ML17251A532

From kanterella
Jump to navigation Jump to search
Partially Withheld Insp Rept 50-244/89-08 on 890417-21 (Ref 10CFR2.790).Violations Noted.Major Areas Inspected:Mgt Support,Security Program Plans & Audits,Protected Area & Vital Area Physical Barriers & Packages & Vehicles
ML17251A532
Person / Time
Site: Ginna Constellation icon.png
Issue date: 05/25/1989
From: Keimig R, Lancaster W, Sylvester E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML17251A530 List:
References
50-244-89-08, 50-244-89-8, NUDOCS 8906070041
Download: ML17251A532 (26)


See also: IR 05000244/1989008

Text

~.o~Z'-~s-sp

(M 'I

'1

U. S

~

NUCLEAR REGULATORY COMMISSION

REGION I

Report

No.

50-244/89-08

Docket No.

50-244

License

No.

OPR-18

Licensee:

Rochester

Gas

and Electric Cor oration

Facility Name:

R.

E. Ginna

Power Plant

Inspection At:

Ontario

New York

Irspection

Conducted:

A ril 17-21

1989

Type of Inspection:

Routine

Unannounced

Ph sical Securit

Irspector s: &'

'.

K. Lancaster,

Physical Security Inspector

date

E.

D.

Sy

,

S

or

tor Engineer,

Physical Security

date

Approved by:

.

R. Keimig,

ief,

S

guards

Section

Division of Radiation

afety and Safeguards

date

Ins ection

Summar

Routine

Unannounced

Ph sical Securit

Ins ection

Re ort No. 50-244/89-08

Areas

Ins ected:

Onsite Follow-up of Previously Identified Items;

Management

Support,

Security

Program Plans

and Audits; Protected

Area and Vital Area

Physical Barriers,

Detection

and Assessment

Aids; Protected

and Vital Area

Access Control of Personnel,

Packages

and Vehicles; Alarm Stations

and

Communications;

Power Supply; Testing,

Maintenance

and Compensatory

Measures;

and Security Training and qualifications.

Results:

Th'e licensee

was found in noncompliance with the NRC-approved

Physical

Security Plan in the areas

of Physical Barriers - Vital Areas,

and

Protected

Area Assessment

Aids.

8'70607

Opqq

PDR

>DOCK. 0>oopNU

6

DETAILS

1.

Ke

Personnel

Contacted

I

Licensee

and Contractor Personnel

  • R. Smith, Vice President - Engineering

and, Production

"S. Spector,

Plant Manager

"T. Powell,

Manager - Risk Management

Department

"R. Marchionda, Director of Outage

Planning

"W. Borland, Electrical

Engineer

"R. Wood, Supervisor - Nuclear Security

"M. Fowler, Coordinator - Nuclear Security Training

T. Porter, Acting Foreman - Instrumentation

and Controls ( I&C)

R.

Benne,

Project Manager - Wackenhut

U.S. Nuclear

Re viator

Commission

NRC

"N. Perry,

Resident

Inspector

"Indicates those present at the Exit Interview

2.

Onsite Follow-u

of Previousl

Identified Items

a

~

(Closed)

VIO 88-18-01.

The licensee failed to provide test

procedures

for the protected

area

(PA) intrusion detection

system

( IDS).

The licensee's

response

to the Notice of Violation, as

documented

in

a letter to the

NRC dated

December

5,

1988,

was

verified and corrective actions

were found to be satisfactory.

The

inspectors

observed

tests of the

PA IDS during the period of

April 17-21,

1989,

and found no discrepancies.

(Open)

VIO 88-12-02.

The licensee

was found with inadequate

barriers

at

a certain vital area.

The licensee

estimates

that the barriers

on

this vital area

would be upgraded

by August

1,

1989.

The inspectors

verified that compensatory

security measures

for the degraded

barrier s were in place.

3.

Mana ement

Su

ort

Securit

Pro

ram Plans

and Audits

a.

Mana

ement

Su

ort Management

support for, and attention to, the

physical security program appeared

to have decreased

in certain

areas.

This is based

upon the inspectors'eview

of various aspects

of the licensee's

program,

and the nature of the apparent violations

and security concerns identified during the inspection.

