ML17250A994

From kanterella
Jump to navigation Jump to search
Insp Rept 50-244/89-18 on 890626-30 & 0717-0824.No Violations Noted.Major Areas Inspected:May & June 1989 Events Which Occurred During Annual Refueling Outage & Subsequent Plant Startup
ML17250A994
Person / Time
Site: Ginna Constellation icon.png
Issue date: 09/08/1989
From: Mccabe E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML17250A993 List:
References
50-244-89-18, NUDOCS 8909210239
Download: ML17250A994 (34)


See also: IR 05000244/1989018

Text

ENCLOSURE

1

U.S.

NUCLEAR REGULATORY COMMISSION

.

REGION I

Docket/Report

No.

50-244/89-18

Licensee

No.

DPR-18

Licensee:

Rochester

Gas

and Electric Corporation

49 East Avenue

Rochester,

New York

Facility:

R.

E. Ginna Nuclear

Power Plant

Location:

Ontario,

New York

Inspection

Conducted:

June 26-30,

1989; July

17

August 24,

1989

Inspectors:

Approved by:

~Summar:

N.

S. Perry,

Resident Inspector,

Ginna

P.

D. Drysdale,

Reactor

Engin.oer,

Region I,

DRS

R. A. Laura,

Resident Irspector,

Nine Mile Point

E.

C.

McCabe, Chief,

eactor Projects

Section

3B

9/e/sV

Date

Areas Ins ected:

Special

inspection

(107

hou> s) of May and June

1989 events

(Table

1

hich occurred during the annual refueling outage

and subsequent

plant start-up.

Results:

Adequacy of control of modifications (Sections

10,

11,

12) and of

non-safety,

non-plant personnel

work which could adversely

impact plant safety

(Section 7) is in question.

Failure to follow procedures

produced

a safety

injection signal

(Section 3).

The licensee did not implement effective cor-

rective actions for failure to perform weekly rodding of boric acid tank level

bubbler tubes (Section 5).

There was

a failure to obtain

a grab

sample of the

containment

atmosphere

as required (Section 9).

An independent verification

deficiency was noted (Section 8).

A waste

gas release

performed outside the

specified time limit (Section

4) and incorrect setting of intermediate

range

detector trip setpoints

(Section

6) were evaluated

as being of minimal safety

significance.

S909210239

S90912

PDR

ADOCK 05000244

0

PDC

I,

~

~

TABLE OF CONTENTS

PAGE

1

Persons Contacted....................................................

1

2.

Introduction.

3.

Unanticipated

Safety Injection Signal

(93702).

2

4.

Waste

Gas Release

(93702)

.

.

.

.

. ..

. ..

. ...

.

.............

2

5.

Cleaning of Boric Acid Tank Sensing

Lines (93702)...... .............

3

6.

Intermediate

Range Detector Trip Setpoints (93702)...................

3

7.

Main Generator

Current Transformer Sliding Links (93702).............

4

8.

Average Temperature

Channel

403 Sliding Link (93702).............

~ ~ ..

5

9.

Containment Radiation Monitors R-10A, 11,

12 (937C2).

5

10.

Safety Injection System Recirculation Valves (93702).................

6

ll.

Safety Injection System Modifications (37702,

37828).

12.

ASS/AMSAC Modification (37702, 37828)................

7

~

~

~

~

~

~

~

~

~

~

~

~

~

~

~

11

13.

Exit Interviews......................................................

12

~ p

I

DETAILS

Persons

Contacted

During this inspection period,

inspectors

held discussions

with and inter-

viewed operators,

technicians,

engineers

and supervisory level personnel.

The following people were

among those contacted:

R. Baker, Electrical Engineer

J. Bergstrom,

Nuclear Engineer

D. Berry, Shift Supervisor

J.

Bodine, Nuclear Assurance

Manager

D. Filkins,

HP

8 Chemistry Manager

T. Harding, Modification Support Coordinator

G. Hermes,

Engineer,

Nuclear Safety Licensing

  • T. Marlow, Superintendent,

Ginna Support Services

A. Morris, Maintenance

Manager

M. Ruby, Shift Supervisor

T. Schuler,

Operations

Manager

  • S. Spector,

Plant Manager,

Ginna Station

J. St. Martin, Corrective Acticn Coordinator

  • J. Widay, Superintendent,

Ginna Production

G. Wrobel,

Manager. of Nuclear Safety

and Licensing

All persons listed above attended

the interim exit meeting

on June

30,

1989.

  • Attended the supplemencal

exit meeting

on August 24,

1989.

Introduction

Within a five week period priot to, during,

and after start-up

from the

1989 annual

refueling outage,

Ginna experienced

several

problems

(see

Table 1).

Most of these

were related to recent modifications

and system

lineups.

The

1989 refueling outage

was 74 days

long and included the

ten-year inservice inspection

( ISI), extensive

steam generator

work, and

plant modifications.

