ML17227A047

From kanterella
Jump to navigation Jump to search

NRR E-mail Capture - Calvert Cliffs, Nine Mile Point, and R.E. Ginna - Request to Use a Later Edition of the ASME BPV Code,Section XI (CAC Nos. MG0079-MG0083)
ML17227A047
Person / Time
Site: Calvert Cliffs, Nine Mile Point, Ginna  Constellation icon.png
Issue date: 08/14/2017
From: Blake Purnell
Plant Licensing Branch III
To: Tom Loomis
Exelon Corp
References
MG0079, MG0080, MG0081, MG0082, MG0083
Download: ML17227A047 (3)


Text

1 NRR-PMDAPEm Resource From:

Purnell, Blake Sent:

Monday, August 14, 2017 3:56 PM To:

Loomis, Thomas R:(GenCo-Nuc) (thomas.loomis@exeloncorp.com)

Cc:

Wrona, David; Barstow, James:(GenCo-Nuc)

Subject:

Calvert Cliffs, Nine Mile Point, and R.E. Ginna - Request to Use a Later Edition of the ASME BPV Code,Section XI (CAC Nos. MG0079-MG0083)

Mr. Loomis:

By application dated August 10, 2017 (ADAMS Accession No. ML17222A002), Exelon Generation Company, LLC (the licensee) submitted a relief request in accordance with Paragraph 50.55a(g)(4)(iv) of Title 10 of the Code of Federal Regulations to use a portion of a later edition of the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code (ASME Code) at Calvert Cliffs Nuclear Power Plant, Units 1 and 2; Nine Mile Point Nuclear Station, Units 1 and 2; and R. E. Ginna Nuclear Power Plant. Specifically, the licensee is requesting to use Subarticle I-2600, Appendix VIII Examination, of Mandatory Appendix I to the ASME Code,Section XI, 2007 Edition through 2008 Addenda. This would allow the licensee to use the Appendix VIII performance demonstration initiative techniques for components to which Appendix VIII is not applicable.

The purpose of this email is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this relief request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

The NRC staff has reviewed your application and concluded that it provides technical information in sufficient detail to enable the staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed relief request in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review, as compared to the detailed technical review, there may be instances in which issues that impact the staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. You will be advised of any further information needed to support the staffs detailed technical review by separate correspondence.

Based on the information provided in your submittal, the NRC staff estimates that review of this request will take approximately 125 hours0.00145 days <br />0.0347 hours <br />2.066799e-4 weeks <br />4.75625e-5 months <br /> to complete. The staff expects to complete its review by your requested date of February 1, 2018. These estimates are based on the staffs initial review of the application and they could change due to several factors, including requests for additional information. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes to the forecasted hours, I will inform you of the reason for the change and provide the new estimates.

Sincerely, Blake Purnell, Project Manager Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission

2 Docket Nos. 50-317, 50-318, 50-220, 50-410, and 50-244

Hearing Identifier:

NRR_PMDA Email Number:

3663 Mail Envelope Properties (Blake.Purnell@nrc.gov20170814155600)

Subject:

Calvert Cliffs, Nine Mile Point, and R.E. Ginna - Request to Use a Later Edition of the ASME BPV Code,Section XI (CAC Nos. MG0079-MG0083)

Sent Date:

8/14/2017 3:56:07 PM Received Date:

8/14/2017 3:56:00 PM From:

Purnell, Blake Created By:

Blake.Purnell@nrc.gov Recipients:

"Wrona, David" <David.Wrona@nrc.gov>

Tracking Status: None "Barstow, James:(GenCo-Nuc)" <James.Barstow@exeloncorp.com>

Tracking Status: None "Loomis, Thomas R:(GenCo-Nuc) (thomas.loomis@exeloncorp.com)" <thomas.loomis@exeloncorp.com>

Tracking Status: None Post Office:

Files Size Date & Time MESSAGE 3144 8/14/2017 3:56:00 PM Options Priority:

Standard Return Notification:

No Reply Requested:

No Sensitivity:

Normal Expiration Date:

Recipients Received: