|
---|
Category:Meeting Briefing Package/Handouts
MONTHYEARML23335A0822023-12-0707 December 2023 NRC -Crystal River LTP Public Mtg Slide Deck Final ML23335A0832023-12-0707 December 2023 ADPCR3 - Crystal River LTP Public Mtg Slide Deck Final ML20022A0262020-01-22022 January 2020 NEI Presentation Status Update for Ropte Short Term Action Plan: Removed Planned Unavailability for Mitigating Systems Performance Index ML17227A2362016-02-18018 February 2016 Presentation Slides from February 18, 2016, Meeting with Duke Energy Regarding Crystal River Unit 3, Cyber Security Plan Implementation Schedule Milestone 8 ML14024A2632014-01-16016 January 2014 Handouts for Post-Shutdown Decommissioning Activities Report Public Meeting, January 16, 2014 ML13308A0072013-11-0101 November 2013 Open Phase Resolution Update Meeting Duke Energy Entitled Open Phase Detection and Protection. ML13238A3072013-08-29029 August 2013 Slide for 08/29/13 Meeting CR-3 Decommissioning Submittals ML12305A2752012-11-0101 November 2012 11/1/12 Meeting Presentation - Regarding GSI-191 Strainer Fiber Bypass Test Plan on November 1, 2012 for Crystal River 3 Generating Plant ML12132A3442012-05-11011 May 2012 NRC-AERB Bilateral Meeting Slide Presentation (Nro/De), Aerb, India - May 16-17, 2012 ML1204402842012-02-16016 February 2012 Public Meeting Construction Experiences - Evaluate Impact of Concrete Degradation ML12200A2492011-12-22022 December 2011 Presentation Slides on Shield Building /Containment Delamination ML11314A2552011-11-10010 November 2011 Summary of Pubic Meeting with Crystal River Nuclear Plant Docket No. 50-302 ML11307A4072011-11-0707 November 2011 Pp Presentation NRC Regulatory Conference Presentation 11/07/2011 ML11180A2752011-06-28028 June 2011 Preliminary Site-Specific Results of the License Renewal Environmental Review for Crystal River Unit 3 ML1116400592011-06-0707 June 2011 Meeting Summary - Crystal River Nuclear Plant - Presentation Slides ML11123A0422011-04-21021 April 2011 4/21/11 Crystal River Unit 3 Meeting Slides Regarding EPU Pre-Application ML1025810962010-09-0202 September 2010 Unit #3 Containment Investigation and Repair ML1019405242010-06-30030 June 2010 2010 June 30 NRC Technical Meeting ML1013200462010-05-12012 May 2010 Annual Assessment Meeting Presentation ML1028710902010-03-0808 March 2010 Mar 8 Pnsc De Tensioning Briefing ML1028710912010-03-0303 March 2010 Mar 3 Pnsc De Tensioning Briefing P1 ML1028804582010-02-18018 February 2010 7.8 Excessive Water Jet Pressure Part 3 ML1029106492009-12-28028 December 2009 Failure Modes of CR-3 Containment Concrete Delamination Issue ML1010603462009-11-20020 November 2009 Unit #3 Containment Delamination Update ML1029205092009-11-16016 November 2009 Presentation to Pnsc Containment Update & Discussion of Repair Options ML1029105912009-11-0505 November 2009 Unit #3 Containment Update by Garry Miller ML1029105902009-11-0505 November 2009 2009 Nov 5 - NRC Telecon Briefing.Pdf ML1029106712009-10-30030 October 2009 2009 Oct 30 - Root Cause Analysis Metrics.Pptx ML1029107232009-10-29029 October 2009 Condition Assessment (29Oct09).doc ML1029106722009-10-29029 October 2009 2009 Oct 29_NRC Copy_Containment Delamination.Pptx ML1007504142009-10-14014 October 2009 Email from F. Saba to R. Kuntz, Et Al, Subj: Fyi: Pop for E. Leeds Briefing ML1007504252009-10-13013 October 2009 Email W/Briefing on CR3 Containment Project Overview ML0913201652009-05-12012 May 2009 Summary of Category 3 Public/Open House Meeting with Crystal River to Discuss Annual Assessment ML1029106992009-01-23023 January 2009 2.7 Inadequate Vibration During-Pour ML0830800052008-10-31031 October 2008 Meeting Slides, Progress Energy Public Meeting, NRC Region II Visit ML0810103922008-04-0808 April 2008 Public Meeting - Progress Energy Slides ML0612206932006-05-30030 May 2006 & 11/15/2006 Summary of Conference Calls with Florida Power Corporation. Progress Energy Presentation Slides ML0610304862006-04-11011 April 2006 NRC CY2005 Annual Assessment Meeting - Crystal River - Presentation Slides ML0610305062006-04-11011 April 2006 Presentation Slides for 04/11/06 NRC Public Meeting