This special

NRC inspection

examined

ten events

(Table 1), all of which were licensee identified, to assess

licensee

per-

formance,

especially determination of root causes

and corrective actions,

and to determine if programmatic

weaknesses

caused

the high number of

events.

In particular,

the design

change

and modification programs

and

processes

were examined.

Specific attention

was given to the'ecent

modi-

fications of the Safety Injection System

and the

ATWS (Anticipated Transi-

ent Without Scram) Mitigation System Actuation Circuitry (AMSAC).

Related

operational

and preoperational

problems

led to a reactor trip and

a plant

shutdown.

~ f

~

\\ ~ '

Unantici ated Safet

Injection Si nal

With the plant shut down,

and while performing the Plant Safeguard

Logic

Test

on May 18,

1989,

an unanticipated

Safety Injection (SI) signal oc-

curred.

During review of plant response,

control

room personnel

noted

a

containment ventilation isolation signal

should

have

been generated,

but

was not.

The licensee attributed the unanticipated

SI signal to lack of detailed

procedural

guidance.

Technicians

were accustomed

to placing bistables

in

the tripped condition prior to insertion of a test signal.

However, the

Plant Safeguard

Logic Test procedure did not instruct technicians

to trip

the bistables

in this case.

The technicians,

after questioning

the proce-

dure step

and getting

no additional direction,

assumed tripping the bi st-

ables

was intended

and caused

the SI signal

by placing the bistables

in

trip.

The licensee attributed the cause to procedure

inadequacy,

provided

clarification to the technicians,

and the Plant Safeguard

Logic Test was

satisfactorily completed.

The

NRC concluded that the proximate cause of

the unanticipated

SI was failure to literally follow procedures.

This

violates Technical Specification 6.8. 1, which requires

procedures

for sur-

veillance and test of safety related

equipment to be established,

imple-

mented,

and maintained.

Other than the importance of literally following

procedures

for safety systems,

there

was

no safety significance to this SI

signal.

Most safeguards

equipment

was out of service

and the test is only

performed with the plant shutdown (50-244/89-13-06).

The licensee

determined that the failure of the SI signal to generate

a

containment ventil'ation isolation signal

was due to a wire missing from

the logic circuitry.

The wire was missing

due to a system modification

not yet completed.

The licensee

concluded that failure of containment

ventilation isolation to occur

was

an expected result considering

the in-

progress modification.

Post-modification testing

was adequate

to insure

the containment ventilation isolation signal functioned

as required.

The

modification was subsequently

completed

and successfully tested.

The in-

spectors

concluded that licensee

review of failure of the SI signal to

generate

a containment ventilation isolation signal

was thorough

and

ap-'ropriate.

Minimal safety significance

was attributed to the absence

of

the ventilation isolation signal

since operability of that isolation was

not required at the time.

The inspectors

had

no further questions

regard-

ing this item.

Waste

Gas

Release

On May 29,

1989, the waste

gas decay tank was

sampled at 6:43 a.m.

and

a

release

permit was initiated.

The release

was initiated at 8:40 p.m.

and

completed at 1:57 a.m.

on May 30,

1989.

The tank was isolated per proce-

dure from the time of the

sample

through the release.

Additionally, the

release

was monitored by radiation monitors

and

no alarms

were received.

Technical Specification Table 4. 12-2 requires

the sample to be taken with-

in 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> prior to the release.

In this case,

the release

was initiated

approximately

14 hours1.62037e-4 days <br />0.00389 hours <br />2.314815e-5 weeks <br />5.327e-6 months <br /> after the tank was sampled.

The release

was later

than expected

due to operations

personnel

being unavailable to perform the

release

while they were controlling plant start-up.

The error

was identi-

fied during the licensee's

normal permit review.

No similar late releases

were identified.

The licensee

counseled

personnel

involved and informed

all shift supervisors

of the event

and the need to verify strict compli-

ance with technical

specifications.

At the close of the inspection period

the licensee

was reviewing the release

process.

Because

the tank was isolated

from the time of the

sample

through the re-

lease,

and

no additional radioactivity was introduced to the tank prior to

release,

and the release

was monitored,

the release

was within release

limits on radioactivity.

This apparent violation (50-244/89-18-01)

had

minimal safety/environmental

significance,

and licensee

corrective actions

were assessed

as acceptable.

Cleanin

of Boric Acid Tank Sensin

Lines

On June

7,

1989, the licensee

discovered that Periodic Test PT-21, Clean-

ing Boric Acid Tank Sensing

Lines,

was not performed

as required

on June

1,

1989.

The sensing

lines are cleaned

weekly as preventive

maintenance

to ensure operability of the level instruments

by removing any boron

build-up in the level bubbler tubes. 'n this case,

the boric acid tank

level indication remained

operable

and there

was

nu safety significance to

the missed weekly cleaning.

PT-21 also was not performed

when required

on

Octuber 21,

1988.

Corrective

action taken included altering the schedule

for'"performing PT-21 to weekly on Thursday rather than Friday to allow for

timely verification of completion.

