ML17250B289

From kanterella
Jump to navigation Jump to search
Insp Rept 50-244/93-08 on Stated Dates. Violations Noted.Major Areas Inspected:Svc Water Sys Valve Failures & Underground Piping Leak
ML17250B289
Person / Time
Site: Ginna Constellation icon.png
Issue date: 06/22/1993
From: Eapen P, Gregg H
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML17250B288 List:
References
50-244-93-08, 50-244-93-8, NUDOCS 9307060058
Download: ML17250B289 (6)


See also: IR 05000244/1993008

Text

REPORT NO.

U.S. NUCLEARREGULATORY COMMISSION

REGION I

50-244/93-08

DOCKET NO.

50-244

LICENSE NO.

DPR-18

LICENSEE:

Rochester

Gas and Electric Corporation

1503 Lake Road

Ontario, New York 14519

FACILITYNAME: R. E. Ginna Nuclear Power Plant

INSPECTION AT: R. E. Ginna Nuclear Power Plant, Ontario, New York

and Rochester

Gas and Electric Corporation,

Rochester,

New York

INSPECTION

CONDUCTED:

April 12-16, May 24-28, and June 14-18, 1993

INSPECTOR:

H.. Gregg, Sr. R

tor Engineer,

Systems Section, Engineering Branch, DRS

Date

APPROVED BY:

Dr. P. K. Eapen, Chief, Sy tems Section,

Engineering Branch, DRS

Date

Areas Inspected: Service water system valve failures and underground piping leak.

Results: The licensee's valve inspection and replacement were aggressive after identifying

two locked open manual valves that had failed in the closed position.

The two valves were

in the closed position for an undetermined time during operation and were not identified as

failed until the 1993 outage.

The untimely identification and corrective action of the failed

valves was identified as an apparent violation.

9307060058

930h28

PDR

ADQCN 05000244

PDR

DETAILS

1.0

Review of Service Water Problems

1.1

Background Review

Two recent SW valve failures were identified during the licensee's inspection of

March 28, 1993.

An unrelated underground SW piping leak observed in the screen house

basement wall was identified by the licensee on January 7, 1992.

The purpose of this

inspection was to assess

the licensee's actions in response to the two valve failures and the

underground SW piping leak.

The R. E. Ginna valve improvement program of inspection-refurbishment-replacement

during

the current 1993 outage included motor-operated

and manual valves in the service water

system (SWS).

The licensee's

SWS maintenance planning for the 1993 outage started in

1989, with con'tracted reviews.

Improvement plans were documented in the licensee's

correspondence

of May 22. and June 13, 1991, that pointed out the need for extensive

refurbishment, targeted a large number of service water valves, provided data on strategies

to

isolate the SWS, and detailed the planning needs of long lead obsolete valve replacements.

Additional considerations

such as extensive service water system reconfiguration and* fuel

offload to enable work to be performed on the system, refurbishment of safety system valves

assigned higher priorities, extensive installations of new recirculating fan cooler heat

exchangers

inside containment, and need to have on-hand replacements for obsolete valve

models that were ordered in 1991 were factors in the licensee's

reasons for delaying service

water (SW) valve repairs until the 1993 outage.

The licensee's

awareness

that the Crane model 101 gate valves and several other models of

SW gate valves were obsolete was factored into the licensee's planned phase V valve upgrade

program work to be performed in the 1993 outage.

A more current Crane model 47'h XU

gate valve required extensive evaluation in accordance with the Ginna commercial dedication

program and were the purchased

replacements.

1.2

Valve 4669 and 4738 Failures and Licensee's Actions

The inspector reviewed corrective action report (CAR) 2077 and related correspondence

that

documented

the licensee's-2993

outage inspection finding, of the valve failures.and subsequent

actions.

The inspector also observed in-process work, the material condition of many

removed valves, and the condition of in-place piping.

The CAR identified two locked open manual valves (4669 and 4738) that had stems separated

from their discs with the discs in closed position, and valve 4739 (identical in design and

function to valve 4738) with its stem marginally attached to the disc.

The material at the

disc T-slot was found entirely consumed by corrosion on valves 4669 and 4738 and almost

entirely consumed on valve 4739.

The valves were Crane model 101XU original installation

equipment and have been in service approximately 23 years.