ML0615301932006-03-27027 March 2006 NFPA 805 Pilot Observation Visit Trip Report - March 2006 - Handouts ML0525604472005-08-17017 August 2005 B&W Owners Group Reactor Vessel Working Group Summary of the Plans of the B&Wog Reactor Vessel Integrity Program ML0523604402005-08-11011 August 2005 Attachment 4 - Progress Energy Slides ML0511903302005-04-26026 April 2005 Steam Generator Inspection Presentation ML0436402692004-12-0909 December 2004 Progress Energy, Meeting Briefing of 12/9/04, Fire Protection Program ML0403505052004-01-0707 January 2004 Meeting Handouts with Progress Energy to Discuss Fire Protection Initiatives ML0327206212003-09-24024 September 2003 Examiner - Vendor Matrix with Phone Number ML0327206112003-09-22022 September 2003 Exam Process ML0327206422003-02-27027 February 2003 Project Plan Sample ML0213404582002-05-16016 May 2002 Training Managers Conference Handouts 2023-12-07
[Table view] Category:Slides and Viewgraphs
MONTHYEARML23335A0832023-12-0707 December 2023 ADPCR3 - Crystal River LTP Public Mtg Slide Deck Final ML23335A0822023-12-0707 December 2023 NRC -Crystal River LTP Public Mtg Slide Deck Final ML20022A0262020-01-22022 January 2020 NEI Presentation Status Update for Ropte Short Term Action Plan: Removed Planned Unavailability for Mitigating Systems Performance Index ML17227A2362016-02-18018 February 2016 Presentation Slides from February 18, 2016, Meeting with Duke Energy Regarding Crystal River Unit 3, Cyber Security Plan Implementation Schedule Milestone 8 ML14024A2632014-01-16016 January 2014 Handouts for Post-Shutdown Decommissioning Activities Report Public Meeting, January 16, 2014 ML13308A0072013-11-0101 November 2013 Open Phase Resolution Update Meeting Duke Energy Entitled Open Phase Detection and Protection. ML13238A3072013-08-29029 August 2013 Slide for 08/29/13 Meeting CR-3 Decommissioning Submittals ML13134A1732013-05-13013 May 2013 Public Meeting Summary - Category 3 - Annual Assessment Meeting - Crystal River Unit 3 Nuclear Plant ML12305A2752012-11-0101 November 2012 11/1/12 Meeting Presentation - Regarding GSI-191 Strainer Fiber Bypass Test Plan on November 1, 2012 for Crystal River 3 Generating Plant ML12184A1382012-07-0202 July 2012 Public Meeting Summary of Category 3 - Annual Assessment Meeting Crystal River 2011 Annual Assessment Meeting Summary ML12132A3442012-05-11011 May 2012 NRC-AERB Bilateral Meeting Slide Presentation (Nro/De), Aerb, India - May 16-17, 2012 ML1204402842012-02-16016 February 2012 Public Meeting Construction Experiences - Evaluate Impact of Concrete Degradation ML12200A2492011-12-22022 December 2011 Presentation Slides on Shield Building /Containment Delamination ML11314A2552011-11-10010 November 2011 Summary of Pubic Meeting with Crystal River Nuclear Plant Docket No. 50-302 ML11307A4072011-11-0707 November 2011 Pp Presentation NRC Regulatory Conference Presentation 11/07/2011 ML11180A2752011-06-28028 June 2011 Preliminary Site-Specific Results of the License Renewal Environmental Review for Crystal River Unit 3 ML1116400592011-06-0707 June 2011 Meeting Summary - Crystal River Nuclear Plant - Presentation Slides ML11123A0422011-04-21021 April 2011 4/21/11 Crystal River Unit 3 Meeting Slides Regarding EPU Pre-Application ML11102A0052011-04-12012 April 2011 Progress Energy - Slides for NFPA 805 Pre-LAR Application Meeting April 12, 2011 ML1034806342010-12-16016 December 2010 Summary of Meeting with Florida Power Corporation Regarding Crystal River'S Proposed License Amendment Request to Support the Independent Spent Fuel Storage Facility Project ML1029201882010-10-19019 October 2010 Appendix Slides ML1029205162010-09-20020 September 2010 Photo ML1029200732010-09-20020 September 2010 Containment 40 Undated Delamination Investigation Report ML1025903962010-09-15015 September 2010 Summary of Public Meeting - Special Inspection Results Crystal River Nuclear Plant ML1025810962010-09-0202 September 2010 Unit #3 Containment Investigation and Repair ML1024402052010-09-0202 September 2010 NRC Special Inspection Team Exit Meeting for Crystal River - September 2, 2010 ML1019405242010-06-30030 June 2010 