ML17250B242

From kanterella
Jump to navigation Jump to search
Insp Rept 50-244/91-80 on 910506-0607.Violations & Deviations Noted.Major Areas Inspected:Functionality of Electrical Distribution Sys
ML17250B242
Person / Time
Site: Ginna Constellation icon.png
Issue date: 08/21/1991
From: Anderson C, Cheung L
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML17250B239 List:
References
50-244-91-80, NUDOCS 9109060005
Download: ML17250B242 (66)


See also: IR 05000244/1991080

Text

U.

S.

NUCLEAR REGULATORY COMMISSION

REGION I

Report

No.

Docket No.

License

No.

Licensee:

50-244/91-80

50-244

DPR-18

Rochester

Gas

and Electric Corporation

89 East Avenue

Rochester,

New York

14649

Facility Name

Ginna Nuclear

Power Station

Inspection

Conducted:

May 6 through June

7,

1991

Inspection

Team

L. Cheung,

Team Leader,

'RI

J.

Lara,

Reactor

Engineer,

RI

R. Mathew, Assistant

Team Leader,

RI

NRC Consultants:

M. Goel,

Mechanical

Engi'neering,

AECL

S. 'Inamdar, Electrical Engineer,

AECL

J.

Leivo, Leivo Associates

P repared

By:

Le nard Cheung,

Team Leader,

El

Engineering

Branch

Section,

ate

Approved By:

CD J.

An

rson,

hief, Electrical Section,

date

Engineering

Branch,

DRS

Inspection

Summary:

Ins ection

on

Ma

6 throu

h June

7

1991

Re ort No. 50-244/91-80

Areas

Ins ected:

Announced

team inspection

by regional

and contract personnel

to review the functionality of the electrical distribution system.

Results:

As described

in the Executive

Summary.

9.'i QPQ/>QQQR

P i Q~~ ~ g

PDR

AGCICK QHQQ<):3+4

F riF

0

4

Table of Contents

EXECUTIVE SUMMARY .

1. 0

INTRODUCTION

2.0

ELECTRICAL SYSTEMS

2. 1

Offsite Power and Grid Stability

2.2

Bus Alignment During Start-Up,

Normal

and

Shutdown Operation

2.3

Bus Transfer

Schemes

2.4

Emergency

Diesel

Generators

.

2.5

Degraded

Voltages

on Class

1E Buses

.

2.6

Over-Voltage

on Class

1E Motors

.

2.7

AC Systems

Short Circuit Review

.

2.8

Protection of Class

1E Motors

2.9

Selection

and Sizing of Power Cables

2.10 Electrical Penetration

Sizing and Protection

2.11

120

Vac Class

1E System

2.12

125 Vdc Class

1E System

2.13 Conclusion

3.0

MECHANICAL SYSTEM

3. 1

Power

Demands for Major Loads

.

3.2

Diesel

Generators

and Auxiliary Systems

.

3.3

Heating, Ventilating and Air Conditioning System

3.4

Service Water System

3.5

Conclusion

PAGE

8

12

13

14

15

15

16

17

18

19

19

19

22

24

25

0

Table of Contents

4. 0

.

ELECTRICAL DISTRIBUTION SYSTEM

E UIPMENT........

~ ..

25

4. 1

Equipment Walkdowns

.

4.2

Equipment Maintenance

and Testing

.

4.3

Protective

Device Setpoint Control

and Calibration

4.4

Conclusion

5.0

ENGINEERING AND TECHNICAL SUPPORT

5. 1

Organization

and

Key Staff

5.2

Root Cause Analysis

and Corrective Action Programs

5.3

Self Assessment

Programs

5.4

Equipment Modifications

5.5

Temporary Modification Program

5.6

Engineering Support/Interface

.

5.7

Technical Staff Training

5.8

Conclusions

6.0

UNRESOLVED ITEMS

7. 0

EXIT MEETING

ATTACHMENT 1

Persons

Contacted

ATTACHMENT 2

Electrical Distribution System One-Line Drawing

25

26

28

31

32

32

32

33

34

36

36

37

37

38

38

EXECUTIVE SUMMARY

During the period between

May 6 and June 7,

1991,

a Nuclear Regulatory

Commission

(NRC) inspection

team conducted

an Electrical Distribution System

Functional

Inspection

(EDSFI) at Ginna Nuclear

Power Station.

The inspection

was performed to determine if the. Electrical Distribution System

(EDS) was

capable of performing its intended

safety functions

as designed,

installed,

and

configured.

The team also assessed

the licensee's

engineering

and technical

support of EDS activities.

For these

purposes,

the team performed plant

walkdowns

and technical

reviews of studies,

calculations

and design drawings

pertaining to the

EDS,

and interviewed corporate

and plant personnel.

Based

upon the

sample of design drawings,

studies

and calculations

reviewed

and

equipment

inspected,

the

team determined that the electrical distribution

system at Ginna Station is capable

of performing its intended functions.

In

addition,

the

team concluded that the engineering

and technical

support staff,

both at the Ginna Station

and at the corporate offices in Rochester,

New York,

provide adequate

support for the safe operation of the plant.

The inspection

also identified one violation, two deviations,

and three

unresolved

i'tems,

as discussed

in the paragraphs

below.

In addition,

one previously identified

item (Violation 50-244/89-81-06)

was closed,

as discussed

in pa'ragraph

4.2.2.

i

The licensee

has

implemented controls to maintain the electrical

system

configuration.

Equipment inspected

was observed to be well-maintained

and

an

effective fuse control

program

was evident.

The development of a molded

case circuit breaker test

program is ongoing.

The testing attributes

being

addressed

are comprehensive

and thorough.

A deficiency

was identified in

handling the as-found data of the protective relay testing.

The dropout

voltage settings of three protective relays drifted below the Technical

Specification limits during the

1991 refueling outage yet

no evaluation

was

performed

as required

by station

procedures.

The corporate

and site technical

engineering

and modification support personnel

are adequately

staffed with competent

personnel

and are very familiar with the

EDS and its support

systems.

Effective interfaces

exists

between

station

and

engineering

personnel.

Communications

between

the various engineering

and

technical

support organizations

were

found to be good.

Engineering

support to

operating

and maintenance

activities was determined to be good.

The team

determined that the licensee

has

an aggressive

self assessment

program

and

considered this to be

a strength.

The licensee

has

a good program to investigate deficiencies,

identify root

causes

and to complete appropriate

corrective actions

in

a timely manner.

Technical training and guality Assurance

Programs

were

found to be adequate.

The team observed

several

examples

of a lack of attention to detail in the

design calculation process.

The examples

included power demand calculations for

the diesel

generators,

circuit breaker coordination calculations,

battery

room ventilation and hydrogen concentration

calculations

and

use of incorrect

fuel oil storage

requirements.

Corrections of these calculations

were

completed during the inspection

except for circuit breaker coordination which

is an unresolved

item.

Part of this weakness

was due to the fact that the

licensee's

engineering

personnel

had generated

a large

volume of design

calculations within a,short

time before this inspection.

Increased

management

involvement to improve the existing design control process

and quality of engineering

work was demonstrated

by the completion of P&ID

Update

Program, Electrical Configuration Controlled Drawing Program,

Engineering

Work Request

(EWR) Procedure

upgrades,

ongoing Design Basis

Reconstitution

Program and.Configuration

Management

Control

Program.

Improvement in the licensee's

design control

and modification process

was noted

during this inspection.

The inspection

findin'gs are

summarized

as follows:

One Violation

Discussed

in

Para

ra

h

Item Number

Protective relay settings

.

drifted below Technical

Specification limits

and were not evaluated

Two Deviations

1. Onsite

power supply not

meeting the single

failure criterion

4.3.3

2.2

50-244/91"80-04

50-244/91-80-01

2.

Redundant control cables

of component cooling

water

pump control

circuits were not

adequately

separated

Three Unresolved

Items

2.2

50-244/91-80-02

1. Completion of a

comprehensive

coordination analysis

for all circuit breakers

2.8

50-244/91-80-06

2.

Degraded

voltage effects

on Class

lE Motors

3. Completion of dynamic

response

analysis of

emergency diesel

generator, loading

2.5

2.4.2

50-244/91-80-05

50-244/91-80-03

Three Observations

1. Unprotected diesel

generator

output cables

2.4.6

2. Undersizing of

certain circuit

breakers

2.7

3.

Lack of loss of

field protection

for emergency

diesel

generators

2.4.5

One Meakness

lack of attention to detail in the desi

n calculation

rocess

examples:

1.

Power demand calculation

for the diesel

generator

2. Circuit breaker

coordination

calculations

3. Battery

room

ventilation

and

hydrogen concentration

calculations

3.1

2.8

3.3.5

4.

Use of incorrect fuel

oil specific gravity in

calculating the fuel oil

storage

requirements

3.2.1

1. 0

INTRODUCTION

During inspections

in the past years,

the Nuclear Regulatory

Commission

(NRC)

staff observed that, at several

operating plants in the county, the

.

functionality of related

systems

had

been

compromised

by design modifications

affecting the. electrical distribution system

(EDS).

The observed

design

deficiencies

were attributed,

in part, to improper engineering

and technical

support.

Examples of these deficiencies

included:

Unmonitored

and

uncontrolled

load growth on safety related

buses;

inadequate

review of design

modifications;

inadequate

design calculations;

improper testing of electrical

equipment;

and

use of unqualified commercial

grade

equipment

in safety related

applications.

In view of the above,

the

NRC developed

an Electrical Distribution System

Functional

Inspection

(EDSFI) program for operating plants.

There are

two

objectives for the

EDSFI.

The first objective is to assess

the capability of

the electrical distribution system's

power sources

and equipment to adequately

support 'the operation of safety related

components.

The second objective is to

assess

th'e performance

of the licensee's

engineering

and technical

support in

this area.

To achieve

the first objective,

the inspection

team reviewed calculations

and

design

documents.

Particular attention

was paid to those attributes

which

ensure that quality power is, delivered to those

systems

and

components

which

are relied upon to remain functional during and following a design basis

event.

The review covered portions of onsite

and offsite power sources

and included

the 34.5

kV offsite power grid, station auxiliary transformers,

4. 16

kV power

system,. emergency-diesel

generators,

480

V Class

1E buses

and motor control

centers,

station batteries,

battery chargers,

inverters,

125

Vdc Class

lE

buses,

and the

120

Vac Class

1E vital distribution system.

The team verified the adequacy

of the emergency

onsite

and offsite power

sources for the

EDS equipment 'by reviewing regulation of power to essential

loads, protection for calculated fault currents, circuit independence,

and

coordination of protective devices.

The team also assessed

the adequacy

of

those

mechanical

systems

which interface with and support the

EDS.

These

included the air start,

lube oil,. and cooling systems for the emergency

diesel

generator

and the cooling and heating

systems

for the electrical distribution

equipment.

A physical

examination of the

EDS equipment verified its configuration

and

ratings

and included original installations

as well as equipment installed

through modifications.

In addition,

the team reviewed maintenance,

calibration

and surveillance activities for selected

EDS components.

The team's

assessment

of capabilities

and performance of the licensee's

engineering

and technical

support covered organization

and

key staff, self

assessment

program

and technical training, temporary

a'nd permanent

plant

modifications, operating

procedures

for EDS, root cause

analysis

and corrective

action programs

and engineering

support in design

and operations

and their

interface.

In addition to the above,

the team verified general

conformance with General

Design Criteria

(GDC)

17 and

18, Systematic

Evaluation

Program

(NUREG 0821

and

Supplement

1),

and appropriate criteria of Appendix

B to 10 CFR Part 50.

The

team also reviewed the plant's Technical Specifications,

the Updated Final

Safety Analysis Report

and appropriate

safety evaluation reports to ensure that

technical

requirement's

and licensee's

commitments

were being met.

The details of specific areas

reviewed,

the team's

findings and the applicable

conclusions

are described

in Sections

2 through

5 of this report.

2.0

ELECTRICAL SYSTEMS

The characteristics

of the power system electrical grid to which the Ginna

plant is connected

were reviewed to assess

the adequacy

of important

parameters

such

as voltage regulation,

short circuit contribution, protective

relaying,

surge protection, control circuits, stability, and reliability.

The

station auxiliary (startup)

transformers

were reviewed in terms of their

kilo-volt-amperes

(kVA) capability, their connections

to the safety buses,

protection,

and voltage regulation.

The emergency

diesel

generators

(EDGs)

were reviewed to assess

the adequacy of the kilo-watt (kW) rating,

the ability

to start

and accelerate

under assigned

safety

loads in the required time

sequence,

the voltage

and frequency regulation, under transient

and steady

state

conditions,

compliance with single failure criteria,

and the applicable

separation. requi.rements.

