration that one-pump operation durirxy the recirculation phase
would be adequate.
If the licensee intends to support an~np operation
for the recirculation phase,
the updated containment analysis
(see
Section 3.1.2.5)
should also address
scenarios in which the CACs will not
be supplied with an adequate
design flow.
Determination of the
a~ropriate
number of pumps that should be operable as defined in the TS
will be addressed
by the staff in its assesanent
of SEP Topic IX-3.
Refer to Section 3.1.7 for further discussion.
10
(3) ~ SNS was originally aligned with the SW supply to the two DGs split
between the two SW loop hemhers.
Hammer, the alignment for the
supply to the DGs has been clanged to aperate with the cross~nnect
valves bet~ the two locp he.~rs
open. ~ canfiguratian makes both
DGs susceptible to a pipe crack in the safety-related
14-inch locp A
header supply piping.
%he team did nat find that a safety evaluatian had
been performed to assess this canfiguratian change.
(4)
During an SI actuatian,
non-safety-related
beakers are not autanatically
isolated unless thexe is a concurrent urxh~ltage canditian.
9hus,
a
pipe break in the non-safety-related
SW piping could starve safety-
related
SW loads.
I
A gasket failure an the discharge side of any punp cauld potentially
spray dawn all of the
SW punp motors, rendering all of the
SW pumps
inop~~le.
The NRC staff reviewed arxl accept
the SNS for Ginna urger SEP %epic IX-3.
Items (1) and
(3) arise because the current system canfiguratian is different
fran the configuration discussed in the SEP SER.
Item (2) was not fully
adchessed
by the licensee.
Item (4) arises because of the inaocuxacy in the
UFSAR and SEP SER regarding isolation on an SIS. ~se items alter the design
basis of the SNS as stated in the NRC staff's
dated November 3, 1981.
Refer to Sectian 3.1.7 for further dimxmsian.
3.1.4
Potential for Service Water Pump Overheatirg
%he team observed that a number of licensee reports and consultant analyses
(e.g., the p~mratianal test report,. BR 4232~
nSNS Punp Motor Studi
the NUS hydraulic report) indicated a potential for the
SW punps to overheat.
'Ihe licensee stated that this was nat a valid cancern because
(1) the
precperational report did nat identify the method of current measurement,
did
not address
motor efficiency, and did not indicate that motor voltage was a
measured value;
(2) the ENR 4232 analysis
was based
on an incorrect assunption
of lear slip for these actors;
and (3) the NUS hydraulic report repeated the
incorrect conclusions fern ERR 4232.
'Ihe licensee had been reviewing the
sizing requirements for an
SW pump/m~r assembly and was canctuctiag tests to
determine the maxhaun capacity of the motor (horsepaMm ard torque) .
Test
results reviewed durirg the inspection did not indicate a punp averheatmp
problem,
and the team concluded that the licensee
was addressing this issue
appropriately.
3.1.5
Heat Exchanger Heat Transfer Testing Prn ram
Action II of Generic letter
(GL) 89-13 requ~ that licensees
conduct a test
procp~ to verify the heat transfer capability of heat exchangers
cooled by
open-cycle
SNSs.
In its Service Water System Reliability Optimization Prawn
(STROP), the licensee canmitted to axplete heat transfer test~ in
accordance with the GL request
(includiLng frequency) for the CXRHXs, SFESX B,
the CACs, and the cooling units for the standby auxiliary f~ter pump zacan.
~
~
~
~
" During the ~mction, the licensee
added the
coolers to the heat transfer test program.
%he licensee had slightly delayed
11
I
~
'
t
al
't ~
~
~
~
4
its initiatian of the heat transfer test pnxgram and had nat satisfied the
schedule stated in the GL, but in sane instances,
the licensee had to install
tlat
1
b
team considered the delay a~Rable.
'lhe licensee's
SNSRDP stated that the ranaining heat exchamgrs that perform
a safety-related
functian would be opened ard inspected in accordance with
9 ~! i
performance testing.
Although the team agreed with this approach,
the
licensee had nat established
a sound basis for the preventive maintenance
frequencies for these heat em%angers. ~ is part of Observation
No. 91-20109 in Apperdix A.
3.1.6 Modification Review
%he team reviewed three modificatian padcages:
(1) MR 3316, 'Mditional
Analysis ard RxLification of Service Water Pumps";
(2)
ENR 2512, "Seianic
gq
%he doamantation
associated with these madificatians was satisfactory even
though:
(1) a number of the cansultant's
reports carrtained in the abave
modification packages
lacked proper review ard a~ance
by the licensee
Y
June
6,, 1984) ard
(2) the donnnent verificatian and control process
was
inadequate for ENR 3689 since the design analysis dated June 19, 1984, had not
been revised to include necessary
correctians.
Selected design documents
fram
ather modification packages,
e.g.,
ENR 4232 and MR 4658, were not adequate,
as discussed in Section 3.1.1.
3.1. 7
UFSAR Discrepancies
In evaluating the adequacy of sy ~n design, the team reviewed the UPSAR
description of the
SNS ard ax@ared it to the installed system. ~ following
discrepancies
were identified:
(1)
'Ihe UFSAR stated that the SNS locp is isolated by normally closed valves
to pravide two ardent sy.~ns with no sizable cross-connections.
We team fourd that, in fact, the SNS was normally cross-cannected
through the 14-inch supply header to the ChCs, ard that the system was
normally cross-connected
by the ~ly headers
(rxxunally 3-irish
diameter) for the equi@rent being supplied by the SNS.
(2)
'Ihe UFSAR stated that all of the engineered safety features equignent is
split between the two systenns
so that anly half of the equipnent would be
affected by a malfunction.
%he team fourd that the system was not being
operated
as a split, or divided, system because the crom-connect valves
were open.
Also, in the case of SW coolie to the thrust bearings for
the three SI pumps, it was nat possible to align the SNS so that ane loop
header pravided cooling to ane SI puap and the other locp beach'ravided
cooling to the ather two SI puris.
(3)
'Ihe UFSAR stated that the SNS is designed to isolate non-safety-related
loads on an SIS.
'Ihe team fourd that the non~fety-related
loads were
only isolated on an SIS coincident with an urdervoltage cordition.
12
(4)
UFSAR Table 9.2-2 did nat accurately reflect the total flow to the CACs
because it neglects the flaw to the CAC fan motors.
%he NRC staff reviewed the canfiguration ard the design of the SNS at Ginna
within the framework of the SEP urger Topic IX-3.
9he team ~uded that
staff aocx~ce of the design and canfiguratian of the Ginna SNS was baal,
in part, an the ability of the SNS to perfozm its function ard nat be
adv~y affected by a single active or passive failure.
Ihe following
system design features were recognized:
(1) nan-critical loads are
autamatically isolated following an SIS (did nat include isolation of the
CCNEM) and
(2) normal sy.~ alignment did not pexmit a single active or
passive failure to result in the loss of sexvice water flaw to redurdant
critical loads.
As discussed
above and in Section 3.1.3, the first corxKtion
was not satisfied by the SNS design and canfiguratian.
%he secard candition
has not been satisfied frcxn 1988 to the present
and also fran initial plant
cperation until sane undeterauned
time when the cross-tie valves were closed.
%he SEP review, ard the licensee after receiving the SEP SER, did not
~nize these ina~cies in the discussion of system design.
Ghe licensee
ccamnitted to svkxnit a letter to NRC identifying inaccuzacies in the staff's
As needed,
the staff will initiate further review of SEP Topic ZX-3
to address the inacxuzacies.
9he licensee s letter is Observation No. 91-
201-10 ard the UFSAR discrepancies
are Deficiency No. 91-201-11; both are
fourd in Apperdix A.
lhe licensee
was vezy re~mnsive in resolvinp the UFSAR discrepancies
identified by the team, either correctirg them in its Dexmnber 1991 UFSAR
update or irdicatirg that they would be corzeetex2 in the 1992 update.
3.1.8
Conclusions
'Ihe team concluded that. the licensee
was maintaining the SNS design in
accordance with licensing canmitments ard regulatory requirements with the .
exceptions of the deficiencies
and cbsezvations identified in the inspection.
Identified weaknesses
include failure to maintain an accurate
UFSAR consistent
with plant configuration, the lack of adequate cperability calculations for
the
DG jacket water cooler, the lack of cmpmhensive single failure analysis
of the
SW pump discharge
check valve, the irxnnsistmcy of TS with the sir@le
failure licensing basis,
ard the lack of adequate
documentation control.
Action IV of GL 89-13 requ~ that licensees
canfirm that the SNS will
perform its intended function in accordance with the licensixxy basis of the
plant.
the team's cbservations irdicate that the licensee's
review did not
identify those licensing basis items identified by the team ard thus did not
fully satisfy GL 89-13, Action IV. Gris is part of Obsexvation No. 91-201-09
in ApperxUx A.
~noghout the course of the inspection, the team corducted in-depth reviews
of available documentation,
system walkdowns,
and alternate calculations to
detezmine whether the SNS would perform its interxM safety functian.
'Ihe
i
review and corrective actions are necessazy:
13
1
~
~
(1)
%he licensee will reanalyze the SNS flaw balance to ensure that all
safety-related
equipment would be supplied with adecpate
fleer and then
apply results to the system (Section 3.1.2.1) .
(2)
Ghe licensee will analyze the single failure of a punp discharge check
valve.