Although there

was

no safety significance to the missed weekly cleaning in

this instance,

the failure to adequately

correct

a previously identified

problem indicates

a weakness

in the oversight

and assurance

of quality.

10 CFR 50, Appendix B, Criterion XVI requires correction of conditions

. adverse

to quality.

The Ginna Quality Assurance

Manual, Section

16,

Corrective Action, Paragraph

2.0, requires,

in part, that the licensee

identify, report and correct conditions adverse

to quality, that Ginna

Station correct conditions adverse

to quality,

and that the Plant Opera-

tions Review Committee

(PORC)

recommend interim corrective actions.

Cor-

rective actions for failing to perform weekly rodding of boric acid tank

level bubbler tubes

on October 21,

1988 were inadequate

to prevent recur-

rence

on June

1,

1989.

This is an apparent violation (50-244/89-18-02).

Intermediate

Ran

e Detector Tri

Set pints

During the start-up

on June

1-2,

1989 the two intermediate

range detector

high level trips were set at 32 percent

and

40 percent current equivalent

of rated power.

Procedure P-l, Reactor Control

and Protection

System,

specifies

a trip setpoint of 25 percent of rated

power.

The inspectors

noted that trip setpoint accuracy is not assured until a calorimetric has

been performed

and the 25 percent trip setpoint cannot

be accurately

set

before start"up after refueling.

In this case,

there

was little safety significance

since the trip is

blocked when above

10 percent reactor

power, the trip does not provide

a

primary safety function (it is

a backup to the power range detector trip),

and credit is not taken for the trip in the licensee's

accident analysis.

The licensee

determined that they were not in compliance with P-1,

and is

evaluating resetting

the intermediate

range trip setpoint at an earlier

point during initial plant start-up.

The inspectors

had

no further con-

cerns.

This apparent violation (50-244/89-18-05) is considered

an iso-

'ated

instance for which appropriate corrective action. has

been initiated

and which has minimal safety/environmental

significance.

Main Generator

Current Transformer Slidin

Links

While placing the main generator

on the grid during plant start-up

on

May

30, 1989, the generator

breaker

was closed.

It immediately tripped open,

resulting in a main turbine trip.

Since reactor

power was less

than

50

percent,

approximately

17 p-rcent,

no reactor trip occurred.

All turbine

trip responses

functioned properly.

Licensee investigation

revealed that six sliding links in the generator

current transformer were incorrectly open.

During the

1989 refueling out-

age, offsite

RGEE personnel

conducted

maintenance

and testing of the main

transformer.

That work was not controlled by plant management.

The cog-

nizant substation

crew supervisor

stated that the cause of the links being

out of position could not be determined

since

some activities performed

were not specifically procedurally controlled.

During discussions

with

the licensee

on August 24,

1989, the

NRC was informed that the gasket

con-

dition indicated the enclosure

had not been

reopened

since the work in

question.

This indicated that the mispositioning occurred

during the

authorized

work.

This is the second

example of non-safety-related

equipment outside the

plant impacting plant operation;

a substation

breaker

bushing failure

caused

a loss of offsite power on July 16,

1988.

In that case,

the bush-

ing failure was attributed to low cooling oil level with the level

gauge

stuck high.

The

NRC concluded that the control over electric

power system

equipment

needs to be addressed

by licensee

management.

Absent information on electric power breaker maintenance

controls

and cor-

rective actions,

and absent

information showing adequate

control

and cor-

rective actions

on deficiencies

such

as the sliding link mispositioning,

these conditions appear to violate

10 CFR 50, Appendix A, Criteria

1 and

17 requirements for assuring that electric power systems will satisfac-

torily perform their safety function (50-244/89-18-07).

4

Aver a

e

Tem erature

Channel

403 Slidin

Link

On June

13,

1989,

the licensee identified that the average

temperature

channel

403 sliding link was inadvertently left open following an align-

ment.

Instrumentation

and Control (I&C) technicians

had opened

the link,

performed

an alignment

and failed to return the link to the closed posi-

tion as specified in Calibration Procedure

CP-7,

T AVG and

DELTA T Align-

ment at 70 Percent

Power or Greater,

Loop B, Unit 1,

Channel

3.

This link

is located in a cabinet in the back of the control

room.

The average

tem-

perature

instrument is safety-related

and provides inputs to the reactor

protection

system.

The safety significance of the link being out of posi-

tion was minimal; it functions to connect the correction for lead resist-

ance

changes

due to temperature

changes.

The error introduced did not

affect system operability.

The inspector

found that the

IKC technicians

had

an independent verifier

reviewing status of the links.

However,

the procedure

lacked

a second

signo'ff provision for documentation

of the independent verification.

Plant management

acknowledged that procedure.

were previously identified

as weak.

A Procedure

Upgrade

Program in process

includes reworking all

procedures.

Licensee

management

committed to have two independent

tech-

nicians initial each critical step regarding

equipment status

as

an in-

terim measure until the Procedure

Upgrade

Program is completed.