The

480

V safety buses

and their connected

loads were

reviewed to assess

load current

and short circuit current capabilities,

voltage

regulation, protection,

adequa'cy

of cable connections

between

loads

and buses,

compliance with single failure criteria,

and applicable

separation

requirements.

The team reviewed the regulation of the

EDS loads,

the overcurrent protection,

and coordination of protective devices for compliance with regulation,

design

engineering

standards,

and accepted

engineering

practices.

The review included

system descriptions,

station

Updated Final Safety Analysis Report

(UFSAR),

equipment specifications,

licensee

event reports

(LERs), operating

procedures,

one line diagrams,

and equipment

layout drawings.

The team also reviewed procedures

and guidelines

governing the

EDS design

calculations,

design control

and plant modifications,

and

EDS single line

diagrams

and wiring schematics.

A simplified single line diagram of the Ginna

EDS is

shown

on Attachment 2.

, 2. 1

Offsite Power

and Grid Stabi lit

The Ginna Station receives its power from two independent

34.5

kV circuits

(circuit 751

and circuit 767).

Circuit 751- receives

34.5

kV direct from the

RG&E station

204 and circuit 767 receives

34.5

kV from the Ginna switchyard

station

13A via the

115

kV to 34.5

kV stepdown transformer

No. 6.

Four

115

kV lines (908,

911,

912,

and 913) connect to substation

13A through

the breaker-and-a-half

technique of switching.

This arrangement

provides the

versatility of dual

feed for each line and the ability to remove

any breaker or

transmission

line without deenergizing

any other part of the substation.

The Ginna electrical

power system

was initially designed with a single

auxiliary ( startup)

transformer

12A but

a spare

transformer

'12B was

added after

the beginning of commercial

operation.

However,

the station continued to

operate with only one auxiliary transformer

feeding all safety related

loads.

To increase

the availability margin in the event of a single

system failure,

the 34.5

kV bus

was split and the

system

was re-configured in 1989 to its

present

state.

Each of the auxiliary transformers

is rated

34500-4160-4160

V, 28-41.8

MVA.

These

two transformers

have

two load ratings associated

with them,

the

OA

(oil-air) and the

FA (forced-air) rating .

All safety

loads are supplied

by 'the

these transformers,

however,

according, to 'Load flow and voltage profile

analysis'ocument

No.

EEA-03001,

Revision 0,

each of these

feeders

is capable

of supplying the entire load.

The worst case

loading for the

12A and

12B

transformers

occur when the main generator trips and when all auxiliary loads

are connected

to the offsite grid.

Maximum system loading is 29.6

MVA, split

evenly between

the two secondaries.

The safety related

buses

do no't have

access

to either the main generator

output system or the

115

kV network.

The safeguards

or

1E distribution is divided into two redundant

and completely

independent trains,

A and

B.

'Train A and

B are

each

made

up of two safeguards

480

V buses.

Train A consists

of buses

14 and

18 while train

B consists

of

buses

16 and

17.

2.2

Bus Ali nment Durin

Startu

Normal

and

Shutdown

0 eration

During normal operation,

the main generator

feeds electrical

power at

19

kV

through

an isolated

bus to

a 19-120

kY stepup transformer.

The bulk of the power

required for auxiliaries is supplied

by unit auxiliary transformer

11,

connected

to

a

19

kY isolated

phase

bus

~

During normal

shutdown all auxiliary loads

are transferred

to the station

auxiliary transformers

12A and

12B.

During startup operation all station

loads are energized

from auxiliary

transformers

12A and

12B.

Bus

11B is connected

to bus

12B and bus

11A is

connected

to bus

12A.

After successful

startup

the operator manually transfers

buses

11A and

11B to the main generator.

When the main generator trips, the plant auxiliary loads

from the transformer

are automatically transferred to buses

12A and

12B by closing tie breakers

BTB-B

and BTA-A.

Upon loss of offsite power the loss of voltage relay

on 480

V

emergency

buses

14,

16,

17 and

18 will start the emergency

diesel

generators

DG A and

DG

B and connect

them to their respective

buses.

While reviewing the emergency

bus'es configuration,

the team identified

a design

deficiency in the 'emergency tie breaker

arrangement

between

buses

17 and

18 in

the screenhouse.

Bus

17 (train B) and

bus

18 (train A) are tied with a single

breaker (BT17-18).

Interlocks are provided to prevent closure of the

tie breaker if more than

one

AC power source

were serving the Class

1E buses.

To close the tie breaker,

either (a) both diesel

breakers

must be tripped .and

one offsite breaker tripped,

or (b) both offsite source

breakers

must

be

tripped and one diesel

breaker

must be tripped.

While the interlocks preventing closure of the tie breaker

were redundant,

only

one control circuit for the breaker

was provided within the switchgear;

therefore,

spurious closure of the breaker

due to

a fault in the control

circuit could be postulated

during an event requiring onsite

power sources.

If this occurs

when both EDG's are running out of phase,

buses

17 and

18 plus

one of buses

14 and

16 could be lost (assuming

one of the

EDG breakers trips

before tiebreaker

BT17-18,

because

of a lack nf a comprehensive

breaker

coordination

program).

The team concluded that this design deficiency

constitutes

a deviation

from paragraph

3. 1.2.2.8 of Ginna Updated Final Safety

Analysis Report

(UFSAR), General

Design Criterion 17, which states,

in part,

"the onsite electric

power supplies,

including the batteries,

and the onsite

electric distribution system,

shall

have sufficient independence,

redundancy,

and testabi lity to perform their safety functions assuming

a single failure"

(50-244/91-80-01).

In response

to the team's

concern,

the licensee

withdrew the tiebreaker to the

test position,

so that the tiebreaker

cannot

be closed inadvertently during

plant operation.

The licensee

also revised

the affected

procedures

to accom-

modate this new'onfiguration.

While reviewing the control logic for the component cooling water

(CCW)

pump

operation,

the team identified that

125 Vdc control circuit conductors

from

Train A and Train

B Component Cooling Water

Pumps

shared 'the

same four-

conductor cable.

The cable

was routed within a relay cabinet,

through

a

conduit,

and into a cable tray.

This deviates

from UFSAR Paragraph

8.3. 1.4.2,

Separation

of Redundant Circuits, which states,

in part, "All components

requiring redundant

cabling,

as well as the cabling for redundant

components,

have

been identified and the redundant

power, instrumentation,

and control

cables

are run separately."

This constitutes

a deviation (50-244/91-80-02).

The licensee

stated that this deficiency will be corrected

during the next

refueling outage.

~

~

I

The above

separation

deficiency combined with the ground detection

procedure

(Procedure. M-38.23) could cause

operational

problem of the

CCW system.

According to Procedure

M-38.23,

removal of grounds in the

DC system is not

mandatory-,

and could permit

a ground to persist for a long time.

Suppose

two

conductors of the unseparated

cable are shorted to the conduit (this may be due

to cable insulation deterioration).

If this condition is not isolated

and

corrected

and

a second

ground develops

somewhere

in the

DC system negative

side

(either in Train A or Train B),

a hidden potential

problem will be created.

The

CCW system would appear to function normally until

a postulated

accident

occured.

When this happened,

assuming

the

EDG's started, all

CCW pumps would

be de-energized initially (per load sequencing

requirements).

When restart of

the

CCW pumps is later required,

the short-to-ground

would blow (and continue

to blow) the fuses of the control circuits, causing'oth

CCW pumps to be

inoperable.

According to the licensee,

the plant had about

12 to

18 grounds

per year in the

DC system.

In response

to the team'

concern,

the licensee

checked with the plant to

confirm that

no ground currently existed in the

DC system.

The licensee

also

initiated

a revision of Procedure

M-38.23 to strengthen

isolation

and correc-

tion of detected

grounds

in the

OC system.

The licensee

also conducted

a

comprehensive

analysis

to determine if other similar situations exist in the

design.

The team

had

no further questions.

2.3

Bus Transfer

Schemes

The team reviewed the transfer

schemes

to ensure that transfer occurs without

any inrush in the

system 'and without adversely affecting any class

1E

equipment.

The team noted that during any maintenance

work on transformer

12A or 12B, the

loads

are normally transferred

to the unaffected

side

by closing ei .her breaker

12AX or 12BY as required.

The operator follows procedure

0-6.9.2

"Establishing and/or transferring offsite power to bus

12A/bus 12B."

The team

was

concerned that the procedure

did not address

the

maximum permitted

phase

angle shift between

the

two sources.

Since the transfer is

'make before

break'he

out of phase transfer could cause

high inrush currents

and high transient

torques at the motor shaft.

The licensee

stated that its preliminary analysis

indicated that the

maximum

phase shift between

buses llA and

11B,

12A and

12B,

and

PPSX

and

PPSY will not

exceed

15 degrees,

based

on simulations that considered

reasonable

contingency

conditions.

The team determined that this response

is acceptable

based

on the

fact that 1) During normal operation

the Class

1E buses

are lightly loaded

and

hence

the voltage drop

on these

buses will not be very significant; 2) A 15

degrees

phase difference will not cause

an appreciable

inrush current.

2.4

Emer enc

Diesel Generators

EDG

The

EOGs consist of two Alco 16 cylinder Model

251F engines

coupled to

a

Westinghouse

1950

kW (continuous rating), 0.8 power factor,

900 rpm,

480 Vac

generator.

The team reviewed the licensee's

steady-state

and dynamic loading

analyses

for

EDG 1A, since

these

analyses

indicated that

EDG 1A had lower

loading margins

than

EDG 1B.

The acceptance

criteria for these

analyses

were

that the short-time ratings would not be exceeded

and the minimum voltage

and

frequency recovery requirements

of Regulatory

Guide 1.9 would be met.

The team

reviewed the licensee's

assumptions,

analytical

procedures,

and results with

respect

to those criteria.

Protection of the

EDGs was also reviewed.

This is discussed

as follows.

2.4. 1

Stead

State

Loadin

Anal sis

The team reviewed the Licensee's

Design Analysis

EEA-01002,

"Diesel Generator

1A Steady State

Loading Analysis", Revision 0, dated

May 6,

1991 to ensure that

the loading was within the capability of the

EDG rating.

The team identified two discrepancies.

The first involved an incorrect deter-

mination of brake

horsepower for the residual

heat

removal

pumps

and the safety

injection pumps.

The effect of this error

was to add 20.6

kM to the load

on

each

EDG.

The Licensee

updated

the data

base accordingly during the inspec-

tion,

and demonstrated

that there

was

no substantial

effect

on the existing

load margin.

This issue is also discussed

in Paragraph

3. 1.

The second discrepancy

in the steady-state

calculation

involved the licensee's

incorrect

and nonconservative

assumption

that "The

EDG can

be loaded to its

two-hour rating immediately after it has

been

loaded to its 30 minute rating".

This assumption

for short-time rating is not permissible

by Regulatory

Guide

1.9 and

IEEE Standard

387-1984,

which defines the short time rating as:

"The

electrical

power output capability that the diesel

generator unit can maintain

in the service

ehvironment for 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> in any 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> period, without

exceeding

the manufacturer's

design limits and without reducing the maintenance

interval established

for the continuous rating." Based

on the above,

the team

concluded that the

2 hour2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> rating could not be applied again for at least

22

hours.

During the inspection,

the licensee

re-evaluated

some of its conservative

assumptions,

and re-adjusted

the operating

time of the safety injection

pump to

58 minutes instead of 2.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br />.

They demonstrated

that the short-term

and

continuous

loading of the

EDG does not exceed

the

EDG rating at any time.

The

team did not have

any further questions.

2.4.2

D namic Loadin

Anal sis

The team reviewed the licensee's

Design Analysis

EEA-01001,

"Diesel Generator

Dynamic Loading Analysis," Revision 0, dated

May 6,

1991.

The licensee

had

identified this analysis

as

an interim use

document for providing reasonable

assurance

that the

EDGs were properly sized to meet their loading requirements.

The licensee

stated that they intended to revise

and refine the analysis

as

more data

became

available

from field testing.

t

10

On the forgoing basis,

the team concluded that the licensee's

general

approach

to the analysis

was acceptable.

However,

the licensee

had identified several

unverified assumptions

in the analysis.

These

included unvalidated

model

software,

unknown constants

for the exciter

and the governor,

and unretrievable

v'alues for speed-torque

curves

and motor inertia.

The licensee

committed to

complete the final dynamic loading analysis,

including justification of the

unverified assumptions,

by May 1992.