In the interim, axrpensatazy
maasures (i.e., cyeratars
made aware
of this potential event,
a means of prcapt detectian develcped,
and
operator cxxnpensatoxy action indicated) willbe effected (Sectian 3.1.3) .
(3)
'Ihe licensee willestablish
based an minimum
(4)
%he licensee willprovide assurance that no additianal single failures
will affect system operation due to the cross-carmected
canfiguration
(Sectian 3.1.3) .
(5)
%he licensee will assess
the preopezatianal test results and perfoxm
te.~ as necmmary to canfixm adequate
system operation (~an 3.4.1),
alxl
(6)
'Ihe licensee will ensure that the appropriate
number of cyezable purtps
are included in the Mchnical Specifications
(Sectian 3.1.3) .
't
However,
we conclude that, with the interim actians taken for items
(2) and
(6), a presunption of operability is warranted while the issues
abave are
fully resolved.
3.2
Operations
Plant operations
were reviewed to assess
the knowledge of the cgerators
and
the accuracy and canpleteness
of procedures
and training they received
regarding the SNS.
In reviewing the operation of the SNS, the team performed
detailed system waDcdawns;
reviewed the procedures for normal, off-nozmal, and
emexgency corditions; assessed
the conduct of cpezations in the field and
control roam; and evaluated trainirg manuals
and lessan plans.
3.2.1
System Configuration Wal3cdcams
%he team conducted detailed walkdcams of the safety-related portions of the
i
(P&XCs)
(No. 33013-1250,
Sheets
1, 2, ard 3) ard the system lineup procedure,
T-36.1, "Station Service Cooling Watex-Re-der Valve Alignment for Two Zacp
Operation."
The safety-related portions were fourd to be aligned in
accordance with the procedure
and drawings. ~ averall system material
condition reflects its age of operation and its continuous exposure to a
fresh-water envirornnent ard surface condensation.
Unpainted, external
sections of piping systems were corroded,
having pitted or pocketed surfaces
and
metal loss.
Bodies of small, manually apemted valves, flanges, bolts, and
supports were rusting to varying decrees.
'Xhe extent of surface corrosion
reflected the lack of a dedicated preservation
pxogram.
Hmmver, due to the
lm energy nature of the SNS, the system did not appear to be degraded to the
extent that the averall operability would be affected.
One small, manually
opexated valve (V-12502, an SNS packing drain valve to the A and B circulating
14
~
I
~
~
r,
rr
f4
"gjf
r
~
s
~
water puaps)
was faund open with the valve stem ~nically frozen, contrary
to the positian specified in the lineup prcxxdure.
A flarxyxi joint in the
traveling scamn wash, system was leaking slightly.
'Ibese cancKtians have
minor safety significance and were previously identified by the lioensee.
Ghe drawings were detailed and accurate.
'Ihe alignment procedure was also
W
verification of valve positian was rectuired by signoffs thnmghout the
procedure
o
Individual caqmnents
were appropriately identified using calor~ded durable
plastic tags.
Six valve tags were missing,
and ane valve tag was wnzg
(V-4620 was tagged as V-4620A) .
Ihese dis~ancies
had nat been identified
by the licensee's staff during routine plant tours and inspections,
nor while
performinp surveillance or maintenance activities.
3.2.2 ~actions Procedures
'%he team reviewed varicvs procxxtures associated with the
SWS operations
including:
Overall Plant Opmzltians (0), Turbine Plant ~actions
(T),
Reactor Plant Systems Operatices
(S), Abnormal Procedures
(AP), Zhergency
yell
(
), ~ y~
(ECA), Functional Restoration
(FR), Equignent Re~ration
(ER), Site
Contingency
(SC), and Alarm Response
(AR) .
Overall, the majority of
y '~
.
In particular, definitive guidance was provided for locating valves whose
locations were not readily parent.
%he alarm-respanse
pzacechuas
accurately
agreed with annunciator tile labels and system setpoints.
Hcamver,
wealcnesses
were identified in certain procedures.
Specifically:
(1)
In step three of AP-SW.1, "Service Water Leak," operators
were directed
~ to initiate actions should
SWS homier pressure
be 40 psig or less.
'Shee
was no engineering basis for this setpoint; it was chosen as a best
estimate.
'Ihe licensee
was aware of this issue but had taken no action
until requested
by the team. ~ licensee planned to establish
an
a~ropriate 1m'-pressure setpoint based
on an assessnent
that system
loads would continue to be ~lied.
this item is Unresolved Item
No. 91-201-12 in Appendix A.
(2)
'Ihe required actions specified in ARM-9, "AuxiliaryFeed
Pump Cooling
Water Filter High Differential Pressure," in response to high dp on the
auxiliary feecheter
pump cuoling water filter did not identify by number
the valves to be operated.
'Ihe licensee prcxnptly changed the procedure
to identify the valves by number.
(3 )
AR I 17 g
Travel Screen High Differential Zavel 6"," and AR I 25 g "Travel
Screen Emergency High Differential Level 10"," were essentially the same
procedure in content and required actions.
Both procedures required only
that verifications be performed for the identified ~tion and relied
heavily on operator judgment for folio@up actions.
Ihe licensee
processed
changes to improve the p~ure,
inclucUing identifying
w>>* ~
.
Clw
the relevant procedure should additianal actions be necessary.
l
p
L.
t~
< ~
Por ~tians that caqxxmise a reliable source of SH, the team determined
I
actian levels.
9he procedure identified the diverse methods of measuring
water levels and graded responses
based
on level deczeases
that oat affect
the capabilities of plant cooling equipnent.
Actices included evaluating and
~ ~
I
I
I
I I
Implementing Pmcxxhue
(EPIP) 1-0, <<Gima Station Event Evaluation and
Classification," inplementing the applicable ecmxgency procedures
rechx-lng
pm~, ~~ing circulating water pux~, and shutt~ dawn the plant, if
necessaxy
o
3.2.3
Operator
Walkdawns
She team formally intexviewed several licensed senior reactor cyeratoxs,
reactor operators,
and nonlicensed auxiliary aperators
(ADs) to determine the
depth arxl scape of their technical krmrledge xegardirg routine operation of
the SNS, its role in accident mitigatian, and ~licable technical
/
Personnel
interviewed were knowledgeable recpu~ their specificI
F.
alignment and reconfiguration of the SNS during accident canditians.
'Ihese
personnel
were vezy aware of potential flew re.~ictian or plugging problems
that cauld result fnm zebra mussel grcmth.
Every faur hours,
ADs logged
differential pressure
real:bags
across
44 separate plant oarponents that are
~I
management to identify possible flew reduction fran zebra nussel claggirg.
'lhe team had operators walk through pnxxxiural steps,
perform specific tasks,
and explain their response
when implementing procedures
T-36.1, "Station
Service Water-Header Valve Alignment for Two Zaop Operatian<<;I AP-SW.1,
<<Sexvice Water Teak<<;
and ER-DG.2, "Alternate Cooling for the Bnergency Diesel
Generators."
In performing these procedures,
the operators
demonstrated
strict procedur~
adherence,
a sound knmrledge of canponent locations,
and the
skills necess-~ to operate the
SNS equignent.
When challenged by the team to
locate infrequently aperated
SNS valves on the plant's secorx3ary side,
operators readily found the valves using available resources,
including the
plant valve index,
P&IDs, ard associated
procedures.
Khnmgh observing the
operators,
the team concluded that the procedures
could be performed in a
timely manner and that SNS cxmponents were accessible for normal and emexgency
apemtion.
For a limited rabber of elevated valves that were anly accessible
by ladder, there were ladders staged near the valves.
Aft~ the team observed
performance of ER-DG.2, the licensee prcaaptly respanded to a team
renxmendation that two spanner wrenches,
rather than ane,
be available in DG
roam hose cabinets to assist
an operator in more quickly coupling/uncoupling
hose co~ions
when implementing ER-DG.2.
3.2.4
Operations Training
3.2.4.1
Txainirg Paxpmns
I I
I~
I
I
nonlicensed operators
were de.xxibed in the '%6&E Nuclear Training Manual" ard
<<RQ6Z Training Pxograns.<<these
manuals described in detail the training
16
~ I
~
process
and cantents of specific trainirx~ programs.
'Ibe opmatians training
pmclrMn had been accredited by the Institute of Nuclear Pea~ Operations
(INPO) .
Operatians training an the SNS consisted of classxaan,
simulator
scenarios,
in-plant training assignnents,
(JEAN) .
Separate
classman les.~ plans vere pzavtded far ADs and for licensed
operators.
Mesc lesson plans were sufficiently detailed, describing system
bJ,
p
Y
under emergency ccexhtians.
Licensed persannel also received classman
training on actians to be taken in the event of a loss of service water when
implementing AP-SW.1.
Qm simulator lesson plan dealt with the actians to be followed by control
roan personnel in the event of loss of sexvice water, inclu~ imxxHate and
elemental actions.
'Jhe simulator txaining allawed the operators to
experience
an SW leak and take actians to mitigate the event.
%he in-plant training assigrunent
allowed the operators to study the actions
necessary to pravide alternate cooling to the DGs (Pnxxdure ER-DG.2) .
would be necessaxy
should the
SW perps be unavailable to pzavide cooling to
the DGs when they were neared.
Performance of this task,
as athers,
was
measured using an ~zapriate JM.
'
Auxiliary Operator Qua1ification Stand ud.
'Xbe ADs
performance of actions
contained in various emergency cgerating and abnornel procxRures was measured
against six JMs.