I

The inspectors

concluded that the licensee's

policy on independent verifi-

cation

needs

to be reviewed

by licensee

management

to determine whether

the second

check is sufficiently independent

of the first.

The licensee

cotmfritted to further define the independent verification process.

The in-

spectors

had

no further questions

about this specific occurrence.

The

weakness identified does,

however, reinforce the concerns

generated

about

procedure

adequacy

and adherence

elsewhere

in this report.

Containment Radiation Monitors R-10A

11

12

On June

16,

1989,

the licensee identified that radiation detectors

R-10A,

11,

12 for the containment

atmosphere

were not returned to service pro-

perly after routine calibration.

The detectors

were

removed

from service

for calibration

and

a grab sample

was obtained

on June

14,

1989 at 8:30

a.m.

After the calibrations

were completed

on June

15,

1989 at 4:30 p.m.,

the detectors

were not restored to their required condition.

Another grab

sample of the containment

atmosphere

was not obtained

because it was as-

sumed that the monitors were continuously monitoring the containment at-

mosphere.

On June

16,

1989 at 12:57 a.m.,

the licensee

discovered that

the radiation detectors

were aligned for continuous recirculation,

which

samples

ambient air.

The inspectors

reviewed CP-211, Calibration and/or Maintenance of

RMS

Channel

R-11 (Containment Particulate),

and found that the restoration

section contained

inadequate

instructions.

The procedure

required notifi-

cation to operations

and

assumed Administrative Procedure

A-52.4, Control

of Limiting Conditions

For Operating

Equipment,

would properly restore

the

system.

The licensee

issued

a procedure

change to provide step-by-step

restoration to service instructions.

Long term correction involves re-

writing all maintenance

procedures

as part of the Procedure

Upgrade Pro-

gram.

'echnical

Specification

3. 1.5. 1. 1 requires that, with Reactor

Coolant Sys-

tem (RCS) temperature

greater

than

350 degrees

Fahrenheit,

two of the

listed leak detection

systems,

including one system sensitive to radio-

activity, shall

be in operation.

Since the R-10A, 11,

12 radiation moni-

tors were not placed

back in service,

the licensee

did not have

any leak

detection

system sensitive to radioactivity in operation.

Technical

Specification

3. 1.5.1.2 allows

a system sensitive to radioactivity to be

inoperable

provided grab

samples of the containment

atmosphere

are ob-

tained

and analyzed at least

once every 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />,

Oue to the inadequate

restoration,

the containment

atmosphere

was not sampled for about

32 hours3.703704e-4 days <br />0.00889 hours <br />5.291005e-5 weeks <br />1.2176e-5 months <br />.

Although the safety significance of this event

was low because

the con-

tainment

was not purged during this tirrp period, the inspectors

concluded

that there

was

an apparent violation of Technical Specification

3. 1.5. 1. 1:

the

RCS temperature

was greater

than

350 degrees,

no system sensitive

to'adioactivity

was in operation,

and the compensatory

action of drawing and

analyzing

a grab

sample of the containment

atmosphere

at least every

24

hours

was not accomplished

(50-244/89-18-03).

Safet

Injection

S stem Recirculation Valves

On .brune

19,

1989, the control

room shift foreman identified that two of

the three Safety Injection (SI) system recirculation valves were out of

their required position.

The licensee

commenced

a shutdown until SI sys-

tem recirculation flow was restored

to the specified value by throttling

these

valves

from locked fully open to locked approximately

80 percent

shut.

During the

1989 refueling outage,

the licensee

implemented

an SI modifi-

cation which required throttling the recirculation valves to obtain the

desired

performance characteristics

(see

section

11).

Prior to this modi-

fication, the valves were required to be locked full open.

The inspectors

found that, during post modification testing,

the recirculation valves

were throttled to approximately

80 percent shut,

and this change

in re-

quired position

was not incorporated into the applicable

SI system lineup

procedures (i.e., S-30. 1, S-16.A).

Licensee

management

and the security department

investigated

to determine

how the valves were mispositioned

and were unable to determine

the cause.

These valves were procedurally controlled under

a locked valve list and

a

key is required to unlock the valves.

Several

members

in the operations

staff were

unaware of the change

in required position of the recirculation

valves.

Station

management

stated

the reason

why the valves were out of

~ ~

I

position is still under investigation.

The inspectors

concluded that the

impact of the modification was neither properly communicated

from engi-

neering

and the test group to operations

nor followed to resolution.

Administrative Procedure

A-52.2, Control of Locked Valve and Breaker Oper-

ation, required

two of the three

SI recirculation valves to be throttled.

On June

19,

1989, all three

SI recirculation valves were found in the full

open position.

This is another

example of the violation cited in Section

ill of this report (50-244/89-18-04).

Subsequently,

the licensee

determined that, if the SI system automatically

initiated while the recirculation valves were out of position, the re-

quired SI core delivery flow would have

been attained.

This is due to

a

20 percent error in the conservative direction

made during the SI flow

transmitter calibration.