The inspectors

observed

that the licensee's

physical security program

has

some notable strengths;

however, it also

has

some

weaknesses

that

are in need of attention.

The following are examples

of program

strengths:

~ A very professional,

performance

oriented,

and effective

security force;

~A positive attitude toward security is displayed

by all plant

personnel;

~ Enhanced barriers at key locations

on the protected

area

(PA)

perimeter to protect against

penetration

by unauthorized

vehicles;

~ Large clear isolation

zones

and

a double

PA fence barrier system

to aid alarm station operators

in detection

and assessment;

~ An excellent fixed security lighting system;

~Strategically located defensive positions for the response

teams;

and,

~ Excellent armament

(types, distribution and locations) for the

response

teams.

The following are

examples of weaknesses

observed:

THI$ PNAMhPH NNTIIIi SAFEMAR0S

iNOBNIR Pi~ l3 hH

FOR PSI.IP

M,"'CLONki, l7 l5

liVL'NIONR't'f:)-f

Nh<K

The inspectors

expressed

the concern that, while most aspects

of the

program appeared

to be performance-oriented

and received appropriate

attention,

some aspects,

notably equipment

and systems,

have

been

neglected

to the, point that they are only marginally effective.

The

licensee

indicated that

a bid specification

was being prepared for a

consultant

to evaluate

the program and expected

the evaluation to be

conducted

in 'the near future.

The inspectors

indicated interest in

reviewing the evaluation results after the licensee's

review and

assessment.

b.

Securit

Pro

ram Plans - The inspectors

reviewed the NRC-approved

security plan (the Plan)

and met with licensee

representatives

to

discuss

several

inconsistencies

in the Plan.

The following are

some

representative

examples:

"SLYLY MQ~>I$ $NMM9$

Nl$ PNVuEh

>'$

tNBki~i)le kk9 lS KM f a

9NNW3%

i"1 5 lN.'INWIT

EP,

SLOTS.

Subsequent

to these discussions,

which included

a review of the above

examples with the licensee,

the inspectors

stated that the Plan

and

implementing

procedures

need to be reviewed to identify and resolve

any

additional

inconsistencies

and to ensure

that the implementing procedures

reflect the commitments

in the Plan.

The licensee

committed to include

a section

on security plan and plan

implementing

procedures

review in the consultant's

evaluation of the

licensee's

program.

Audits - The inspectors

reviewed the report of the

1988 annual

security

program aud'it,

conducted

by Quality Assurance

(QA), and

verified that the audit

had

been conducted

in accordance

with the

Plan.

The inspectors

noted that there

were

no adverse

findings,

concerns

or recommendations

made in the official transmittal of the

audit report.

Apparently,

the

QA auditors

found all aspects

of the

security

program to be satisfactory.

Based

on the

inspectors'indings

during this inspection

and

an interview of a

QA auditor who

participated

in the

1988 audit, the inspectors

questioned

the depth

of the audit and/or the security expertise of the auditors.

The licensee

agreed to look into the inspectors'oncern

in this

area.

The licensee's

audit program will be reviewed further during

the next inspections

Protected

and Vital Area

Ph sical Barriers

Detection

and Assessment

Aids

a.

Protected

Area Barriers

The inspectors

conducted

a physical

inspection of the

PA barrier

on April 17,

1989.

The inspectors

determined,

by observation,

that the barriers

were installed

and

maintained

as described

in the Plan.

b.

Protected

Area Detection Aids - The inspectors

tested

the

PA

perimeter intrusion detection

system

( IDS) on April 18,

1989,

and

determined that it was installed,

maintained

and operated

as

committed to in the Plan.

C.

Isolation Zones - The inspectors verified that isolation zones

were

very well maintained

and free of obstructions.

However,

as discussed

in paragraph

4'.e., obstructions

outside of the isolation zones

obscured

assessment

capabilities

in two areas.

d.

Protected

Area

and Isolation

Zone Li htin

- The inspectors

conducted

a lighting survey of the

PA and isolation zones

on April 17 and

19,

1989.

The inspectors

determined,

by observation,

that lighting

in the isolation

zones

was adequate.

However,

elsewhere within the

PA, the inspectors

identified several

isolated

areas

where lighting

was marginal

due to on-going outage activities.