This is an unresolved

item pending

NRC

review of the final analysis

(50-244/91-80-03)

~

2.4.3

Emer enc

Diesel Generator

Protection

The team reviewed the co-ordination

curves for breakers

EG1A1,

EG1A2,

EG1B1,

1B3,

and

EG1B2 which provide the protection for the

EDG.

The team observed that the co-ordination

study did not contain sufficient

information to evaluate

the adequacy

of the protective devices.

The curves

lacked the following information:

1) The maximum and minimum loads

on the

generator

breakers;

2) The maximum and minimum fault currents;

3) The cable I>t

curves;

4) The generator

damage

curve;

5) The decremental

characteristic

of the

EDG and the time/current charasteristic

of voltage control overcurrent relay

(51V) .

During the inspection

the licensee

provided additional

information to support

the coordination of the

EDG breakers.

They demonstrated

that the

EDGs were

adequately

protected.

The licensee

agreed to include this information into the

coordination analysis

program discussed

in Section 2.8.

The team concluded

that the

EDGs were adequately

protected

against

overloads

and did not have

any

further questions.

2.4.4

Emer enc

Diesel Generator

Field Ground Fault Protection

The team reviewed the

EDG wiring diagram

and was concerned

that the field was

not protected

against

ground faults nor was there

any alarm to warn the

operator of

a fault situation.

The generator field circuit is ungrounded.

Thus

a single ground fault will not

result in equipment, damage,

or affect the operation of the generator.

If,

however,

a

second

ground fault should occur,

there will be

an unbalance

in the

rotor magnetic field.

This unbalance

may be enough to develop destructive

vibrations within the generator.

The licensee

acknowledged this concern

and stated

t,hat the probability for the

field circuit to have

a second

ground was very low and that this was not

a

safety issue

since in the case of the loss of one

EDG, there

was still

another

EDG available.

The team

had

no further questions.

0

1'I

11

2.4.5

Emer enc

Diesel Generator

Loss of Field Protection

The team observed that the

EDG did not have loss of field protection for the

EDG nor was there

an alarm to warn the operator of this condition.

This

protection is of value

when the

EOG is being tested

and connected

in parallel

with the grid.

Should

a generator

lose its field excitation during testing, it

will continue to operate

as

an induction generator

obtaining its excitation

from the grid.

This causes

the generator rotor to quickly overheat

due to

induced slip frequency currents.

The licensee

stated that this type of

protection is not generally provided

on 480

V generators.

However,

in nuclear

power plants,

where the availability of safety support

system is of importance,

this feature

would minimize failures during testing.

This is not considered

a safety issue

because

only one

EDG would be affected. at

a time.

2.4.6

Un rotected

Cables

Connected

to the

Emer enc

Diesel Generators

The team reviewed the

AC Electrical

System

One Line Diagram,

Drawing Number-

33013-2409

and found that the two cables

feeding

480

V buses

14 and

18 were

directly connected

to the

EOG without any protection.

The team

was concerned

with the potential for a fault at the

end of the unprotected

long screenhouse

feeder cables

since the cables

are buried underground

and are susceptible

to

water exposure.

Normally such cables

are prone to faults and

a fault could

remain undetected

for a long period of time.

If a ground fault develops, it

can

cause

the loss of two emergency

buses.

The licensee

stated that these

cables

have not been

a problem.

Furthermore

these

cables

are meggered

annually

per procedure

M15. 1.

The team observed

that

a fault could occur between

the

testing periods.

2.4.7

Emer

enc

Diesel

Generator

Drop

Mode Alarm

During periodic testing of the

EDGs, the

EDG has to be switched in the "Droop"

(parallel)

mode

so as to enable it to be paralleled to the grid.

The team

noted that the switch position in Parallel

mode is not alarmed in the control

room.

The team

was concerned

that after the test is over,

the operator

may

inadvertently

leave the switch in the droop mode, affecting the availability of

the

EDG during

a loss of offsite power event.,

The licensee

responded

by stating that the monthly test procedures

PT 12. 1 and

PT 12.2 require the Unit/Parallel

switch be placed in the ".Unit" mode prior to

procedure

completion.

The team

had

no further questions.

12

2.4.8

Safet

Injection Si nal While Testin

Emer enc

Diesel Generator

The team noted that when the

EDGs are tested

every month, they are operated

in

the .parallel

mode (parallel with the grid). If a safety injection (SI) signal

occurs at this stage,

the following takes

place:

The two Class

1E buses

associated

with the

EDG under test are isolated

from the offsite power;

- The SI signal

does

not bypass

the 'Test'ode;

- All non-class

1E loads are tripped;

- All non-sequenced

Class

lE loads are tripped;

-, The sequencer

is initiated and loads

are connected

to the

EDG in a

predetermined

sequence;

Since the

EDG is in the parallel

mode,

the generator

terminal voltage is

not automatically regulated.

As the load increases,

the frequency

and voltage

drops,

causing

the generator

to trip on overloads

In response

to the team's

concern,

the licensee

stated that this deficiency was

known to them and

had existed

since the plant was built.

They had

raised

a

PCAQ (Potential

Condition Adverse to Quality) to correct this

deficiency

(PCAQ 8 91-029

was subsequently

issued

on June

3;

1991 for this

problem).

The team concluded that this is not

a safety

issue

since only one

EDG is

tested at

a time.

The other

EDG is available

to carry the

sequenced

load.

2.5

De raded Volta e

on Class

lE Buses

The'team

reviewed

Document

No.

EEA-03001,

Rev.

0, dated April 27,

1991,

"Loadflow and Voltage Profile Analysis" and

Document

No.

EWR 4525-2,

Rev.

1,

dated July 24,

1990,

"Adequacy of Electric System Voltages".

The team noted

that each

safeguards

bus (14,16,17

and

18)

had four undervol tage relays to

sense

both

a complete

loss of voltage

and also

a degraded offsite source.

The

four relays

were divided between

type 27D, which was

used to detect

a complete

loss of voltage,

and type 27, which detected

abnormally

low voltage.

Any one

of the four undervoltage

relays could start the

EDG associated

with its train.

However,

two relays were required to cause tripping of the bus breaker.

The

degraded

voltage relays

on Class

1E buses

14,16,17

and

18 were set to trip at

418 V, and loss of voltage relays

were set to trip at 372 in 0.5 seconds

~

The team noted that the analysis

did not include the effect of degraded

voltage

on

some of the Class

1E motors.

The licensee

provided preliminary computer

results indicating expected

voltages

on

some of the Class

1E motors'uring

worst case conditions with LOCA loads

on the system, if the grid voltage dips

to 116.47

kV, the Class

lE bus

14 could be at 418 V.

This may not cause

tripping of the degraded

voltage relay.

This condition

may result in motors

13

'perating

at

a degraded

voltage at the motor terminal.

In response

to the

NRC

concern,

the licensee

carried out

a preliminary study for large motors

and

found that there

was

no concern

except for the

RHR pum'p motor.

The study

revealed that the voltage at the terminal of

RHR pump

1A could be as

low as

413

V. 'The threshold operating voltage limit for this motor is 414

V.

Below this

voltage the motor could get overheated

causing

degradation

of the motor winding

insulation.

However,

the team concluded that 413

V is close to the threshold

voltage of, 414

V and this degraded

voltage condition will not last long enough

to cause

damage

to the motor winding.

However, the team

was concerned

about degraded

voltages at

some of the Class

1E

MCCs.

For example

MCC

1C could have

a degraded

voltage of 411

VS

The study

did not analyze

the voltage levels at the terminals of all vital loads supplied

from Class

1E

MCCs that are required to operate

during accident conditions.

Therefore,

the

team could not determine if such motors could operate

safely

under the degraded

voltage condition.

The licensee

committed to complete the

analysis of the degraded

voltage situation,

on

a motor by motor basis,

by- June

1992.

This is an unresolved

item pending

an

NRC review of the analysis

(50-244/

91-80-05).

2.6

Over-Volta es

on Class

lE Motors

The team reviewed

Document

No.

EEA-03001,

Rev.

0,

"Load Flow and Voltage

Profile Analysis ", to determine if any of the Class

1E loads could be

subjected

to

a high voltage during lightly loaded conditions or grid voltage

fluctuations.

The team noted that there were

no restrictions

on overvoltage

operation

in the Ginna Station Technical Specification or UFSAR.

The team

observed that the

maximum voltage

seen at bus 17'could

be as high as

496

V.

The team was specially concerned

about the

300

HP Service Water

Pump which

would'be subjected

to voltages

beyond its rating (440

V +10

% = 484 V) while

operating

in the 1. 15 service factor (SF) range

(EWR 4232,

Revision 0, dated

May 9,

1980

" Insitu Motor Load Determination

" indicated that the above motor

could operate

in the

1. 15

SF range during

a design basis accident).

The licensee

presented

a letter dated January

21,

1980,

from Westinghouse

Electric Corporation

(WEC) stating that the average

temperature

rise of the

above motor was 68'C at 500

V and 72'C at 515 V, which is below the

90

C

temperature

rise (above

40'C ambient) allowed for a Class

B insulation

system.

The team however noted that the letter did not specify if the temperature

rise

calculations

were done for a service factor of

1 or 1. 15.

The licensee

gave further clarification of the

WEC letter stating that the

temperature

calculations

were based

on the

maximum winding resistance

temperature

immediately after starting the motor and not the steady

state

winding resistance.

With continuous

operation this temperature will decrease.

The team did not have

any further concern with this issue.

14

2.7

AC

S stem Short Circuit Review

The team reviewed

EWR 4525-1, "Fault Current Analysis of Power Distribution

System",

Revision

1, dated July 27,

1990, to determine if the Class

lE

equipment

was properly sized to withstand the available short circuit current.

The team noted the interrupting current ratings of the Class

1E 480

V circuit

breakers

are

as follows:

Bus

Ratin

Am

s

s

m.

14

8( 16

17

8( 18

DB-50

DB-25

50,000

30,000

The team observed

that the fault currents

were significantly above the breaker

ratings

when either

EDG was running in the test

mode.

The test

mode configur-

ation required

EDG

1A to be paralleled with both its

1E buses

(14

8 18).

Similarly, the test

mode configuration for

EOG

1B required it to be

paralleled with both of its Class

1E buses

(16

& 17).

The calculated fault

currents

were

as follows:

Bus

Without

EDG

With EDG

14

16

17

18

39,099

39,463

24,336

22,260

55,337

56,418

51,148

48,879

The licensee

stated that they had evaluated

the probability of such

an fault

current occurring

and found it to be very low (3xl0-'er year).

2.8

Protection of Class

lE Motor s

The team reviewed Amptector Response

Characteristics

for several

large Class

1E

motors

and was concerned

that the curves did not include the motor character-

istic for degraded

voltage situations.

In some

cases

the margin between

the

motor full load current

and the lower band of the pickup current

was very

narrow.

This could cause tripping of a motor at degraded

voltage conditions

while attempting to start or while operating

in the service factor zone during

an accident condition.

The industrial practice is to set the pickup at

115-125% for motors with a 1.00 service factor and

125-140% for motors with a

1. 15 service factor.

The team

was specially concerned

about the Containment

Recirculation

Fans

and the Service

Water

Pumps where the margin between

the

full load current of the motor and the lower band of the relay pickup set point

was very small.

The licensee

provided preliminary calculations

which indicated

that there

was

no cause for concern.

However,

the acceleration

time was based

on

an Electrical Transient Analyzer Program

( ETAP) that modeled

these

two

motors,

since the acceleration

time characteristics

at various voltages

were

not available

from the manufacturer.

1

15

The licensee

stated that

a comprehensive

coordination analysis is being prepared

to document

the basis for all Amptector setpoints.

Since this document is not

yet complete all factors for setpoint

changes

have not been

evaluated.

The

licensee

committed to complete

the coordination analysis of the 480

V and 4160

V

breakers

by November

1992.

This is an unresolved

item pending

NRC review of

the coordination analysis

and the evaluation of the factors for setpoint

changes

(50-244/91-80-06).

2.9

Selection

and Sizin

of Power

Cables

The team reviewed document

EDG-4A, Revision 0, dated April 9,

1991,

"Cable

sizing analysis for cables installed in conduit and cable trays".

The team

noted that the document

was very recent

and was intended for new. installations'

similar document did not exist in the past.

The team found that the analysis

was adequate

and considered

the effect of short circuit current that could

damage

the cable,

cable routing requirements,

cable construction

requirements,

cable capacity

and the necessary

derating factors.

However,

the analysis did

not address

the

maximum allowable voltage drop in the feeder .or the review of

the cables for voltage drop during starting of motors.