Additionally, ADs were trained an the 'IS requiranents
applicable to the SNS.
Licensed cyeratozs were requalified yearly in
responding to a loss of sexvice water event and received refresher trains on
the
SNS every three years.
ADs received
SNS trainirg annually.
3.2.4.2
Training Materials
Lhe team reviewed
SNS training materials,
includ.'mg relevant lesson plans,
JEKs,
AO qualification standards,
and associated
procedures.
In additian to
describing the system operation and function for the various aperatianal
nedes,
the trainboy materials
emphasized
adherence to plant procedures
when
performing tasks affecting the SNS.
Accordingly, these procedures
weze
incorporated into the lesson plans.
Tzainirg materials were current,
adclzessing recent plant modifications and operational experiences.
Details on
zebra mussel infestation, installation of chlorination equipnmt,
and
replacement of the SNS discharge valve and elbmr for the
CCRHX during the 1991
refueling autage were presented to licen~nonlicensed
pezsonnel in a timely
manner.
Training materials were pnxnptly updated due, in part, to good cxxmunications
between plant departments
and the training organization.
In addition to
formal training change requests that cauld be submitted by plant departments
to improve an a~~ of training, curriculum canmittees,
such as the ane that
specifically addressed
the SNS, routinely met to evaluate and readjust
training content.
'Xhe SNS curriculum cxxnmittee was particulaxly effective in
ensuring that personnel
were receiving pex~ent subject matter with the
appropriate level of detail.
Involveae~ by the txaining ozganizatian in
daily plant planning meetings
and use of a cxmputerized networking system by
tzaining managers
and instre~zs to mmpmR to inquiries and suggestions
also
enhanced the timeliness of training materials.
17
~ ~
'0
)
A
~
t
t'
3.2.5
Canclusians
The team concluded that the aperaticas
axea was a strength.
Operators were
knowledgeable of normal and emergency
system operation,
cazpanent locatian,
Pp
WM i
ll
unresolved item was identified regarding subsitantMtian of an ~zyriate law-
pressure set~int for the system.
Action U of GL 89-13 asked licensees to canfixm that aperating prcredures
and
training involving the SNS is adequate to ensure that safety-related
equignent
cooled by SW will functian as intended and that aperators of this equipment
will perform effectively.
On the basis of its review of specific cperating
p~ures,
practices,
and training documentatian,
the team cancluded that
Action U regarding cperatians materials was agyrcpriately a~lished.
3. 3
Maintenance
p p
~p li
tl i~i
whether the SNS components
and piping were being adequately maintained to
ensure their operability and to detect system equi@Dent that required frequent
maintenance
personnel.
3.3.1
PronRures
l
procedures ~licable to the SHS ard associated
equipment.
'Xhese procedures
addressed
predictive, preventive,
and corrective maintenance activities; i.e.,
~ion and repair of pumps, motors,
and valves; lubrication and adjustrrent
of equipnent;
and periodic overhaul of active canponents.
Althoucg the
procedures generally were well written and sufficiently detailed,
mast did not
include clearly defined acceptance criteria.
The procedures
required that
after the work was finished; but, in most cases,
there were no acceptance
criteria included in the prceedure to detexrnine ifthe measuxed data fell
within the a~able
range.
For example,
Procedure N-11.34.1,
"Fan
Maintenance
and Inspection; Safety Injection Pump A," Rev. 7, did not include
quantitative data for a~ance criteria for bearing temperature
and
Inspection and Maintenance,"
Rev. 16, required that the final torque value of
the flanges be within +5 ft-lb.
Hcamver,
no final value of the torque was
given in the procedure
as an a~ance limit against which the specified
tolerance
was to be ~lied.
In Pnxxdure H-11.24, 'Main Feec~np ~mction
ard MainUMance," Rev. 8, the data sheet of Attachment
2 irdicated the factory
specifications for the pumps, but did not irdicate that these values were
mardatory for ~plding.
Procedure M-15.9, "Clean and Inspect
Jacket Water Coolers," Rev. 7, did nat contain any aoa~~ance criteria.
the licensee
had initiated a Maintenance
Procedure
Upgrade
Program in 1989 in
which such procedural
weaknesses
as the general lack of a~ance criteria
would be addressed.
The program was scheduled for ocapletian in 1994-1995.
18
3;3.2 Activities Observed
fl~
~
SNS Pump B - MicrIn~ion - Work Package
No. 914 1062
~
SNS Pump B - Breaker Inspection - Work Package
No. 914 0651
~
SNS Pump B Replace Packing Gland Studs - Work Package
No. 902 4081
~
SNS Pump D - Adjust Packing - Work Pa~
No. 910 2046
Overall, the tas)cs weze well planned, cantrolled, ard coozdinated. ~ work
p
.,
'~
hg~p
detailed aperatianal
review chec)Gist,
assuring that the release of specific
cxxnpranise plant safety; specific work instructians unique to the task
performed;
and a supporting department's
review check~eet.
'Ihe team noted
that for the activities obsezved
acceptance criteria were either contained in
P
NQ. tY
quality control department actively monitored and performed requisite
verifications thrnxpxut the obsexved tasks.
Pze-job and post-job briefings
t
as-found and as-left equipmnt condition were terse praviding limited
information to the maintenance analyst during subsequent
review.
Hold tags were properly enployed,
and good procedure adherence
was cbsezved
with technicians
signirx~ off~ as they wexe cxepleted.
Post~intenance
testing was a~zopriately performed when specified.
Technicians were
adequately trained and demonstrated
the skills required to perfozm the
maintenance task.
Me team did observe
a casual
approach to a safety practice
in which technicians
who were helping an electrician install a brealmr in a
480 V bus entered the cabinet without wearing protective glaves.
Mhen this
was pointed out, the licensee took agprcpriate corrective action.
and co~ive maintenance
(CH) actians for the SNS and related systems.
Khese were reviewed to determine the rationale and ahxpxacy of the bases of EK
requirements
and effectiveness of CR activities.
In its review of SNS
activities, the team did not identify any recurrent equi~ent failures or
prcblems due to inadequate
CN.
Hm~er, the team was unable to establish
and
verify the basis for required W frequencies
on pumps, valves,
and motors.
'Ihe team determined that there was no fozmal structured program to tzerd the
adequacy
and effectiveness of recpured
XKs ard CÃs in the area of mechanical
equipnent.
'lhe original M program, which was berg replaced by a
reliability-centered maintenance
(RCM) procpmn,
was developed
an the basis of
individual engineering judgment.
In the area of electrical equipnent,
a
formal tze~
pzocpmn existed to trend the performance of electrical
breakers
and correlate the perfozmance to maintenance activities.
Hm~er,
motors and other rotating equipment were not cavered by a formal trending
program.
%he electrical maintenance
analysts informally created
and
maintained the equipnent hi.~ries to identify any apparent trends;
hcamver,
there was no formal policy guidance in this area.
19
~
~
y
reference,
but detexmiLning an apparent trend fran this data base zequhxrl a
1
.I
!&K
q
analyzed,
and correlated
equ~lpnerrt histary data fran the beginning of service
to 1987.
No formal program had been established within the RCH program to
continue the trending of equi~ant performance to assess
the effectiveness
ard
9 i;,
I
had not been implemented at the time of the in~ian.
As an example of the KR program nat appropriately incorporating data
P
trending proc'or vibration analysis.
Hanover, the vibration masuranents
on the
SW pump motors were nat able to show a trend of vtbratian changes aver
a period of time because the cbtained data anly reflected whether or not
'
t
%he licensee represmtatives
stated that there was a plan to consider and
develop a ocxnprehensive trencting program in the area of machanical equignent
ard to enlarge the scca of the electrical equipnent trenching procj~n.
(~y )f
tt
I
3
for the
SW pumps (except pm@ D which recpured major motor repair) cansisted
mainly of inspections,
averhauls,
and packing adjustamts.
Host activities
for the
DG lube oil ard jacket water coolers cansisted of inspections ard
cleaning.
%he CACs ard their fan nestor coolers eqmrienced leaks whiW
required tube plug maintenance,
patckurg,
and scrne replacement of coils.
Ihe
licensee
had recxgnized the prcblem of leaks and instituted a
repair/replacement
program for these ocaponents until they could be replaced.
Valves experienced
expected age-related
decpadation,
and no sir@le valve had a
significant amount of maintenance.
Despite the lack of a formal maintenance
trending proctram, the work orders reviewed did nat indicate evidence of any
recurring problems or trends that were not being addressed
by the licensee.
3.3.4
Training
lhe training procJram for Ehanical mainbmance personnel
was described by
Procedure
TRC.9
s'Mechanical Maintenance Personnel Training Procgam,<< ~.
3
'Ihe training program
agape +ed rigorous and thorough.
Xhe ~noedure
was
intended for training a new employee with basic education and ability to
became
a journeyman craftsman through structured classrocxn lectures ard
practical on-the-job trainirg.
%he program was divided into ~es with
specific time periods,
learning objectives,
and skill attainment goals.
Achievement of these goals was measured
by objective euuninations ard
assessments
at predetermined milestones.
%he specific academic or skill
coume modules were established with adequate
course content and learning
objectives.
%he lesson plans, tests,
job performamx. measures,
and other
training materials were adequately used by instnmtors during classes.
In addition, a program of continu~ education ard skill maintermme was
implemented to refresh and strengthen the skill and expertise of journ~man-
level personnel.