The stem material was

410 stainless steel and the disc material was SA 105 carbon steel with weld deposited

410 stainless on the disc seating surfaces.

Valve 4669 in series with valve 4760 are 4" locked open valves in a cross connection

, between the A and B headers

and supply SW to the emergency diesel generators.

Valve

4738 in series with valve 4739 similarly are 3" locked open valves in a cross connection

between the A and B.headers

and supply SW to the safety injection pump thrust bearing

coolers.

The licensee's staff with high level management

direction was aggressive in expanding the

scope of the SW valve inspection-refurbishment-replacement

outage plan upon identification

of the stem separation problem.

The original scope of 20 valves was increased

to 31 and

included all Crane 101 SW valves except 4612, 4621, and 4705.

The expanded work scope

included replacement of 14 of 20 SWS Crane 101 valves and the refurbishment of three

others.

An upgraded Crane model 47'A that has a 410 stainless

steel disc was the

replacement valve.

The remaining Crane model 101 SW valves are to be replaced in the

1994 outage.

The NRC inspection report 50-244/93-06 also contains information relating to

the two failed SW valves.

1.3

Safety Concern Review of Failed Valves

The inspector reviewed the safety significance of the failed valves (4669 and 4738).

The

inspector determined from a review of the UFSAR and the SWS drawings that there are

individual flow paths to supply SW to the safety-related components

(diesel generators,

containment fan coolers, and pump coolers).

In addition, the 14" crosstie line with normally

open valves (4639 and 4756) enable the safety-related components to be supplied from either

SW loop.

However, the closing of valve 4739 for brief time periods up to 45 minutes during

monthly SW pump surveillance tests would have isolated flow to the safety injection pump

thrust bearing coolers.

The licensee had developed several documents relating to the. isolation of SW fiow to the

safety injection pump thrust bearing; one was an engineering letter of April,9, 1993, and

another was a recent telephone memorandum dated May 21, 1993, of a conversation with the

pump manufacturer.

These documents provided information on the safety injection pumps

capability with SW flow to thrust bearing coolers isolated ifsafety injection pump initiation

occurred.

CAR 2077 action item 26 assigned to fuHy document justification of SW isolation

to the safety injection pumps was completed with the issuance of a comprehensive

design

analysis report DA-ME-93-101, on June 14, 1993.

The licensee's analysis concluded that

during monthly SW performance testing with valves 4738 and 4739 in closed position,

complete loss of SW cooling to the safety injection pump thrust bearing did not affect

operability of the safety injection pumps.

The inspector reviewed the SW valve corrective maintenance history and determined there

were two prior instances of stem separations from discs due to severe disc corrosion.

These

occurrences

were valve 4675 in May 1990 and valve 4690 in April 1992.

Both valves were

the Crane model 101 type and were in the nonsafety-related

portion of the SWS.

No plant

incident reports were written because

the valves were nonsafety-related.

Based on interviews

with engineering and management personnel the inspector determined that although there was

no documentation that established why the safety-related valves were considered satisfactory

at that time, there was discussion concerning similar valves in the safety-related portions of

the SWS.

Acceptable and consistent SW pump performance tests, unchanged normal

operating parameters,

and the two loop SWS configuration capability to withstand a single

failure and not render SWS inoperable were some of the licensee's

reasons why the safety-

related valve repairs could be made in 1993.

The inspector also reviewed the current maintenance

requirements

and determined there were

no periodic preventive maintenance required inspections of SWS valve internals.

Motor-

operated valves require stroke testing on a quarterly or monthly basis and diagnostic testing

on a periodic basis.

Manual valves have no requirements for stroke testing.

Failure to promptly identify the failed condition of valves 4669 and 4738 is contrary to

10 CFR 50, Appendix B, Criterion XVI, requirements

to promptly identify and correct

nonconfoimance conditions and is an apparent violation (EI 50-244/93-08-01).

1.4

Observations of In-Process Work

The inspector observed

the removal of Crane model 101 valves 4013, 4027, 4028, and 4675.

Each of these valves had significant amounts of silt build-up in the valve inlets and in the

piping at the valve inlet. The valve internals and bodies had significant corrosion deposits

and the discs and body guides were badly corroded.

The stems were found to be undamaged

once the external corrosion product was removed from the stem T-slot area.