The team conducted

a spot check of recent modifications

and did not identify

any improperly sized cables.

2. 10 Electrical Penetration

Sizin

and Protection

UFSAR 8.3. 1.3 stipulates

GDC 50,

IEEE Std 317,

and Regulatory

Guide 1.63

as the

design

bases.

In addition,

the

UFSAR cites manufacturer's

fault tests

and

studies

conducted

in support of SEP Topic VIII-4, "Electrical Penetrations".

The team selected

a penetration

analysis

package for review.

This analysis

was

documented

in the licence's

SEP Technical

Evaluation Topic VIII-4 Report,

"Evaluation of Selected

Penetrations

to Mithstand

Low Magnitude Faults", dated

June

3,

1981.

The Izt values for the silver brazed

and soft solder penetrations

were

calculated

based

on the equivalent of I.

M. Onderdon'

fusing current-time

equation for copper conductors

and connections.

An adiabatic

thermal

process

was

assumed.

The initial temperature

of the penetrations

was

assumed

to be the

LOCA temperature.

A review of the protection analysis

using short circuit

values

from more recent calculations

did not identify any protection

concerns

for the

sample

reviewed.

The team identified that several

of the original Standard

Evaluation

Pl'ant

(SEP)

commitments for backup protection

had not been implemented'he

licensee

explained that, subsequent

NRC staff guidance

allowing exceptions for backup

protection,

where the circuit is Class

1E qualified or where the circuit is

isolated,

resulted

in eliminating the

need for backup protection in some cases.

On that basis,

this was acceptable

to the team for the penetrations

reviewed

during the inspection

(480 Vac penetration

CE-21 serving containment recircu-

lation fan A motor).

0

16

No anomalies

were found for the review of the 4160

Vac penetration

CE-25

(Reactor Coolant

Pump

1 A), and

a field check of a

sample of protective relay

settings did not identify any deficiencies.

2. 11

120 Vac Instrument

Bus

S stem

Section 8.3. 1. 1.S of the

UFSAR and the licensee's

drawing 03201-0102,

120 Vac

Instrument

Bus One-Line Diagram",

Rev.

0 dated April 20,

1991 describes

the

design basis

and configuration of the

120 Vac Class

1E system.

Only three= of

the buses

supporting

the four channel

protection

system instrumentation

are

Class lE, and only two of the Class

1E buses

are battery-backed.

In addition

to the four instrument

buses,

one channel

each of certain engineered

safety

features actuation

system

(ESFAS) instrumentation

is served

from a separate

inverter.

The licensee's

one-line diagram indicated that this additional

inverter was served

by battery

A (which is also the source for instrument

bus

1A), but the loads were identified as Instrument

Channel

D.

2.11.1

S stem Confi uration

The team asked

the licensee

to demonstrate

that the

use of a non-lE power

source for one channel

did not compromise

the

independence

of the four

instrument buses.

The licensee'nalysis

indicated that the power feeder for

instrument

bus

1D shared

the

same conduit as the power feeder for instrument

bus

1C.

The licensee

stated this was acceptable

under the. original design

basis

and

was

supported

by the failure analysis

provided during the inspection.

The team identified to the licensee

that the

UFSAR provided

a commitment that

the instrument

buses

meet separation criteria of IEEE Std 384-1974.

Based

on

the foregoing description of the configuration of the buses,

the design

does

not conform to

IEEE Std 384.

The licensee

agreed,

and stated that this was

an error in the

UFSAR that occurred during the

FSAR update,

and that

a

correction to the

UFSAR had been identified to delete this commitment.

The team concluded

on the foregoing basis that the

system configuration

appeared

to conform to the original design basis

as reviewed

by the

NRC staff,

although the design did not conform to more recent

st'andards

and practices with

regard to qualification,

independence

and separation.

2. 11.2

Loadin

and Continuous

Ratin

s

The licensee

monitored the loading of the instrument

buses for normal operating

conditions;

the values for known additional

loads of instrumentation

being

retrofit and the margins for normally de-energized

loads were determined.

The

values

were totalled to determine

the

system loading.

The licensee

determined

that the existing loading

on buses

1A and

1C was acceptable,

but that future

additions of loads

should

be restricted until

a load monitoring program is

established.

2. 11.3

Fault Protection

and Coordination

The licensee's

analysis

indicated that the existing breakers

used in the

120

Vac distribution system

(Buses

1A and

1C) have

adequate

interrupting ratings for

g

I

0

17

the maximum available short circuit currents.

The analysis

evaluated

coordi-

nation of all breakers

in the

Bus

1A and

Bus

1C panels,

and determined it was

adequate.

In the instances

where coordination could n'ot be demonstrated,

the,

analysis

showed that the lack of coordination

was

bounded

by the system failure

analysis.

Based

on

a review of the foregoing analyses,

the team concluded that

fault protection

and coordination

was adequate

on buses

1A and

1C.

2. 12

125 Vdc Class

1E

S stem

The

125

Vdc Class

1E system is divided into two buses.

Each

bus contains

two

battery chargers

(200'mp

and

150 amp).

Each of the

200

amp chargers,

was sized

to recharge its battery within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> while carrying its load..

Two 60-cell,

lead-acid,

batteries

are provided for supporting control power,

emergency

lighting, and the instrument

bus inverters.

The team reviewed the battery

capacity,

load profile, fault protection

and coordination,

and voltage drop

analyses

to determine

the design

adequacy.

The results

are discussed

as follows.

2. 12. 1

Batter

Ca acit

and

Load Profile

The batteries

were replaced

approximately five years

ago.

The team reviewed

the licensee's

confirmatory Design Analysis

EEA 09004,

Rev.

0, dated

May 4,

1991,

and

EWR 3341 Design Analysis

No. 5,

"DC System

Load Survey",

Rev.

1,

dated

February

3,

1988.

The analysis

confirmed adequate

battery capacity in

accordance

with IEEE Std 485-1983.

The analysis

established

the basis for

battery sizing for a four hour station blackout

(SBO) event pursuant

to

10 CFR 50.63.

The licensee

was aware that the

UFSAR describes

an 8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> duty cycle

as

the basis for sizing.

The licensee

indicated that the

UFSAR would be revised

to reflect the

SBO four hour duty cycle

as the limiting condition.

The team reviewed the analysis

assumptions,

the basis for individual load

contributions to the profile, and performed

an independent

check of cell sizing.

The team noted that each battery

load profile depended

on automatic

shedding at

twelve minutes of a significant load (for non-safety related

DC lube oil pump

of the main feedwater

pump)

by

a timer that was not in the surveillance

program.

The timer was replaced

during the last outage with a qualified timer

in order to provide

a reliable load setting.

The setting of the timer had been

verified to be less

than twelve minutes

as part of the post maintenance

test.

The team

was concerned

about the possibility that the load would not be

shed

within twelve minutes,

thus affecting the reserve

capacity of the battery.

In

response,

the licensee

agreed

to include the timer setting in their surveillance

program.

2. 12.2

Fault Protection

and Coordination

The team reviewed the licensee's.

Design Analysis

EEA-09005,

Rev. 0, dated

April 29,

1991,

supplemental

data

on panel ratings,

and

EWR 3341 Design

Analysis

No.

10,

"Fuse Isolation

and Coordination",

Rev.

1 dated

February

12,

1988.

The

125

Vdc system

uses

fuses

as protective devices

except for a small

t

0

18

number of load side breakers.

The team also reviewed the

DC one-line diagram

33013-1036

Sh.

2-,

Rev.

5 dated

March 1,

1990.

The team concluded that avai 1-

able short circuit currents

were acceptable

for the fuses

and panels installed

and that

a fault on any Class

1E or non-class

1E branch circuit would not

result in

a main fuse degradation.

2. 13 Conclusion

Based

on the team's

review of the

EDS design,

the

team concluded that the Ginna

electrical distribution system is capable of performing its intended function.

The team also noted that the licensee

had carried out major modifications to

the

34 '

kV bus to increase'he

availability margin in the event of a single,

off-site power system failure.

However, the team identified two deficiencies

in the

EDS:

1)

A single short in the control logic or

a single mechanical

malfunction (although unlikely) could cause

the

EDS to lose three

emergency

buses;

and

2)

The redundant

control cables for'the two Component Cooling Water

(CCW)

pumps

have

no separation.

This deficiency,

combined with the

existing ground detection

procedure,

could cause

both

pumps to be

inoperable.

The team also identified three

unresolved

items which require further correc-

tive actions

by the licensee:

1)

A comprehensive

coordination analysis for all safety related circuit

breakers;

2)

Analyses of degraded

voltage effects

on the

480

V MCC motors;

3)

Completion of the dynamic loading analyses

of the

EDG did consider

the scenario

where the

CS

pump

and the third SI

pump could occur as

random load on'he

EOG.

In addition, the

team

made three observations:

1)

Unprotected

output cables

from emergency diesel

generators.

2)

Undersizing of circuit breakers

of buses

14,

16,

17,

and

18.

3)

Lack of loss of field protection for the emergency diesel

generators.

With the exception of specific findings, observations

and unresolved

issues

identified in the report,

the

EOS components

were adequately

sized

and

configured.,

19

3.0

'ECHANICAL SYSTEMS

To determine

the functional ability of mechanical

systems

to support the

EDGs

during postulated

design basis accidents,

the

team reviewed

sample

documenta-

tion and conducted

a walkdown of the fuel oil storage

and transfer,

lubricating

oil, starting air,

and diesel

heating

and cooling equipment.

The team also

reviewed equipment associated

with the heating, ventilation and air condition-

ing (HVAC) of the diesel

generator buildings,

service water screenhouse,

relay

room, battery

rooms, control

room,

and selected

EDG and

HVAC design modifica-

tions.

The team also reviewed the power demand for major loads (selected

'pumps) for input into design basis calculations.

3.1

Power

Demands for Major Loads

The team reviewed the power demands

for the major

pump motors

powered

by the

EDGs following a loss of offsite power during

LOCA conditions.

The team noted that the peak Residual

Heat

Removal

(RHR)

pump loading occurs at

runout condition and peak Safety Injection (SI)

pump loading occurs prior to

.

runout.

The

RHR pump brake

horsepower

(bhp) based

on the manufacture's

pump

curve for the flow of 2500

gpm near runout condition

was

173 and the motor

power

demand

was

139.2

kW.

The

EDG loading calculation

EEA-01002,

Revision 0,

May 6,

1991

assumed

the

RHR pump bhp as

165 and the motor power demand

132.8

kW.

For the SI pumps,

the

maximum bhp based

on the manufacturer's

pump curve

corresponding

to

a flow of approximately

400

gpm was

367

and the motor power

demand

was 289.7

kW.

-The

EDG loading calculation

assumed

358 bhp for the SI

pump and 282.6

kW for the motor power demand.

Based

on the team's findings,

the licensee

agreed

to revise the

EDG loading calculations to correct these

loads.

In summary,

as

a result of the team's finding, the automatic

and steady

state

loads will be increased

by 20.6

kW (6.4

kW for the

RHR pump,

7. 1

kW for the SI

pump and 7. 1

kW for the

SI swing

pump)

from the existing loading calculations.

The licensee

incorporated this

new power demand into the

EDG loading calculations,

resulting in

a load increase

of about

one percent.

This issue

was also

discussed

in Paragraph

2.4. 1.

3.2

Diesel

Generator

and Auxiliar

S stems

The team reviewed the licensee's

calculations,

procedures,

and other

documentations

to determine. the design

adequacy

of diesel

generator

cooling,

air start

system,

fuel oil storage

and transfer

system.

These

are discussed

as

follows.

3.2. 1

Diesel

Generators

Coolin

Two Alco 16 cylinder

model

251F turbocharged

and aftercooled diesel

engine

generator

sets

are provided to generate

the required

emergency

power for all

the engineered

safeguards

equipment.

Each diesel

generator-has

a continuous

rating of 1950

kW,

a two hour rating of 2250

kW and

a 30 minute rating of 2300

kW.

20

The team reviewed performance

trending data

from May 15,

1990 to April 21,

1991 for both

EDGs.

The trending

program was utilized to measure

jacket water

and lube oil outlet temperatures

to verify the

EDG cooling function.

The team

noted that these

temperatures

must

be maintained within a normal range's

defined in plant procedures

PT-12. 1 and PT-12.2.

However, if a measurement

was

obtained which was outside the specified

range,

remedial

action would be taken.

Within the

scope of this review,

no unacceptable

conditions were identified.