Although the licensee

thought they were in an

unanalyzed

condition regarding

the valves out of position,

they later de-

termined they were not due to sufficient flow always being available.

The

NRC concluded that, although the violation did not result in inability to

meet design

requirements, it represented

an unacceptable

practice.

Safet

Injection

S stem Modificatior.s~Engineerin

Work Re vest

EWR-38~81

The Safety Injection (SI) system modifications were designed

to increase

the piping size for the

pump recirculation lines

and replace

three

SI re-

circulation valves.

The increase

in recirculation flow for the SI

pumps

was to reduce the likelihood that

pump damaae

might occur if operated

against

deadhead

pressure f)r an extended

time.

The recirculation flow

was-4esigned

to be increased

from approximately

35

gpm to 100

gpm for a

single

pump.

A new flow gauge

(FI-916, 0-350

gpm) was installed to allow

direct reading of the recirculation

and test flows.

Engineering

aspects

of the system design modifications were completed

by

the corporate

engineering

group.

Installation

was performed

by the modi-

fication project construction

group during the

1989 refueling outage.

System instrumentation

was adjusted

and calibrated

by the site

ILC depart-

ment during the outage.

Prior to plant start-up, modification functional

testing

was performed by the Results

and Test group with recirculation

flow set at

100

gpm through

each recirculation valve.

During plant startup after the

1989 refueling outage,

operational

system

testing

was performed with RCS pressure

greater

than

1000 psig.

The re-

sults indicated that the modified system

was unable to produce the SI flow

delivery to the reactor

as specified

by the

FSAR injection flow curve.

The SI system

was reconfigured to throttle two of the SI recirculation

valves to 35-50

gpm (approximately

80 percent closed) to achieve accept-

able recirculation flow and the required injection flow.

System recircu-

lation flow was established

by monitoring the

new flow gauge,

FI-916.

An

Engineering

Change Notice

(ECN 3881-16)

was issued

by the responsible

engineer to authorize

a revision of the system preoperational

test speci-

fication (MET-024) to require the recirculation valves to be throttled.

The system lineup sheets

required the recirculation valves to be Locked

Open

(LO) because

the modification was not carried through to change

the

position of these

valves from LO to throttled or locked/throttled.

Ap-

proximately three

weeks after the plant was operating,

a Procedure

Change

Notice (PCN) was written to change

the designated

position of the SI

pump

recirculation valves to throttled.

Since the operations shift supervisor

knew the valves were full open,

the

pumps were declared

inoperable

due to

inability to confirm required SI injection flow and

a technical specifi-

cation

LCO was .entered

on June

19,

1989.

A reactor

shutdown

was begun.

The recirculation valves were reconfigured to the designated throttled

position,

and normal operation

resumed.

During the monthly SI system operational

surveillance test

on June

21,

1989, inconsistent

and unrepeatable

flow results

were obtained with the

recirculation valves throttled to 80 percent shut,

The test results indi-

cated flows from 50 to 70

gpm on several trials.

The reactor

was manually

shut

down after the SI pumps were declared

inoperable

due to the inability

to obtain repeatable

flow rates.

During the efforts to analyze

the incon-

sistent flow results,

the

RG&E modification desi~n consultant

(NUS Coro.)

informed the engineering

group that the Flow Transmitters

(FTs) in the SI

injection piping may be calibrated incorrectly for the ins'.alled

Flow

Elements/orifices

(FEs).

Available vendor information indicated that the

flow transmitters

could be matched with several different orifice designs

(with different calibration characteristics),

but no specific information

was available

on the orifices installed in the SI system

(FT-924/FE-924

&

FT-925/FE-925).

The orifices were removed

and found to be of a design

with a calibration curve different from the one tte plane

has

used

since

1972-.

The curve error resulted in the actual

SI injection flow being ap-

proximately 20 percent greater

than the indicated flow.

Engineering per-

sonnel installed

a

new orifice design which provided more accurate

FE/FT

calibration data.

On June 24,

1989,

the SI system

was retested

with the

SI system recirculation valves fully open.

The required reactor delivery

curves were met with SI recirculation flow at the original design value

for the modified system (approximately

100

gpm each with two pumps

run-'ing).

Site operations

participated

in SI modification preoperational

testing

and

signed verification steps

in the test procedure

which reconfigured (i.e.,

throttled) the recirculation valves.

No related information was entered

into the control

room logs, the operations

required reading

program, or

other plant notifications.

The

ECN was issued

by the responsible

engineer

to allow throttling of the recirculation valves,

but operations

was not on

distribution and did not receive

a copy.

Approximately three

weeks trans-

pireB before

a

PCN was initiated to change

the valve lineup sheets

to re-

flect locked throttled recirculation valves.

No interim drawing change

was

made

by the liaison engineer to reflect the correct throttled position

of the recirculation valves.

There was

no indication that the liaison

engineer

was

made

aware of the change in the valves'ositions

or that he

was aware of the existence of the

ECN.

This demonstrated

a lack of ef-

fective communication

between corporate

and onsite groups.