While these lighting

deficiencies

did not represent

a violation of the Plan,

the

inspectors

noted that their existence

was not indicative of an

aggressive

security lighting program.

Security force post orders

and the Plan

implementing

procedures

were

reviewed

by the inspectors.

They noted that these

documents did not

specifically require security force members

to be alert for and

identify potential lighting deficiencies.

The inspectors

also

determined

through interviews with security force members that the

security shift supervisors

do not have ready

access

to

a light meter

with which to quantitatively assess

security force identified

potential lighting deficiencies.

The licensee

committed to revise post orders

and procedure's

to

specifically address

the responsibilities of security force members

to be alert for areas

of marginal lighting.

The licensee

also stated

that shift supervisors

would be provided with a light meter.

PA

lighting will be reviewed during subsequent

inspections.

e.

Assessment

Aids - The inspectors

observed

the

use of assessment

aids,

and other security equipment in operation at the Central Alarm

Station

(CAS) on April 18,

1989.

The inspectors

found that two

portions of the

PA barrier and associated

isolation zones could not

be adequately

assessed.

".-!i'NNRIPH CNAlNS SNMONN

!'" 3Pi/Q!M 00 lS RM N8 PSUf

-

",~~LONI'6', 0'

lNNBGMLQ

.;. 7 Si.NE.

The inspectors

interviewed security

and

I&C personnel

about this

matter ard determined that the problem

has existed for over two

years.

However,

when the matter

was discussed

with licensee

security

management

personnel,

they disclaimed

knowledge of the problem and

could offer no explanation of how the problem could exist for that

period of time without it coming to their attention.

The inspectors

expressed

the following concerns

to the licensee:

1)

Why was there not

a deficiency report written concerning

the problem when it was first identified?

(The inspectors

could not find one nor was

one offered by the licensee.)

2)

If a deficiency report was written,

why was the problem not

corrected?

3)

Why was security management

not aware of an apparent

system

problem that existed for over two years

when it was general

knowledge

among security

and

ICC personnel?

4)

How could the problem exist for over

two years without

being corrected,

especially

since

the

NRC had given the

licensee credit for the system during the security plan

approval

process?

5)

Why were compensatory

measures

not implemented

when the

problem first occurred?

6)

If a conscious

decision

was

made

by someone

not to correct

the problem,

who made that decision

and why was the

NRC not

notified and

a security plan change

submitted7

The inspectors

reviewed the

Plan, and found the following

requirements:

VIS PAIIII6RAPII CONNIIS NE6NIf

lIii'~BHlAlIOIINQ

'LS

ROY fOR PUSUL":

9)'St'lOS~JIIf, H 5 1N."IIQN5<

tkFf 8LIINn.

The inspectors

determined that the licensee's

failure to comply with

commitments

in the Plan is

an apparent violation of NRC requirements

(50-244/89-08-0j).

The inspectors

also observed

the

use of assessment

aids during the

hours of darkness

on April l7,

1989.

The licensee

implemented

compensatory

security measures

for these

potential

weaknesses

and committed to review the entire

CCTV system

in the near future.

The licensee's

actions to resolve

these matters

will be reviewed during the next inspection.

f.

Vital Area Barrier - The inspectors

conducted

a physical inspection

of Vital Area

(VA barriers

on

A~re g~Qg@gg$

-

IlS PAR """

R PI

INOSQ'LNl NO (S %7 fOR

NSENNRE, 6 5 lm'.lIQIN

.

l'ER SlANIL

, The licensee

agreed

to correct

these deficiencies

by the end of the

current outage.

This will be reviewed Muring subsequent

inspections.

TIIIS PIINMPNII CMfmtIS MFEIIMM

NFOPNQIOh L')U lS EB FM

PIIUzt'ISI,"NEIJkf,

IT 5 II)L"III!MET

LH; El.V!li.

The inspectors

reviewed

the Plan

and found the following require-

ments:

VIS PNiMAAPH COAIPS

SAFEGNRIIS

IHFGIIIIINION ACRID IS

NOT

FOR

PUBUG

OISCLOSIJN,

IT IS INTMWLN

Lr~F, BLNK

The inspectors

determined 'that the licensee's

failure to comply with

the above requirements

in the Plan is an apparent violation of NRC

requirements.