According to the

UFSAR, Section 8.3. 1. 1.6.4,

and technical specification, Section 3.7;2,

an onsite diesel

fuel oil inventory at all times

was maintained

to assure

the operation of both

EDGs carrying design

load of all the engineered

safeguards

equipment for at least

40 hours4.62963e-4 days <br />0.0111 hours <br />6.613757e-5 weeks <br />1.522e-5 months <br />.

Technical specification, Section 3.7. 1, stated that the reactor would not be maintained critical without two

EOGs operable with an onsite

supply of 10,000 gallons of fuel oil available.

The team noted that calculation

ME-91-0011,

Revision 0, dated

May 2,

1991,

"Diesel fuel oil minimum onsite

storage

requirements,

PECAQ 91-0010",

used

a

fuel oil specific gravity of 0.89 which was not conservative

for evaluating

the technical

specific onsite fuel oil storage

requirements

since the fuel

consumption

was converted

from lb/hr to gallons/hr.

The licensee

agreed that

fuel oil could be at

a specific gravity as

low as 0.82

and still satisfy all

other fuel oil specification

requirements.

The licensee

determined that the

specific gravity of the fuel oil used in the fuel consumption test

was 0.865

and after applying correction factor for the higher heating

value for the lower

specific gravity fuel oil, the net effect of minimum fuel oil specific gravity

would be

an increase

of 3.5% in the onsite fuel oil storage

requirement.

In

addition,

the increase

in

EDG loads mentioned

in Section

3. 1 would have

an

effect of further increasing

the onsite fuel oil storage

requirement

by about

1%.

The licensee

provided preliminary calculations to include the effect of minimum

fuel oil specific gravity and the increased

EOG loads

on onsite

storage

requirement which indicated that to assure

the operation of both

EDGs at design

load of all the engineered

safeguards

equipment for 40 hours4.62963e-4 days <br />0.0111 hours <br />6.613757e-5 weeks <br />1.522e-5 months <br />,

an onsite fuel

oil storage

capacity of about

10,600 gallons would, be required.

The team reviewed calculation

EWR 4526 ME-23, Revision 0, dated April 30,

1991,

"Diesel Generator

Fuel Oil Storage

Tank Usable

Volume" and noted that the

usable capacity of the two fuel oil storage

tanks

was

5827 gallons

each,

giving

a total capacity of 11,654 gallons.

The team also reviewed procedure

0-6. 13, "Daily Surveillance

Log," Revision

65,

and noted that by following the procedure,

the volume of onsite diesel

fuel oil

in each tank was maintained at the required

value of 5,300 gallons.

The

licensee

agreed

to correct value of 10,000 gallons stated

in the technical

specification.

This is one

example of a weakness

in engineering calculations.

21

3.2.3

Fuel Oil Transfer

S stem

The team noted that there

was

no fuel oil transfer

pump trip on low storage

tank level.

The licensee's

response

was that the Technical

Support Center

was

mandated to be fully actuated within one hour of an accident.

It would be the

duties of the recovery staff to assure that enough diesel

fuel was available or

could be ordered

and delivered in sufficient time to assure

that

a low level in

the storage

tank did not occur.

In addition, operations

personnel

would be

monitoring the diesels if they were running during

an accident.

The team

had

no further questions.

3.2.4

Fuel Oil Stora

e and

Da

Tank Vents

The team determined that the exposed

fuel oil storage

and day tank vents were

not qualified to withstand tornado generated

missiles.

The licensee

stated'hat

in addition to having

an inconsequential

probability of a missile stri ke

to the fuel oil tank vents, diversity was available in venting.

As shown

on

P8

ID's 33013-1239,

sheets

1 and 2,

each

storage

and day tank has

independent

venting as well as

a

common vent

on each of the recirculation/overfill lines.

Therefore, if a missile strike were to occur on any of the vents,

venting

capability would not be lost.

The

team

had

no further questions.

3.2.5

Air Start

S stem

The team reviewed instrument calibration data

sheet

CP-I-DG-INSTR-64A, Revision

01

Page

236 of the data

sheets

indicated that the setpoint for the

EDG low

starting air pressure

alarm was

90 psig.

However, after the air boosters

were

installed in 1975,

there

was

no test data to demonstrate

that the

EDG would be

capable of starting

and

be ready to receive

the load within 10 seconds

with 90

psig starting air.

The team reviewed

CYGNA Energy Services calculation

92528-001,'evision

1, dated

May 9,

1991, "Evaluation of the capacity of the

Diesel Air Start

System"

and noted that after four starts,

the air pressure

in

the receivers

would be about

1'l7 psig.

The licensee

provided

a copy of the Auxiliary Operator's

Log sheet

to the

team

and stated that the, starting air receiver pressure

log was performed twice per

shift to ensure that the receiver pressure

remained within the

normal

range of

225-260 psig.

'he

licensee

also stated that the Alarm Response

Procedure

directed the

Auxiliary Operator to verify that the air compressor

was running and the

correct valve aligned.

The alarm response

directed the Auxiliary Operator

to notify the control

room of the alarm

and cause of the alarm.

If the low air

pressure

condition could not be corrected

immediately,

the

EDG would be

declared

inoperable

and the other

EDG would be started

in accordance

with

Technical Specification, Section 3.7.

The team

had

no further questions.

I

~

~

1

3.3

22

Heatin

Ventilation and Air Conditionin

HVAC S stems

The team reviewed the licensee'rawings,

calculations

and other documentations

to determine

the design

adequacy of the

EOG room

HVAC system,

Screenhouse

Ventilation System

and Battery

Room ventilation.

These

are discussed

as

follows:

3.3. 1

Emer enc

Diesel Generator

Rooms

Tem erature

In response

to the team's

concern,

the licensee initiated

a procedure

change

notice

(PCN 91-3283) to revise

procedure

0-6: 16 to monitor the

room

temperature

and manually start the ventilation,fans

when the temperature

reached

90

F..

The team

had

no further questions.

EDG Rooms Ventilation

S stem

3.3.2

According to the

UFSAR, Table 3. 11-1, all equipment

in the

EDG rooms was

designed for operation at

104

F when the diesels

were not in operation.

However, the ventilation system for the

EOG rooms

was designed

to maintain the

room temperature

below 104'F, with the

EOGs running, during

summer with an

outside air design temperature

of 91~F.

The team noted that the ventilation

system for the

EDG rooms would not start unless

the

EDGs were running and,

therefore,

the heat

loads

in the rooms could raise

the temperature

above, 104'F.

The

team noted that the calculation

assumed

an

ALCO provided heat loss of 4

Btu/Bhp per minute from all the

ALCO EOG and auxiliaries

and electrical

components

excluding the heat

load from the exhaust

stack.

However, the

licensee

could not provide the contributions

from various heat

sources

to

arrive at this value.

Therefore,

the

team

was unable to verify that all the

EOG heat

sources

were included in the

HVAC calculation.

In response

to the

team's

concern,

the licensee

contacted

the

EDG manufacturer,

Canad',an

General

Electric, to verify that all 'the

EDG heat

sources

including the electric

components

but excluding the exhaust

stack were in fact included to arrive at

the

4 Btu/Bhp per minute heat rejection to the

EDG room air.

Calculation

ME-91-0010 indicated that the

maximum predicted

temperature

in the

EDG room would be 104.3

F.

The

team noted that the calculation

had

assumed

an

air density

based

on

a temperature

of 70~F,

whereas

the outside air design

temperature,was

91~F.

Correcting for the air density,

the

maximum predicted

EDG room temperature

would be 104.8'F which was above the design

temperature

of

104~F.

The licensee

stated that

NUMARC 87-00,

Appendix

F established

a

continuous

temperature

of 140'F for the

EDG electronic governor which was the

limiting piece of equipment.

This provided reasonable

assurance

of continued

functionality of the

EDGs at the maximum room exhaust

temperature

of about

105~F for the

GINNA EDG rooms.=

23

3.3

~ 3

Seismic

uglification of Steam Heaters

and Associated

Pi in

in the

EDG Rooms

In response

to the team's

question

regarding

the seismic qualification of- the

steam heaters

and the associated

piping in the

EDG rooms,

the licensee

stated

that the heaters

and the associated

steam piping were evaluated

using

SQUG

methodology during

an interaction

review of the

EDG air start

system.

According to Section 4.5 of EQE report 42031-R-001,

Revision 0, dated January

18,

1991,

"Seismic Verification of the Diesel Air Start

System at the Ginna

Nuclear Power Station," the

space

heaters

and piping were 'judged'o

be

adequate

to maintain position

and structural integrity during and after

an

SSE.

The licensee further stated that they would conduct

a seismic analysis of the

steam line inside the

EDG room to evaluate

and confirm the

SQUG finding. The

analysis

would be completed

by July 31,

1991.

3.3.4

Screenhouse

Ventilation

S stem

The team reviewed the screenhouse

HVAC calculation

ME-91-0009,

Revision

1,

dated

May 15,

1991.

The team identified the following discrepancies:

(i) Air infiltration was

assumed

to be 1.25

room air change

per hour whereas

based

on the

ASHRAE recommended

value of 0.6 cfm per

sq. ft, the air

infiltration would be

1. 1 room air change

per hour.

(ii) The calculation did not address

the effect of the loss of non-1E powered

ventilation fans

on the

screenhouse

temperature

during

summer with the

outside air temperature

of 91~F.

In response

to the team's

concerns,

the licensee

revised calculation

ME-91-0009,

Revision 2,

May 24,

1991.

The revised calculation demonstrated

that the screenhouse

temperature

could

be maintained

below the design

value of

104

F by natural ventilation alone.

3.3.5

Batter

Room Ventilation

There

was

no calculation to demonstrate

that

on loss of non-1E powered

ventilation fans

and air conditioning unit, the

DC powered

backup ventilation

fan could maintain the hydrogen concentration

in the battery

rooms below the

required limit of 2% and room's temperature

below the

summer design

temperature

of 104

F with the outside air at 91'F.

In response

to the team's

concerns

the licensee

evaluated

the flow split to the 'A'nd 'B'attery

rooms

to demonstrate

that the hydrogen concentration

in the 'B'attery

room (lower

ventilation flow) would remain below the

2% limit.

The licensee

evaluated

the

battery

room temperature

to demonstrate

that the

maximum temperature

would be

within the design limit of 104OF.

The fact that there

were

no calculations

for

the battery

room temperature

and hydrogen concentration

before the team's

arrival is

an example of a weakness

in engineering calculations.

3.4

Service Mater

S stem

The service water

(SW) system takes

suction

from Lake Ontario

and supplies

cooling water to the

EDG h'eat exchangers

and other plant loads.

The system

discharges

back into Lake Ontario.via the discharge

canal

or via Deer Creek.

The system consists

of four vertical,

two stage,

centrifugal

pumps rated at

5300

gpm each.

The normal flow requirement is provided by two or three

pumps,

with the remaining

pump(s)

on standby.

Materhammering

can

cause

severe

damage

to the piping and other mechanical

equipment

in the

SW system.

There are

two cases

where waterhammering

can

occur:

1)

SW pumps switching operation,

and 2) loss of power to

a

SW pump,

The licensee

stated that both cases

have occurred at Ginna Station.

Service

water

Pump switching was

a planned operation that occur red frequently; whereas,

loss of

SM pump power was

an unplanned transient condition that had occurred

a

couple of times.

During any planned starting or stopping of the

SW pumps,

an operator is

stationed

in the Screen

House Building to observe

the operation.

The operator

was able to hear the check valve close

a'nd did observe

minor pipe movement

during the operation;

however,

no loud banging occurred

and

no major movement

of the

SW piping was noticed.

At 1'east

two occurrences

of loss of power to

SW pumps

had occurred at Ginna

since

1980 based

upon

a review of LERs.

Based

upon the

20 years of operations

experience

accumulated

to date in

combination with the valve and support inspections

routinely performed at the

Ginna Station

as part -of the Inservice Testing

( IST) and Inservice Inspection

( ISI) programs,

the flow-induced thermal hydraulic transients

associated

with

SW pump discharge

check valve slamming

had

no

caused

any observable

damage to

date to the check valves

themselves

or to the

SM piping and its supports.

The licensee

provided

a

summary of the waterhammer

problems

experienced

in the

SW piping to the Standby Auxiliary Feedwater

(SDAFW)

Pump

Room Cooler,

and

included the status

of activities performed to date to address

the issue.

The

licensee

stated that during the mid 1980's

the plant experienced

waterhammer

in

the 4"

SW piping to the

SDAFW Pump

Room Coolers during performance

of Plant

Procedure

PT-2.7.

