L-83-514, Forwards Draft Emergency Operating Procedure, Alternate Shutdown & Indices App R Cables W/Fire Area Routes & App R Equipment & Cables by Fire Area, Per 10CFR50,App R, Section III.G.3 Requirements

From kanterella
(Redirected from ML17214A500)
Jump to navigation Jump to search
Forwards Draft Emergency Operating Procedure, Alternate Shutdown & Indices App R Cables W/Fire Area Routes & App R Equipment & Cables by Fire Area, Per 10CFR50,App R,Section III.G.3 Requirements
ML17214A500
Person / Time
Site: Saint Lucie NextEra Energy icon.png
Issue date: 10/07/1983
From: Robert E. Uhrig
FLORIDA POWER & LIGHT CO.
To: Eisenhut D
Office of Nuclear Reactor Regulation
Shared Package
ML17214A501 List:
References
L-83-514, NUDOCS 8310170222
Download: ML17214A500 (12)


Text

y >g4t

,P REGULATORY ORMATION DISTRIBUTION SV..M (RIDS)

ACCESSION NBR:8310170222 DOC,DATE: 83/10/07 NOTARIZED:

NO FACIL:50-335 St, Lucie P]anti Unit ii Florida Power L Light Co, AUTH,NAME AUTHOR AFFILIATION UNRIG r R ~ E ~

F1or ida Power L Light Co, RECIP ~ NAME RECIPIENT AFFILIATION EISENHUTiD,G, Division of Licensing DOCKET 05000335

SUBJECT:

Forwards draft emergency operating procedure "Alternate Shutdowni" L indices "App R Cables P(/Fire Area Routesi" App R Equipment fl Cables By Fire Areai." per 10CFR50 App R

Section III,G~ 3 requirements

~

~~a&/

DISTRIBUTION CODE:

A006S COPIES RECEIVED:LTR srzE:g +ZJPF TITLE:

OR Submittal: Fire Pr otection NOTES:

RECIPIENT ID CODE/NAME NRR ORB3 BC 01 I INTERNAL: ELD/HDSP.

IE/WHITNEYr L NRR iiAMBACH NRR/DL DIR RONa COPIES LTTR ENCL 3

3 1

1 1

1 RECIPIENT ID COPE/NAME IE FILE 06'RR FIORAVANT07 N

D 09 E

F 04 COPIES LTTR ENCL 9

2 1

1 IEXTERNAL: ACRS NRC PDR'T1S 11 02' 1

1 1

1 LPDR'SIC i 03 05 TOTAL NUMBER OF COPIES REQUIRED:

LTTR P.l ENCL

,P 1

~

~

8

t BOX 14000, JUNO BEACH, FL 33408 yQiigqi 0

i k'vI04%

FLORIDAPOWER & LIGHTCOMPANY October 7,

1983 L-83-514 Office of Nuclear Reactor Regulations Attention: Mr. Darrell G. Eisenhut, Director Division of Licensing U.S. Nuclear Regulatory Commission Washington, D.C.

20555

Dear Mr. Eisenhut:

RE:

St. Lucie Unit ~No.

1 I

Docket No. 50-335 Fire Protection Alternative Shutdown Report 10 CFR 50 A endix R Section III.L Pursuant to the requirement of 10 CFR 50 Appendix R Section III.G.3, Florida Power and Light herewith submits the Alternative Shutdown Report for St. Lucie Unit 1.

Alternate shutdown capability is being provided in accordance with the requirements set forth in Appendix R Section III.L for a fire in either the Control Room or the Cable Spread Room.

Alternate shutdown will be accomplished through the use of the Hot Standby Panel (HSP) which is capable of maintaining the unit at hot standby.

To achieve and maintain cold shutdown, local manual actions will be coordinated by the HSP operator.

If additional information is required, please contact us accordingly.

Very truly yours, Robert E. Uhrig Vice President Advanced Systems and Technology REU/GJK/mp Attachment cc:

J.P. O'Reilly, Region II Harold F. Reis, Esquire 8310170222 831007 PQR ADQCK 05000335 F

PDR PEOPLE... SERVING PEOPLE

0502s FLORIDA POWER

& LIGHT COMPANY ST LUCIE PLANT - UNIT NO.

1 ALTERNATIVE SHUTDOWN Since the separation defined in Appendix "R"Section III.G.2 cannot be provided for essential components and circuits in the Control and Cable Spread Rooms, alternative shutdown capabi1ity is provided.

This insures that in the unlikely event a fire makes the Control Room uninhabitable or renders equipment in either room inoperable, the plant can be safely taken to co1d shutdown from a remote location.