%his program enghasized the developM.nt of atMitianal skills
specifically identified through plant equipnent history, irdustxy experiences,
20
~
~
I
Ill
,L
I
and new pmctuct develegnent in the industxy.
Ghe licensee's policies ensured
general refresher course annually and ~ved any special training on an as-
n~ basis.
q~li
I
4H
I
was adequate to ensure that safety-related
equignent cooled by sexvice water
W
program and other efforts in this area were vexy good and axe ccmsidered
a
Wt.BJ~
I
appropriately accanplished.
3.3. 5
System Unavailability
~ unavailability of major SWS caqxments
was calculated for use as
statistical data in prababilistic risk assesstnent
(PBA) reviews ard to assess
the safety effects of remcving equipnent fran service.
Because Ginna's
SHS
contained several cross-ties
between redundant equi~ent, entire headers
were
not taken aut of service for maintenance
on a canponent.
Kherefore, the team
focused on the unavailability of the
SW pumps.
Out of service toms were
collected frcm equipnent hold records,
maintenance
work reports,
and limiting-
conDition-for-c~ration
(?CO) control reports for the period August 1989 to
Septenher
1991.
'Ihe team also included punp surveillance te.~ in the aut-
of sexvice time since the test removed the system fran its normal accident
alignment.
'Ihe calculated unavailability of ane of the four pumps during
palmr operation was 27%.
KtMrefoxe,
73% of the time the sy ~n was operating
with four SW pumps available.
Ihe individual pmp unavailabilities were:
pump A
1
9% g pump B
13 ~ 9% ~ pump C
1 3% g and pump D
9
8%
Because
current TS only required that two of the four pushes be operable,
the licensee
performed the majority of maintenance
during power operation, including
reaaving a single pump for lcnp-texm maintenance.
'Ihe team considered this
policy unconservative in view of its finding ~rhine the need for more than
two pumps to be operable,
as discussed in Section 3.1.3, ard requested that
the licensee ~~luate its scheduling practices for larg-texm pump
maintenance
during plant cperation.
'Ihis is CR~exvation No. 91-201-13 in
AppencUx A.
Unavailability of the
DG coolers and CACs due to maintenance or
cleardzx~ on the
SW side of the heat mcchangers
was very law:
0.1W.34 for the
DG coolers and 0-0.14 for each of the CACs.
'Ihe licensee
was in the process of developing its ERA at the time of the
~ion.
In response to the team's concerns regarding equignent out of
service for surveillance ard the need for more than two pumps to be operable,
the licensee revised its HQ. to explicitly model the potential of pumps being
unavailable due to testing and to evaluate the impact of requiring three
pumps to be cpmwble.
3.3. 6
Conclusions
Ihe team concluded that the mairrtenance
program related to the
SWS was
procedures
were well written and canprehensive.
%he documentatian of
completed work was available and clear,
and the maintenance
pexsanne1
were
knowledgeable of procedures
and equignent in the plant.
No ocncerns were
identified during the cbsexvation of maintenance activities.
9he maintenance
21
I
i
ll
p
~'~~
strength.
%here was no structured txendirg program to assess
the adequacy of
M fzequencies
and to deterndae asap~ event degradaticn;
hmmver,
no
unidentified trends were found. ~ team identified an umxnsezvative
~
E- ~~d
&pp
operation.
3.4
Surveillance and Testirg
Surveillance and testing were inspect@6 to detexmine if sufficient testirg had
Cf
t ~
'
periodic suzveillance
and insexvice testing
(IST) wexe adequate to maintain
continued cperability of the system.
In this regard, the team reviewed
p~mrational test procedures
and cmpleted surveillance procedures.
Ghe
team also reviewed the licensee's
IST pxogram and implementing pzacechues.
3.4.1
Precperational
Testing
Preopezational testing of the SNS was ccapleted at Ginna in accordance with
Procedure
SU-4. 17
"House Sexvice Water," dated November 1, 1968.
She team's
review of the campleted precperational test procedure
focused primarily an the
test scope,
methodology,
and results.
'Ihe Ginna
SWS preogexational test was ccxrpleted between May and August 1969,
and the quality of the p~uxe and documented test results reflected the
less-rigorous
standards in effect at that time.
For exanple,
documentation of
system alignment and test data was not rigozms,
a test dier's log was not
maintained,
and a fozmal record of review and a~ance
of the test zesults
was not maintained.
During its review of the Ginna precpmatianal testing, the team made the
follmring observations:
MF
l~ capacity would meet the min:imun fleer requQ~nts for safeguard
operation given the system configuration resulting fran an SIS.
%he
actual test was performed with non-safety-related
loads isolated,
which
was inconsistent with the system alignment for SI actuation.
(2)
Me test did not evaluate sy~ vulnerability to punp runout conchtions.
(3)
Lhe system f1m'alance
was est'ablished
an the basis of three pumps
operating, rather than an the worst-case candition of ane pump operating
and supplyirg all safety-related
and non-safety-related
loads.
(4)
Although two pumps were required to handle the postaccident
decay heat
load, various cambinations of two-pump operation were not tested.
'lhe team concluded that the pzecperatianal test did nat fully dananstzate
that
the
SWS at Ginna could perform its functian during all pa.~lated conditions.
dpW U~
h
pt
substantiate
one-pump cperation during the recirculation phase.
On the basis
of these ~sments,
additional testing may be neechd to support operation in
22
~
~
0
IH,
I*
required system canfiguratians.
%his is Deficiency No. 91-201-14 in
Appendix A.
3.4.2
Surveillance Procedures
4d
1
most part, were limited to valve alignment and punp operability verification,
and insexvice testing of purrps and valves (discussed in Secticn 3.4.3) .
The
W
iW
found that, in general, the procedures
were well written and a~lished
their stated cbjectives.
However, the team also found that intecjrated system
testing per BSSP-2.1,
"Safety Injection Functianal Test," and RSSP
2 2g
"Diesel Generator
Zaad and Safecpmxd Sequence Test," did nat fullytest the
contxol cirn6txy for the
SW pmrps.
Specifically:
{1)
Each
SW pump selector switch (one each for tx~ A and train B) se1ects
one of two pumps to start an an SIS (i.e., twa~iticn switch) .
Testing
was not coordinated to ensure that each of the
SW puap selector switches
.
was test in both switch positions.
(2)
Testing was not performed to ensure that the
SW punp selector switches
were not shorted between the two switch positions.
A short be~mn the
two switch positions would allow two SW pumps to be loaded an a single
during an SI actuation coincident with an unck~~ltage condition.
The licensee planned to revise its procure to actress
item (1) and was
evaluating resolution to item (2) .
3.4.3
Insexvice Testing of Pumps and Valves
'?he team found the licensee's
insexvioe testing
(IST) pxogram for SNS pumps
and valves to be generally cxxnplete, in cxxrpliance with ASME Code Sectian XI,
and adecpmte for detezauning the operability of the systeun.
'Ihe team reviewed
the licensee's
program dated June 7, 1991, ard verified that all requixM SNS
valves and punys were included and that proper suxveillance intervcQ.s were
WW
and VR-17 pertaining to disassembly
and inspection of the pump discharge
check
valves,
had been approved on an interim basis.
Ihe team reviewed the
procedures for alternate testing and deterauned that VR-17 was acceptable
as
it ccmplied with the zecp.urenents
outlined in the staff's safety evaluation
approving the program.
'Bm staff granted interim relief for EB-7 based
an the ability of the licensee
to shee that reputable
and mearuLngful pump test data could be obtained by
measuring flew at the CACs rather than at the outlet of the pur~.
%he
procedure required obtaining a flow reading of 1100 gran in each
CAC line while
isolating all other loads except the
DG coolers.
%he team questioned whether
this method established
repeatable test conditions since
SW flow thxough the
DGs was not measured.
At the time of the inspection, the licensee
was
implementing a nedification which would allow it to measure the flow at the
outlet of each pump, providing more accurate test data and eliminating the
need to isolate loads.
The licensee also had available portable test
equipnent which, if used in a repeatable
manner,
would eliminate the question
regarding the current test method.
23
~
1
I
~'I
ip
X)1
(
~
(
~
'Ihe team reviewed the following prcma9ure. relating to SNS testing:
PZ-2.7,
nSexvt.ce Water System)i
~ ET 36Q
nStandby AuxiliaryF~ter Systems
~
PT 2 10 11 g
Sexvioe Water System RsQUndant Discharge Line BcBxcising
g aIxl
M-37.142, 'V-4601, 4602,
4603,
4604 Disassembly."
9'rocedures
cantained
clear ard sufficient preparatian
and realignment steps,
acceptance criteria,
ard specific responsibilities
and qualificatians of test perscenel.
'Ihe team reviewed records of test results and found that the licensee trended
results for each car@anent to det~ degradatian;
recenfirmed reference values
dp
verified that new reference values represented a~able
cperation.
When
test data exceeded limits, the licensee increased the test frequency.
%he
licensee
had established
a policy of returning to regular testing frequency
after entering an alert rarge whenever two consecutive
normal te.~ were run.
13m team was concerned that this practice cauld result in equignent
degradation going unchecked. ~ team observed a case in which vibration
me-cerements for an
SW pump were in the alert range for appvmimately two
months.
When the vibratian zetxuned to the normal range, the licensee
returned to the recpQar testing frequency per plant policy despite the fact
that no maintenance
had been performed or cause determined as directed by ASHE
Code Section XI, Article IWP-3230.
%his issue is scxrewhat mitigated because
the licensee teats these
pumps mere often than required by the oode.