Observations

and test data

gathered

during the performance

of PT-2.7 indicated that pressure

spikes

were occurring in the 4"

SW piping

during the opening of

SW valves

4616,

4735,

4615,

4734 after these

valves

had

been closed for a period of time in excess

of a couple of minutes.

PT-2.7

required that these

valves

be closed prior to the performance of periodic

testing of portions of the

SW System,

After completion of

SW testing,

the

valves were stroked

open

from the control

room.

It was only during the opening

of the valves after they had been closed for a long period of time that

pressure

spikes of a couple

hundred

psi were measured

by temporary pressure

transmitters

connected

to the vent valves

on the 4"

SM piping to the

SDAFM Pump

Room Coolers.

Testing of stroking the valves closed followed immediately by

stroking the valve open demonstrated

that

no severe

pressure

spikes

were

experienced.

(

25

As an immediate

response,

Plant Procedure

PT-2.7

was revised to require that

the four

SW valves

be manually opened to approximately the

50% position;

and

then stroked with the motor operator the remainder of the travel.

This was to

be done after the valves

had

been

closed

as part of the SW'ystem alignment for

performance of PT-2.7.

Due to the longer time required to manually stroke

these valves,

the plant reports that the pressure

spike previously experienced

during the automatic valve openings

had

been eliminated.

On a long term basis,

EWR-4612 was initiated on December

17;

1976 to evaluate

changes

to the

SW System to alleviate the potential for water

hammer

due to

the opening of the above service water valves.

The team

had

no further concerns

in this area.

3.5

Conclusions

The team concluded that the appropriate

technical staff was knowledgeable

of

the mechanical

systems affecting the

EDG.

Sufficient information was available

to review and assess

the operability of these

mechanical

systems.

i

A number of issues

were identified in the mechanical

area with regard to the

design

and calculations.

These

issues

indicated the

need for establishing

a

thorough design

review of the

EDGs

and associated

equipment.

These

issues

are

'onsidered

by the

team

as examples

of a lack of attention to detail in the

original design calculations.

The identified issues

were fully addressed

and

resolved during the inspection.

However,

the

team

had

no concerns

regarding

the operability of this equipment.

Il

ET

The

scope of this inspection

element

was to assess

the effectiveness

of the

controls established

to ensure that the design

bases

for the electrical

system

is maintained.

This effort was accomplished

through the verification of the

as-built configuration of electrical

equipment

as specified in electrical

single-line diagrams,

modifications packages,

and site procedures.

In

addition, the maintenance

and test

programs

developed for electrical

system

components

were also reviewed to determine

the technical

adequacy.

4. 1

E ui ment Walkdowns

The team inspected

various areas of the plant to verify the as-built

configuration of the installed equipment.

Areas inspected

included the diesel

generator,

switchgear,

battery,

and electrical

panel

rooms.

Transformer,

protective relay and

pump motor nameplate

data

were also examined.

This

information was collected to verify the completeness

and accuracy of system

calculations.

) ~

In summary,

walkdown inspectio'ns

indicated that adequate

measures

are in place

to effectively control

system configuration.

The inspected

equipment

was

found to be installed in accordance

with design drawings.

Equipment inspected

was

found to be well kept with surrounding

areas

clear of safety hazards.

26

4.2

E ui ment Maintenance

and Testin

The team reviewed various operations,

maintenance

and.testing

procedures

for

equipment

such -as diesel

generator,

switchgear, circuit breakers,

batteries

and battery chargers,

inverters

and protective relays.'

Licensee

personnel

were

interviewed to ascertain their understanding

of the testing

programs.

The

team also reviewed the program established

to control instrument setpoints

during the calibration

and testing process.

The team's observations

are

described

below.

4.F 1

Diesel Generator Testin

The

team reviewed licensee

periodic surveillance tests for the

EOG units.

The

tests

are performed in accordance

with approved

procedures

which demonstrate

the

1950 to 2250

Kw capability required

by the technical

specifications.

The

team reviewed test procedure

PT-12. 1,

"Emergency Diesel Generator

1A" which

provides instructions for performing surveillance testing of

EOG

1A as required

by the Technical Specifications.

The

team witnessed

a surveillance test performed

on

May 24,

1991.

The team

observed that the test procedure

does

not require the recording of the as-found

no-load

EDG voltage

and frequency.

This data is valuable

since

any abnormal

readings

could indicate that either the as-left settings

were left incorrectly

or the control

knobs

were adjusted

subsequent

to the previous test.

The effect

of such abnormal

readings

would be that the

EDG may not be able to carry the

design

loads during required operation

since the unit voltage

and frequency

are critical parameters

for proper operation.

In response

to the team's

concern,

the licensee

stated that verification and documentation

of the as-found no-load

voltage

and frequency at the startup of the 'units would be evaluated for

incorporation into station procedures.

The team observed that procedure

step

6. 12 requires that the

EDG voltage

be

raised to approximately

5 volts higher than the running bus voltage prior to

synchronizing with the offsite system.

During the surveillance test,

the

EDG

no-load voltage

was observed

to be approximately

10-15 volts higher than the

bus voltage.

The control

room operator,

nevertheless,

closed the

EDG output

breaker onto the bus.

In response

to the team's

question

as to the acceptability

of the operator's

action,

the licensee

evaluated

the voltage difference

and

concluded that

a voltage difference of 0 to 25 volts would not exceed

the

generator

or breaker capabilities.

Nevertheless,

the licensee

stated that

further operator

guidance

would be provided as to an acceptable

voltage

range

prior to closing the output breaker.

The team

had

no further questions.

4.2.2

Molded Case Circuit Breaker Testin

A deficiency (Violation 50-244/89-81-06)

pertaining to

a lack of scheduled

periodic testi'ng of Class

lE 480

V molded case circuit breakers

(MCCB) and the

lack of established

acceptance

criteria for testing

the

125

Vdc system

undervoltage

relay alarms

was previously identified during

a

1989 Safety

System

Functional

Inspection

(SSFI)

~

27

In response

to the

NOV, the licensee

stated that it was developing appropriate

test methods for MCCBs as part of the Reliability Centered

Maintenance

(RCM)

program.

Corrective Action Report

1985 was initiated to formally track and

address

the lack of MCCB testing.

A corrective action plan was developed to

systematically

evaluate

the identified violation.

This consisted of:

Evaluation of 10 CFR 21 notifications pertaining to MCCBs;

Review of data of installed

MCCBs to ensure

proper setpoints

and

conditions;

Investigation of industry methods for periodic testing of MCCBs;

Development of a program for such testing;

and

Initiation of a program for periodic

MCCB testing

by the next refueling

outage.

The licensee

performed

a failure mode analysis

to determine attributes for the

MCCB testing

program.

Maintenance

Work Requests,

industry experience

and

practices,

vendor manuals

and Ginna station

procedures

were reviewed in this

effort.

This resulted

in recommended

items to address

the considered

fai lure

modes.

These

recommendations

included performing periodic electrical

exercising of over load devices

and instantaneous

tripping units of the circuit

breakers.

In addition, it included performing periodic inverse-time

characteristic

tests.

Presently,

program development is ongoing with completion expected

by the

end

of 1991

and implementation

expected

by 1992.

Through discussions

with the

licensee staff, the team concluded that although the program is still being

developed,

the expected

program attributes

address

the requirements

of periodic

testing of MCCBs.

With respect to the lack of established

acceptance

criteria for the dc

undervoltage

relay alarms,

the licensee

has revised test procedure

PT-11,

"60-Cell Battery Banks 'A'

'B'" to explicitly define the acceptance

criteria

for the undervoltage

relay alarms.

As part of the corrective actions,

the

licensee

revised

PT-9. 1, "Undervoltage Protection - 480 Volt Safeguard

Busses"

to incorporate explicit acceptance

criteria.

The team concluded that the corrective action plan initiated to address

the

lack of MCCB testing

was comprehensive

and addressed

the essential

elements

to

develop

an effective testing

program.

Based

on the licensee's

continuing

MCCB

test

program development

and the revision of appropriate test procedures,

this

violation is closed.

4.2.3

Inverter Testin

The

120

V instrument

buses

lA and

1C are provided with uninterruptible

power

supplies

from a separate

inverter, regulating transformer

(Constant

Voltage

Transformer

CVT), and static switch combination.

These

combination units

ensure reliable

power to Class

1E instruments.

Normal

power to these units is

from Class

1E battery

systems.

A static switch is provided to transfer to the

alternate

AC power supply from respective

MCCs

on

a loss of inverter output.

. 1

C

28

As stated

in the

UFSAR, the

maximum transfer time, including sensing

time, is

1/4 cycle.

The automatic static-switch transfer is initiated by one of the

following conditions:

Inve'rter failure

Overcurrent

beyond the static switch

Inverter output undervoltage

Manual

The team reviewed maintenance

procedure

M-38.2, "1-A Inverter/CVT Maintenance

or Repair",

Revision

14 which

provides instructions for preventive

and

corrective maintenance

for the

1A inverter/CVT.

Through review of the

procedure

and discussions

with licensee

personnel

the team concluded that there

had

been

no initial or subsequent. testing to verify that in fact the static

switch would be able to transfer

from the normal to the alternate

power source

within 1/4 cycle.

The licensee

stated that the static transfer switch capability was not

a safety

function since the fai lure of the auto transfer would result in de-energizing

an instrument

bus

and therefore protective devices

would fail to the safe

mode.

The licensee

stated that the manufacturer's

operating

manual

lacks sufficient

instructions for testing the transfer capabilities.

An additional

manual w'ill

be procured

and existing procedures will be revised to demonstrate

the transfer

switch capabilities.

4.2.4

Class

lE Batter

Testin

The Ginna Technical Specification

(TS) Surveillance

Requirement

4.6.2 requires

that each

125

Vdc battery

be subjected

to load (service)

and discharge

(performance)

tests.

Additional maintenance

requirements

are also specified in

the TS.

The team revie'wed surveillance

test procedures

PT-11 "60 Cell Battery

Banks

'A'

'B'" and PT-10.2 "Station Battery

1B Service Test."

Within the

scope of this review no discrepancies

were identified.

4.2.5

Other Electrical

E ui ment

The team reviewed test procedures

for other Class

1E electrical

equipment.

This review included battery chargers,

circuit breakers

and relays.

The

procedures

reviewed were determined

to be technically adequate

with applicable

acceptance

criteria.

4.3

Protective

Device Set oint Control

and Calibration

4

The team reviewed the licensee's

program for controlling protective device

setpoints

to assure

that equipment will operate

at predetermined

levels.

In

addition,

instrument calibration procedures

and records were'lso

reviewed to

determine

whether the contents

of procedures

and test results

were acceptable.

These

are discussed

as follows.

P

~

I

C

29

4.3.1

Protective

Rela

Set oint Control

The licensee

provides control of protective device setpoints

through the

Engineering

Work Request

(EWR) process

and applicable

design output documents.

Once

a design

change

to protective device setpoints

has been'determined

to be

required,

an

EWR is initiated to assure

adequate

review and control.

Documents

generated

during the review and approval

process

include:

Design Criteria,

Safety Analysis,

Design Analysis,

and Design Verification.

The team examined

the installed equipment to assess

the control of protective

device setpoints

and

system configuration.

As-found settings for overcurrent

relays, circuit breakers

and undervoltage

relays were

compared against controlled

documents.

The team also verified the installed fuse sizes

and types in several

control circuits'he installed fuses

were the

same

as that specified in wiring

diagrams.

.No discrepancies

were identified.

4.3.2

En ineered

Safet

Feature

ESF

Load

Se uencin

Timers

The team reviewed procedure

RSSP-2.7

"Safety Injection Sequence

Timers Train

A

and B".

This procedure

is used to set the individual

ESF load sequencing

timer.

The procedure

describes

the initial conditions,

precautions,

and instructions

for, the performance of the test.

The t'est results

provide verification that

the timers

have not drifted significantly from the previous as-left values.

This assures

that the

ESF loads will load onto the respective

480

V buses

at

appropriate

time intervals to preclude

the

EDGs from being overloaded.

The

as-found times for each individual timer is recorded

and evaluated

against

specified values.

These

values

are derived

from Engineering

Work Request

(EWR)

4960-1

"Time Delay Relay Setpoints

ESFAS System",

Revision

4.

The

EWR analyzed

the individual timers considering

instrument drift and

ESF motor acceleration

times.

Although the times are derived

from the

EWR, the as-found values

are

compared against

the

UFSAR.

The procedure

requires that any timer which does

not fall within the specified required time band

be evaluated

to ensure full

compliance with the values specified in UFSAR Table 8.3-2.

The

UFSAR table

lists the individual

ESF load running times,

which are the times by which each

individual motor is required to have

reached full speed.