(50-244/89-08-02).

THIS PNMRIIPH CONNHS SAFEIIllAMR

NFOBHATION IIO IS

NOT FOR PIISUC

DlSCLOSURE,

IT IS INTJITNNALLV

LEPi

BLANK.

g.

Vital Area Oetection Aids - The inspectors

observed

and witnessed

testing of the

VA intrusion detection

aids

and determined that they

were installed, maintained

and operated

as committed to in the Plan.

5.

Protected

and Vital Area Access Control of Personnel

Packa

es

and Vehicles

a.

Personnel

Assess

Control

The inspectors

determined

that the licensee

was exercising positive

control over personnel

access

to the

PA and

VAs.

This determination

was based

on the following:

1)

The inspectors verified, by observation,

that personnel

are

properly identified and authorization is checked prior to

issuance

of badges

and key-cards.

2)

The inspectors verified that the licensee

has

a fitness for duty

program in place.

A drug testing

program

has

been

implemented

and includes:

~All prospective

licensee

employees

(who would be assigned

to the plant) are tested prior to employment;

~All consultants

and contractors

must certify to the

licensee

that their employees

have

been drug tested;

and,

~ Testing for cause.

The inspectors

noted that the testing

program does

not include

annual testing of licensee,

consultants

or contractor

employees

who have

access

to the

PA and

VAs at the station.

3)

The inspectors verified that the licensee

has

a search

program,

as

committed to in the Plan, for firearms,

explosives,

incendiary devices

and other unauthorized material.

The

inspectors

observed

plant per'sonnel

and visitor access

processing

several

times during the inspection

and interviewed

members

of the security force and the licensee's security'taff

regarding

personnel

access

procedures.

%lS PNNRAPH CIISAlNS SNNMDS

MORNNlMNI !5 RM NR PSU6

srMxosuaa,

O ~s Wr.eoIIu.V

le 85Nh.

4)

The inspectors

determined,

by observation,

that individuals in

the

PA and

VAs display their access

badges

as required.

10

5)

The inspectors verified that the licensee

has escort procedures

for visitors to the

PA and VAs.

6)

7)

The inspectors verified, by a review of security procedures

and

records,

that the licensee

has

a program to confirm the

trustworthiness

and reliability of employees.

This program

includes

checks

on employment history, criminal history,

physical examination,

and

a psychological

examination.

The inspectors

reviewed the procedures

for the control of

security locks and

keys

and determined

that they were consistent

with commitments

in the Plan.

The inspectors

also reviewed the

PA and

VA key inventory logs,

and discussed

lock and key control

procedures

with members of the security force and the licensee's

security staff.

No deficiencies

were identified.

8)

The inspectors verified that-the

licensee

has provisions for

expediting

prompt access

to vital equipment during emergencies,

and that the provisions

are

adequate

for that purpose.

9)

The inspectors verified that unescorted

access

to

VAs is limited

to authorized individuals.

The

VA access list is revalidated at

least

once every

31 days

as committed to in the Plan.

'I

Packa

e Access Control

The inspectors

determined that the licensee

was exercising positive

control over hand-carried

items that are brought into the

PA via the

main gatehouse.

The inspectors

reviewed the search

procedures

for

the main gatehouse

and found

them consistent with commitments

in the

Plan.

i

11

The licensee

agreed to assess

and re-evaluate

this area of the Plan

~

The

NRC considers

the licensee's

practices

regarding

searches

of

packages

and materials

entering the

PA to be

a Unresolved

Item

(50-244/89-08-01).

c.

Vehicle Access Control

The inspectors

determined that the licensee

properly controls vehicle

access

to and within the

PA.

The inspectors verified that vehicles

are properly processed

prior to entering

the

PA.

The process

was

consistent with commitments

in the Plan.

The inspectors

also

reviewed the vehicle search

procedures

and determined that they were

consistent with commitments

in the Plan.

This determination

was

made

by observing vehicle processing

and search,

inspection of vehicle

logs,

and by interviewing members of the security force and

licensee's

security staff about vehicle processing

and search

procedures.

6.

Alarm Station

and Communications

The inspectors

observed

the operations

of the

CAS and

SAS and determined

that they were maintained

and operated

as committed to in the Plan.

CAS

and

SAS operators

were interviewed

by the inspectors

and found to be

knowledgeable

of their duties

and responsibilities.

The inspectors

verified that the

CAS and

SAS do not contain

any operational activities

that would interfere with the assessment

and response

functions.

The inspectors

also observed

tests of all communication capabilities

in

both the

CAS and the

SAS and reviewed the testing

records for the

communications channels'll

were found to be as committed to in the

Plan.

7.

Emer enc

Power

Su

1

The inspectors verified that there are several

systems (batteries,

dedicated

diesel

generator within a VA, and plant on-site

AC power) that

provide backup

power to the security systems.

The inspectors

reviewed the

test

and maintenance

records

and procedures

for these

systems

and found

that they were consistent with the Plan.

The inspectors

also verified that the door

access

control

system for VAs

will permit emergency

ingress

and egress

when the system's

normal

power is

lost.

8.

Testin

Maintenance

and

Com ensator

Measures

The inspectors

reviewed testing

and maintenance

records

and confirmed that

the records

committed to in the Plan were

on file and readily available

for review.

The station

uses

experienced

instrumentation

and controls

12

(IAC) technicians

to repair/replace

and test

any security equipment which

requires. preventive or corrective maintenance.

A check of repair records

indicated that repairs,

replacements

and testing is being accomplished

in

a timely manner.

The review also included the 1988/1989 quarterly

Security

Event

Logs and tlI~EtQQ+~)gaqrygggqgequest

records.

IhF0R:;IhTI0H N9 IS H0T F0R

P~JSLIC

OISCL0SIIIIE

IT

<S IhT'.NI0IILLf

LFl 0LIK

The licensee

agreed

to review the maintenance

history for these

components

in an effort to determine

the reliability of this equipment.

This matter

will be reviewed during subsequent

inspections.

The inspectors

also reviewed the licensee's

use of compensatory

security

measures

and determined

that they were being

implemented

as committed to

in the Plan.

9.

Securit

Trainin

and

uglification

Several

Security Officers (SOs)

were interviewed to determine if they

possess

the requisite

knowledge

and ability to carry out their assigned

duties.

The interview results

indicated that they were very professional

and knowledgeable

of their job requirements.

The licensee's

contract security force consists of forty-seven

SOs

and

watchmen,

ten supervisory

personnel

and

one project manager.

The

inspectors

verified that the

armed

response

force meets

the commitments

in

the Plan

and that there is always

one full-time member of the security

organization on-site

who has

the authority to direct security activities.

THIS PARACIIPH CONAIIIS SAFEGNROS

NI'0IIQQI0N AII0 IS MT MR

PIIIIU{'ISEL0$

IIIIE

IT IS ltiTEHTIWLLy

LEFT 5UNP.

13

TP5 PN4P<f'tl MNhl>Z $NKIJMM

fhMF~~h'APE NN l3 P<M flà PiJN.I5

<3)kruLOMPE, IT !S NTENHONt.N

KPi'NN.

The licensee

agreed

to review this matter.

This matter will be reviewed

aga.in during subsequent

inspections.

On April 20,

1989,

at, 12: 19 a.m.,

the security shift supervisor

found

a

security force member asleep

on-post at

a

VA access

point.

The licensee

properly reported

the incident to the

NRC in accordance

with 10 CFR 73.71.

The inspectors,

who were

on site at the time,

reviewed the incident and

determined that the security force member could have

been

asleep for only

approximately

seven minutest

The licensee

took immediate

and appropriate

compensatory

security measures.

The inspectors

determined that all

appropriate

actions

had

been

taken.

The inspectors

also

found that the

licensee

has

an effective program in place to guard against

members of t,he

security force being inattentive while on duty for a length of time that

would de'grade

security.

1C.

Exit Interview

The inspectors

met with the licensee

representatives

indicated in

paragraph

1 at the conclusion of the inspection

on April 21,

1989.

At the

time, the purpose

and

scope of the inspection

were reviewed

and the

findings were presented.

At no time during this inspection

was written material

provided to the

licensee

by the inspectors.

W