A11 other areas of the plant containing essential equipment comply with Section III.G.2 of Appendix "R".

A description of the alternative shutdown capability provided is given be1ow:

a)

Table 2 lists those systems and the components within those systems which are relied upon to provide alternative shutdown capability.

Employing this equipment, plant operators can maintain the Unit at hot standby conditions from the Hot Standby Panel (HSP) and bring the Unit to co1d shutdown with local manual actions.

A11 equipment is operable fo11owing a loss of offsite power.

(See Table 3 for a complete 1ist of instruments and controls avai1able at the HSP).

1 b)

Alternative shutdown.capability is provided for the Contro1 and Cab1e Spread Rooms which contain control circuits for virtua1'ly al1 essential equipment.

A detailed list of the essential components and cables in these areas can be found in Attachment 2 under Fire Zones 70 and 57 respectively.

Existing components and systems as 1isted in Table 2 will be employed to achieve and maintain cold shutdown in the event of a fire in either of these areas.

Wherever necessary, eIectrica1 components and circuitry required for the operation of the above equipment will be relocated or protected to insure both physical and e1ectrica1 separation from the Control and Cable Spread Rooms.

Physical separation is achieved by means of protective enclosures within or complete relocation from these areas and will meet the requirements of Section III.G.2.

Electrical isolation devices are provided where necessary.

c)

Process and Instrumentation Drawings (P&IDs> for piping and components essential to alternative shutdown are presently contained in the SL-1 FSAR since on1y existing systems are utilized.

The fire zone locations of a>>.

equipment containing breakers and isolation devices are listed

$ n Table 1.

Three examples of Control Wiring Diagrams (CWDs) showing typical isolation devices are presented in Attachment 3.

d)

All new isolation or control switches required for alternative shutdown will be installed in a manner consistent with FSAR design criteria and will not degrade that system.

In general, isolation, switches actuate an alarm in the Control Room when placed in the "isolated" position.

0502s PLORIDA POWER

& LIGHT COMPANY ST. LUCIE PLANT - UNIT NO. 1 ALTERNATIVE SHUTDOWN e)

Attachment 1 outlines the basic steps required to bring the plant to cold shutdown from outside the Control Room.

This procedure has been developed to instruct plant operators in the specific tasks required to effect safe shutdown.

f)

The manpower available to perform safe shutdown functions as well as fight fires is described in Attachment 1.

g)

Tests will be performed periodically in accordance with Technical Specification requirements for the remote shutdown system.

h)

Technical Specifications will be prepared to cover all new isolation/

transfer switches added for alternative shutdown.

i)

Only existing components and systems will be employed for alternative shutdown.

As such, verification of system capabilities is not required.

Circuitry modifications will be consistent with existing design criteria.

j)

No credit is taken for repair of damaged cold shutdown equipment.

0502 s PAGE 1

OF 3

TABLE 2 EQUIPMENT RE UIRED FOR ALTERNATE SHUTDOWN ST LUCIE UNIT NO 1

SYSTEM/FUNCTION EQUIPMENT 1.Diesel Generator:

DOT Pump 1B DO Storage Tank IB DG-1B Set SE-17-1B (DG Fuel Oil Supply Valves>

S22, S231 S24 (DG Day Tank 1B Level Switches) 2.

Auxiliary Feedwater:

AFW Pump 1B.

1-MV-09-10 (AFW Pump 1B Iso Valve)

(162)

Condensate Storage Tank 3.

CVCS:

Charging Pump IB Boric Acid Makeup Tank IA or 1R V-2508 or 2509 BAMT Gravity Feed Valves>

V-2504 (RWT Supply Valve)

I-SE-02-0 I (Charging Line Iso Valve)

(I&2i 4.

Reactor Coolant:

V-1404 (Power Operated Relief Valve) 5.

HVAC Equipment:

HVS-5B (Elec Equip Rm Supply Fan)

HVE-12 (Elec Equip Rm Exhaust Fan)

HVE-9B (ECCS Area Exhaust Fan)

0502 s TABLE 2 PAGE 2 OF 3

EQUIPMENT REQUIRED FOR ALTERNATE SHUTDOWN ST L CIE UNIT 6.

SYSTEM/FUNCTION Electr ical Equipment:

EQUIPMENT Battery 1B Battery Charger lB 7.

Safety Infection:

Refueling Water Tank LPSI Pump 1B V-3651 (SDC Iso Valve)

V-3652 (SDC Iso Valve)

FCV-3306 (SDC Control)

V-3453 (SDC Block Valve)

V-3457 (SDC Block Valve)

HCV-3657 (SDC Control.)