The team noted that

MOVs 871-A/B have individual timers to ensure

proper

closing

upon receipt of

a safety injection (SI) signal

and are included in

procedure

RSSP-2.7.

However,

the

MOVs are not listed in the

UFSAR Table 8.3-2

and therefore

cannot

be evaluated

against

the

UFSAR.

This was evident

from the

review of records for a test performed in April 1990.

In this instance,

-the

procedure

specified time band for the timers were exceeded.

However,

these

values

were not evaluated

since

they are not specifically listed in the

UFSAR

table.

The

MOV required times are

based

on the capability of the swing SI

pump

1C to operate.

These times,

as well as those for other timers listed in the

UFSAR table,

have

been

analyzed with the required times

summarized

in

EWR

4960-1.

The team

asked

why the procedure

required evaluation of the

30

as-found timer values against

the

UFSAR load running times instead of the

established

timer setpoints

in

EWR 4960-1 'since the

EWR already

has considered

the

UFSAR values

in the analysis.

Use of the setpoints

from the

EWR would

ensure that all loads,

including the subject

MOVs, are properly evaluated.

The

licensee

agreed that the

EWR criteria will be incorporated into the RSSP-2.7

procedure.

The out-of-band

MOV timer values

were subsequently

evaluated

and

were determined to be adequat'e

such that the

swing SI

pump

1C would still have

been able to operate

during

an accident

since there

was sufficient margin in

the setpoint value.

The team

had

no further

questions.'.3.3

Under volta

e and

De r aded Volta

e Rela

s

Ginna Station Technical Specifications

(TS) Section

2.3 specifies

the Limiting

Safety

System Settings for Protective

Instrumentation.

Section

2.3'. 1

specifies that

480

V undervoltage

relays will be tested to ensure that they

operate

in accordance

with their design characteristics.

Figure 2.3-1

identifies the .loss of voltage

and undervoltage

relay operating

ranges.

In

accordance

with TS Table 4. 1-1,

each

channel

is required to be tested

on

a

monthly basis

and calibrated

every refueling outage.

Ginna Station procedure

PT-9. 1 "Undervoltage Protection - 480 Volt Safeguard

Busses"

provides instructions for testing the operability of the loss of

voltage

and degraded

voltage relays associated

with 480

V Safeguard

buses

14,

16,

17,

and

18 .

This procedure

implements

the

TS monthly, survei

1 lance test

requirements.

Procedure

PR-1. 1 "Protective Relay Calibration

480

V

Undervoltage

and Ground Alarm Scheme

For Buses

14,

16,

17 and

18" provides

instructions for the calibration of protective relays.

It implements

the

refueling outage

TS Surveillance

requirement.

Review of procedure

PR-1.1 calibration results

performed during the

1991

refueling outage

(March 1991)'indicated

that three (3) as-found relay values

we'e below the

TS limits specified

in TS Figure 2.3-1.

Specifically, the

as-found relay dropout voltage settings

were less

than the

TS limit of 103.5

V

(equivalent to 414

V at the

480

V buses).

These

are denoted

below.

~Rela

As-Found

Dro out

V

Volta e at 480

V Bus

27B/14

27/16

27B/18

103.39

103.07

103.38

413.6

412.3

413.5

Although the above as-found values

were below the

TS limits, the results

review

performed

by the

1'icensee

did not identify this condition.

Therefore,

no

evaluation

was performed to determine

whether safety-related

motors would still

have

been

able to operate

at reduced

voltages prior to the relays dropping out.

In response

to the team's

concern,

the licensee

performed

an evaluation

and

determined that

no adverse effect

on the safety related motors would

result'ue

to the small voltage deviation.

In addition, the licensee initiated

a

31.

Ginna Station

Event Report to document

and evaluate

the above condition for

reportabi

1 ity.

Procedure

PR-1.1 "Protective

Relay Calibration

480

V Undervoltage

and Ground

Alarm Scheme for Buses

14,

16,

17 and 18", section

5.3 requires

an I&C/Electrical

Equipment Failure Safety Related

Report

be prepared

to evaluate

those relays

that exceed

the calibrated tolerance.

Failure to prepare

the I&C/Electrical Equipment Failure Safety Related

Report

for the protective relays described

above constitutes

a violation of Ginna

Technical Specifications, Section 6.8. 1, which requires that written procedures

be established

and implemented for surveillance

and test activities of safety

related

equipment (50-244/91-80-04).

4.4

Conclusion

The licensee

has

implemented controls to maintain electrical

system

configuration.

Equipment

inspected

was observed to be well-maintained

and

an

effective fuse control program was evident.

The development of the molded case

circuit breaker test

program is ongoing.

The testing attributes

being

addressed

are comprehensive

and thorough.'

deficiency was identified in

handling the as-found data of the protective relay testing.

The droupout

voltage settings

of three protective relays drifted below the Technical

Specification limits during the

1991 refueling outage yet no evaluation

was

performed

as required

by station

procedures.

5.0

En ineerin

and Technical

Su

ort

The team assessed

the capability and performance

of the licensee's

organization

to provide engineering

and technical

support

by examining the interfaces

between

the technical disciplines internal to the engineering

organization

and

the interfaces

between

the engineering

organization

and the technical

support

groups responsible

for plant operations.

The

team also reviewed

a sampling of the licensee's

Potential

Conditions

Adverse to Quality (PCAQ) reports,

Nonconformance

Reports

(NCRs),

Licensee

Event Reports

(LERs), major,

minor

and temporary modification programs,

training, quality assurance

(QA) audits,

root-cause

investigation

and

corrective action programs,

and self assessment

programs.

5. 1

Or anization

and

Ke

Staff

The Engineering

and Technical

support for the Ginna Station is provided by the

Corporate

Nuclear

Engineering

Services staff at Rochester,

New York, the Site

Technical

Engineering

group

and Site Modification Support group.

The Corporate

Nuclear Engineering

Services

group is headed

by the Manager,

Nuclear Engineering

Services.

The Corporate

Engineering

support for the

electrical distribution system is provided by the Electrical

Engineering

group

within Nuclear Engineering

Services Division.

The Site Technical

Engineering

32

group

and Modification Support group are responsible

for providing site

engineering

support to plant operations,

maintenance

and design

support.

The corporate

engineering staff performs all major engineering design,'nd

the

Ginna Station performs all minor modifications.

Engineering consultants

are

used only to supplement

the in-house capabilities,

on

an

as

needed

basis.

The

team noted that the Nuclear Engineering

Services

Department Staff has

been

increased

from 68 to

104 from 1989 to'present

to improve the engineering

support for the station.

Throughout the inspection,

the corporate

and site

engineering staff provided timely and thorough

responses

to the team members.

The team concluded that the engineering

positions

are adequately

staffed with

knowledgeable -personnel.

5.2

Root Cause

Anal sis

and Corrective Action Pro

rams

The team reviewed several

Licensee

Event Reports,

Potential

Conditions Adverse

to Quality (PCAQ) documents,

Non-Conformance

Reports

(NCRs), Corrective Action

Reports

(CAR) and

QA Audits to assess

the effectiveness

of the licensee's

root

cause

analysis

and corrective action

programs

The

NCRs reviewed

by the

team indicated that corrective actions

were

appropriate

to address

the problems identified in the

NCRs and in accordance

with procedure

QE-1501.

Engineering dispositions

and applicable

10 CFR 50.59

and Part

21 reviews were found -to be thorough.

Several

PCAQ reports

in accordance

with Procedure

QE-1603 were reviewed to

determine

whether safety concerns

were properly identified, reported

and

corrected.

The team noted that in all cases,

the licensee

promptly identified

potential, safety concerns,

made accurate operability and preliminary safety

assessments,

reportability evaluations,

and necessary

corrective actions

were

initiated.

Quality Assurance

audits

reviewed were found to be adequate

and

addressed

various elements

of engineering

organization

design control

and

surveillance

programs.

Corrective actions

and response

to the audit findings

were prompt and proper engineering

management

attention

was noted

as evidenced

by the minimal outstanding

open audit findings.

The team also reviewed selected

LERs to assess

the adequacy of engineering

organization

involvement in

NRC reporting requirements

(in accordance

with 10

CFR, Parts

20, 21, 50.72,

50.73

and 50.36)

and to determine

the adequacy

of

root cause

analysis

and corrective actions.

Corrective actions

were generally

broad in scope to address

the root and contributing causes.

The root cause

investigation

process

was thorough

and self critical to identify weaknesses.

This was evidenced

during the review of LER 87-008,

inoperable circuit breakers

for "1B" RHR and "1B" safety injection

pump and

LER 90-005,

low safeguards

bus

voltage during start of "A" RCP.

The team noted that

a corrective action group

working for the manager

tracks

and initiates corrective action reports for LERs

and any potential

safety concerns

identified by the station.

The

sample

review

of open

CARs indicated that

CARs were closed out in

a timely manner.

33

The team determined that the licensee

has

a good program to identify and

investigate discrepancies

and root causes

and to complete corrective actions

in

a timely manner.

5.3

Self Assessment

Pro

rams

The team reviewed the licensee's

self assessment

programs to assure

that safety

issues

are properly identified and corrected.

The team noted that the licensee

had performed

an electrical distribution system functional inspection to make

an independent

assessment

of the

EDS.

The independent

assessment

covered

electrical

and mechanical

design

review, operations,

testing

and modifications.

The assessment

was comprehensive

and several

technical

issues

were identified

in the report.

The corrective actions to resolve

these

issues

were being

pursued at the time of inspection.

Another self assessment

program reviewed

was the licensee's

Potential

Conditions Adverse to Quality (PCAQ) Program which identifies and resolves

safety significant issues with appropriate

engineering

and station personnel

review.

Several

potential

safety concerns

were identified by the licensee

during this year.

The review of sample

PCAQ indicated that potential

safety

concerns

were reviewed in

a timely manner to determine operability and safety

concerns

and were found to be thorough.

The quality assurance

area

was also

reviewed

by the

team to evaluate

the

involvement of QA personnel

in assessing

the quality of engineering

services'he

team concluded that

QA audits

and

QA involvement in monitoring engineering

effectiveness

were adequate.

The team noted that the licensee

had performed internal

and independent

assessments

to assess

the capability and quality of output generated

by their

Nuclear Engineering

Services Division.

These

comprehensive

self assessments

were performed to address

design control

and engineering

assurance

weaknesses

identified during previous

NRC SSFI Inspection

(No. 89-81).

The team noted

that in order to improve the Ginna Station's

performance,

'licensee

management

has committed to implement configuration

management

engineering

projects

such

as

P&ID Upgrade,

Electrical Controlled Configuration Drawing (ECCD) upgrade,

Q

list, Design Basis

Documents,

Programs

and Commitment Tracking Systems.

Some

of the projects

such

as

P&ID upgrade,

Q list document

and

ECCD upgrade

were

completed

and the remaining configuration

management

projects

are scheduled

to

be completed

by 1994.

The team concluded that the licensee's

self assessment

program efforts were

thorough

and aggressive

and considered

to be

a strength

for achieving the

licensee's

nuclear mission goals for attaining outstanding

performance

in all

aspects

of operation

and safety of the Ginna Station.

l

5.4

E ui ment Modifications

The team reviewed the program for plant design

changes

and modifications to

ascertain

that they were performed

in conformance with the requirements

of the

Technical Specifications,

l0 CFR,

FSAR,

and applicable

procedures.

n

The

RGEE modification process

is categorized

into major-mods

and minor-mods..

Major modifications are performed through the licensee's

Engineering

Work

Request

(EWR) process

and are performed

by the Corporate

Engineering group.

The major modifications are either mostly safety related

changes

or non-safety

related plant changes

that are

complex in nature.

Minor modifications are

performed

by Ginna Station Technical

Engineering

group

and are either generally

non-safety related

changes

to the plant or safety related

changes

which are

minor in nature.

All minor modification requests

(TSR process)

are reviewed

by

the

RG&E corporate office to determine

whether modifications are classified

approproately

in accordance

with procedures

gE 322 and

A 301. 1 and also to

provide corporate

engineering

oversight

in the Modification Process.

The major and minor mods reviewed are identified in Attachment

2 and include

a

variety of permanent

plant changes

to the electrical distribution and support

systems.

The team noted that engineering

procedures

for modification process

were

prescribed

in several

individual, "gE" procedures.

No single procedure

exists describing

the whole modification process.

The modification packages

reviewed (1984-1990)

indicated that design criteria, design verification,

design input and safety evaluation

thoroughness

and technical

review could be

improved.

