ML17229A527

From kanterella
Jump to navigation Jump to search
Insp Repts 50-335/97-15 & 50-389/97-15 on 971008-30.Apparent Violations Being Considered for Escalated Enforcement Action.Major Areas Inspected:Deficiencies W/Plant Containment Cooling Sys
ML17229A527
Person / Time
Site: Saint Lucie  NextEra Energy icon.png
Issue date: 11/06/1997
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML17229A526 List:
References
50-335-97-15, 50-389-97-15, NUDOCS 9711190294
Download: ML17229A527 (14)


See also: IR 05000335/1997015

Text

U.S.

NUCLEAR REGULATORY COMMISSION

REGION II

Docket Nos: 50-335,

50-389

License

Nos:

DPR-67,

NPF-16

Report

Nos: 50-335/97-15,

50-389/97-15

Licensee:

Florida Power

8 Light Co.

Facility:

St. Lucie Nuclear Plant.

Units

1

8 2

Location:

6351 South

Ocean Drive

Jensen

Beach,

FL

34957

Dates:

October

8 - October

30.

1997

Inspector:

J.

Munday, Acting Senior Resident

Inspector

Approved by:

K. Landis, Chief, Reactor Projects

Branch

3

Division of Reactor

Projects

Enclosure

97iii90294 97ii06

PDR

ADQCK 05000335

8

PDR

EXECUTIVE SUMMARY

St. Lucie Nuclear Plant.

Units

1

8 2

NRC Inspection

Report 50-335/97-15,

50-389/97-15

This special

inspection resulted

from the identification of deficiencies with

the St. Lucie Unit 2 containment cooling system.

During the performance of a

technical specification surveillance

on October 8.

1997, the licensee

discovered that containment cooler

fan 2-HVS-1D, was running in the reverse

direction in slow speed.

The licensee's

investigation concluded that the fan

motor was replaced

on May 9,

1997,

and post maintenance testing failed to

identify the reverse rotation while operating in the slow speed.

Additionally, subsequent

performance of the safeguards

test.

conducted

on May

19. failed to identify the problem.

Conclusions

included the following:

~

An apparent violation of Technical Specification 3.6.2. 1 was identified

for having less than two trains of containment cooling operable,

when

required.

~

An apparent violation of 10 CFR 50 Appendix B, Criterion V, was

identified for failure to perform a proper post maintenance test of

containment cooler fan 2-HVS-1D.

~

An apparent violation of 10 CFR 50 Appendix B, Criterion XI, was

identified for failure to adequately test the containment cooler fans

required by Technical Specification 4.6.2. 1. 1.a. 1.

~

The insepctors

observed that the work history revealed three separate

missed opportunities to identify that the containment

fan cooler motor

leads

had been reversed:

1) the

PMT on 05/16/97,

2) the safeguards

test

on 05/19/97,

and the

PMT on 05/21/97.

The questioning attitude

on the part of the Assistant

Nuclear Plant

Supervisor,

who identified that the containment cooler fans were not

being tested in its emergency configuration,

was highly noteworthy.

The root cause analysis

and corrective actions taken by the licensee,

upon identification of the issue,

were comprehensive

and timely.

N8

M8.1

R~ttl t

11

Miscellaneous

Maintenance

Issues

Unit 2 Containment Cooler Fan Ino erabi lit

37551

62707

71707

and

~93702

Ins ection Sco

e

On October

8, the licensee

discovered that containment cooling fan,

2HVS-1D, rotated in the reverse direction when operated in slow speed.

The inspector monitored the licensee's

activities regarding the

identification and subsequent

investigation of the inoperable

containment

cooler fan.

The inspector monitored the Event Response

Team

activities, the management

meetings

surrounding this event,

and reviewed

CRs 97-1860,

97-1868.

and 97-1880.

In addition,

work documents

applicable to the event were also reviewed.

Observations

and Findin s

R~tt

The containment cooling system consists of two trains of containment

spray

pumps,

two trains of containment

fan coolers

(each train

consisting of two fans),

and two trains of shutdown cooling.