2010 June 30 NRC Technical Meeting ML1011803132010-03-19019 March 2010 E-Mail from Kuntz to Craver, Crystal River Containment Repair Plan Update ML1028710902010-03-0808 March 2010 Mar 8 Pnsc De Tensioning Briefing ML1028710912010-03-0303 March 2010 Mar 3 Pnsc De Tensioning Briefing P1 ML1028804582010-02-18018 February 2010 7.8 Excessive Water Jet Pressure Part 3 ML1028702742010-02-0606 February 2010 6.4 Rigid and Flexible Sleeves ML1029105792009-12-28028 December 2009 Email - from: Thomas, George to: Lake, Louis Cc: Khanna, Meena; Franke, Mark; Farzam, Farhad; Carrion, Robert; Masters, Anthony; Nausdj@Ornl.Gov Dated Monday, December 28, 2009 6:15 PM Subject: CR-3 Schedule and Root Cause Failure Modes Upd ML1011708192009-12-0303 December 2009 Root Cause Analysis - PII Metrics as of Dec 3rd 2009 ML16175A6062009-11-20020 November 2009 Unit #3, Containment Delamination Update ML1010603462009-11-20020 November 2009 Unit #3 Containment Delamination Update ML1029306172009-11-16016 November 2009 2009 Nov 16- Pnsc - Repair Update Final ML1029205092009-11-16016 November 2009 Presentation to Pnsc Containment Update & Discussion of Repair Options ML1029306522009-11-12012 November 2009 2009 Nov 12 - Containment Unfolded Graphics_Ir Mosaic.Pptx ML1029105542009-11-12012 November 2009 Email - from Orf, Tracy to: Lake, Louis Dated Thursday, November 12, 2009 7:05 Am Subject: FW: CR3 Information Update ML1029105772009-11-0606 November 2009 Containment Unfolded Buttress 2 to 5 ML1029105912009-11-0505 November 2009 Unit #3 Containment Update by Garry Miller ML1029105902009-11-0505 November 2009 2009 Nov 5 - NRC Telecon Briefing.Pdf ML1029105932009-11-0404 November 2009 Email - Subject: CR3 Status Meeting ML1029106712009-10-30030 October 2009 2009 Oct 30 - Root Cause Analysis Metrics.Pptx ML1029107232009-10-29029 October 2009 Condition Assessment (29Oct09).doc ML1029106722009-10-29029 October 2009 2009 Oct 29_NRC Copy_Containment Delamination.Pptx ML1007504252009-10-13013 October 2009 Email W/Briefing on CR3 Containment Project Overview ML1028804922009-10-0505 October 2009 10/6/09 Crystal River 3 Nuclear Safety Review Committee Handout Page ML0913201652009-05-12012 May 2009 Summary of Category 3 Public/Open House Meeting with Crystal River to Discuss Annual Assessment 2023-12-07
[Table view] |
Text
Cyber Security Plan Implementation Schedule Milestone 8 r..
- ~ DUKE February 18, 2016 ENERGY@
Current Cyber M-8 NRC completion date acknowledged Last day of permanent Established (Plant Security SFP certified critical reactor cessation of Nuclear remediation to be clean operation power ops Island complete) of SNM/SF Sept26, 2009 Mar 23, 2013 Oct 30, 2014 Dec 31 , 2017 June, 2018 Dec 31 , 2012 Sept26, 2013 Mar31 , 2015
- Feb, 2018 Dec 31, 2018 Cyber M 1-7 Spent Fuel Permanently ISFSI Complete, REQUESTED completion Pool Defueled all SF stored in Cyber M-8 calculations Emergency ISFSI completion date Plan (PDEP)
- - Completed Milestones * - In Progress Milestone * - Future Milestone - Requested Change
- On February 20, 2013, Duke Energy submitted a certification of permanent cessation of power operations pursuant to 10 CFR 50.82(a)(1 )(i).
- By letter dated March 13, 2013, the NRC acknowledged CR-3's certification of permanent cessation of power operation and permanent removal of fuel from the reactor vessel.
- Accordingly, pursuant to 10 CFR 50.82(a)(2), the 10 CFR Part 50 license for CR-3 no longer authorizes power operation of the reactor or emplacement or retention of fuel in the reactor vessel.
- The CR-3 reactor was last critical on September 26, 2009. Most radioactive sources are in the SFPs, and decay heat and source term continue to diminish.
- CR-3 determined that the only remaining credible design basis accident in the permanently defueled condition is the fuel handling accident (FHA).
- Accident source terms no longer contain particulates (alkali metals) or halogens (iodines), the only source term is from noble gas KR-85 that contribute to dose consequences.
- ISFSI construction project is ongoing and planned completion of SFP offload is currently scheduled for February 2018.