'Ihe team found that the licensee did nat enter ICOs during IST since it did
nat consider the equignent being tested to be aut of service.
Nat entering an
ICO allied the licensee to take redundant equignent out of service
simultaneously with IST.
%he IST of the
SW ~m recpdred that the system be
aligned differently fran its normal accident lineup.
Since marMal actians
would be required to return the system to its co~ aligrunent upon an SIS,
the team could not conclude that the train being tested was available to
perform its safety function for the period of the test.
Ibis candition
existed for several surveillance tests,
inclucUiag that for the contairnnent
spray pump in which the test would clearly disable the system.
Ghe team
questioned this practice and was oancerned
about the lack of procedures to
ensure that redundant equipnent would not be taken out of service while the
companion equipnent is undergoing testing.
She licensee stated that it would
reevaluate its testirg policy. ~ is Unresolved Item No. 91-201-15 in
Appendix A.
3.4.4
Piping and Canponent Inspectians
Action IIIof GL 89-13 requested that licensees establish
a routine inspection
and maintenance
program for cyen-cycle
SNS piping and cmponents to ensure
that corrosion, erosion, protective coating failure, silting, and biofouling
cannot degrade the performance of the safety-related
systems supplied by SW.
'The team reviewed the licensee's
SHSROP and implementing procedures
and
concluded that the licensee's
program for routine inspection and maintenance
of piping and ccanponents did nat satisfy the action requested by the GL.
More
specifically, the team identified the following we Qmesses:
(1)
Although the licensee had procedures in place for disassembly
and
inspection of certain oarponents,
measures
were nat taken to ensure that
24
J
~
~
the population of ~xeents being inspected
was acaplete
arxl that the
frequency of inspection was adequate.
(2)
'Ihe licensee
had nat included in its program any periodic inspection
Itb
instrunant lines were nat degraded.
(3)
Program elarents
were not established
and tzaiz~ was nat provided to
I~
ard operating activities, ard that apprcpriate follawup actions would be
taken upon di:~vexy of zebra mussel debris.
In response to the team's obu~tions, the licensee agreed to review its
SNSROP and to make changes
as ~rcpriate to better address the GL actions.
'Ihis is part of Observation No. 91-201~ in Appendix A.
3.4. 5 Biofauling Ccrdxal and Ru~illance During Systen Operatian
Action I of GL 89-13 requested that licensees
implement and mairrtain an
ongoing program of surveillance ard control techniques to significantly reduce
the incidence of flaw blockage prcblens as a result of biofauling.
%he GL
also requested that licensees in~ their intake structures during each
refuelirg outage and remove any accumQations of macroscopic biological
gmwth.
%he team reviewed the licensee's
SNSRQP and implementing procedures
and
concluded that the licensee's
program for in~ing the intake!~~~
during each refueling outage was a~able.
%he team also found that the
licensee
was age ressively inpleaM nting chlorination practices to the extent
allowed by envirorunental restrictians.
Hm~er, ~ropriate actions were not
defined to ensure that infrequently used loops and stagnant areas,
such as the
alternate discharge to Deer Creek, the
SNS ~lies to the auxiliary feaster
and stardby auxiliary feedwater sy.~-, the SNS ~ly to the
DG cooling
water expansion tank, and isolated heMer piping, would not berne clogged.
areas.
Also, the licensee
s SNSROP did not specifically define when system
layup would be required and layup procedures
were not established per the GL
request.
%he licensee
agreed to review its SNSRDP and make changes
as
appropriate to better adams the acticns requested by the GL.
'this is part
of Olmervation No. 91-201~ in A~dix A.
3.4.6
Conclusions
In general,
the team concluded that the lioensee's
performance in the area of
surveillance
and testing was satisfactory.
However, the team found that
certain impravements cauld be made to surveillance procedures to help ensure
the operability of the
SW pumps.
'Ihe team also found that cmMin
impravements in the licensee's
SNAB were necessary to more adequately
a&bess Actions I and IIIof GL 89-13.
Also, on the basis of its review of
the p~xzational test data, the team faurd that system flaw balancing,
and
possibly additional testing, is warranted.
A concern was identified regarding
the practice of nat entering an ZCO and taking redm9ant equignent cut of
service simultaneously.
25
~
~
p
~
r'
3.5 Quality Assurance
and Oarrective Acticas
3.5.1
Root-Cause Evaluations
'Ihe team reviewed a list of entries into the Nuclear Plant Reliability Data
System
(NHKG) related to the
SWS at Ginna.
Ghese entries
reacceded
specific
cxmponent failures back to 1970.
~me were 26 SWS-related failure reports in
the list.
'Xhe zeviev of the root causes
contained in these reports appe~ued
to be adequate,
but thexe was no documentation available to indicate the
proces used for zoot~use detern~ticn or to establish the validity of the
zoot cause itself.
In many cases,
the root cause indicated was a simple statement that the
failure was due to normal service wear.
In the case of two sucomsive
pump
mator failures for SW pump D, the first cause
was listed as "unknown."
%he
pump D actor repair was performed by Reliance Electric.
2gpzaximately three
months after repair, the motor failed a seoced time.
%he vendor determined
that the second mator failed because of service loading (avexvoltage)
an the
gator beyord its design ratings.
She licensee,
however, disagreed with this
conclusion and, in the fall of 1990, provided data to Reliance Electric to
support its contention that the puap motor failure had not been caused by
ovexvoltage.
However, na documentatian
was provided to shaw that the zoot
cause of the failure had been detaradned
by the end of the inspection.
In
addition to the lack of a donanented root cause detexrnination, the failure
analysis
and zepair of this mator was performed without ooxrective action
reports
(CARs) because
the licensee's
program required initiation of a CAR
only in the case of a "significant" cordition adverse to quality; the licensee
did not consider this failure significant.
%he licensee
was develcping a procedure, with a March 1992 implertentation
schedule, to formalize the root~use analysis process.
9he draft procedure
included a structured formal process for initiatirg arxl docunenting zoat-
cause analyses for "significant ~tians adverse to quality," but the
process would not be mandatoxy for any conchtion that would nat be deemed
significant.
'Ihis was a weakness in the prcpcmed pzogzam because
a condition
that may nat initiallyappar to be significant may be found to be significant
when the root-cause is detexmined.
In the area of co~ive actions, the team found that the licensee's
corrective actions for identified deficiencies
and problems had been generally
effective.
'lhe corrective action implemented for failure of circuit breaker
DB-25 was an mamtple of effective ard extensive corrective action.
3.5.2
Comparison of Findings
In ccmparing its firxhngs to the licensee's
awn assessment
of system status,
the team found areas in which the licensee
had nat identified or resolved
items the team had noted.
For example, the potential of a single failure of
an
SW pump discharge
chec3c valve should have been zecxxpu.zed and addressed
as
part of the licensee's
evaluation in zespanse to GL 89-13.
Qhe licensee
should also have been alerted to this condition by the Altxan single-failuxe
report.
She lack of thorough reviev of the Altran report was an illustration
of the team's finding regarding inadequate
document control.
A 1989 NRC
mction recagnized the lack of engineering assurance
as a weakness.
26
~
~
~
~
I
I'
Holmver,
a Decanber
1990 selfmudit of the document ocetml pmcess
("Audit of
Ginna Configuration and Document Control") did not.
Another finding of the
team involving discrepancies
bedpan the UPBEAR description ard actual system
design was not identified by the licensee until October 1991 in a PCAQ report
(No. 91047) which recognized that the UFSAR was incorrect in stating that the
train cd-cannect valves were closed.
'Ihe team's cbservation that the root-cause analysis
and maintenance trending
programs were weak was also identified by the licx~~a in its 1990 Quality
management
evaluate the co~ive actian system to eliminate ccanplexities,
unify all sources of trerding data,
and use the system to eliminate prcblems
rather than as a tracking system.
She recaanerdatians
had not been acted upon
to date.
Nalkdawns corducteD by the team revealed scaa missing or inaccurate
tags ard bent valve stems.
'Ihe fact that these were not faund by the licensee
irdicated that the routine plant tours and inspections by plant personnel
were
not fully effective.
3.5. 3
Conclusions
On the basis of the inspectian findings, the team concluded that the licensee
did not have an approved and structured root~use evaluatian program.
Although the corrective actions implemer~ for identified problem appeared
adequate,
there was a lack of objective docunentatian to establish the
evaluation process
arxl the depth of evaluatian.
%he licensee,
however,
was in
the process of developing a more statured root~use evaluatian prcxpam,
which may improve the process.
lhe team identified certain issues that the
licensee either had not identified, or if identified, had not acted upon.
4. 0
EXIT M&1'ING
On Decetnber 20,
1991, the team conducted
an exit meeting at the Ginna Nuclear
~ Station.
NRC and licensee personnel atterding this meeting are listed
in Apperdix B.
'Ihe licensee did not identify as proprietary any materials
given to the insIxation team.
During the exit meeting, the team sunanarized
the scope ard findings of the inspectian.
27
~'
APE%ÃDIX A
SUt%ARY OF INSPKCTICN FINDINGS
CZE8CY
.
- 0 Wl
(Section 3.1.1)
DescTi
ion of Conchtion:
During its review, the team noted that the licensee
was not properly
controlling, verifying, and a~ing design reports, calculations, or
analyses.