C i

Engineering did not have verifiable information on the exact design of the

original injection flow orifices.

Design information from the original

construction

plans listed the orifice sizes only.

According to the ven-

dor, different orifice shapes

could have

been

used with the specific

FT

model installed.

The

new orifices installed were the

same

size

and had

the

same flow characteristics,

but had

a different shape

which was able to

provide more accurate calibration data.

The revised data were used to

confirm that FSAR-required injection flow was met with the recirculation

valves fully open

as originally designed.

The inspectors

questioned

the original engineering

department

assumption

that the modified SI system could be reconfigured with recirculation

valves throttled nearly closed

and 35-50

gpm as indicated

on FI-916.

FI-916 is not a linear gauge

and there is no incremental

mark at 35 gpm.

The inspectors

checked the calibration data for FI-916 and it was noted

that FI-916 was least accurate

in the low range where the initial incre-

mental

markings are

spaced at 25

gpm and where the gauge is more non-

linear.

This item is not being separately

pursued.

It is, however,

an-

other indication of lack of thorough design control

o+ field changes

to

modifications.

The

new recirculation valves

had to be throttled to approximately

80 per-

cent shut to achieve

measured

flows in the 35

gpm range.

The responsible

engineer

stated that these

valves were not designed to be throttled in

this region because

of the

unknown consequences

from flow instabilities

induced

by

a two piece

stem

and disc.

Also, the long zerm consequences

from high velocity flow were not

known for a nearly cl)sed valve.

This

question

on the part of the responsible

engineer also

showed ex',stence

of

failure to thoroughly review and resolve

a field change to a modification.

Inasmuch

as the valves did not remain throttled, this issue is not being

separately

addressed.

It is, however,

another pertinent input in consi-

dering the extent of the modification control problem.

The joint modification follow group is constituted primarily to verify

that

a modification is complete

and ready for installation in the plant.

All activities associated

with preparing

a design

package

are usually com-

pleted in time for the construction,

and for site training and operations

groups to prepare

documents

required to integrate

the modification into

plant operations.

The modification follow group provides the primary in-

terface for all principal groups dealing with the design, installation,

testing,

and operation of a modification.

The formal business

of the

group is completed

when turnover to the site groups begins.

The inspec-

tors concluded that this happens

too early in the modification process,

because

of the ongoing

need for design engineering

involvement in modifi-

cation installation, testing,

and initial operation,

and because

of the

need for more effective communication

between

the modification follow

group members.

10

Site Administrative Procedures,

A-301 series,

Control of Station Modifi-

cations,

allow informal turnover of control of plant modifications.

Also,

turnover punchlists

were found to be unofficial, uncontrolled

documents

without binding requirements

on the parties

who produce

them.

Group man-

agers

are responsible

for resolving punchlist items before final system

turnover,

but there is no accountability

system for ensuring that punch-

list items are resolved to the satisfaction of the parties

involved.

This

condition increases

the possibility of missing the transfer of design in-

formation and/or required action items.

Acceptance

of a plant modification is accompli shed

by the

modification'esign

coordinator

and liaison engineers

who do not have defined design

responsibility for modifications.

Most of the system design

and testing

information is accepted

from corporate

engineering

and the Results

and

Test

(R&T) group.

The

R&T group does not participate

in the preparation

of operations

procedures

which may be developed

from or affected

by opera-

tional testing.

Operations

does not always participate fully in

preopera-'ional

or operational

acceptance

testing.

In this case,

the inspectors

found

no effective operations participation in SI modification functional

testing.

SI operational

procedures

were developed after the modification

follow group closed out formal activities early in the modification in-

stallation process.

Information given to operations

during modification

training was based

upon

a system configuration with fully open recircula-

tion valves

Most operations

personnel

assumed

the valves

should always

be open.

They did not functionall'y participate

in the system testing

and

modification field change

processes.

TheWiaison engineer is responsible

for issuing interim drawing changes

to

the plant system

P&IDs in a timely manner

so that control

room operators

are informed of changes

to system

and component configurations while P&ID

changes

are in progress.

The interim drawing changes

for the SI system

were reviewed.

One SI system

P&ID (33013-1262)

had

been

used to indicate

system

changes for three

separate

P&IDs (33013-1261,

-1262,

and -1266).

Although the changes

were not complex, the areas

of the SI system

on each

plan were represented

differently and the potential for misunderstanding

was clear.

No administrative controls were found to effectively control

this practice

and the liaison engineer

stated that this case

was not in

accordance

with standard practice at Ginna Station.

This drawing change

control inadequacy

was assessed

as another indicator of inadequate

overall

control of modifications.

The Ginna Quality Assurance

Manual, Section

3, Confi uration Control,

Paragraph

2.3, requires,

in part, that Ginna Station prepare

or revise

plant procedures

or documents

as necessary

to reflect modifications.

Pro-

cedures

requiring SI recirculation valves to be verified full open were

not revised to require the valves to be throttled in accordance

with the

design

change.

