Forwards IE Insp Rept 50-335/81-05 on 810202-0310.No Noncompliance Noted
ML17209B017
Person / Time
Site: Saint Lucie NextEra Energy icon.png
Issue date: 03/26/1981
From: Robert Lewis
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Robert E. Uhrig
FLORIDA POWER & LIGHT CO.
Shared Package
ML17209B018 List:
References
NUDOCS 8105010153
Download: ML17209B017 (3)


See also: IR 05000335/1981005

Text

~j

~

gp,fl RECy

0

Cy

I

nO

Ol,'

/

t

+y

q9

++**+

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION II

101 MARIETTAST., N.W., SUITE 3100

ATLANTA,GEORGIA 30303

HQI';

P.

6 1981

Florida Power and Light Company

ATTN:

R. E. Uhrig, Vice President

Advanced Systems

and Technology

P. 0.

Box 529100

Miami, FL

33152

<~f/(Pp

'entlemen:

Subject:

Report

No

5 -335/81-05

This refers

to the routine safety

inspection

conducted

by

S.

A. Elrod of this

office on February 2, - March 10,

1981, of activities authorized

by NRC Operating

License

No.

DPR-67 for the St.

Lucie

1 facility and to the discussion

of our

findings held with C.

M. Wethy at the conclusion of the inspection.

Areas

examined

during

the

inspection

and

our findings

are

discussed

in the

enclosed

inspection

report.

Within these

areas,

the

inspection

consisted

of

selective

examinations

of procedures

and representative

records,

interviews with

personnel,

and observations

by the inspectors

Within the scope of this inspection,

no violations or deviations were disclosed.

In accordance

with Section

2.790 of the

NRC's "Rules of Practice",

Part 2, Title

10,

Code

of

Federal

Regulations,

a

copy of this letter

and

the

enclosed

inspection

report will be placed

in the

NRC's Public

Document

Room.

If this

report

contains

any

information that you (or your contractor)

believe to

be

proprietary, it is necessary

that you make

a written application within 20 days

to this office to withhold such

information from public disclosure.

Any such

application must include a full statement

of the reasons

on the basis of which it

is claimed that the information is proprietary,

and should

be prepared

so that

proprietary information identified in the application is contained

in a separate

part of the document.

If we do not hear

from you within the specified period,

the report will be placed in the Public Document

Room.

Should you have

any questions

concerning this letter,

we wi 11

be glad to discuss

them with you.

Sincerely,

~

~,C,

. C.

L

i s, Acting Director

Division of Resident

and

Reactor Project Inspection

Encl osur e:

(See

page 2)

/

II

H

fl

(

4 ~ t

g

l1

N

r

1

e

S'lorida Power and Light Company

MAR 2

S l98I

Enclosure:

Inspection Report No. 50-335/81-05

cc w/encl:

C.

M. Wethy, Plant Manager

N. Weems, Assistant

QA

Construction Manager