For example,
'Ihe NUS Corporation calculation supporting Engineering Work Ra~st
(ERR)
1594, "Hydraulic Analysis of the Sexvice Water System," dated February
1988 g was suhaLtted to the licensee marked "preliminaxy, for review and
caament" in March 1988.
As of December
1991, the analysis had not been
reviewed and accepted by the licensee,
but was being used for hydraulic
analysis
and balancing of the SNS follawiing installatian of SF'.
(2)
Bechtel-KHU Report, 'Beat Zaad Capacity/Design Margin Analysis for RHRHX,
CCRHX, SF%Kg Non-Regenerative
HX," Job No. 20031,
1g dated
January
22,
1989, did not have any indication that it had been reviewed
ard accepted
as required by the licensee's Quality Assurance Manual, Rev.
13, dated Navenher 1, 1986.
(3)
(4)
Rochester
Gas ard Electric Corporatian
(RG&E) design analysis document
entitled "Insitu Motor Zaad Determinations" for ERR 4232,
"SWS Pump Motor
Studies," dated July 15, 1986, included incorrect assumptians
based
on a
low slip motor and ~rcpriate equations.
Consequently,
the results
were also inca~.
'Ihe licensee had known this for moxa than a year:
however, action to revise the calculation and conclusions
was not
initiated.
'Ihe incorrect assumptions
had not been identified by the
design verification process.
Two copies of the RG&E design analysis for SR 3689,
"Containment Fan
Cooler Air Flaw," Rev. 0, dated June 4, 1984, were given to the team.
One contained handwritten notes and correctians,
the other did not.
licensee stated that the correct design analysis
was the ane with
handwritten additions even though they had not been incorporated into a
new revision.
(5)
RG&E design analysis for ERR 4658~-009,
"Minimm Diesel Generator
Cooler and tube Oil Cooler Water Flow Requirmants,"
Rev.
0, dated
July 25, 1991,
was prep-wed to justify DG ~~iilitywith high
differential pressure
(dp) across the coolers due to zebra musel tube
plugging.
%he calculatians
were prepare based an data fran the Gilbert
and Associates Bill of Material No. 216048 which did not use the
applicable design conditions, e.g., cooling water inlet tenyexature
arxl
A-1
g A
C
t
Y4
h,
heat load.
%he incorrect design values resulted in incorrect assumptions
and results.
the team identified items
(3) and
(5)
(abave)
as instances in erich the lack
of appropriate
document control and verification resulted in technically
inadequate
analyses.
BRQtRS
Ginna QMlityAssurance Hanual, Sectian 3, <<Configuration Control," Rev. 13/
dated Novemkmr 1, 1986, states in Section 3.4.3,
"Design Verification," <<The
design verification shall assure that the design outputs (i.e., drawirgs,
analysis arxl specifications)
including design outputs fran equi~M nt y~ y
apped. <<Section 3.4.4, <<Interface Gantrol," states that interface
procedures
between
RG&E engineering
and carrtractor eng~ing organizations
shall include <<instructians regarding the canted:s of docutnent transau.ttals
9
docenents shall identify the status of the docenents
and identify, where
necessary,
inccaplete items which require further evaluation,
review, or
~roval."
10 CFR 50, ApperxRuc B, Criterian III, "Design Control,<<requiresg
in partI
that '94easures
shall be established for the identification m9 control of
design interfaces
and for coordination
among participating design
organizations.
~me measures shall include the establistmant of p~ures
among participating design organizatians for the review, appraval,
release,
distribution, and revision of docunents involving design interfaces.
%he
design control measures shall provide for verifying or cheaking the adequacy
of design,
such as by the performance of design reviews."
10 CFR 50, Appendix B, Criterion VI, <<Docuaant Contmlg
requires
in part,
that 'measures
shall be established to control the issuance of documents,
such
as instructions, p~ures
and drawings, including changes thereto,
which
prescribe all activities affecting quality.
these measures shall ensure that
doaments,
including cbees,
are reviewed for adequacy
and appraved for
release by authorized personnel..."
~ferences:
None
A-2
s
ind
3.1.2.4)
i
ion of Condition:
of SNS Hphaulic Model (Sections 3.1.2.1 and
%he team reviewed the SNS hydraulic mxhl developed by NUS Oorporatian in
~rt of EWR 1594 and ~uded that it was relatively accurate for most of
the process
equipment
and piping.
%be major limitatian associated with the
model was the limited amount of actual plant data used to verify the flmr
resistance.
For example, the differential pressure
was av~imated
and the
fleer rate was underestimated for the
DG coolers as a result of using an
ezzoneously high zesistance miLtiplication factor for all egui~ent and
piping.
In response to these fixxUirgs, the licensee informed the team that it
was planning to upcpade the hydraulic zesistances
associated with the major
fleer paths in the safety-related portion of the SWS.
As a muumum, the
licensee caamitted to detezxaine the actual floe and pressure'drop for the flmr '"
paths through the CACs,
CCWHXs, ar6 DG coolers,
and to ~ly an apprcpriate
resistance multiplication factor in the model.
Ihe pressure
drop and flew
data would then be used to adjust actual system flows by setting throttling
system valves as appropriate.
'Ibe licensee caanitted to su?xnit a letter to
NRC outlining its plans and schedule for impzavirg its flmr mocha. and applying
those results to actual system flow balancing.
BRAGI
~
~
~
~
~
~
~
~
Ginna Technical Specification 3.3.4,
"Sezvice Water System," mcpxires, in
part, that at least two sezvice water puaps and one locp header be operable.
Reference:
1.
'lhe NUS Corporation calculation,
"Hydraulic Analysis of the Sezvice Water
System," dated Februazy
1988 ~zting ERR 1594.
A-3
I
4
I
0
~
~
~
~
~
~
3
Find'itle:
Oarponent Cooling Water Heat Exchanger Vibration Potential
(Section 3.1.2.2)
i
ian of
%he team identified that at normal flmr rates through its shell side, the
cxxnponent cooling water heat exchangers
(OCMHXs) were susceptible to flow-
induced vibration which could result in tube deterioratian
due to fretting.
Bechtel-KHU Report No. 20031 arrived at a similar canclusian. ~ team
requested the sexual
OCHHX shellmide flaw rate to assess
the flaw-induced
vibration potential at flaw rates
above normal.
this informatian was not
provided to the team,
and the licensee
had nat deteradumd the maxirum flaw
rates nor assessed
whether a greater potential for flow-irx'b.red vibration
ex1sts
~
ference:
1.
Bechtel-MJ Report No. 20031, %eat Load Capacity/Design Margin Analysis
for RHRHX,
OCMHX, SF&K," dated Januazy
22, 1989.
A-4
ii i
~-
W
Safety-Related
(Section 3.1.2. 3)
'on of~ti
'Ihe licenc~ installed a second spent fuel pool heat exctmnger
(SFBK B) and
in dairy so relegated
SFRK A to sexving a backup function.
ikrwever, this
heat mxhanger was not isolated and cantinued to perform as an ASME Cede
Section IIIpressure
boundary.
9herefore, it appears that SFBK A should
retain its safety-related classificatian
and be subject to applicable code and
W
P
re~mnents
are being met for SFHiX A.
irement:
10 CFR 50.55a(a) (1) ~dry; that "structures, sy.~ns,
and nx~onents shall
quality standards
caixnensurate with the importance of the safety function to
be performed."
References:
None
A-5
BoUI:
1*
I d
y
1 I
hN the
(Sectians 3.1.2.4 and 3.1.2.5)
i
ion of Co
't'n
the course of its in~ion, the team asked
a rnmnber of questians in
response to which the licensee generated
a preliminary calculatian.
Each of
these calculatians
neech to be finalized within the licensee's
review and
approval pm'~ for ergineering documents.
She calculatians include:
(1)
%he licensee provided a preliaLinmy calculation of the
DG jacket water
coolers'perability using correct design inputs and assuming that zebra
mussels would block an appropriate
number of jacket water cooler tubes
(66~ to 76% of first tube pass).
(2)
%he licensee prepared
a preliminary calculation to demonstrate that the
containment air coolers had adequate
drainage capability.
(3)
'Ihe licensee develcped
a preliminary calculation of DG cooler tube
thinning criteria to ahav at what point of tube thirsting that tubes
shauld be plugged.
%he team reviewed the prelinunary calculaticns
and found that they addressed
the issues raised by the team.
References:
None
A-6
~y
~
~
P
i
ion of Cordition:
Analysis (Section 3.1.2.5)
'%he licensee initiated potential
No.91-048 on November 18,
1991 identifying that the Updated Final Safety
i
p
gggg
response,
the licensee performed a majber of analyses to determine that the
contairunent pressure integrity would not be htpaixed by this diverted flow.
t
gg
g
t
g
g
still be met, but, at a heat removal rate lower than 47 MHIU/hr in sare cases.
(Ibe UFSAR curtly indicates a value of 47 MBIU/hr.) ~ reanalysis,
tt
'
>>'gg
longer and higher temperature transient than originally determined.
Because
the containment temperature profile changed in cxxparison with the original
profile, the team advised the licensee to include consideration of this change
as part of an updated containment analysis to NRC.
'Ihe licensee will do so as
part of a licensirg submittal to ~rt a propc~ boron concentration
modification due in approxunately
6 months.
References:
1.
Potential
Condition Mverse to Quality Report No. 91048 dated
tt~
g
I
~
~
November 18,
1991.
2.
Updated Final Safety Analysis Report Table 9.2-2, "Service Water System
Design Flows. "
A-7
T
P
P,
r
L
u
i
se
t!