This is an apparent violation (50-244/89-04).

P

r

11

ATWS/AMSAC Modification

En ineerin

Work Re vest

EWR-4230

AMSAC is

a Westinghouse

Plant Owner's

Group system

upgrade

designed

to

comply with the

ATWS rule of 10'FR 50.62.

The system is designed to in-

itiate auxiliary feed flow and trip the main turbine when turbine header

pressure

exceeds

40 percent of full power turbine header

pressure

and

a

loss of main feed flow is anticipated.

AMSAC mitigates plant transient

consequences if no reactor trip occurs.

The

AMSAC modification was installed

and functionally tested.

Acceptance

testing

was accomplished prior to plant start-up

by

R&T and

I&C personnel.

During plant startup

on June

1,

1989,

the system

was placed into operation

with reactor

power at approximately

53 percent

and turbine header

pressure

greater

than

40 percent.

When

AMSAC was "unblocked" to bring it on-line,

the main turbine tripped.

The reactor also tripped since

power was

greater

than

50 percent.

Once again,

the inspectors

concluded that the modification follow group

had completed its business

too early.

During the modification follow

group ..eetings,

uncontrolled

and unofficial design information drafted

on'G&E

title block drawing paper

was distributed to the site operations

and

training departments.

These drawings were

AMSAC logic diagrams

which con-

tained incorrect design information.

They were

used

by site groups to

develop onerating

procedures

and training packages

for the modification.

This condition is another

example of inadequate

design control.

The

AMSAC responsible

engineer

stated that

he often distributed uncon-

troDed and/or unverified design

information for general

purposes

and did

not know specifically what it was

used for, or if it was

used for any of-

ficial purpose.

In this case,

he did not know he was putting out incor-

rect logic information.

The responsible

engineer

also stated that

RG&E

purchased

the design

package

for the

AMSAC and that corporate

engineering

had

no real direct need for the system logic.

There does not appear to

have

been

any licensee

engineering effort to ensure that the system con-

figuration matched

the

system, logic.

This is another

example of inade-

quate design control.

The site

I&C group participated

in AMSAC operational

testing.

Technicians

reportedly understood that,

when the test procedure

removed the conditions

which initiated the trip signals,

the relays would maintain

a trip signal

if the system

was deactivated

before allowing the

200 second timer to run

out.

The test procedure did not require

a 200 second wait time to permit

the trip signals to clear.

The operating

procedure

assumed

the system

was

clear of any trip signals.

The procedures

were inadequate

because

the

test procedure

did not leave the system in the configuration the operating

procedure

assumed it to be in. It also left the system in a configuration

that could not be cleared

by resetting

the

system at the time specified

by

the operating procedure.

l

12

The AMSAC operations

procedure

was generated

as

a

PCN to procedure 0-1.2,

titled

Plant from Hot Shutdown to. Full Load,

and was sent to the Plant

Operations

Review Committee

(PORC) without going through the normal pre-

PORC process

defined by Adminis'trative Procedure

A-601.2, Procedure

Con-

trol - Permanent

Changes, (i.e., without the specified technical

reviews

and approvals).

PORC did not perform

a technical

review of this proce-

dure.

The inspectors

and the licensee

concluded that the operating

and

logic error s probably would not have

been detected

in the normal

pre-PORC

process.

NRC review also concluded that,

since the

18C department

under-

stood the problem of leaving the

system with a trip signal

locked in, the

error could have

been identified and associated

problems prevented prior

to system operation if 18C and operations

had communicated effectively.

Operations

did not participate in the preoperational

acceptance

testing to

the extent necessary

to fully understand

that the assumed

system logic was

wrong.

Current

system drawings were not used during the preparation of

the operational

procedure for AMSAC.

The system construction

drawings

were not part of any formal design

package

given to operations.

The opera-

tional procedure

was developed

from the incorrect

system logic and from

operating information made avai'.able

from the designer.

Corporate engi-

neering did not normally review operations

procedures.

In addition, engi-

neering drawings were not normally being

used to verify or validate

changes

to operating

procedures.

No formal check of the validity of the

system logic was performed

by the plant operations

group.

The Ginna guality Assurance

Manual, Section

3, Confi uration Control, Para-

graph 2.3, requires,

in part, that Ginna Station prepare or revise plant

procedures

or documents

as necessary

to reflect modifications.

Procedures

incorporating

changes

due to the

AMSAC modification were not revised

as

necessary

to reflect proper operation of the modified system.

This is

another

example of the apparent violation (50-244/89-04)

described

in Sec-

tion

11 of this report.

Exit Interviews

An interim exit interview was held with the licensee

on June

30,

1989.

After subsequent

information development

and review, another exit inter-

view was held with the licensee

on August 24,

1989.

That second exit in-

terview was held primarily to emphasize

the seriousness

with which the

NRC

regarded

the design control

inadequacies

identified in thi s report.

'

TABLE 1

Date

May 18,

1989

Event

Containment ventilation isolation signal

not generated

during safety injection actuation

due to missing wire.