For example,

(1)

EWR 3891-Design criteria for DC battery replacement

did not consider

guidance

for cell sizing, design margin, charger capacity;

the

safety analysis did not consider

hydrogen evolution; the increase

in short

circuit current contribution did not coordinate

and design

a verification

appeared

to be more administrative in nature rather

than

a technical verif-

ication.

(2)

EWR 2929-Safety analysis

and design verification did not appear

to identify the potential for degrading

the coordination of system protection

when back

up protection is applied to electrical penetrations.

I

However, recent

analyses

reviewed

by the

team indicated that these

aspects

have

since

been identified and addressed.

The team observed that the documentation

of completed modification packages

were not kept in one specific location

and

were difficult to retrieve.

Numerous

weaknesses

were identified with respect

to design documentation

and calculations during the previous

NRC SSFI

(inspection

Report

No. 89-81).

The

team noted that in order to address all the

design control plant modifications process deficiencies,

the licensee

had

performed

a comprehensive

internal

and independent

assessment

of the above

area.

Increased

management

involvement to improve the existing design control process

and quality of engineering

work was observed

by the the team during this

inspection.

As

a result,

Nuclear Engineering

Services modification design

process

standard

and flow chart describing

the integrated

design modification

process

were developed

and in the final stages

of approval.

Several

"gE"

procedures

were revised to provide

a better understanding

of the existing

design

process

and appropriate

procedure training were completed.

A sampling

of work orders for the

EDS completed

in 1990-1991

was reviewed to assure

that

maintenance activities did not result in design

changes.

No unintended

design

changes

were identified.

35

During this inspection,

the team observed that several

calculations

were

developed

by the licensee

in

a very short time duration.

The

team deter-

mined that technical

review and thoroughness

of some of the calculations

could

have

been

improved.

The team interviewed several

members of the engineering staff (both corporate

and site) to determine their understanding

of the design control

and modif-

ication process.

The engineering staff were found to be knowledgeable

and

have

a good understanding

of the modification process.

The team noted, that

a design

basis reconstitution

program

and configuration

management

controls are being

implemented to enhance

the documentation

so that it more accurately reflects

as-built conditions

and to better

assure

that the Ginna plant is operated

and

modified within its design basis.

The team observed

a positive improvement in the design modification process,

engineering

procedures

and

EDS calculations.

However,

the team concluded that

,the effectiveness

of licensee's

design control

and modification process

cannot

be determined at the present

time since most of the proposed corrective actions

for the identified weaknesses

are yet to be completed.

5.5

Tem orar

Modification Pro

ram

Temporary modifications for electrical

systems

(Bypass of Safety Function

and

Jumper Control) are administered

and controlled by procedures

A-1402,

1405

and

1406.

These

procedures

identify the controls for use of bypass

features

on

safety related

and non-safety related

equipment.

The team's

evaluation of

selected

temporary modifications revealed that they contained

appropriate

review and approval

by the Technical

manager

and the Shift Supervisor

and

appropriate

safety evaluations/reviews

'were performed to meet the intent of the

10 CFR 50.59 requirements.

However,

the

team noted that the procedures

do not

require

a detailed

formal 50.59 review or safety evaluations.

The licensee

state that temporary modification procedures

are being updated

to address all

program weaknesses

'as part of 'the procedure

update

program.

'The team noticed

that four of the non-safety related modifications were found to be approx-

imately six years old.

The licensee

stated that these

temporary modifications

are being replaced

by permanent

plant modifications through their

EWR/TSR

modification process

and are

scheduled

to be wor'ked in accordance

with the

priority assigned

to the modifications.

The licensee

also stated that the

Ginna Station's

goal is to closeout

the temporary modifications before the end

of one year.

The team reviewed the log kept in the control

room for tracking temporary

mods

and interviewed control

room supervisors.

The review indicated that

open'emporary

mods are reviewed periodically and tracked.

The team determined that

the licensee

has

an adequate

program for controlling temporary modifications

and bypasses

in the plant.

I

r

'

'

5.6

En ineerin

Su

ort/Interface

36

The team reviewed the involvement

and effectiveness

of the engineering staff to

support design functions, operations,

maintenance

and other organizations

at

.

the site.

The team noted that the licensee

has

an integrated prioritization

system for controlling and assessing

engineering

work activities.

The inter-

face between station and.engineering

personnel

at Ginna was found to be

effective as evidenced

by the presence

of technical

engineering,

modification

support staff .and corporate staff, at the site, to support the engineering/

technical

needs of the plant.

A close working relationship

between

the

engineering

and operations

personnel

was noted during this inspection.

Several

corporate,

plant engineering,

maintenance

and operations staff were interviewed

during the course of the inspection to understand

the communication channel/

interface established

for Ginna Station.

The licensee

has established

morning

and, afternoon meetings to discuss

plant activities pertaining to design,

operation

and maintenance

action items.

The active participation of management

representatives

from different organizations

for these

meetings exhibits the

effective interface

between

engineering

and plant organizations.

Furthermore,

the team observed that the licensee

was able to provide required

design

documents

and calculations within a short time indicating

a good coor-

dination between different organizations

and the Ginna Station.

The team found

the engineering staff to be very knowledgeable

of the

EOS.

The team that

interacted with the

NRC inspection

team indicated

a good familiarity with their

area of responsibility.

A good -interface

between

support organizations

was

noted during this inspection.

5.7

Technical Staff Trainin

The team reviewed the licensee's

technical training program to evaluate

the

adequacy

of training given to the corporate

and site engineering staff.

The training program is conducted

in accordance

with licensee's

procedure

No.

gE 102, "Indoctrination and Training."

This procedure

provides instructions

for'he control

and documentation

of indoctrination

and training for Nuclear

Engineering

personnel

for their specifically assigned

functions.

The training

program consists

of initial and continuing training.

The initial training

program depends

on the qualification and experience

of the individual. The

initial training program extends

up to

2 years.

The continuing training

program is an ongoing program

and it covers at least

4 - 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> of classroom

training.per quarter.

The Ginna training center provides

adequate

training in

several

courses

such

as

System Engineering,

50.59/safety

evaluations,

LER

process,

modifications process,

industry events

and simulator training.

Furthermore,

the technical staff is required to attend administrative

and

engineering

procedures

training in addition to the normal required

reading

assignments.

The

team noticed that training d'ocuments

are pro'perly maintained

and tracked in the computer data

base

and updated periodically to maintain

an

effective training program.

The team also

noted that the licensee

engineers

.4

0

37

actively participate

in industry groups

and programs,

and are

aware of

technical issues'he

team concluded that the licensee

has

an adequate

training program for the technical staff for performing engineering

and design

functions

and for providing adequate

technical

support for the plant's

operational activities.

5.8

Conclusion

The corporate

and site technical

engineering

and modification support personnel

are adequately

staffed with competent

personnel

and are very familiar with the

EDS and its support

systems.

Effective interfaces exist between station

and

engineering

personnel.

Communications

between

the various engineering

and

technical

support organizations

were found to be generally good.

Engineering

support to operating

and maintenance

activities are generally

good with an

effective interface

evidence

in many areas of projects.

The team determined

that the licensee

has

an aggressive

self assessment

program.

This program is

considered

to be

a strength.

The licensee

has

a good program to investigate deficiencies,

identify root

causes

and to complete appropriate corrective actions

in a timely manner.

Technical training and guality Assurance

Programs

were found to be adequate.

The team observed

several

isolated

examples

which indicate that the thorough-

ness of technical

reviews

and attention to detail

could be improved in the

design calculation/modification

process.

Increased

management

involvement to

improve the existing design control process

and the quality of engineering

work

was evidenced

by the completion of P8 ID update

program, Electrical Configur-

ation Controlled Drawing Program,

EWR Procedure

upgrades,

ongoing Design Basis

Reconstitution

Program

and Configuration Management

Control

Program.

Improvement in the licensee's

design control

and modification process

was noted

during this inspection.

6.0

Unresolved

Items,

Weaknesses

and Observations

Unresolved

items are matters

about which more information is required in order

to ascertain

whether they are acceptable

items or violations.

Unresolved

items

identified during this inspection

are discussed

in detail,

Paragraphs

2.42,

2.5

and 2.8

~

Weaknesses

and observations

are conditions that do not constitute

regulatory requirements

and are presented

to the licensee for their

evaluations.

7.

The inspector

met with licensee

corporate

personnel

and licensee

represent-

atives (denoted

in Attachment I) at the conclusion of the inspection

on June

7,

1991.

The inspector

summarized

the

scope of the inspection

and the inspection

findings at that time.

1'

Attachment

1

Persons

Contacted

1.0

Rochester

Gas

and Electric Cor oration

RG5E)

S.

Adams, Technical

Manager

C. Anderson,

Manager, Quality Assurance

B. Carrick, Mechanical

Engineer

R. Carter,

Mechanical

Engineer

G. Daniels, Electrical

Engineer

B. Flynn, Engineer,

Nuclear Safety

and Licensing

C.

For kell, Manager, Electrical Engineering

B. Hunn, Electrical

Engineer

M. Kennedy,

CM Program Directory

M. Lilley, Manager,

Nuclear Assurance

D. Markowski, Mechanical

Engineer

R. Mecredy,

Vice President,

(Ginna) Nuclear Production

J. Metzger,

Senior

Mechanical

Engineer

T. Miller, Electrical

Engineer

  • R. Morrill, Operation

Experience

Coordinator

T. Newberry, Mechanical

Engineer

J.

Pacher,

Electrical

Engineer

L. Rochino,

Lead Mechanical

Engineer

W. Roeltger, Electrical

Engineer

J. Sargent,

Electrical

Engineer

E. Smith, Mechanical

Engineer

L. Sucheski,

Supervisor,

Structural

Engineering

P. Swift, Electrical Engineer

C. Vitali, Mechanical

Engineer

  • G. Voci, Manager,

Mechanical

Engineer

  • T. Weigner,

Technical Assistant to Dept.

Manager

P. Wilkens, Dept.

Manager,

NES

J. Widay, Superintendent,

Ginna Production

G. Wrobel, Manager,

Nuclear Safety Licensing

2.0

Nia ara

Mohawk Power Cor oration

F. Constance,

Electrical

Engineer

D. Goodney,

Lead Electrical

Engineer

  • A. Julka,

Supervisor,

Nine Mile 2 Electrical

A. Pinter,

Licensing Engineer

"T. McMahon, Supervisor,

Nine Mile

1 Electrical

3.0

United States

Nuclear

Re ulator

Commission

C. Anderson,

Chief, Electrical Section,

DRS

M. Hodges, Director, Division of Reactor Safety

A. Johnson,

Project Manager

NRR

R.

Wessman,

Project Director PDI-3,

NRR

N. Perry Ginna Resident

Inspector

  • denotes

those

not present at the exit meeting

on June

7,

1991.

'

ATTACHMENT 2 - GINNA ELECTRICAL DISTRIBUTION SYSTEM

STA 204

STA 42

STA 122

STA 204

STA 42

I

CKT 913

CKT 912

CKT 9'I1

STA 121

52

91302

91202

52

1GISA72

52

7XISA72

52

8X13A72

52

9X13A72

CKT 908

52

90812

52

91102

STA 204

I

I

I

I

I

I

I

I

NO. 6 TRANS F.

30/40/50

MVA

I

CKT751

CKT 909

52 90912

SWITCHYAAO115KV

STATION 13A

CKT 767

STA AUX.

TRANSF. 12A

52

52

12AX

12AY

NO

Nc

STA AUX.

TRANSF. 12B

52

52

12BY

NO

19KV/4160V

UNIT

AUX.TRANS F. NO. 11

REMOVABLE

LINK

RFMOVABLE

LINK

REMOVABLE

LINK

MAINTAANSF.

19KV/115KV

ONSITE

SPARE M/UN

TRAN5F.

DUMMY

BREAKER

52

52

DUMMY

BREAKER

4160V BUS 12 B

4160V BUS 11 8

4160V BUS 11 A

4160V BUS 12 A

52

52

52

52

52

52

52

52

STA SERV

TRANS F. NO. 16

STA SERV

TRANSF. NO. 15

STA SERV

TAANSF. NO. 13

STA

SERV

TRANS

NO. 14

GEN

EXC

PMQ

480V BUS 15

480V BUS 16

480V BUS 14

480V BUS 13 )

)

)

)

)

)

)

NEUTRAL

TAANSF.

STA 5ERV

~ TAANSF. NO. 17

EMER. GEN.

)

NO. IB

480V BUS 17

EMER. QEN,

NO. 1A

STA SERV

TRANSF, NO. 18~

480V BUS 18

,J'

~

(

0