Ne M
Valve (Sectian 3.1.3)
ion of ConH i
'Ihe SHS has been operated in a cross-connected
configuration since 1988.
'Ihis
alignment cauld render the entire SNS inoperable during a safety injection
actuation if the discharge
check valve for ane of the SH puaps failed to close
upon system realignment such that. if the associated
pump was nat operating,
water could be pumped in the cpposite du~tion through the check valve irrto
the
SW intake bay. Its scenario was identified, but nat appropriately
analyzed, in a single-failure report developed by Altran.
'Ihe licensee will
mare campletely evaluate this item to ensure that such a single failure would
not camprcanise
systen capabilities.
Bm licensee will also review the Altran
report thoroughly ta ensure that other single failures identified had been
~rcpriately analyzed.
Zn the inte~, the licensee institut~ measures to
alert the cyerations staff to this potential event,
develcped
a means of
prompt detection,
and identified mitigating acticas.
ts 0
10 CFR 50.46(d) states,
in part, that the criteria in 50.46(b) recpa3ilxf
cooling perfonnance calculated in accordance with an acceptable
evaluation
medel are in implementation of the general reguh~nts of ECCS performance
coolie design inclucUirg Criterion 35 of 10 CFR 50, Appendix A.
10 CFR 50, Apperdix A, Critexion 35 requires, in part, that the ECCS safety
function "can be accaqplished,
assuming
a sir@le failure."
Reference:
1.
Altran Report No. 90121.6,
"Single Active Failure Analysis of the R.E.
Ginna Station Sexvice Water System," Rev. 1, dated November 18, 1991.
A-8
IW
I
WW
'tV~
ion o
Existing 'IS 3.3.4 anly requires
ane locp header and two service water pumps to
Iv
not ensure the capability of the service water system to perform its safety
function in accordance with the SNS licensing basis as defined in the UFSAR.
According to the UFSAR, two service water pumps are rapxired for post-accident
heat rival during the recirculatian phase of the accident.
Hmmver, the TS
d
sufficient to ensure that two pmtps would be available during recirculation.
'Ihe staff's
SER dated November 3, 1981, regarding
SEP Topic IX-3, specifically
requested that the licensee address the single failure susceptibility when
anly having two pumps curable.
Dais issue had not been addressed
by the
licensee.
10 CFR 50.36 requires limiting carxhtions for cperation to be established that
are representative
of "...the l~ functional aq~ility or perforaence
levels of equignent rmyured for safe cgeration of the facility."
Refmwnam:
1.
2 ~
3.
Ginna UI'SAR Section 9.2.1,
"Service Water System."
Ginna Technical Specification
3 3 4~ nService Water System
NRC Safety Evaluation Report an SEP Tcpic IX-3, "Station Service and
Cooling Water Sy <<~as," dated November
3g 1981.
(
I
1
f
t
0
3.4.4,
and 3.4.5}
'on of Ceexht on:
Action I of GL 89-13 requested that licensees
implement and maintain an
ongoing program of surveillance
and control techniques to significantly reduce
the incidence of flow blockage p~lems as a result of biofouling. ~ GL
also requested that licensees
inspect their intake stnmtures during each
refueling outage
and reaave
any acnumlations of macroscopic biological
~h.
~rcpriate actions were not defined in the licensee's
u'ev rye
'
~
~y
and stagnant ~, such as the alternate discharge to Deer Creek, the SNS
supplies to the auxiliary feedwater and standby auxiliary feedwater systems,
the SNS supply to the
DG cooling water expansion tank, and isolated header
piping, would not becane clogged.
For example,
inspection and flushirg
requirements
were not defined for these areas.
Also, the licensee's
SWSRDP
did not specifically define when system layup would be required and layup
pvmadures
were not established per the GL request.
Ghe licensee agreed to
review its SNSROP mxl make c9vmpes as ~ropriate to better address the
actions requested
by the GL.
Action II of GL 89-13 requested that licensees
conduct a test program to
verify the heat transfer capability of heat exchangers
cooled by open-cycle
service water systems.
%he licensee's
Service Water System Reliability
Optimization Program stated that the renaining safety-related heat exchangers
(besides the CCNHXs,
SFESX B, the CACs, the cooling units for the standby
auxiliary f~ter pump roan,
and the
DG coolers)
would be opened ard
w>>
p
lieu of heat transfer performamm testing.
Although the team agreed with this
approach,
the licensee
had not established
a sound basis for the preventive
maintenance
frequencies for these heat exchangers.
Action IIIof GL 89-13 request that licensees ~lish a routine inspection
arxl maintenance
program for open-cycle
SNS piping and catpanents to ensure
that corrosion, erosion, protective coating failure, silting, and biofculing
cannot degrade the perfoxamree of the safety-related
systems supplied by SW.
%he team concluded that the licensee's
program for routine inspection and
maintenance of piping and canponents did not satisfy the action requested
by
the GL.
'lhe licensee
agreed to review its SNSRDP and to make changes
as
appropriate to better address the GL actions.
Ihe team identified the
following weakness<+:
(1)
Although the licensee had procedures in place for disassembly
and
inspection of certain ccaqnnents,
measures
were not taken to ensure that
the ~ation of canponents
being inspected
was camplete and that the
frequency of inspection was ac@quate.
(2)
'Ihe licensee had not included in its pnxpam ~ periodic inspection
tt
W
lllIW
instruaent lines were not degraded.
(3)
Program elements were not established
and training was not provided to
l
tl
and operating activities,
and that ~rrpriate followup acticns would be
taken upon discovery of zebra mussel debris.
Action IV of GL 89-13 requested that licensees
confirm that the SHS will
perform its intended functian in accordance with the licensing basis of the
plant.
'Ihe team's ck~rvatians irdicated that the licensee's
review did not
fullysatisfy Action IV of GL 89-13 because,
for exanple,
UFSAR dis~ancies
were not identified, the single failure of the SW puap discharge
chec3c=valve
WW
l
ll, ~t
licensing basis ard TS for SW pump operability was not identified, adequate
operability calculations for the
DG )acket water cooler had not been
performed,
systzun hydraulic fidel inadequacies
wcisIted, and inacauacies in
the staff 's SER related to SEP Topic ZX-3 were not identified.
ferences:
1.
Generic Letter 89-13, "Service Water System Problems Affecting Safety-
Related Equitant," dated July 18, 1989.
2.
Rochester
Gas ard Electric, Ginna Station,
"Sexvice Water System
Reliability Optimization Program," dated November 19, 1991.
-0-0
i
ion of
2m NRC staff reviewed the canfiguratian and the design of the SNS at Ginna
during SEP under Tcpic IX-3, "Station Service and Cooling Water Systems,"
as
donunented in its SER dated November 3, 1981.
She team cancluded that staff
acceptance of the design and canfiguratian of the Ginna
SWS was based, in
part,
on the ability of the SNS to perform its function ard not be adversely
affected by a single active or passive failure.
She following system design
features were recognized:
(1) nan-critical loads are autcaatically isolated
follcaring an SIS (did not include isolation of the OCRHXs) and
(2) normal
system alignment did not permit a single active or passive failure to result
in the loss of service water fleer to redundant critical loads.
She first
condition was not satisfied by the
SNS design and canfiguratian because
non-
critical loads are only isolated follmrimp an SIS coincident with an
undervoltage condition and a critical load, the CCRHXs, are isolated during
the injection ph.me.
Also, the second condition has not been accurate since
1988 plus frcan initial plant operation until sane undetermined
time when the
crom-tie valves were closed.
Ghe SEP review, and the licensee after
receiving the SEP SER, did nat recxxp6ze these inaccuracies in the dimxxssion
of system design.
Also, the SEP SER specifically requested that the licensee
address the sir@le failures associated with the
SW pur~.
9%is issue had not
been addre~A by the licensee.
'Ihe licensee amnitted to m9mit a letter to
NRC clarifying the SEP SER inaccuracies.
As needed,
the staff will initiate
further review of SEP Topic ZX-3 to ahhxas the inaccuracies.
Reference:
1.
NRC Safety Evaluation Report on SEP Tcpic ZX-3, "Station Service and
Cooling Water c~~ns~ n dated November
3~ 1981
A-12
k
IL
.
~
E
J
l5;
i
ion of Ccexhtion:
The team identified a number of discrepancies with the Girna Updated Final
Safety Analysis Report regardirg the discussion of the SNS.
(1)
UFSAR Set&ion 9.2.1.3 stated "...the service water locy is isolated by
cross-connections."
'Ihe SHS is cross connected by the 14" ~ly header
for the contairttl.nt air coolers.
The system is also cross~meted
at
the three inch equignent cooler supply heelers, at the three inch SI pump
supply headers,
and at the four inch ~xodent coolizg water cross-
connect in the supply header.
(2)
UFSAR Sectian 9.2.1.3 stated "...Allengineered safety features equi~mt
is split, between the two systens
so that only half of the sy ~n would be
affected by a malfunction."
The systen is not designed with half of the
safety equipnent split between the two headers.
In fact, the c~~ is
designed with each loop header typically crom~nected at the various
supply headers for the safety equipment,
and if the system were operated
split the three safety injection pumps would all be an ane header since
they cannot be divided between headm~.
(3)
UFSAR Sections 9.2.1.2.1 arrl 9.2.1.2.2 stated that the service water
system is designed to isolate non-safety-related
leeds an an accident and
a safety injection signal, respectively.