The

containment cooling fans are powered

by two speed

motors,

which allow

fast and slow speed operation.

Post-accident

containment

heat

removal

is satisfied

by one containment

spray

pump and two containment coolers

operating in slow speed.

This design allows for the failure of a single

Emergency Diesel Generator

(EDG), which supplies

power to one complete

train.

The system is normally operated with three coolers in service with the

fans in f'ast speed.

The remaining fan is in standby.

Upon initiation

of a Safety Injection Actuation Signal

(SIAS), the three operating fans

shift to slow speed

and the idle fan starts in slow speed.

The inspector

reviewed the operating procedures

associated

with this

.system,

the applicable sections

in the

UFSAR, electrical

schematics

depicting the SIAS initiation logic, and conducted

interviews with

several

licensed operators

and engineers

to verify both normal

and

emergency

system response.

Identification of Ino erable

Containment Coolin

Fan

Technical Specification Surveillance 4.6.2. 1. 1.a requi red, in part, that

each cooling train be demonstrated

OPERABLE by starting

each cooling

train fan unit from the control

room and verifying that each unit

operated for at least

15 minutes.

(The Technical Specification

does not

discern

between fast and slow speed.)'he

licensee

performed this

surveillance weekly, in accordance

with Normal Operating

Procedure,

NOP-

2-2000020,

Revision 2,

"Containment Cooling'ystem Operation."

The idle

fan would be started in fast speed

and one of the running fans would

then be secured.

Over

a period of four weeks,

each of the fans

was

operated,

in fast speed,

for a period of time in excess of 15 minutes..

An Assistant

Nuclear Plant Supervisor

(ANPS), expressed

concern that the

containment cooler fans were not being tested in their emergency

configuration,

slow speed.

CR 97-1860

was initiated to determine if

Technical Specification Surveillance 4.6.2. 1. 1.a

was being satisfied.

The licensee

subsequently

determined that the surveillance

was

inadequate

and tested the fans in slow speed,

thei r emergency

configuration.

When the "D" fan was started,

a low air flow annunciator

was received.

CR 97-1868 was written to document the events

evaluate operability,

and

develop

a troubleshooting

plan.

The licensee

subsequently

declared the

fan inoperable

and entered the action statement of the Technical

Specification,

which required that the fan be returned to service within

seven

days.

or

be in Mode 3 within six hours

and in Mode 4 within the

following six hours.

On October 7.

as part of the troubleshooting effort, the licensee

operated all four fans in the slow speed to simulate operation following

a SIAS.

As expected,

the low air flow annunciator for the

"D" fan

alarmed

when the fan was initially started.

In addition, after the fans

had operated

approximately

10 minutes,

the "A" low air flow annunciator

alarmed.

At that point, the licensee

declared the "A" fan cooler

inoperable

and entered into the action statement

which required that one

of the coolers

be restored to operable status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />,

or

commence the aforementioned

shutdown.

On the morning of October 8, the licensee

entered

containment to

troubleshoot

and perform inspections of the "A" and the "D" fan units.

The duct f'r the

"D" fan was opened,

and the fan was observed to be

rotating backwards while operating in the slow mode.

The fan rotated

proper ly in the fast mode.

The licensee initiated

CR 97-1880 to

document the event

and the requi rement that

a one hour

NRC notification

be made in accordance with 10 CFR 50.72(b)(ii)(B), as

a condition during

operation that resulted in the nuclear

power plant being outside the

design basis of the plant.

This decision

was based

on the design basis accident occurring

simultaneously with the single fai lure of the

EDG supplying power to the

train in which both fans were operable.

Because the

"D" fan operated

backwards in the other train, the event would result in having only one

containment cooler fan operable.

Although the containment

spray

pump

would still be available,

the loss of the

"D" cooling fan would have

resulted in the plant being in- an unanalyzed condition.

On October 9, the licensee rolled two of the fan motor leads at the

Motor Control Center to correct the reverse rotation.

Post maintenance

testing verified proper rotation.

Maintenance Histor

The licensee

reviewed the work history associated

with the

"D" fan motor

to determine

how and when the error occurred.