The exposed

piping viewed by the inspector had build-up of corrosion product type nodules of

approximately 1/8" to 3/8" on all internal surfaces; however, there did not appear to be any

wall thinning at the exposed pipe cuts.

The inspector observed a significant number of other

removed SW valves and internals and assessed

their material condition as poor.

The inspector noted that engineering had taken actions to improve silt removal by extending

flush times at the auxiliary feedwater pump valves, realigning the flush flow.path to the

turbine driven auxiliary feedwater pump valves, and submittal of an EWR to increase the

drain line size.

1.5

Service Water Leak in Screen House

The inspector reviewed the nonconformance report NCR 92-001 and subsequent

correspondence

relating to the licensee's identified underground SW leak in the screen house.

The interim use justification dated January

14, 1992, provided basis for continued

operability, hypothesized

on possible leak locations, and presented generalized

measures

to

identify significant leakage increases.

The NCR interim use expiration was June 30, 1993.

A request for the second interim use extension through June 30, 1994, was issued on

March 18, 1993.

The licensee's

basis for the second extension included the earlier

measures.

Additional reasons for the extension were to institute measures

to locate, quantify

and assess

the leak and to develop an adequate repair plan.

The licensee's EWR 5405 to

permit robotic viewing of the SW underground piping was also delayed until the 1994 outage

due to the higher priority containment recirculation fan cooler installations performed in the

'993

outage.

The licensee has installed an elapsed time counter on the screen house sump

pump and has determined the leak to the sump to be approximately

1 gpm.

Additionally,

auxiliary operators on their 8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> tours log the elapsed time on the counter and are required

to notify management of any significant time change indicating increased leak rate.

1.6

Conclusions

The licensee's SW valve improvement program was aggressively expanded after the failures

of valves 4669 and 4738 were identified during 1993 outage.

However, the licensee was

unaware for some period of time that these two locked open valves had failed in closed

position and measures

to identify and correct defective SW valves was not timely considering

the two identical failures of Crane model 101 valves discovered in May 1990 and

April 1992.

2.0, Management Meetings

Licensee management

was informed of the scope and purpose of the inspection at the

beginning of the inspection.

The inspection was continued with an additional site visit on

May 24-28, 1993, to reconfirm licensee's actions on earlier valve failures and other service

water issues,

and on June 14-18, 1993, to review the licensee's design analysis that assessed

the safety injection pump operability.

The findings of the inspection were discussed with the

licensee management

at the April 16, 1993, May 28, 1993, and June 18; 1993, exit

meetings.

The licensee acknowledged the inspection findings.

Attendees at the exit meetings

are listed in Attachment 1.

,(

ATTACEBHFAT1

Persons Contacted

h

r

as

nd Electri

ti n

0

+S. Adams, Technical Manager

J. Bettle, Preventive Maintenance Engineer

+R. Bryan, Station Engineer

B: Carrick,'r. Mechanical Engineer

+~1. Cook, Technical Manager

  • J. Fischer, Maintenance Planning and Scheduling Manager

+N. Goodenough,

Maintenance Corrective Action Analyst

G. Herrick, Maintenance Analyst

W. Harding, Modification Control Engineer

J. Janney, Project Manager, MOVATS

x+R. Jaquin, Licensing Engineer

+S. Lawlor, Associate Mechanical Engineer

  • ¹ Leone, Quality Improvement Specialist
  • R. Marchionda, Superintendent Support Services

+*R. Mc Mahon, Quality Control Engineer

x+T. Newberry, Sr. Mechanical Engineer

~R. Ploof, Technical Engineer

+*W. Rapin, Modification Support Engineer

+T. Schuler, Operations Manager

+*J. St. Martin, Corrective Action Coordinator

  • J. Wayland, Reactor Engineer

x*P. Wilkens, Manager Nuclear Engineering Services

  • J. Widay, Plant Manager, R. E. Ginna

~G. Wrobel, Manager, Nuclear Safety and Licensing

N iclear R

lat

mmi in

x"T. Moslak, Senior Resident Inspector

+E. Knutson, Resident Inspector

  • denotes those present at the exit meeting on April 16, 1993.

+ denotes those present at the exit meeting on May 28, 1993.

x denotes those present at the exit meeting on June 18, 1993.