She
SNS does not isolate non-
safety-related
loads on an SIS unless
an undmvoltage ccexhtian also
exists
o
(4)
UF.'AR Table 9.2-2 did nat a~tely reflect the total fleer to the CACs
because it neglected the flaw to the CAC fan motors.
In 1988, the licensee altered the system operating configuration by opening
the second containment air cooler isolation valve.
The UFSAR was not revised
to reflect this change.
tsar
10 CFR Part 50.34(b) states,
in part, '"Ihe final safety analysis report shall
include information that describes the facility, presents the design bases
and
the limits on its operation,
and presents
a safety analysis of the structures,
systems
and camponents...and
shall include...a description and analysis of the
...caqmnents
of the facility, with emphasis
upon perfonnance
requirements,
the bases,
with tet:9mical justification therefor,
upon which such requinanents
have been established,
and the evaluations required to shor that safety
functions will be acxxxrplished.
The chmcriptian shall be sufficient to peraut
understarding of the system designs
and their relationship to safety
evaluations."
1
~
ll
10 CFR Part 50.71(e) states,
in part, ~ person licensed to cperate
a
nuclear pm'eactor...shall
update periodically, as provided in paragraphs
(e) (3) and
(4) of this section, the final safety analysis report
(%SAR)
originally su}mitted as part of the application for cperating license, to
assure that the information included in the FBAR oarMins the latest material
developed...Ghe
updated
FSAR shall be revised to include the effects of all
changes
made in the facility or pracahuas
as described in the
FSAR...revisions shall be filed no less frequently than annually and shall
reflect all changes
up to maxixmm of 6 months prior to the date of filing..."
ferences:
I
i
ion of Oordition:
In the review of cperations p~ures,
the team noted that in step three of
AP-SW.1, >>Service Water Leak,>> operators were du~ted to initiate actions
should
SNS header pressure
be 40 psig or less.
%bmoc was no engineering basis
for this setpoint that was chosen as a best est&nate.
Wit2xmt sufficient
system pa~sure,
the pumps may be unable to supply sufficient fleer to critical
system components
such that the system would be cxesidm~ inoperable.
%he
licensee
was aware of this issue but had taken no action until recpmsted by
the team.
'Ihe licensee will establish
an ~rcpriate 1m'-pressure
setpoint
based
on an assesarant
that system loads would continue to be sqpplied.
i'ent:
Ginna Technical Specification 3.3.4, "Service Water Sy:Mm,>> requires, in
part, that at least two service water pur~ and one locp he.Wr be operable.
Reference:
l.
Rz)cedures
AP-SW.1, >>Service Water Leak."
A-15
~
I
Y
i
ion of Oondition:
Practices
(Section 3.3.5)
Because current TS only axydxed that two of the fear pm>ps be operable,
the
>> ~
>>>>
>>
consi~ this policy urxoonservative in view of its finding regaling the
need for more than two pm~ to be operable,
as discussed in Section 3.1.3 and
Deficiency No. 91-201-08,
and ~mted that the licensee reevaluate its
scheduling practices for long-term punp maintenance during cperation.
References:
1.
Ginna Technical Specification
3 ~3.4, "Service Water System."
2. J~ A. Widay memorandum to operatices staff dated December 5, 1991,
>>>>>>
A-16
w
i
ion of Condition:
Startup testing of the SNS was performed in accordance with procedure SU-4.17.
'Xhe testing that was performed did not fullyverify the capability of the
sy ~.
'Ihe licensee had not reviewed the preoperatianal test results in
cxxnparison to current sy.~n cperation and configuration and determined the
need for additional testing to support operation in ret:px'uxd system
configurations.
Ibis had not been done despite
system cperating changes since
initial licensing involving the numtmr of pumps normally cperating and various
changes to the system valve alignment.
(1)
'Ihe non~fety-related
loads were isolated fnxn the 1oap hem3ers
when the
safety-related
performance of the system was tested
(single pump
operation) .
Current operation of the plant does not isolate the non-
safety-related
loads during an SIS.
(2)
We safety-related
performance of the system was not tested with two
pumps operating.
Two pumps are rmpured to handle the post-accident heat
load dur~ recirculation.
(3)
'lhe system flow balance was established
ban% on three pump operation,
not based
on the limiting case of one pump operating ~lying all
safety-related
and non-safety-related
loads.
(4)
Pump run-out conditions were not evaluated or considered.
ts 0
10 CFR 50, Appendix B, Criterion III( "Design Oanhx)1," requires that design
control measures
"...provide for verifying or checkirg the adequacy of design,
such as by the performance of design reviews, by the use of alternate or
simplified calculational methods, or by the perforaence of a suitable testing
procpmn."
10 CFR 50, Appendix B, Criterion XI, '~ Control," recp6ras, in part, that
test results be documented
and evaluated to ensure satisfactory cxxopletion of
test requirenents.
8
1.
Procedure
SU-4.17,
"House Service Water," dated November 1, 1968.
A-17
g 'I
~l~
t
L
i
ion o ~tion:
~
~
~
~
~
5
M:
p
1%M
Similtaneously Taking Ebxhndant P~prent Out of Sezvioe
(Section 3.4.3)
She team found that the licensee did not enid. Gxjs during IST since it did
not consider the equignent beirut tested to be aut of service.
Not entering an
UX) allured the licensee to take redundant equignent aut of sezvice
simultaneously with IST.
'Ihe IST of the
SW punps required that the system be
aligned differently freya its normal accident lineup.
Since manual actions
would be required to return the sy ~n to its correct alignment upon an SIS,
the team cauld not conclude that the train being tested
was available to
perform its safety function for the period of the test.
Quis condition
existed for several surveillance Umts, including that for the containment
spray pump in which the test disables the system by blodcinp the spray path to
the spray rirg.
The team questianed this practice ard was concerned about the
lack of procedures
to. ensure that rmhxndant ecp.CipMnt would not be taken aut
of service while the oanpanion ecpugrlent is urxkxgoing testing.
Bm licensee
stated that it would reevaluate its policy in this regard.
10 CFR 50, Appendix B, Criterion V, "Instructions, Procedures,
and Drawings,"
requires that "activities affecting quality shall be prescribed by doamented
instructions, p~ures,
or dzawirgs."
Reference:
1.
GL 91-18, "Information to Licensees
Regarding
Two HRC Inspection Manual
Sections
on Resolution of Degraded
and Nancmfozming ~tians
and on
Operability," dated November 7, 1991.
A-18
>i
~
~ g
4 (
~ ~ *g
~
t
1
EXIT MEETING ATHXQANCE LIST
HK%KKR 20,
1991
'ensee
Personnel
Steven Adams
Charles Anderson
Bernard Carrick
Matt Clark
John Cook
'Ihcanas Daniels
James
Dunne
Clair~
Mark Fitzsimmons
Brian Flynn
Charles Forkell
Paul Gorski
'Ihcaas Harding
Glenn Hermes
Gregg Joss
Michael Kennedy
Steven Iawlor
Russ Lingl
Richard Marchionda
'Ihamas Marlow
Robert Mecredy
Jack Metzger
Theodore Miller
John St. Martin
Gene Voci
J~ Widay
Paul Wilkens
George Wlubel
Technical Manager
Qh Manager
Team Manager
Team Leader
Reactor Engineer
PRA Project
Mechanical Engineer
Manager, Electrical/I&C
tural Engineer
Nuclear Safety and Licensing
Manager, Electrical Engineerirg
Modification Support Coordination
Nuclear Safety and Licensing
Results
and Test Supervisor
Mechanical Engineer
gmrations Shift Supervisor
Superintendent,
Sugmrt Services
Superintendent,
Ginna Production
Vice President,
Ginna Nuclear Production
Nuclear Safety and Licensing
Electrical Engineer
Co~ive Action Coordinator
Manager, Mechanical Engineering
Plant Manager
Nuclear Engineering Services
Deponent
Manager
Manager, Nuclear Safety and Licensirg
NRC Personnel
Suxesh Chaudhary
Robert
Grar((m
Eugene Imbro
Allen Johnson
James Linville
Melanic Miller
Khanas Moslak
Jerzy Parkitny
Donna Skay
James
Talcum
Senior Reactor Engineer,
Region I
Section Chief,
Branch Chief,
Project Manager,
Branch Chief, Region I
Team Leader,
Senior Resident Inspector,
Region I
Consultant,
AECL
General Engineer,
Senior Reactor Engineer,
AE%%NDIX C
ABHREVIATIGHS
auxiliary operator
American Society of Mechanical Engineers
containtmnt air cooler
corrective action report
cmponent cooling water heat exchanger
diesel generator
differential pressure
ERR
emergency plan inplemeMIng procedure
engaging
work z&p36st
Final Safety Analysis Report
generic letter
Institute of Nuclear ~~ Operatians
inservice te~irg
job perfornance
me mure
limiting cordition for operation
U.S. Nuclear Regulatory Gxmlission
Nuclear Plant Reliability Data System
PCAQ
EH
potential conchtion adverse to quality
preventive maintenance
prcbabilistic risk assessment
'tY
Rochester
Gas ard Electric Oorporatian
SFERX
SWSOPI
SWSROP
Systematic Evaluation Pnxpmn
safety evaluation report
safety injectian
safety injection signal
spent fuel pool heat exchanger
service water system
Service Water Systxua ~~~tianal Performance Inspection
Service Water System Reliability Optimization Pmgram
Technical Specifications
Updated Final Safety Analysis Report
C-1
$gsp