- Based on analysis, with no ventilation across the SFP, the time to boil after loss of all cooling is approximately 240 hours0.00278 days <br />0.0667 hours <br />3.968254e-4 weeks <br />9.132e-5 months <br /> (10 Days).
- Based on this analysis, the time to uncover fuel in the Spent Fuel Pool (SFP) on a complete loss of forced cooling is estimated at 34 days with an estimated average heat-up rate of the SFP of 0.43°F/hr and an estimated boil off rate of approximately 6 gpm.
- It should be noted the SFP temperature is maintained at approximately 80°F year round and the aforementioned analysis assumes the event begins at a SFP temperature of 110°F, this provides an additional 3 days of margin until the SFPs would boil.
- Based on analysis for the Fuel Handling Accident shows the following dose consequences compared to the limits (in brackets):
Control Room 1.3E-04 rem TEDE [5 rem TEDE]
Exclusion Area Boundary 5.9E-05 rem TEDE [6.3 rem TEDE]
Low Population Zone 1.0E-05 rem TEDE [6.3 rem TEDE]
- These results show that the licensing basis accident scenario generates very low doses. The Exclusion Area Boundary (EAB) and Low Population Zone (LPZ) limit of 6.3 rem TEDE is taken from Regulatory Guide 1.183 and is 25°/o of the 25 rem offsite dose limits of 10 CFR 50.67. The 5 rem TEDE Control Room dose limit is also established in 10 CFR 50.67.
- Based on analysis for the Fuel Handling Accident determined that the most limiting of the spent fuel assembly stored in the SFP would net a release of 537 curies of Kr-85 as of 9/26/2013.
- Using the EAB dose and dose limit, it can be estimated that as of 9/26/2013, if all 1243 spent fuel assemblies failed and contained the same amount of curies as the most limiting spent fuel assembly, the dose at the EAB would be - .0733 rem, as compared to the dose limit at the EAB of 6.3 rem TEDE.
- There is no design basis accident scenario or credible accident that could cause damage to this amount of fuel.
- Based on analysis of a complete SFP rapid drain down event. As of 9/26/2013 (conservative data by more than two years), the analysis determined that clad failure would not occur and therefore the only dose at the EAB would be from gamma shine, which would only be a small fraction of the dose limits.
- This analysis demonstrates that on a rapid drain down event, the fuel clad would not catch fire in the empty pool.
- Hypothetically even if the clad failure did occur, the resultant dose would result in a dose of 0.178 rem at the EAB.
- The analysis shows that at four years post reactor operation, cladding failure would not occur.
Crystal River is currently 6.3 years post operation, therefore providing additional margin.
- Crystal River is currently a nuclear island and has modified the Spent Fuel Cooling System to be cooled by a system independently from original plant design.
- All connections to originally designed plant cooling system have been severed and those systems are now abandoned.
- To date, all safety related systems and most of systems important to safety for cooling the spent fuel are abandoned.
- Milestones 1 through 7 are complete.
- The Portable Mobile Media Device (PMMD) Program is established at Crystal River.
- The Plant Security System was chosen first to assess and determine remediations.
- Crystal River is focused on the security remediations of the Plant Security System that are scheduled to be completed on or before 12/2017.
- Crystal River is requesting an extension from 12/31/2017 to 12/31/2018 to complete the Cyber Security Plan Milestone 8.
- We will fully comply with Milestone 8 for the Security System and complete all remediations.
- We will transition from wet to dry storage early in 2018.
- Duke Energy feels that it would be undo burden to exhaust the resources and expense to comply with the remaining portions of the cyber security rule for the remaining few months to transition from wet to dry spent fuel storage.
- This would impose minimal risk to the public based on the age of the fuel and results of the calculations discussed previously.
- Crystal River was still an operating plant when Milestones 1-7 were completed.
- The status and configuration of Crystal River has significantly changed.
- Nearly all of the Safety Related and Systems Important to Safety have been abandoned and can no longer affect reactivity, the Spent Fuel Systems or Emergency Planning.
- The Plant Security System remediations will be completed on or before the end of 2017, which reduces Cyber Security vulnerabilities.
- A new Plant Security System will be installed as part of the ISFSI project permitting a majority of the existing Plant Security System to be abandoned.
- Duke Energy believes that extending the completion date for Milestone 8 by 1 year poses a very low risk to the health and safety of the public.
- The extension would allow CR3 to remain in compliance with the cyber rule through the transition to an ISFSl-only site whereas the cyber security requirements for an operating facility will no longer be applicable.
- CR3 intends to submit a LAR to remove the cyber security license condition for ISFSl-only.
- The requested 12/31 /18 date provides for additional time to allow the spent fuel pools to be certified free of license materials, allow for any emerging items in the ISFSI project and allow time for the site to prepare for and implement ISFSl-only Security and Emergency plans.