The details of that

investigation are

as follows:

1

04/14/97

Containment cooler fans A, B,

C,

and

D removed from service.

(The unit was in a refueling outage.)

05/01/97

1&C Maintenance

removed containment cooling fan D, air flow

switch, to support

removal of 'the fan motor by Mechanical

Maintenance.

05/04/97

Mechanical

Maintenance

removed fan assembly

and motor

as

part of normal preventive maintenance.

in accordance with

Work Order

(WO) 96023113

and Haintenance

Procedure

2-

0950173,

Revision 9,

"The Overhaul

Of Containment

Fan Cooler

Motors 2HVS-1A. 1B,

1C,

1D (EQ Motors)."

05/09/97

Mechanical

Maintenance installed refurbished

fan assembly

and motor.

05/10/97

05/16/97

05/19/97

I&C Maintenance reinstalled

containment cooling fan D, air

flow switch.

Electrical Maintenance

performed

motor rotation verification

in accordance

with HP-2-0950173.

section 9.9.

Safeguards

test is performed,

which satisfied,

among other

things, Technical Specification 4.6.2. 1. 1.b.

It requi red

that,

each containment cooling train be demonstrated

OPERABLE .at least

once per

18 months,

during shutdown,

by

verifying that each containment cooling train start

automatically

on an SIAS test signal.

05/21/97

Operations

reported trouble with containment cooling fan D,

air flow switch.

WO 97012388

was initiated which stated.

"Alarm coming in for no reason."

05/21/97

I&C Maintenance identified air flow switch mounted upside

down with the flow element facing in the reverse direction.

The switch was

removed

and oriented properly.

A post

maintenance test,

consisting of a channel

check

and

functional test.

was completed satisfactorily.

(The

functional test operated the fan in fast speed.)

05/22/97

Unit 2 enters

Operational

Mode 3.

The insepctors

observed that the above work history revealed three

separate

missed opportunities to identify that the containment

fan

cooler motor leads

had been reversed:

1) the

PMT on 05/16/97,

2) the

safeguards

test

on 05/19/97,

and the

PMT on 05/21/97.

The licensee

concluded that the motor leads

had been reversed

when the

new motor was installed in accordance

with WO 96023113.

The post-

maintenance test following replacement of the motor required the fan to

be operated

in both the slow and fast speeds

with verification of proper

fan rotation.

However, the licensee collected historical data

from the

sequence

of event's

recorder which indicated that,

although the fan was

started twice, it was started in the fast

mode both times.

The licensee

attributed this failure to poor communication

between the personnel

observing the fan during testing

and the Operator

who started the fan

for the test.

Vendor Evaluation of Si nificance

The licensee

requested

ABB Combustion Engineering

Nuclear Operations

(ABB CENO) to perform an evaluation

on the safety significance of'he

inoperable

containment

fan cooler.

The assessment

focused

on the

containment

response to the Loss Of Coolant Accident

(LOCA) coincident

'ith

the loss of an Emergency Diesel Generator.

The assessment

focused in two areas;

1) containment

peak pressure

and 2)

equipment qualification temperature

envelope.

The most limiting case

with regard to containment

peak pressure

was

a double-ended

suction leg

slot break with minimum safety injection flow.

This case

produced

a

peak pressure of 36.2 psig.

This pressure

was within both the

Integrated

Leak Rate Test (ILRT) pressure of'1.8 psig and the

containment

design pressure of 44 psig.

The most limiting case with

regard to equipment qualification was

a double-ended

discharge

leg slot

break with minimum safety injection flow.

Each of these

cases

assumed

only one containment

spray

pump and two containment cooler fans were

operational.

I

The assessment

concluded that the loss of an additional

containment

cooler fan would result in a containment

peak pressure

increase of 0.5

psig for the

same scenario..

For the case

concerning

equipment

qualification, the assessment

concluded that the loss of one containment

cooler fan would cause

a slight increase in the long term temperature

profile.

However, it was stated that this increase

would not challenge

the capability of the Class

1E equipment to perform its intended safety

functions.