May 29,

1989

Release

of waste

gas outside

12 hour1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> Technical Specifica-

tion limit.

May 30,

1989

June

1,

1989

June

1,

1989

June

13,

1989

June

16,

1989

Turbine trip due to current transformer

open links.

Plant trip from 53 percent

power due to AMSAC modification.

Surveillance

PT-21 not performed

as required.

Slide links feeding

one Tavg and Delta

T channel

found open.

Radiation monitors

R-10A, 11,

12 found misaligned to sample

ambient air rather than containment air.

June

16,

1989

Intermediate

range bistables'rip

setpoints

found set at

40 percent

and 32 percent equivalent

power.

June

19,

1989

Safety Injection recirculation valves

1820

B and

C found

locked full open.

June

21,W989

Safety Injection recirculation flow found out of tolerance

with nonrepeatable

resul ts.

~

$

4

~

~ 'Aa

~

~

N

ENCLOSURE

2

POTENTIAL ENFORCEMENT ITEMS

1.

Contrary to Criterion III, Appendix B,

10 CFR 50 and Section

3 of the

Ginna guality Assurance

Manual,

measures

to control design

changes

were

inadequate

for modifications accomplished

during the

1989 refueling out-

age.

Specifically, the following conditions indicate

a breakdown

in de-

sign control:

On June

1,

1989,

when the recently completed

ATWS Mitigating System

Actuating Circuitry modification was placed into operation during

plant star t-up,

a main turbine

and reactor trip resulted.

This was

due to incorrect

system design

information being

used to develop

operating

procedures

and training packages

for the modification.

Further, uncontrolled

and unofficial modification information had

been distributed to the operations

and training departments.

On June

19,

1989,

about three

weeks after the plant had be~~ returned

to operation after the outage during which Safety Injection (SI) sys-

tem mod:fications were accomplished

under Engineering

Work Request

EWR-3881

and Engineering

Change

Notice

ECN 3881-16,

and w'ith two SI

system recirculation valves required to be throttled to 80 percent

closed,

these

valves were fully .open.

This condition was identified

when the procedure

change

notice requiring the valves to be throttled

was identified by the operating shift supervisor

as not being

com-

plied with, and the system line-up sheets

had not been modif ed to

--reflect the positioning change.

Therefore,

the as-prescribed

design

basis

was not correctly translated

into the operating

procedures.

On June

21,

1989, the SI system recirculation flow measuring orifice

design calibration curve was found to be different than the

one the

plant has

been

using since

1971:

Although this error resulted in SI

injection flow being about

20 percent higher than indicated, it also

showed that the design basis recirculation flow was not correctly

translated

into instructions,

procedures,

and drawings, in that the

prescribed recirculation flow valve throtting to 80% shut was in-

appropriate.

As of June

21,

1989,

the modification control series

A-301 procedures

and the informal "punch list" of items to be completed for turnover

of modified systems

to Operations

was found to not require completion

of items necessary

for turnover.

Further,

Operations

was not pro-

perly involved in modification review and approval,

inasmuch

as docu-

ments

(such

as the Engineering

Change Notice which prescribed throttl-

ing of the safety injection recirculation valves)

were not distri-

buted to or required to be reviewed by Operations.

Also, although

Operations

personnel

participated

in testing the SI modification,

'I $

'

a

~

0

4

Pj

cl

Enclosure

2

there

was

no indication of thorough Operations

review of the modifi-

cation prior to and during its accomplishment,

or of Operations

par-

-ticipation in the modification process

to the extent that significant

specified

changes

in safety-related

valve positions

were monitored

and verified complete

by the operating staff.

2.

Contrary to Criteria

1 and

17, Appendix A, 10 CFR 50,

based

on the July

16,

1988 loss of offsite power and the

May 30,

1989 turbine trip, the lic-

ensee

did not exercise

adequate

control over and corrective action for

electrical

power supply distribution equipment.

3.

Contrary to Technical Specification 6.8. 1,

and Criterion V, Appendix B,

10 CFR 50 and Section

5 of the Ginna Quality Assurance

Manual, the Plant Safe-

guards

Logic Test procedure

was not implemented (literally followed) as

prescribed

on May 18,

1989,

and

an unanticipated

safety injection signal

was consequently

generated.

4.

Contrary to Corrective Action Criterion XVI, Appendix B,

10 CFR 50 and

Section

16 of the Ginna Quality Assurance

Manual

requirements

for prompt

identification and correction of conditions

adverse

to quality, corrective

actions for failure to perform weekly rodding of boric acid tank level

bubbler tubes

on October 21,

1988 were ineffective in preventing recur-

rence

on June

1,

1989,

'ontrary

to Technical Specification

3. 1.5. 1. 1,

on June

16,

1989 reactur

coolant

system temperature

was above

350 degrees

Fahrenheit

and

no re-

quired reactor

c )olant leak detection

system sensitive to radioactivity

was'peration,

and the compensatory

requirement for sampling the con-

tainment every 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />

was not met.