V-3452 (SDC Block Valve)

I-MV-07-3B (CS Block Valve)

HCV-3645 (SIS Block Valve)

V 36 14 ~

3624

~ 3634

& 3644 (SIT Iso Valve)

I-HCV-08-1A (Atmospheric Dump Valve) 8.

Main Steam:

I-HCV-08-1B (Atmosplieric Dump Valve)

(1&2)'

0502s.

PAGE 3 OF 3

TABLE 2 E UIPMENT RE UIRED FOR ALTERNATE SHUTDOWN ST LUCIE UNIT NO 1

SYSTEM/FUNCTION E

IPMENT 9.

Component Cooling Water:

CCW Pump 1B CCW Heat Exchanger 1B 10.

Intake Cooling Water:

ICW Pump 1B 11.

Instrumentation:

LIC-9006 (Steam Gen lB Level)

(1&2)

PIC-08-1B1 (Steam Gen 1B Pressure)

HIC (EP -1100Y (Pressurizer Pressure>

HIC (EP)-1110Y (Pressurizer Level)

TI (EP-1125 RCS Temperature)

(1&2)

(1&2)

(1 &2)

NOTES:

1)

Isolation Switches are provided for these components.

2)

Available on Hot Standby Panel.

~.

0502s

~ PAGE 1 of 3 TABLE 3 HOT STANDBY PANEL INSTRUMENTATION & CONTROLS ST LUCIE UNIT NO.

1 INSTRUMENTATION TRAIN HIC-.1100X HIC-1100Y HIC-lllOX HIC-1110Y TI (EP) -1115 TI (EP)-1125

-PIC"08-1Al PIC-08-1B1 LI-9005 LI-9006 LI-9012-1 LI-9022-.1 VI-09-2 Pressurizer Pressure and Spray Valve Control Pressurizer Pressure and Spray Valve Control Pressurizer Level and Letdown Valve Control Pressurizer Level and Letdown Valve Control RCS Cold Leg Temperature RCS Cold Leg Temperature SG-lA Pressure and ADV Control SG-lB Pressure and ADV Control SG-lA Level SG-1B Level SG-1A Level (Wide Range)

SG-1B Level (Wide Range)

AFW Pump 1C Turbine Speed 1

Source Range Neutro'n Flux CONTROLS A

A A

A AB Auxilia Feedwater CS-629-2 AFW Pump lA CS-630-2 HIC-09-1C1 CS-632 CS-608-2 AFW Pump 1B AFW Pump 1C Turbine I-MV-08-3, AFW Pump 1C Steam Valve I-MV-09, AFW Pump lA Isolation Valve A

0502s PAGE 2 of 3 TABLE 3 HOT STANDBY PANEL INSTRUMENTATION,& CONTROLS ST LUCIE UNIT NO.

1 INSTRUMENTATION CS 609-2 CS-610"2 CS-611-2 CS-612-2 CS-613-2 CVCS CS-177 CS-178 CS-179 CS-189-1 CS-189-2 CS-157-1 CS-157-2 CS-158 Reactor Coolant I-MV-09-10, AFW Pump 1B Isolation Valve I-MV-09"13, AFW IA/1B Cross Tie Valve IWV-09-14, AFW 1A/1B Cross Tie Valve I-MV-09-11, AFW Pump lC Isolation Valve IWV"09-12, AFW Pump 1C Isolation Valve Charging Pump 1A Charging Pump 1B Charging Pump 1C I-SE-03-3, Auxflfary Spray Valve I-SE-03-4, Auxiliary Spray Valve V-2516, Letdown Isolation Valve V-2515, Letdown Isolation, Valve LCV-2110P&Q, Letdown Control Valves TRAIN B

A A

A CS-122 CS-123 CS-124 CS-125 CS-126 Pressurizer Proportional Heater Bank Pl Pressurizer Proportional Heater Bank P2

'ressurizer Backup Heater Bank Bl Pressurizer Backup Heater Bank B2 Pressurizer Backup Heater Bank B3 A

f

0502s PAGE 2 of 2 TABLE I HOT STANDBY PANEL INSTRUMENTATION 6 CONTROLS ST LUCIE UNIT NO.

1 INS TRUMENTATION TRAIN CS-127 CS-128 CS-129 CS-130 Pressurizer Backup Heater Bank B4 Pressurizer Backup Heater Bank B5 Pressurizer Backup Heater Bank B6 PCV-1100E&F, Pressurizer Spray Va1ves B

A