Root Causes

and Corrective Actions

The licensee initiated an Event Review Team

(ERT) to review the event,

identify root causes,

and develop corrective actions.

The root cause for the fan rotating backwards

was determined to be

a

breakdown in communication

between Electrical Maintenance

personnel

inside containment

and the control

room staff.

Other weaknesses

contributing to this root cause

were:

1) the maintenance

procedure did

not identify the fan motor

as having dual windings, 2) the procedure did

not requi re signatures

for verification of rotation in both speeds,

only

the slow speed

and 3) lack of three part communication.

The root cause identified for the inadequate

surveillance

was

an

apparent error in the preparation of the surveillance

procedure.

The

Technical Specification did not explicitly state that the fans were to

5

be surveilled in the slow speed.

The fact that the emergency function

of the fans was for them to operate in the slow speed,

was overlooked.

The licensee's

corrective actions are

as follows:

1)

NOP-2-02000020,

Revision 3, "Containment Cooling System

Operation,"

was approved for use

on October

13,

1997.

2)

MP-2-0950173,

"The Overhaul of Containment

Fan cooler Motors 2HVS-

'1A,

1B,

1C,

1D (EQ Motors)," will be revised to requi re signatures

for rotational testing for both speeds,

and to add

a caution to

test both motor speeds

following maintenance.

3)

ADM-78-01, "Post Maintenance Testing," will be revised to add

a

caution about testing multiple speed

motors.

4)

5)

ADM-17-11, "50.59 Screening," will be reviewed to determine if

additional guidance is needed to ensure that the reviewer

considers

the intent of the Technical Specifications

as well as

the

UFSAR requirements

when revising procedures.

Operations will review control

room practices to determine if

additional tracking of annunciators

is needed

during safeguards

tests.

6)

Maintenance will review the method for installing the air flow

switches to determine if additional

guidance or training is

needed.

7)

Engi.neering will complete the "extent of condition" review.

8)

Maintenance will conduct training on the event

and 3-way

communication.

9)

Operations will conduct training to ensure

missed survei llances

are considered

an operability concern.

10)

Corrective Actions Group will ensure that Condition Reports

associated

with missed surveillances

are considered

an operability

concern.

c.

Conclusions

The inspector

reviewed the documents identified throughout this report

and conducted

interviews with various Operations

and Maintenance

personnel.

Although the assessment

of safety significance generated

by

ABB CENO indicated that the impact on containment

due to the faulted

containment

fan cooler was minimal, the significance of'he event

was

significantly higher because of its duration

and the prior opportunities

that were available to identify the condition.

The inspectors

observed

that the work history revealed three separate

missed opportunities to

identify that the containment

fan cooler motor leads

had been reversed.

X1

In addition, the inspector thought that the lack of rigor in identifying

all annunciators

in alarm during the safeguards

test to be

a particular

weakness

in the performance of that surveillance.

However, the inspector concluded that the questioning attitude

on the

part of the ANPS,

who initially identified the issue, to be especially

noteworthy.

Additionally. the inspector concluded that the root cause

analysis

and corrective actions taken by the licensee.

upon

identification of the issue,

were comprehensive

and timely.

The inspector concluded that containment cooling fan,

2-HVS-1D, had been

unavailable for operation in the slow speed

from April 14,

1997.

when it

was

removed

from service. until October 9,

1997,

when the motor leads

were rolled and proper rotation was verified.

Technical Specification 3.6.2. 1 states

that two containment

spray trains

and two containment

cooling trains shall

be

OPERABLE, in Operation

Modes l. 2 and 3.

However,

on May 22.

1997. the licensee

entered

Mode 3 with only one

train of'ontainment cooling operable.

This was

an apparent violation

of technical specifications that existed

from May 22 unti 1 the problem

was corrected

on October 9,

and is identified as

EEI 50-389/97-15-01,

"Failure to Maintain Two Trains of Containment

Coolers

Operable

as

Required

By Technical Specifications."

