07-14-17 Anchor Darling Valve Industry Resolution Plan Attachment
ML17209A021
Person / Time
Site: Nuclear Energy Institute
Issue date: 07/14/2017
From: Krueger G
Nuclear Energy Institute
To: John Lubinski
Division of Engineering
Wilkins, L, NRR/DPR, 301-415-1377
Shared Package
ML17209A018 List:
References
Download: ML17209A021 (1)


Text

1 ANCHOR DARLING DOUBLE DISC GATE VALVE INDUSTRY RESOLUTION PLAN 7-14-2017 Summary of Resolution Plan NEI developed and is managing this plan to coordinate industry response, actions, and communications to address the resolution of the Anchor Darling DDGV issue. Industry-coordinated actions for assessing the population of installed valves susceptible to the identified condition, communicating industry guidance for identifying and resolving susceptible valves, gaining commitments from stations with valves requiring responsive actions, and investigating similar conditions for other valve types are key elements of the plan. The plan will include interaction with the NRC to achieve the following:

Gain a greater understanding of the coordinated industry actions being taken to respond to this issue Communicate results of industry scope and the graded approach being taken Understand the specific commitment strategy for the industry in response to the Anchor Darling Part 21 Participate in periodic communications and status updates of actions being taken across the industry Revise or augment the resolution plan to reflect new or changes in information Proposed Actions and Due Dates ACTION RESPONSIBLE PARTY DUE DATE

1. Issue revised Anchor Darling Double Disc Gate Valve Part 21 Flowserve Completed (July 11, 2017)
2. Coordinate electronic access to NRC to review BWROG Anchor Darling valve guidance document BWROG July 28, 2017
3. Develop a plan for the analysis of industry Anchor Darling valve information and communication of results.

NEI August 4, 2017

4. Develop industry commitment response strategy and communicate to NRC NEI August 4, 2017
5. Develop the basis for the update of technical guidance in the BWROG document Industry August 4, 2017
6. Issue revision to the BWROG Anchor Darling valve guidance document BWROG August 31, 2017
7. Distribute BWROG guidance document to the PWROG BWROG August 31, 2017
8. Investigate the potential for similar conditions for other valve types or manufacturers Industry October 2017
9. Determine the need to resurvey the industry to assess change in scope or actions resulting from application of the updated BWROG guidance NEI/Industry October 2017