In addition, the inspector

concluded that on May 16,

1997, the licensee

failed to properly implement Maintenance

Procedure

2-0950173,

Revision

9,

"The Overhaul

Of Containment

Fan Cooler Motors 2HVS-1A, 18,

1C,

1D

(EQ Motors)," in that the required post maintenance test for the 2-HVS-

1D was not perf'ormed

upon completion of WO 96023113.

This was

an

apparent violation of 10 CFR 50, Appendix 8, Criterion V, and is

identified as 50-389/97-15-02,

"Inadequate

Post Maintenance

Test

Following Replacement

of Containment, Cooler Fan Motor."

The inspector also concluded that NOP-2-2000020,

Revision 2.

"Containment Cooling System Operation," did not adequately verify

compliance with Technical Specification 4.6.2. l.l.a. 1, in that it did

not test the 2-HVS-1D, in its emergency

alignment.

This is an apparent

violation of 10 CFR 50 Appendix 8, Criterion XI, and is identified as

50-389/97-15-03,

" Inadequate

Surveillance Test of Containment

Cooler

Fans."

V. Mana ement Meetin s and Other Areas

.Exit Meeting Summary

The inspectors

presented

the inspection results to members of licensee

management

at the conclusion of the inspection

on October 29,

1997.

The

licensee

acknowledged

the findings presented.

The inspectors

asked the licensee

whether

any materials

examined during the

inspection should

be considered

proprietary.

No proprietary information was

identified.

Licensee

.7

PARTIAL LIST OF

PERSONS

CONTACTED

C. Bible, Site Engineering

Manager

W. Bladow, Site Quality Manage

D. Fadden,

Services

Manager

H. Johnson,

Operations

Manager

J.

Marchese,

Maintenance

Manager

C. Marple, Operations

Supervisor

J. Scarola,

St. Lucie Plant General

Manager

A. Stall, St. Lucie Plant Vice President

E. Weinkam, Licensing Manager

Other licensee

employees

contacted

included operations,

engineering,

and

maintenance

personnel.

INSPECTION

PROCEDURES

USED

IP 37551:

Onsite Engineering

IP 62707:

Maintenance

Observations

IP 71707:

Plant Operations

IP 93702:

Prompt Onsite Response to Events at Operating

Power Reactors

ITEMS OPENED,

CLOSED,

AND DISCUSSED

~0ened

50-335,389/97-15-01

50-335,389/97-15-02

50-335,389/97-15-03

Closed

None

Discussed

None

EEI

"Failure to Maintain Two Trains of Containment

Coolers Operable

as Required

By Technical

Specifications"

(Section

H8. 1c)

EEI

"Inadequate

Post Maintenance

Test Following

Replacement

of Containment

Cooler

Fan Motor"

(Section H8.1c)

EEI

"Inadequate Surveillance Test of Containment

Cooler Fans"

(Section H8.1c)

ABB

ADM

ANPS

ATTN

CENO

CFR

CR

DPR

EA

EDG

EEI

EQ

ERT

HVS

ILRT

LOCA

MP

NOP

NPF

NUREG

PDR

pslg

SIAS

TS

UFSAR

USNRC

WO

LIST OF ACRONYMS USED

ASEA Brown Boveri

(company)

Administrative Procedure

Assistant

Nuclear Plant Supervisor

Attention

Combustion Engineering

Nuclear

Operations

Code of Federal

Regulations

Condition Report

Demonstration

Power Reactor

(A type of operating license)

Enforcement Action

Emergency Diesel

Generator

Escalated

Enforcement

Item

Equipment Oualification

Event Review Team

Heating

and Ventilating Supply (fan, system, etc.)

Integrated

Leak Rate Test(ing)

Loss of Coolant Accident

Maintenance

Procedure

Normal Operating

Procedure

Nuclear

Production Facility (a type of operating license)

Nuclear Regulatory

(NRC Headquarters

Pub1ication)

NRC Public Document

Room

Pounds

per square

inch (gauge)

Safety Injection Actuation System

Technical Specification(s)

Updated Final Safety Analysis Report

United States

Nuclear Regulatory

Commission

Work Order